Appendix
Introduction
This paper sets out the Government's response to
the Transport Select Committee's report on London Underground
and the Public Private Partnership Agreements (HC 45 published
on 25 January 2008). The Government welcomes the interest that
the Committee has continued to show in the Underground and the
Public Private Partnerships (PPP).
The Underground now carries over a billion passengers
every year and is central to the success of London's economy.
This is approximately the same number as the entire national rail
network in Great Britain, and represents a 65 per cent increase
since 1993. Following years of under-investment and neglect, the
PPP was implemented to deliver the vital maintenance and capacity
upgrades necessary so that the network can cope with this increasing
demand and ensure that London has a Tube system that we can all
be proud of.
Metronet's collapse was a major disappointment to
those with the interests of the travelling public at heart, and
the Government is committed to ensuring that all parties learn
the appropriate lessons for the future. The Government is also
clear that this was predominantly a corporate failure, and that
the structural weaknesses of Metronet led to its own downfall.
The Comprehensive Spending Review 2007 settlement
for Transport for London, details of which were announced on 6
February,[1] provides the
financial framework for the next ten years. This is the first
step towards ensuring that the delivery of the maintenance and
upgrade of the Underground is placed on a stable, long-term footing.
Transport for London is the only party to have tabled a bid for
the Metronet contracts and in the short term the contracts are
likely to pass to their subsidiaries as an interim measure. The
next step is to consider the restructuring of the Metronet contracts
and what offers the best solutions for a lasting structure. A
Steering Group has been established between the Government, Transport
for London and others to develop options for this long-term structure.
It is the Steering Group's ambition to report to the Secretary
of State and the Mayor jointly by Summer 2008. It is clear that
many of the issues identified by the Committee - including risk
transfer, information rights and the role of tied supply chains
- will form key parts of their deliberations. This report is a
welcome and useful contribution to that work.
METRONET'S TIED SUPPLY CHAIN
1. We are not persuaded that Metronet's shareholders
had any inclination to address the problem of the tied supply
chain nor, as the intended beneficiaries of the system, did they
have very much incentive to do so. (Paragraph 16)
There are clearly lessons to be learnt from the structure
that Metronet adopted, and its inability to operate efficiently
and economically in the delivery of the PPP contract requirements.
To date Tube Lines appears to have been successful in delivering
under a more competitive tendering structure, and belatedly Metronet
was moving towards this model.
The Metronet model was perceived as the more traditional
model for PPPs and Private Finance Initiatives (PFIs) but, in
this case, the role of the executive team in separating the shareholder's
interests from the supply chain was not properly developed and
the necessary good corporate governance was not in place. In particular
it was Metronet's inability to act independently of its shareholders
when the deficiencies in its internal arrangements became apparent
that was crucial to its collapse. Following the PPP Arbiter's
Annual Report into Metronet in 2006[2]
some action was taken. This included the appointment of Graham
Pimlott as an independent non Executive Chair in January 2007,[3]
and the decision not to continue to use Trans4m and award the
station modernisation programme through competitive tender to
third party contractors.[4]
But this was too little, too late to make a material difference
to the fate of the company.
2. When the bids for the PPP contracts were being
assessed, it should have been possible for the Government and
London Underground, then under national control through London
Regional Transport, to foresee that Metronet's proposed tied supply
chain model, which guaranteed the lion's share of work to its
parent companies, did not include the necessary safeguards. The
fact that such a management structure was judged to be capable
of efficient and economic delivery seems extraordinary now that
Metronet has collapsed but the ultimate recipients of the money
which was paid to the company have walked away with limited losses.
The Government must not allow this blurring between the roles
of shareholder and supplier in future bids to carry out work by
the private sector. Bids where competitive tendering for subcontracts
is proposed are likely to ensure that the best price is obtained.
(Paragraph 18)
The PPP was thoroughly evaluated before the contracts
were awarded using the public sector comparator. It was objectively
scrutinised by independent observers including the National Audit
Office (who reported in December 2000 on the methodology[5])
and Ernst & Young (who provided an independent review for
the then Secretary of State[6]).
Tied supply chains can, in certain circumstances,
lead to effective delivery. But it is very important that this
structure is suitable for the particular contract, and that the
role of the partners is very clearly distinguished from their
role as contractors. In the case of Metronet this was not apparent,
and with hindsight there was a lack of adequate incentives, policing
and control within the Metronet consortium. This was noted in
the PPP Arbiter's Annual Report in 2006 on Metronet which
identified that the company was unable to demonstrate the high
standards of corporate governance expected, and it could not counter
suggestions of a conflict of interest at shareholder level between
the competing roles of managing the PPP company and providing
services through the supply chain.
