Memorandum from the Department for Transport
(PPP 08)
INTRODUCTION
1. By the mid-1990s it was widely recognised
that the Underground had suffered from decades of under-investment
and that the continued uncertainties about future funding levels
had badly affected the reliability of passenger services. London
Underground (LU) also had a poor record of delivering major infrastructure
projects and maintenance programmes on time and on budget. There
were substantial cost overruns on the Jubilee line extension and
the Central line upgrade (both in excess of 30%) and on a number
of other smaller renewal programmes.[28]
Neither major project was completed on time nor delivered the
expected improvements in journey times.
2. To address this, the 1997 Labour Party
manifesto proposed a new public private partnership (PPP) to improve
the Underground, safeguard its commitment to the public interest
and guarantee value for money for taxpayers and passengers. In
March 1998 the Government signalled its commitment to substantial
extra investment in the Underground and announced that LU would
be restructured to deliver two key aims:
Keeping LU as a single unified body
in the public sector with responsibility for operating passenger
services; and
Utilising the private sector's capacity
in a PPP to overcome the investment backlog, and maintain and
modernise infrastructure.
3. LU considered a number of alternative
structures during development of the PPP before concluding that
the best practical and value for money option was to split the
network into three infrastructure companies each with responsibility
for a number of individual lines. This structure, together with
the partnership approach and proposed performance regime underpinning
it, was supported in general by the industry.
4. In 2002 the Government gave an unprecedented
statement of intent to provide long term funding to the Underground,
averaging more than £1.1 billion a year up to 2009-10. The
PPP, together with this funding, was designed to enable LU to
deliver earlier a modern system that will provide passengers with
a better and more reliable service, and enable the network to
meet future passenger demand.
THE PPP CONTRACTS
5. Under the 30-year PPP agreements the
private sector companies maintain, renew and upgrade the Underground's
infrastructure while LU remains responsible for delivering passenger
services. The PPP companies have specific obligations to deliver
certain projects (eg station refurbishments and line upgrades)
by particular dates and a more general obligation to maintain
assets in accordance with the principles of whole-life cost management.
This requires them to fully consider the future cost of maintaining
the asset throughout its working life, as well as its initial
purchase and installation cost.
6. The PPP also includes a performance payment
regime which provides incentives for the companies to perform
better than the benchmark measures set out in the contracts, while
abatements (financial penalties) are imposed for below benchmark
performance. Payments to the PPP companies reflects their performance
in three key measures:
Availability; which reflects whether
the assets (trains, track etc) are working and available for LU
to deliver passenger services. It is measured in delays to passengers
(lost customer hours), weighted depending on location and time
of the delay;
Capability; which is a long-term
measure of a line's capacity, ie its ability to move more people
and reduce passenger journey time. Most improvement under this
will be seen when the line upgrades, which are currently underway
and are planned to be delivered from 2009 onwards; and
Ambience; which indicates the quality
of the passenger environment, including cleanliness, information
and general condition of the stations and trains.
DELIVERING REAL
BENEFITS FOR
PASSENGERS
7. The PPP is delivering benefits in performance
against the background of continuing growth in demand and an unprecedented
level of works being carried out on the network. The Underground
is carrying more passengers than ever; over 1 billion journeys
were made in 2006-07, 21% above the 832 million passengers carried
in 1997-98. Between 1997-98 and 2006-07 LU has increased the annual
train kilometres run by 12½%, to nearly 70 million and over
94% of scheduled services were run in 2006-07. LU's customer satisfaction
last year was also at the highest level since 1990-91.
8. Availability is currently a key indicator
of PPP performance until the line upgrades are delivered. To date
there has been a wide disparity of performance between the Underground
lines, reflecting the variation in the condition of the assets,
but also the performance of the PPP companies.
9. The latest availability performance figures[29]
show that of the three lines that Tube Lines are responsible for
under their PPP agreement, two (the Piccadilly and Jubilee lines)
are performing significantly better than the benchmark measure.
The Northern line continues to present a challenge with performance
so far this year running at 18% worse than the benchmark figure.
To address this performance Tube Lines and LU have accelerated
the track renewal programme and are looking at ways to improve
the train fleet's reliability.
10. Of the nine lines which are the responsibility
of Metronet under its two PPP agreements, six (the Bakerloo, Circle,
East London, Hammersmith & City, Metropolitan and Waterloo
& City) are performing better than the required benchmark
figure. The major improvement in performance on the Waterloo &
City line reflects the benefits of the upgrade completed last
year.
