Select Committee on Transport Written Evidence


Memorandum from the National Union of Rail, Maritime and Transport Workers (RMT) (PPP 09)

  1.  The National Union of Rail, Maritime and Transport Workers (RMT) welcomes the opportunity to contribute to the Transport Select Committee inquiry in the Public Private Partnership (PPP) and the London Underground. With over 10,000 members employed across both operational and engineering functions on the London Underground, RMT is the largest of the Tube trade unions.

Risk transfer

  2.  Before the transfer of engineering functions to Metronet and Tube Lines a series of organisations including the rail unions, the Transport, Local Government and Regions Select Committee, the Mayor of London, Transport for London, the Industrial Society and the Capital Transport Campaign all issued warnings, on a series of grounds including safety, value for money and contractual complexity, against proceeding with the Public Private Partnership. Regrettably, all of these warnings were completely ignored by Government.

  3.  In June 2004 the National Audit Office published their London Underground PPP: Were they good deals? report which indicated that in the event of termination or administration, 95% of the money loaned by banks and other institutions to the Infracos would be reimbursed by the public purse. Indeed, the NAO noted that whilst negotiating the PPP contracts the Department for Transport and London Underground conceded to the lenders demand that a 90% payback in the event of termination was too low a figure given the market perceptions of the political risks associated with the scheme. The pay-back figure was therefore increased to 95%.

  4.  That the public purse is still responsible for the 95% of Metronet's debt was confirmed in the following exchange at City Hall during Mayor's Question Time on 18 July 2007. The Mayor was accompanied on 18 July by Transport Commissioner Peter Hendy, TfL Managing Director Tim O'Toole and TfL Managing Director of Finance Steve Allen.

    Bob Neil (AM): There was also a piece in The Guardian, I think, yesterday suggesting that there might be some potential liability on either TfL of LUL as its subsidiary, for a considerable chunk of Metronet's debts. It was based on the Standard and Poor's report. Is there anything in that?

    Tim O'Toole (Managing Director, London Underground Ltd): The Metronet debt is guaranteed by us.

    Bob Neil (AM): I think The Guardian was suggesting that in 2004 Standard and Poor's had suggested that TfL or the subsidiary could be liable for up to 95% of the debt. That is correct is it?

    Steve Allen (Managing Director of Finance, Transport for London): That is correct. That is a feature of the PPP contracts.

  5.  RMT's view is that the decision taken by the Department for Transport and the then management of London Underground to allow clauses to be written into the PPP contracts which allows for 95% of Infraco debt, now standing at £1.6 billion,[47] to be guaranteed by the public purse represents, in our view, a dereliction of public duty. It also confirms the long held RMT view that the privatisation of both the national rail network and the London Underground has led to a wholly inadequate level of risk being held by the private sector. It is simply unacceptable that private sector interests are routinely issued letters of comfort or guarantees in the event of project failure. RMT believes that if lenders and/or operators are willing to make profits out of essential public services they should also be prepared to bear the financial risk.

Private sector failure

  6.  The collapse of Metronet comes as no real surprise to the RMT. From transfer in 2003 to administration in 2007 our representatives and activists employed by BCV and SSL were reporting to us poor project management, chaotic financial control and the de-skilling of their work. Two thirds of the PPP scheme—Metronet BCV and Metronet SSL—is now financially and operationally in ruins and essential upgrades are in jeopardy. In the run-up to the 2012 Olympic and Paralympic Games, London cannot afford another failure on this scale.

  7.  Since the collapse of Metronet, several claims have been made that the performance of Tube Lines demonstrates that it is simply the performance of Metronet and not the PPP itself which has proved to be a failure. RMT fully accepts that the performance of the project and engineering managers at Tube Lines has been better than that at Metronet; it could hardly have failed to be so.

  8.  However, the financial environment created by the PPP, and enjoyed by Tube Lines brings into serious question whether the scheme can be considered in any respect to be value for money.

  9.  Your Committee explained in the March 2005 report: "The performance of London Underground" "improvements in facilities and performance are not in proportion to the huge sums of money flowing through the PPP". The report further highlighted that "disregarding the costs of the Jubilee Line extension, central government expenditure in constant terms has increased from £44.1m in 1997-98 to £1,048 in the current financial year (2004-05): an increase of 2,276%".

  10.  In addition to serious value for money concerns, successive Transport for London reports about the performance of London Underground and the PPP brings into some question the claims about the success of Tube Lines.

  11.  The July 2005-06 TfL report London Underground and the PPP indicates that in relation to lost customer hours, Tube Lines performance on the Northern Line was 28% worse than benchmark and 35% worse than bid.[48] The report further reported that Tube Lines had been issued with a Corrective Action Notice due to persistent poor availability performance on the Northern Line.

  12.  The press release launching the 2005-06 report acknowledged that some progress had been made by Tube Lines, particularly in relation to renewals. However, TfL Managing Director Tim O'Toole said "Tube Lines have failed to maintain the Northern Line to the standards we and the PPP contracts demand".