RISK BORNE BY INFRACO SHAREHOLDERS
3. The return anticipated by Metronet's shareholders
appears to have been out of all proportion to the level of risk
associated with the contract. The parent companies were effectively
able to limit their liability to the £70 million they each
invested in Metronet at the outset. Had Metronet survived, they
would also have borne the cost of their own inefficiency along
with a minimal amount£50 millionof any other
cost overruns. In the face of this very limited liability it is
difficult to lend any credence to the assertion that the Metronet
PPP contracts were effective in transferring risk from the public
to the private sector. In fact, the reverse is the case.
Metronet's shareholders, had the company been
operated effectively, stood to make quite extravagant returns.
Now that it has failed, it is the taxpayer and the Tube passengers
who must meet the cost. (Paragraph 25)
The PPP agreements struck a balance between the level
of risk transferred to the private sector and that retained in
the public sector. Previously a key risk on major enhancements
on the Underground was cost overruns and inefficient delivery
when the project had been managed by the public sector but delivered
by the private sector. In the past the cost overruns and late
delivery on the Jubilee and Central line projects of £1.4
billion and £200 million respectively were met by the taxpayer.
However, since 2003 London Underground (as part of Transport for
London) has gained a record of delivering projects successfully
both within and outside the PPP (e.g. the redevelopment of Wembley
Park station).
As the National Audit office stated in their report
'Were they good deals',[7]
the PPP contracts offered nominal returns of up to 20 per cent.
This reflected the unique nature of these contracts and was proportionate
to the risks being borne. While this rate is higher than other
PFI/PPP deals at that time, it was comparable to the expected
rate of return on road PFIs, which then came in at around 15 per
cent. However this rate of return to the shareholder was not guaranteed.
It was dependent on the PPP companies delivering the significant
improvements described in the contracts on time and on budget,
and that they met their bid levels of performance. The National
Audit Office surmised that the likely real rate of returns, at
benchmark levels of performance, would be between 10 to 17 per
cent. However, these levels of return were also dependent on efficient
and economic performance. Under the PPP contracts the costs of
inefficient and ineffective work remains with the PPP companies,
regardless of the materiality threshold. But as noted by the Committee
the effectiveness of this risk transfer within the PPP was based
on the continuing solvency of the companies and their ability
to pay for uneconomic and inefficient work.
RISK BORNE BY INFRACO LENDERS
4. In terms of borrowing, the Metronet contract
did nothing more than secure loans, 95% of which were in any case
underwritten by the public purse, at an inflated cost the
worst of both possible worlds. As with the shareholders, what
minimal risk was borne by Metronet's lenders was disproportionately
well rewarded, at the expense of tax- and fare-payers. Public
sector negotiating parties must be hard-headed in their determination
to achieve the best possible terms for financing private sector
delivery organisations. The banks should be required to take on
substantial risk to reflect the large sums of money available.
Additional risk would also increase the incentive for lenders
to look after their debt properly. A proper assessment should
be made of the cost of higher-risk lending against that of guaranteeing
large quantities of private sector debt in the event of a company's
failure. If finance cannot be secured at reasonable terms without
guaranteeing the vast majority of the debt, loans direct to the
Government, which would enjoy the highest credit rating and significantly
lower costs, would seem to be the more cost-effective option.
(Paragraph 29)
The Government will always try to negotiate the best
and most appropriate deal in any contract. But the greater the
level of risk transferred to the private sector, the higher the
price this will normally lead to as the lenders reflect this greater
risk in the returns on offer. The Underground, in particular,
represents a difficult area to clearly allocate and mitigate risk
due to a number of challenges. These challenges include the ageing
and unknown condition of some of its assets, the difficult and
complex environment and the limited working hours available.
Any Government procurement would normally be subject
to the appropriate level of scrutiny beforehand, including following
the Treasury's Value for Money Assessment Guidance.[8]
This process would consider the particular procurement routes
and the financial options available, and wider factors such as
the strategic benefits, the ability to create a partnership and
risk share as part of the value for money evaluations undertaken.
Current best practice by the Treasury also now requires a transparent
funding competition to be held at the preferred bidder stage.
Where the opportunity arises, refinancing can be used to reduce
the costs of private sector debt. In the case of Tube Lines it
was able to refinance its loans once the PPP contract was complete
and this released benefits for both Transport for London and Tube
Lines.
The role of lenders in monitoring Metronet's performance
was very disappointing, and in particular the failure of the relevant
parties to exercise their right to require an Extraordinary Review
once it was clear that Metronet had exceeded their materiality
threshold. The decision of the parties not to use the right to
ask the Arbiter to provide an annual report on Metronet's performance
in 2005, involving waiver by Metronet's funders of the right to
oblige Metronet to seek such a report, also prevented early scrutiny
of the scale of Metronet's difficulties in delivering the contract.
Lenders exposure should, 95 per cent security not
withstanding, have been sufficient to incentivise full scrutiny
of performance. It is not clear at this stage why Metronet was
able to persuade them not to use those rights rigorously. But
this is an area that we, together with Transport for London, London
Underground and the Arbiter, will be considering closely as we
draw lessons from the experience of Metronet for any future delivery
structure.