11. Performance on the three remaining lines
is running worse than the benchmark figure; 15% in the case of
the Central, 17% on the District and on the Victoria it is particularly
disappointing, running at 61% worse than benchmark.
12. Long term improvements within the PPP
contracts include:
Stations: 247 stations programmed
to be modernised or refurbished by 2010-11, with work on 91 stations
completed.[30]
This included major improvements to Wembley Park station by Tube
Lines, which was completed on time and within budget, delivering
a 70% increase in capacity and enabling the station to handle
37,500 passengers per hour;
Track: Over 115 km of track (14%
of the network) has been renewed, with delivery on some lines
ahead of schedule;
Waterloo & City line: A fifth
train is now in service during the peak periods, providing a 20%
increase in capacity. A £40 million upgrade has seen improved
reliability and a reduction in average journey times;
Jubilee line: Four new trains are
now available and a seventh carriage has been added to all trains,
bringing about a 17% increase in capacity. Work on a new signalling
system is ahead of the contract date for delivery in 2009;
Piccadilly line: The extension to
Heathrow Terminal 5 is on schedule to be completed by March 2008;
Northern line: Work on a new signalling
system is ahead of the contract date and should be completed before
the Olympics;
Victoria line: The first new trains
are being tested, while work on the signalling and power upgrades
is broadly on schedule;
District line: 55 trains have been
refurbished to date. A refurbished train is being returned to
service every two weeks and all trains should be completed by
2009.
SAFETY
13. Passenger safety is of paramount importance.
The Underground is a very safe mode of transport and its safety
record compares favourably with other Metro systems of a similar
age, particularly in key areas such as derailments, collisions
and platform-train interfaces.[31]
Customer injuries average 1.5 persons per 10 million journeys,
and the majority of fatalities on the network are due to trespass
or suspected suicides.[32]
14. LU retains overall responsibility for
passenger safety on the network and the Office of Rail Regulation,
through Her Majesty's Railways Inspectorate (HMRI), regulates
health and safety on the Underground. It is a legal requirement
that LU has appropriate safety management systems and procedures
in place to ensure staff and customer safety which have been accepted
by HMRI. Under the PPP arrangements LU monitors the PPP companies'
safety performance, audits their compliance with their contractual
safety cases and LU's own standards, and agrees an annual Safety
Improvement Programme.
15. LU's Safety Action Tracking System records
progress against the Safety Improvement Programme. For the fourth
year in succession there has been an improvement in the proportion
of actions completed on time and in 2006-07 all three PPP companies
achieved improved levels of compliance with their contractual
Safety Cases than the previous year.
16. The table below provides figures for
derailments, broken rails and signals passed at danger (SPADs)
since 2001.[33]
|
| Year | 2001
| 2002 | 2003
| 2004 | 2005
| 2006 | 2007[34]
|
|
| Train Derailments[35]
| 1 | 1
| 6 | 4
| 4 | 2
| 1 |
| Broken Rails | 29
| 26 | 32
| 51 | 45
| 29 | 9
|
| Category B SPADs[36]
| 180 | 143
| 143 | 221
| 166 | 171
| 158 |
|
17. The number of train derailments of all types has
fallen since 2003. Within these figures the number of passenger
train derailments while in service remains very low. These incidents
have averaged at just over one per year over the last 15 years
or so, but LU recently went 37 months between such incidents.[37]
18. The figures for broken rails reflect the ageing nature
of LU's track and the increase in both volume of trains and passengers.
The PPP, through improved rail inspection technology, asset maintenance
and fault detection has led to an increase in the number or broken
rails detected before they represent a safety hazard to passengers.
The reduction since 2005 is encouraging and reflects the PPP companies
accelerated track renewal programme, at about four times the historic
average.
19. The increase in signals passed at danger (SPADs)
reflects a combination of the failure of ageing signalling equipment
and greater emphasis on reporting incidents. However, the presence
of LU's safety protection systems fitted throughout the network
means that the risk of a collision following a SPAD is extremely
low. Again the signal system upgrades planned for the majority
of lines will address this issue.