  13.  The Committee will also remember that 1.8 million customer hours were lost on the Northern Line in October 2005 due to repeated tripcock failures. Efforts to resolve the problem were compromised by the multiple interfaces which existed between Alstom, who hold the 25 year PFI contract to maintain the Northern Line rolling stock, Tube Lines and Transport for London.

Administration and beyond

  14.  Metronet entered administration on 18 July 2007. RMT's view on what should happen for the future is clear and has been repeatedly put to both this Committee and Government since the PPP was first mooted. All engineering functions that were transferred to Metronet BCV and Metronet SSL in April 2003 should be returned to public ownership under London Underground.

  15.  RMT is squarely against any attempt to re-let the contracts to the private sector and believe that the PPP Arbiter's initial findings that Metronet could recover up to £1.07 billion are an attempt to make the company a more attractive proposition for potential private sector bidders. On the contrary we support TfL's bid to take over the Metronet contracts and trust that the administrator is able to process the transfer of contracts back to the public sector as soon as is possible. Support for public sector control is overwhelming. An ICM poll of published on 4 September found that 76% of those asked wanted London Underground to carry out the maintenance of trains, track, signals and stations. Only 13% of those asked favoured maintenance being undertaken by a private sector company.[49]

  16.  Returning contracts to LUL would deliver an integrated and accountable management structure. When, in October 2003, Network Rail made their decision to bring maintenance functions on the national network in-house, they identified that benefits would include the consistent application of high standards of rail maintenance across the network, significant efficiency savings and improvements to track-side safety standards. Therefore, in order to deliver similar benefits on the London Underground, reduce fragmentation and deal with unnecessary operational and safety interfaces RMT would also want to see Tube Lines contracts returned to public control. This would also help to deliver savings associated with economies of scale and enable LUL to roll out a network wide procurement programme.

  17.  Finally, returning contracts to the public sector will also deliver security to the Tube Lines and Metronet work-forces, transferred against their will to the private sector in 2002 and 2003. The work-force has seen their final salary pension schemes closed to new entrants and has in addition staved off repeated attempts to transfer fleet engineers and depot managers to Bombardier.

  18.  In terms of funding, there is little doubt that the previous "feast and famine" nature of funding which LUL had to endure led some industry insiders to look to the PPP as a guarantee of funding over a protracted period of time. Key to the transfer of engineering functions back to public ownership will be securing stable, long-term investment from Government. The precise nature of the framework is a matter for discussion between the DfT and TfL. However, RMT would expect funding arrangements to deliver an investment stream that would enable LUL to effectively plan the urgently required major upgrade and renewal of the London Underground, which the PPP has self-evidently failed to deliver.

Industrial Action

  19.  The Committee will be aware that RMT members employed by Metronet took lawful industrial action on 3 September 2007 to secure unequivocal guarantees on job security, transfers and pensions. The action followed a strike ballot which saw a 51% turnout and a 93% yes vote.

  20.  The strike action was suspended late on 4 September after the RMT received assurances from the employer that met our concerns, these were as follows.

  21.  On pensions the original proposal on fund rescue was withdrawn and assurances received that a full scheme rescue was to be placed before the TfL pension trustees' board on 5 September. Following the scheme rescue being put in place, the pension entitlements for the Metronet members of the TfL pension fund will operate entirely as normal as if the administration had not taken place.

  22.  On streamlining, confirmation that there would be no streamlining or transfer of employees from Metronet during administration. A written commitment that if, in the post administration period, any subsequent streamlining proposals were raised, the Code of Practice will be applied and a new consultation process will commence. Any issues of concern regarding the application of the Code of Practice to be resolved through the existing machinery of negotiation.

  23.  On Bombardier transfers, confirmation that no transfers would happen during the period of administration. Assurances that the Code of Practice will be applied for the implementation of any transfers post administration and that a new consultation process will commence.

Conclusion

  24.  RMT welcomes the opportunity to contribute to the Transport Committee's inquiry into the Public Private Partnership and the London Underground. Our key contributions to your inquiry are;

    —  The PPP has proved to be an unpopular and expensive failure

    —  The transfer of risk to the private sector has been wholly inadequate and replicates the experience on the national rail network

    —  The administrator should move quickly to return maintenance functions to the public sector under a responsible and accountable management structure

    —  Returning the contracts to public ownership will provide the current workforce the security and stability required to deliver the upgrade of the London Underground

    —  Support for public ownership is overwhelming

    —  A funding framework should be established the delivers sustained investment levels necessary for the urgently needed upgrade of the Underground

October 2007






47   GLA press release 11 September 2007. Back

48   Figures do not include the 1.8 million lost customer hours caused by the tripcock failures. Back

49   ICM poll, commissioned by RMT. 1,028 Londoners were questioned between 1 and 26 August 2007. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 25 January 2008