THE MATERIALITY THRESHOLD
5. Metronet's inability to operate efficiently
or economically proves that the private sector can fail to deliver
on a spectacular scale, although Tube Lines' performance provides
an example of private sector innovation and efficiency. The evidence
is clear: it cannot be taken as given that private sector involvement
in public projects will necessarily deliver innovation and efficiency,
least of all if the contracts lack appropriate commercial incentives.
Future assessments of the comparative value for money of private
sector-managed models for infrastructure projects should not assume
a substantial efficiency-savings factor; a detailed assessment
should be made of the suitability of the proposed structure of
delivery organisations, of bidders' specific expertise and of
the strength of the incentives to efficiency. It is worrying that
the Government's confidence in such savings appears to stem from
a belief that inefficiency is more endemic and irreversible in
the public than the private sector. (Paragraph 32)
The Government is fully aware that the involvement
of the private sector cannot always guarantee success, nor that
they will deliver innovation, efficiency and economy. However
there are also examples when the public sector management of major
projects, including the Underground in the 1990s, has also been
unsuccessful.
It is clear that there is no single procurement model
or formula for success in delivering major and complex projects,
and the appropriate structure must be adopted in each case. In
particular circumstances it is more appropriate that private companies
manage projects and provide services, rather than the public sector.
As noted by the PPP Arbiter's evidence, the private sector can
successfully deliver projects when there are clear outcomes specified
in the contract and the company is free to decide the approach
that it should take to deliver those outcomes. As the Committee
notes, Tube Lines to date has had reasonable success working to
the same contract that was applied to Metronet, though with different
materiality thresholds.
6. It is clear that in negotiating future agreements
the Government should seek as high a Materiality Threshold as
possible in order that public liability is minimised in the event
of an overspend by the private sector. The level of the Materiality
Threshold is crucial in encouraging efficiency and innovation.
If it is set so low as to be, in effect, a cost-plus contract,
this encourages the contractor to hold out for ever-larger payments
over and above what was originally bid. (Paragraph 34)
The materiality threshold was an area that was subject
to serious consideration and negotiation within the PPP, and at
that time was a unique feature of these contracts.
Within the PPP contracts, the PPP companies were
only eligible for efficient and economic costs above the materiality
threshold. Costs, such as those down to its own inefficiency will
always be borne by the PPP companies. The level of the materiality
threshold will be closely linked to the issues of price and risk
transfer. The higher the materiality threshold, the greater risk
that costs will be transferred to the private sector. This is
likely to lead to a higher price being asked for their services.
Any increase in the Tube Lines materiality threshold for the second
period would therefore be priced as part of their payments.
However the Government does not agree that the materiality
threshold is crucial in all contracts to encourage efficiency
and innovation. Many other factors will also play a role in enabling
a supplier to deliver efficiently and with innovation. These include
specified and agreed outcomes and the freedom to operate without
unnecessary constraints or interference.
As the Arbiter discussed with the Committee during
his evidence, a higher materiality threshold will potentially
focus a company's attention on cost overruns as they can reach
a very high level before they can claim. But this raises the risk
that without a suitable mechanism to notify all parties that the
increased costs are occurring, they will then reach an unacceptably
high level before becoming an issue. Increasing the materiality
threshold would therefore only be appropriate if accompanied by
adequate monitoring and safeguards.
In the case of Tube Lines, there is a contractual
mechanism to seek a direction from the Arbiter when it considers
that it has exhausted each £50 million of its £200 million
materiality threshold. To date it has not done so. This mechanism
should draw attention to the fact that cost overruns are being
experienced, and that there is a need for mitigation before the
threshold is breached. But it is dependent on the PPP company
deciding to exercise it, or their lenders requiring them to implement
it. In the second contract period Tube Lines' materiality threshold
will reduce to £50 million, the same as applied to Metronet.
INEFFICIENT COSTS AND THE PRINCIPLE OF THE PPP
7. Now that TfL is in control of the Metronet
contract, there is a danger that private contractors brought in
to upgrade the network will not be alive to its future maintenance
needs, which will be met by TfL. This is not an insurmountable
problem but it means that careful attention must be paid to the
future maintenance of the underground network at a very early
stage in the process of commissioning upgrade work. It might be
that, for part or all of the network, letting combined contracts
for upgrading and maintenance offers the best value for money.
(Paragraph 39)
The Government is fully aware that future maintenance
costs are central to the planning and commissioning of upgrade
work.
A weakness in traditional procurement methods, often
a result of funding constraints, is that public bodies would acquire
assets on a short-term 'cost-only' basis. Any shortcomings in
their construction or design, and longer term issues such as higher
running or maintenance costs, frequently fell to the public sector.
Good industry practice now requires an approach which
considers performance and cost for the whole asset life, including
design, construction, maintenance and its eventual replacement.