VALUE FOR
MONEY
20. Ensuring value for money for taxpayers and passengers
was a key consideration when both the Department and LU concluded
that a PPP structure was the best option. In addition to the value
for money assessment carried out by LU, the Government commissioned
independent advice that confirmed that LU's value for money analysis
was robust.[38] The Committee
of Public Accounts report[39]
noted that the key principles in the Treasury's Value for Money
Guidance had been adopted for the PPP, and that when both the
Department and LU assessed the PPP they had considered wider,
non-quantitative factors alongside the Public Sector Comparator.
This included considering the strategic benefits, the ability
to create a partnership and the risk share between public and
private sectors.
21. The PPP contracts include a number of mechanisms
for ensuring that value for money is secured over the long term:
an outcome based performance and payment regime
that links payments to the delivery of services at a price agreed
with LU;
an obligation on the companies to demonstrate
an efficient and economic whole-life cost approach to asset management;
the use of an independent Arbiter, established
by statute, with powers to determine an efficient and economic
price for services where LU and the companies are unable to agree
a price. The Arbiter provides an important assurance of value
for money in the PPP agreements that allows for possible changes
to the scope of the work, the re-specifying of requirements, and
re-pricing of services as part of the Periodic Review which occurs
every 7½ years. Revisions to the price at these breakpoints
in the agreements will need to meet the tests of efficiency and
economy; and
under both Metronet agreements the Arbiter can
be asked to undertake an annual performance review to show the
extent that the company is meeting the criteria of efficiency
and economy and Good Industry Practice, contained in the PPP agreements.
22. The PPP also allows LU to procure additional works
outside the contracts from alternative suppliers that enables
LU to benchmark prices and test the price competitiveness of the
PPP companies.
RISK SHARING
23. When signed the PPP agreements struck a balance between
the level of risk transferred to the private sector and that retained
in the public sector. The table below[40]
sets out how the key risks were allocated under the PPP agreements.
24. The PPP agreements are outcome based and expose the
companies to risk of performance payment abatements if the contractual
targets are not achieved. The targets demand enhancements by fixed
dates, ie the Jubilee line requires a 48% increase in capacity
and 22% reduction in journey times by November 2009 compared to
when the contracts were signed. The risk for the PPP companies
is that failure to deliver the line upgrades and enhanced performance
by the contract deadlines will mean a step-change in abatements.
This will be exacerbated if the cost of the upgrade exceeds the
budget provided in their bid through the PPP Company's own inefficient
and uneconomic performance.
25. Where risk more properly sits with the public sector
then this has been retained by LU, such as passenger fare revenue,
which can be subject to variations beyond the PPP companies' control.
26. Other risks have been shared, such as where the asset
condition was unknown at the time of PPP procurement (known as
grey assets). The National Audit Office[41]
acknowledged that in these circumstances seeking to transfer too
much risk would be likely to lead the PPP companies to over-compensate
on grounds of uncertainty. This would have caused them to build
in bigger contingency provisions within their bids, leading to
a higher price that would not have represented value for money
for the taxpayer.
ALLOCATION OF KEY RISKS UNDER THE PPP
|
| Risk
| LUL | PPP Co
| Shared |
|
| Revenue | From passenger demand
| E | |
|
| From meeting performance targets
| | E |
|
| Safety | In passenger operation eg driving at the appropriate speed; change in safety law
| E | |
|
| In provision of assets that are "fit for purpose" with As Low as Reasonably Practical Risk
| | E |
|
| Costs | Of Infrastructure work eg design and construction of new trains
| | E |
|
| Of operations eg cost of drivers
| E | |
|
| Of inflation (indexed) |
| | E
|
| Of rectifying the health of unclassified "grey assets" eg deep tunnels
| | | E
|
|
NOTE: Net cost/revenue overruns
are caped at £200 million for Tube Lines in the first 7½
year period and £50 million for each of the two Metronet
contracts if they are acting in an "efficient and economic"
way.
METRONET IN
PPP ADMINISTRATION
27. The PPP Administration of Metronet should not in
itself affect passenger services on the Underground. The GLA Act
1999 provides that PPP Administration must encompass both the
protection of creditors' requirements and keeping passenger services
running safely and effectively, until the PPP company is transferred
out of PPP administration.
28. LU have made clear that the overriding priority continues
to be the provision of a safe and reliable Underground service
for passengers, with the continuance of Metronet's maintenance
and renewal activities pending transfer to a new company.[42]
To date, LU have reported no safety concerns arising from the
Metronet PPP Administration.
29. The PPP Arbiter's Annual Review of Metronet's performance
for the three years to 31 March 2006[43]
identified areas of weakness and potential for costs considerably
higher than those provided under the contracts. On 21 June 2007
Metronet requested that the independent PPP Arbiter conduct an
Extraordinary Review (ER) of its BCV contract. ER is a contractual
mechanism that, among other things, enables the PPP companies
to seek additional payment to meet cost overruns ahead of a periodic
review. The ER process involves the Arbiter making a judgement
about the costs that an economic and efficient PPP company would
have incurred in delivering the same outputs as the Metronet company.
30. To allow a PPP company to perform its obligations
pending the completion of an ER, the Arbiter can also award an
"interim" payment. Metronet accordingly sought an interim
award of £551 million from the Arbiter who, on 16 July published
a draft Direction which provisionally concluded that an efficient
and economic company in Metronet's circumstances would be entitled
to an interim award of £121 million.[44]
Metronet concluded on 18 July that such an award would be insufficient
to keep the company afloat, and Transport for London (TfL) proceeded
to serve the Mayor's petition for PPP Administration of both Metronet
companies.
31. On September 2007, the Arbiter published his Initial
Thoughts on the ER.[45]
The Arbiter's provisional view, based on representations from
LU and Metronet, was that aspects of Metronet's operations were
not efficient and economic (eg deficiencies in the supply chain
and governance arrangements) and that the costs associated with
these would not be allowable.[46]
This suggests that it was failures in the management of the Metronet
companies that were to blame for a large proportion of the cost
overruns that led to their collapse.
32. It is for the PPP Administrators, working with LU,
TfL and the Mayor, to identify the best outcome from the PPP Administration
process. However, we share TfL's objective that the Metronet contracts
should be transferred out of PPP Administration in the minimum
time necessary. We are working closely with TfL, LU and the PPP
Administrators to understand the full implications of any potential
solutions and deliver a long-term outcome which:
secures the best achievable value for money;
addresses lessons to be learned; and
enables the most effective possible transfer of
risk into the private sector.
October 2007
28
London Underground Public Private Partnership Final Assessment
Report published on 7 February 2002, updated on 3 May 2002. Back
29
London Underground Managing Director's Performance Reports. Back
30
61 stations have been delivered into service and accepted by LU.
A further 30 have been declared complete by the PPP companies. Back
31
Community of Metros (CoMET) Benchmarking Report, February
2007. Back
32
Office of Rail Regulation's "Railway Safety Statistical Report
2006" reported 19 suicides and trespasser deaths out of 22
fatalities on the network, their "Annual Report on Railway
Safety 2005" reported 24 out of 28 respectively. Back
33
Figures provided by Her Majesty's Rail Inspectorate. Back
34
2007 figures, provided by LU, are for provisional up to the end
of September. Back
35
Includes passenger trains both in service and those withdrawn,
and other trains (ie engineering). Back
36
Category B, or technical SPADs are caused by signalling failure,
errors by technical staff or train system faults. Back
37
Central line derailments at White City on 11 May 2004 and Mile
End on 5 July 2007. Back
38
London Underground PPPs; Value for Money Review. Independent Review
by Ernst & Young for the Secretary of State for Transport,
Local Government and the Regions, published on 5 February 2002. Back
39
House of Commons Committee of Public Accounts "London Underground
Public Private Partnerships" Seventeenth Report of Session
2004-05, published on 31 March 2005. Back
40
Reproduced from the National Audit Office Report "London
Underground: Are the Public Private Partnerships likely to work
successfully?", published on 17 June 2004, Back
41
The National Audit Office report "London Underground PPP:
Were they good deals?", published on 17 June 2004. Back
42
TfL press release, "Mayor and London Underground act to ensure
smooth transition for Metronet lines", 18 July 2007. Back
43
Office of the PPP Arbiter "Annual Metronet Report 2006",
published on 16 November 2006. Back
44
The PPP Arbiter "Interim level of ISC pending a direction
on ISC at Extraordinary Review, Draft Directions", 16 July
2007. Back
45
The PPP Arbiter "Directions on Form and structure of Extraordinary
Review and Net Adverse Effects and Infrastructure Service Charge
at Extraordinary Review, Initial Thoughts", 21 September
2007. Back
46
The Arbiter's Initial Thoughts said that allowable costs were
likely to be in the region of £140 million and £470
million for BCV and £230 and £600 for SSL. Back
|