This will be a key consideration in any future arrangement. Whether
privately or publicly managed and financed the future structure
will need to ensure that it delivers assets that have the best
whole life cost, i.e. balancing the cost of design and delivery
with the on-going maintenance and operating costs to minimise
the total cost of the asset over its entire working life. This
enables the delivery of innovative, efficient and economic solutions
that meet the operational needs of the Underground. The PPP was
built on the basis of whole life decision making, and this approach
is one that must be taken forward whichever structure is adopted
in the future.
VALUE FOR MONEY
8. The Government should not enter into any further
PPP agreements without a comprehensive and accurate assessment
of the level of risk transfer to the private sector and a firm
idea of what would constitute an appropriate price for taking
on such a level of risk. If it is not possible in reality to transfer
a significant proportion of the risk away from the public purse,
a simplerand potentially cheaperpublic sector management
model should seriously be considered. (Paragraph 45)
The Government does not enter any major contract
without first fully assessing the level of risk transfer and the
appropriate price level for the services being provided. This
will be balanced with value for money considerations. Mechanisms
such as the public sector comparator are used to ensure that the
Government chooses the best value for money deal available. However,
it is recognised that this is not an exact science and once the
contract is working there will always be other factors and variables
that alter the way that the contract performs.
It is inevitable that there will be continued private
sector involvement in the improvement and maintenance of the Underground
at some level. There are no circumstances in which London Underground
would not need to call on appropriate, contracted specialist skills
and experience. The key question will be how these are best harnessed
within an effective contractual framework. There are a wide range
of options being considered within the Steering Group, and these
include London Underground having a greater management control
than under the PPP arrangements. As noted above it is also essential
that any structure allows the enhancement and maintenance of the
Underground to be delivered in an innovative, efficient and economic
way that provides value for money to both the fare and tax payer,
and that the principle of whole life asset management is maintained.
REPORTING ON THE PERFORMANCE OF THE INFRACOS
9. We consider that the gathering and publication
of information by the PPP Arbiter will generally tend to benefit
all interested parties: London Underground as client, the Infracos
as suppliers and the public as users. The Government should also
find such information useful for assessing the benefits and costs
of similar proposals in the future. There is some evidence to
indicate that an earlier review could have mitigated the impact
of Metronet's collapse, if not averted it entirely. However, it
is important that any reporting process is seen as neutral and
is designed to provide the information that both the Infracos
and London Underground require to address performance issues and
to prepare for Periodic Review. It would have been wiser to make
the annual review an automatic process rather than one which had
to be initiated by a party to the contract. (Paragraph 55)
The issue of independent reporting on the performance
of the PPP companies and the PPP as a whole will form part of
the detailed considerations in identifying and taking forward
a preferred structure, including the role and function of an arbiter
under new arrangements.
The Government considers that the statutory appointment
of an independent arbiter for the PPP contracts has had benefits
to all stakeholders in the Underground. The Government also recognises
that there are lessons to be learnt from the reporting of Metronet
under the PPP contracts, and in particular from the lack of a
Metronet Annual Report for 2005 which could have indicated problems
earlier. But, as recognised by the Committee, it may not have
avoided Metronet's eventual collapse.
Under a long-term business model, with a 30 year
view, we must also consider whether an automatic annual review
is the most appropriate mechanism. The materiality threshold,
if properly monitored and enforced, can be subject to a regular
review to determine whether it is likely to be breached. This
breaching could, therefore, be the test of whether the business
is performing.
The cost of any independent reporting structure must
also be weighed up against the benefits in delivering improvements;
an alternative option is that of clarifying and confirming London
Underground's rights for information under the existing contract
structure.
10. Though we have not sought to evaluate Tube
Lines' performance in the course of this inquiry, we believe that,
in principle, annual reports on Tube Lines would be just as valuable
as it could have been in the case of Metronet. An independent
report from the Arbiter in 2008 on the performance of Tube Lines
to date would be timely, particularly in the absence of a 2006-07
London Underground report on the performance of the Infracos.
(Paragraph 56)
See answer to Recommendation 11.
11. We recommend that a mechanism be put in place
to allow the PPP Arbiter to report annually on the performance
of the Infracos, including Tube Lines, whether or not he is called
on to do so; this might require the granting of additional powers
to the Arbiter under the Greater London Authority Act 1999. (Paragraph
57)
The Government will ask the relevant parties, in
particular London Underground and Tube Lines, to consider the
matter of an annual report for Tube Lines, both in 2008 and in
future years. Such a report is not currently part of the PPP,
so a mandatory requirement could only be created through amendment
of the contract. This would require Tube Lines' agreement to change
established contractual provisions.
An alternative is a voluntary agreement by the parties
asking for guidance in the form of an annual review on whether
Tube Lines' performance was efficient and economic. If both London
Underground and Tube Lines agreed to seek such a report from the
Arbiter, he would be required (under the terms of the Greater
London Authority Act 1999) to prepare it. If only one party requested
it, he would have discretion as to whether or not to prepare it.
Under any voluntary arrangement it would be possible for either
party to withdraw from the reference if they so decided.
London Underground has reported annually on the performance
of the PPP since it was implemented, and it is anticipated that
this will continue.[9]
12. As long-term arrangements for upgrading the
Tube are devised, the Government should ensure that there is a
mechanism to guarantee independent reporting of progress and value
for money, no matter what delivery vehicle takes the place of
Metronet's PPP Agreements. (Paragraph 59)
The Government recognises the value that the independent
reporting of the Arbiter has brought to the PPP contracts, and
this will continue for Tube Lines. No decision has been taken
on the long-term arrangements for the Metronet contracts. The
Secretary of State's present intention, as set out in the Memorandum
of Understanding[10]
with Transport for London, is that the role of the PPP Arbiter
should continue upon any transfer of the Metronet contracts to
Transport for London nominee companies, and that it also remains
for the permanent structure. Whatever the new structure of Metronet,
the Government considers it should be subject to at least the
same level of scrutiny, transparency and reporting as Tube Lines.
THE PERFORMANCE OF LONDON UNDERGROUND
13. A contractual arrangement which fails to incentivise
efficiency in the private sector and at the same time fails to
deter poor planning, lack of forethought and goldplating in the
public sector is one which is pretty much useless. Metronet alleges
that part of its overspend is a consequence of decisions by London
Underground, such as changes to the specification of ongoing works.
We recommend that in the future the Arbiter, alongside reporting
the performance of the Infracos, reports the effectiveness of
London Underground as client during the modernisation of the Tube
network. (Paragraph 63)
Responsibility for London Underground rests with
Transport for London and the Mayor of London under the Greater
London Authority Act 1999. London Underground, through the Mayor,
must be accountable to London voters in the first instance, and
to their own audit and accountability processes to ensure that
value for money is achieved on the money spent. Under the terms
of the funding provided to Transport for London, they remain
accountable to the Secretary of State for Transport and Parliament
It may be possible under the existing legislation
and the PPP framework for the Arbiter to report on the performance
of London Underground in relation to the PPP agreement, if that
is what the parties sought and where the Arbiter concludes that
such reporting is consistent with the duty placed on him by section
231 of the Greater London Authority Act 1999. For example, this
could be valid if it could be demonstrated that it was beneficial
in helping the PPP contracts to run more efficiently and economically.
The Government disagrees with the proposal that the
Arbiter should report more generally on the effectiveness of London
Underground within the modernisation of the network outside the
PPP regime.
THE EXTRAORDINARY REVIEW
14. As with the annual report, there is evidence
that had the Extraordinary Review been initiated at an earlier
stage, it might have mitigated the worst effects of Metronet's
failure. We recommend that, for future PPP Agreements, the Government
extend the power to trigger an Extraordinary Review to both contract
parties, rather than only the Infracos. Such a change could reduce
the possibility that an overspend would be allowed to get as far
out of control as it did in the case of Metronet. (Paragraph 66)
This is an issue that will be examined in the development
of the long-term structure.
The Government recognises that in the case of Metronet
the contractual mechanisms regarding the Extraordinary Review
did not work as well as intended. For Metronet the materiality
threshold had clearly been breached but this was not acted upon,
and the Government agrees that an earlier commencement would have
had benefits, but that it may not have been sufficient to avoid
Metronet's eventual PPP administration.
There are certain advantages in the proposal to have
reciprocal arrangements to call an Extraordinary Review in any
future contractual arrangements. This includes the option of preventing
one party having the right to waive an Extraordinary Review when
the materiality threshold has been breached.
15. The uncontrolled spiral of cost overruns,
without any assessment being made of its causes or of the respective
liabilities of the parties to the contract, must never be allowed
to happen again. A mechanism similar to that which is built into
the Tube Lines contract to ensure an early examination of any
cost increases should be included as a matter of course in any
future contracts. (Paragraph 69)
The Tube Lines PPP contract includes provision that
enables them to seek a direction from the Arbiter when they have
exceeded each £50 million stage within their materiality
threshold of £200 million, during the first period of the
PPP contract up to 2010. This enables the Arbiter to asses whether
their cost overruns within the PPP contract have been efficient
and economic. This should provide a very clear signal of whether
Tube Lines is exceeding its projected costs, and whether it is
doing so in an efficient and economic way. After 2010 the Tube
Lines materiality threshold drops to £50 million, the same
as Metronet in Period 1, therefore it will be important that London
Underground and the PPP Arbiter are provided with sufficiently
detailed information to understand any movement in Tube Lines'
costs.
Clearly the materiality threshold mechanism has potential
benefits, and where appropriate the Government will consider including
suitable provisions in other contracts. But each contract needs
to be assessed separately and will be subject to its own negotiations.
As explained earlier, it would be inappropriate for this type
of provision to be routinely included in every Government contract.
While it is sensible for the Government to monitor
whether a private sector company is performing efficiently and
economically within their public sector contracts, the primary
responsibility for this duty must continue to remain with the
Company's own board, shareholders and funders.
COSTS TO THE PUBLIC
16. We recommend that the Government, as a matter
of urgency, make a full assessment of the additional costs that
have been incurred as a result of the failure of Metronet
including the cost of work that has been inefficiently undertaken
and the cost of administration. The Secretary of State should
then come to the House to make a statement on what proportion
of these costs are to be met by central Government and what proportion
she expects residents of London and Tube passengers to pay.
The Government should also consider its contribution
to efficient increases in costs as a result of the unknown condition
of the infrastructure, in order that London Underground is not
forced significantly to reduce the scope of the upgrade programme
during the second Review Period from 2010. (Paragraph 79)
The Government announced to Parliament on 6 February
the settlement for Transport for London under the Comprehensive
Spending Review 2007. This recognised that Transport for London
would need to manage the costs of Metronet in administration and
the PPP contracts up to 2017/18, subject to certain conditions
as outlined in the Settlement Letter[11]
and Memorandum of Understanding. This settlement underlines the
Government's commitment to deliver the transport investment central
to our continued growth and prosperity.
The Comprehensive Spending Review 2007 settlement
included provision regarding the 'Put Option' that was exercised
by Metronet's lenders on 5 February 2008. This related to borrowing
by the Metronet companies to finance work that had already been
undertaken on the maintenance and renewal of the Underground network
under the PPP contracts. The Government made £1.7 billion
available to Transport for London for it to satisfy the terms
of the Put Option. But this was not 'new' money, nor was it a
new cost to the taxpayer and it was already reflected in planned
public spending. A helpful analogy is to say that this scenario
is not dissimilar to someone paying off their mortgage early.
The extent to which Metronet's delivery had slipped
behind their spending, and therefore the scale of any long-term
costs, will only become clear when London Underground and
Transport for London have been able to review the position that
Metronet reached in its works programme, up to its PPP administration
on 18 July 2007. As part of the Steering Group's assessment of
future structures for the Metronet contracts it is important that
we analyse what factors contributed to Metronet's failure. But
as Tim O'Toole emphasised in his evidence, there is limited value
in over-analysing Metronet's past performance. Our main concern
is now learning the lessons from Metronet's failure and moving
forward to deliver a structure that provides the necessary improvements
for the London Underground in an efficient and economic manner.
It is worth noting that not all of the costs of Metronet's
failure will fall on the public purse. Three of Metronet's shareholding
companies (Atkins,[12]
Bombardier[13] &
Balfour Beatty[14]) have
already written off £302 million due to the failure of Metronet.
We understand that the two remaining shareholders, Thames Water
and EDF Energy, have not made any announcements but they are also
believed to have written off their equity stakes.
At the start of the PPP contracts, London Underground's
asset knowledge was not complete, and future costs could not be
properly predicted. The PPP contracts require that all assets
whose condition is unknown are surveyed during the first period,
however 25 per cent of civil assets are still to be surveyed.
Thus the true cost of any required work will not be fully understood
until the Periodic Review is completed.
The future structure for the Underground will be
based on the most efficient and economic way of delivering the
works required by London Underground within its funding constraints.
Government has already indicated how much grant it intends to
provide Transport for London to 2017/18, subject to certain provisions
on further future costs. It is then for Transport for London to
allocate this money between modes such as the Underground, Buses,
Overground and to deliver Crossrail. Additional funding that is
provided by fare revenue, its own prudential borrowing and local
taxation is a matter for Transport for London and the Mayor, and
not central Government. The Comprehensive Spending Review 2007
settlement gives Transport for London the financial framework
needed to manage Metronet's administration, move toward a more
stable long-term footing and continue the work to maintain, renew
and upgrade the Underground.
17. We hope that, in its discussions with Transport
for London as to the future of Metronet's PPP Agreements, the
Government makes full use of the Arbiter's analysis for the partial
Extraordinary Review of Metronet BCV and for a potential Extraordinary
Review of Metronet SSL, and that his insights are utilised to
minimise the chance that further unexpected and wasteful costs
to the public purse might be incurred. (Paragraph 82)
The Arbiter has already contributed to the Steering
Group's work regarding the future structure for the Underground,
and in accordance with the Memorandum of Understanding his views
will continue to be solicited as its work progresses. As an independent
party, his analysis is a valuable contribution to the work of
the Steering Group, and ensures that the scrutiny of Metronet
within his Annual Report 2006 and Extraordinary Review of Metronet
BCV[15] are fully utilised.
EMPLOYEE SAFETY
18. To maintain the highest standards of safety
for employees in the longer-term, the Government must work with
Transport for London and the unions to identify existing communication
deficiencies and ensure that the future structure of the contracts
does not contain inherent safety weaknesses. Where it is necessary
for employees of different organisations to work together, the
utmost effort must be made to ensure the clarity of procedures
for reporting safety concerns. (Paragraph 87)
The implementation of this recommendation is a matter
for London Underground and the PPP Companies, but employee safety
is always a top priority for all stakeholders in the Underground.
The Office of Rail Regulation (ORR) is responsible
for enforcing health and safety legislation on London Underground.
ORR already undertakes work that looks at the safety of contractors
on the Underground, including the arrangements for mutual co-operation,
by carrying out inspections and investigations and providing advice
and guidance on health and safety related matters.
The Government will continue to encourage those organisations
with direct responsibility for employee safety to ensure that
the highest standards are applied to the network, including the
procedures for reporting safety issues. This will remain so in
any future arrangements for the Underground. The Committee will
have noted the supplementary evidence provided by Tube Lines that
indicated that their employees were four times less likely to
suffer an injury in their workplace than they were at the time
of Transfer. This is backed up by Tube Lines' own surveys that
state that in 2005 92 per cent of employees felt safe in their
jobs (increased to 95 per cent in the 2007 survey) and 86 per
cent felt that health and safety is a top priority within the
company (increased to 90 per cent in the 2007 survey).[16]
PASSENGER SAFETY
19. During the transition of Metronet's ownership
from its shareholders to Transport for London and for the duration
of Transport for London's stewardship of the Infracos, as well
as in the longer-term under whatever vehicle is chosen to deliver
the upgrades, passenger safety must be the primary concern of
everyone who is involved.
A key role for the Government in its discussions
with the Mayor and Transport for London will be to ensure that
future contracts incentivise the actions that are necessary to
guarantee the highest standards of safety on the network. (Paragraph
92)
Passenger safety is of paramount importance to all
stakeholders in the Underground. London Underground retains overall
responsibility for passenger safety on the network and ORR regulates
health and safety on the Underground. As part of its role, ORR
is carrying out additional monitoring of safety during the transition
period for the Metronet PPP companies and will investigate and
take appropriate action if there is any evidence to suggest deteriorating
performance.
The current PPP contracts already incentivise the
PPP companies to improve safety. It is a legal requirement that
London Underground has appropriate safety management systems and
procedures in place to ensure staff and customer safety, and that
these have been accepted by ORR. Under the PPP arrangements London
Underground monitors the PPP companies' safety performance, audits
their compliance with their own contractual safety cases and London
Underground's own standards, and agrees an annual Safety Improvement
Programme.
The Underground is a very safe mode of transport
and its safety record compares favourably with other Metro systems
of a similar age, particularly in key areas such as derailments,
collisions and platform-train interfaces.[17]
Customer injuries average 1½ persons per 10 million journeys,
and the majority of fatalities on the network are due to trespass
or suspected suicides,[18]
rather than equipment or systems failures. The future arrangements
for the Underground will continue to build on this safety record.
CONCLUSION
20. The Government should bear the Metronet debacle
in mind if and when its parent companiesAtkins, Balfour
Beatty, Bombardier, EDF Energy, and Thames Water next come
to bid for publicly-funded work. (Paragraph 95)
The letting of government contracts is subject to
procurement law requirements. Within these constraints one of
the issues that the Department will continue to consider is the
relevant experience of all potential bidders, appropriate to the
particular requirement at the time.
21. The Government should remember the failure
of Metronet before it considers entering into any similar arrangement
again. It should remember that the private sector will never wittingly
expose itself to substantial risk without ensuring that it is
proportionally, if not generously rewarded. Ultimately, the taxpayer
pays the price. (Paragraph 96)
There are clearly lessons to be learnt by all parties,
including the Government, from the collapse of Metronet and its
PPP administration. The Government is determined to learn these
lessons and they will be considered by the Steering Group and,
where appropriate, taken forward in the new structure for the
Underground. But the primary cause of Metronet's demise was its
failure to operate efficiently and economically. This was borne
out by the independent PPP Arbiter's Annual Report into Metronet
in the Autumn of 2006, and was noted in both the Arbiter's and
others evidence to the Committee. The Metronet failure was primarily
the responsibility of that company and its shareholders, rather
than the structure of the PPP. Tube Lines' performance to date
is evidence of private sector innovation and efficiency.
22. If the Government is again tempted by a seemingly
good deal from the private sector, it should recall Metronet's
pathetic under-delivery and the deficiencies in the contracts
that allowed it to happen. We recommend that the Government publishes
a candid analysis of the events preceding Metronet's collapse
and its consequences, both in terms of increased costs to the
public and delays to the work programme. (Paragraph 97)
The Government is not a party to the PPP contracts
and does not have access to all the relevant and detailed information
that such an analysis would require. A number of organisations
have also announced their intention to produce reports or already
published them into the failure of Metronet. This includes the
Committee's report, the PPP Arbiter (with his Annual Report 2006
and other documents relating to the Metronet Extraordinary Review)
and the National Audit Office. Together these will provide a full
and wide ranging analysis of the collapse of Metronet. The Government
does not believe that another report would add any value to this
process.
23. Whether or not the Metronet failure was primarily
the fault of the particular companies involved, we are inclined
to the view that the model itself was flawed and probably inferior
to traditional public-sector management. We can be more confident
in this conclusion now that the potential for inefficiency and
failure in the private sector has been so clearly demonstrated.
In comparison, whatever the potential inefficiencies of the public
sector, proper public scrutiny and the opportunity of meaningful
control is likely to provide superior value for money. Crucially,
it also offers protection from catastrophic failure. It is worth
remembering that when private companies fail to deliver on large
public projects they can walk awaythe taxpayer is inevitably
forced to pick up the pieces. (Paragraph 98)
The Government is fully aware that the involvement
of the private sector cannot always guarantee success, nor that
they will always deliver innovation, efficiency and economy. However
there are also many examples when the public sector management
of major projects has also been unsuccessful.
It is clear that there is no single procurement model
or formula for success in delivering major and complex projects,
and the appropriate structure must be adopted in each case. In
particular circumstances it is more appropriate that private companies
manage projects and provide services, rather than the public sector.
As noted by the PPP Arbiter's evidence, the private sector can
successfully deliver projects when there are clear outcomes specified
in the contract and the company is given such flexibility to what
approach it should take to deliver those outcomes. As the Committee
notes, Tube Lines so far has had success working to the same contract
that was applied to Metronet, though with different materiality
thresholds.
24. Finally, now that the Government is considering
the future of the Underground upgrade programme, it should prioritise
transparency and clarity to taxpayers and ensure that any future
contracts result in clear accountability to national or regional
Government, thereby providing the public with the opportunity
of applying sanctions in the event of poor performance. (Paragraph
99)
The Government is working closely with the Mayor
and Transport for London to establish the appropriate long-term
structure to deliver the essential maintenance and enhancement
of the Underground, and the Steering Group will be reporting in
the Summer 2008.
The Central and Jubilee line projects taught us that
previously London Underground in the 1990s did not have the in
house capacity to deliver major enhancements efficiently or effectively.
The Metronet experience is a reminder that effective corporate
governance is not inherent in private sector companies.
Looking forward, the best value for the taxpayer
is likely to continue to come from tasking organisations with
what they are best at, within effective governance regimes and
with appropriate incentives. It would be wrong to assume that
the only option will be to adopt the old, wholly public sector
approach and not consider all the relevant alternatives.
1 Written Ministerial Statement by the Secretary of
State for Transport on Long term Funding for Transport for London,
6th February 2007; http://www.publications.parliament.uk. Back
2
The PPP Arbiter's 'Annual Metronet Report 2006'; http://www.ppparbiter.org.uk Back
3
Metronet Rail news release: Appointment of Graham Pimlott as non-executive
Chairman, 14 December 2006; http://www.metronetrail.com. Back
4
Metronet Rail news release: Metronet awards first six station
projects outside of its supply chain, 23 February 2007; http://www.metronetrail.com. Back
5
National Audit Office Report: The Financial Analysis for the London
Underground Public Private Partnerships, 15 December 2000; http://www.nao.org.uk/publications/index.htm. Back
6
Ernst & Young Report; London Underground PPPs Value for Money
Review, Independent Review for the Secretary of State, 5 February
2002; http://www.dft.gov.uk/pgr/regional/local/lu/modernisation/ppps/. Back
7
National Audit Office report, 'London Underground PPP: Were they
good deals?', June 2004; http://www.nao.org.uk/publications/nao_reports/03-04/0304645.pdf. Back
8
Her Majesty's Treasury Value for Money Assessment Guidance, November
2006; http://www.hm-treasury.gov.uk. Back
9
London Underground and the PPP: Data Summary 2006-07 was published
instead of the Annual Review 2006-07; http://www.tfl.gov.uk/assets/downloads/LU-PPP-report-data-summary-06-07.pdf Back
10
Memorandum of Understanding between the Department for Transport
and Transport for London on Metronet, issued on October 4th 2007,
http://www.dft.gov.uk/pgr/regional/policy/lt/metronetmou.pdf. Back
11
Comprehensive Spending Review 2007, Letter of 4 October 2007 from
the Department for Transport to Transport for London, http://www.dft.gov.uk/pgr/regional/policy/lt/tflsettlementletteroctober.pdf. Back
12
Atkins 2007 Annual Report & Accounts; http://www.atkinsglobal.com. Back
13
Bombardier Second Quarterly Report, 31 July 2007; http://www.bombardier.com. Back
14
Balfour Beatty Interim Report 2007; http://www.balfourbeatty.com. Back
15
PPP Arbiter's Guidance and Directions; http://www.ppparbiter.org.uk/output/page35.asp. Back
16
Figures for the 2007 survey have been provided by Tube Lines. Back
17
Community of Metros (CoMET) Benchmarking Report, February 2007. Back
18
Office of Rail Regulation's 'Railway Safety Statistical Report
2006' reported 19 suicides and trespasser deaths out of 22 fatalities
on the network, their 'Annual Report on Railway Safety 2005' reported
24 out of 28 respectively; http://www.rail-reg.gov.uk/index.php. Back
|