2001
| | |
14 March
|
Dungeness A
|
Carbon dioxide leak from high pressure pump on carbon dioxide plant
|
26 October
|
Hinkley Point B
|
Cooling water leak from turbine alternator 7 excitor
|
3 November
|
Heysham 1
|
Cooling water leak to turbine generator
|
3 December
|
Rosyth
|
Loss of coolant from primary circuit clean-up resin column
|
| | |
2002
| | |
6 February
|
Oldbury
|
Reactor 2 cooling water pipe failure
|
27 February
|
Hinkley point B
|
Leak of tritiated water from reactor bypass gas plant
|
31 March
|
Torness
|
Carbon dioxide leak from refuelling machine
|
14 May
|
Sizewell B
|
Indication of historic leak of primary coolant from control rod drive mechanism housing
|
20 July 2009 : Column 1024W
26 June
|
Hunterston B
|
Leak of carbon dioxide from gas bypass plant
|
26 November
|
Hunterston B
|
Condenser leak on turbo generator 7
|
18 December
|
Hinkley point B
|
Leak of tritiated water from break tank
|
25 December
|
Dungeness B
|
Steam leak on reactor
|
| | |
2003
| | |
31 January
|
Heysham 2
|
Steam leak on boiler half unit valve
|
19 February
|
Heysham 1
|
Release of cooling water from buffer store tube vent valve
|
1 March
|
Dungeness B
|
Carbon dioxide leak from flange on clean side of reactor gas pressurising unit
|
16 March
|
Hunterston B
|
Steam leak in the supply pipe work to Unit 7 main boiler feed pump
|
3 April
|
Hunterston B
|
Clean carbon dioxide leak from failed bursting disc on gas bypass plant on Reactor 3
|
13 May
|
Dungeness A
|
Leak from LP feed water pipe to R1 boilers
|
15 July
|
Heysham 1
|
Carbon dioxide leak from pressure transducer on refuelling machine
|
27 July
|
Dungeness B
|
Leak of water from base of flask E97
|
14 August
|
Wylfa
|
Leak from a Boiler 1 feed water line flange
|
29 September
|
Dungeness A
|
Clean carbon dioxide leak from pipe work in R1 ponds area
|
7 December
|
Heysham 1
|
Leak of water from two failed joints in fuel route emergency cooling water 'A' main
|
| | |
2004
| | |
2 February
|
Oldbury
|
Leak from LF feed main stub pipe
|
30 March
|
Sizewell A
|
Carbon dioxide release through failed vacuum pump oil separator
|
31 March
|
Hunterston B
|
Leak from auxiliary cooling water pipe flange
|
7 April
|
Hunterston B
|
Carbon dioxide release from the gas bypass plant autoclave room vacuum pump
|
14 April
|
Hartlepool
|
Leak through crack in heat exchanger flange
|
19 April
|
Heysham 1
|
Carbon dioxide leak from west storage plant
|
5 May
|
Hunterston B
|
Cooling water leak from generator yellow phase enclosure
|
11 May
|
Hinkley Point B
|
Carbon dioxide leak from storage tank
|
16 May
|
Hinkley Point B
|
Leak from Reactor 4 condensate system
|
9 June
|
Hartlepool
|
Leak of tritiated water from radioactive effluent treatment plant
|
20 July 2009 : Column 1025W
13 June
|
Torness
|
Carbon dioxide leak from storage tank
|
14 July
|
Sellafield
|
Leaking water from flask nappy in B205
|
14 July
|
Hunterston B
|
Carbon dioxide leak from storage tank bursting disc
|
21 July
|
Hinkley Point B
|
Carbon Dioxide leak from blowdown route
|
25 July
|
Heysham 1
|
Carbon Dioxide found in pressure vessel tendon box
|
3 August
|
Heysham 2
|
Carbon Dioxide leak from ring main
|
9 September
|
Hartlepool
|
Leak in low pressure back up cooling system pipe work
|
18 November
|
Heysham 1
|
Alternator hydrogen coolant leak
|
26 November
|
Heysham 2
|
Oil leak from transformer
|
| | |
2005
| | |
1 January
|
Heysham 2
|
Steam leak on Turbine Generator 7
|
5 February
|
Hinkley Point B
|
Carbon dioxide leak from tank
|
19 February
|
Hinkley Point B
|
Carbon dioxide leak from tank
|
25 February
|
Torness
|
Carbon dioxide leak through in-service inspection penetration
|
15 March
|
Torness
|
Carbon dioxide leak from ring main
|
25 June
|
Dungeness A
|
Carbon dioxide leak from main CO2( )plant
|
4 July
|
Sellafield
|
Damp patch discovered adjacent to B30 pond wall
|
25 July
|
Oldbury
|
Steam leak through thermocouple pocket of Boiler 4 on Reactor 1
|
4 August
|
Hinkley Point B
|
Carbon dioxide leak from vaporiser valve
|
30 October
|
Dungeness A
|
Carbon dioxide leak through failed isolation valve to pressure gauge
|
| | |
2006
| | |
30 January
|
Sellafield
|
Leak of dosed cooling water from B832 cooling tower
|
18 February
|
Sellafield
|
Leak of pond water through expansion joint above the stainless steel seal in B310 AGR storage pond
|
24 March
|
Hunterston B
|
Carbon dioxide leak in pipe trench
|
11 September
|
Hinkley point B
|
Carbon dioxide leak from supply pump
|
23 September
|
Hartlepool
|
Alternator hydrogen coolant leak
|
26 September
|
Hartlepool
|
Fracture of emergency cooling water main
|
2 October
|
Dungeness B
|
Auxiliary cooling water pipe work leak
|
15 October
|
Sizewell A
|
Steam leak from Turbine Alternator 1
|
18 November
|
Heysham 2
|
Steam leak from Reactor 7
|
20 July 2009 : Column 1026W
| | |
2007
| | |
7 January
|
Sizewell A
|
Fracture of pond recirculating water system pipe work
|
18 January
|
Sellafield
|
Waste Vitrification Plant electrical inductor cooling water leak
|
1 March
|
Hinkley Point B
|
Carbon dioxide leak outside plant room
|
26 March
|
Dungeness B
|
Carbon dioxide leak in reactor basement
|
1 June
|
Hunterston B
|
Leak from condensate booster pump
|
2 June
|
Heysham 2
|
Leak in low pressure feed heater pipe work
|
18 July
|
Dungeness B
|
Leak of tritiated water Identified
|
19 September
|
Hartlepool
|
Leak of pressure vessel cooling water identified on boiler closure unit
|
28 September
|
Hunterston B
|
Steam leaks in high pressure gland pipe work
|
26 September
|
Dungeness B
|
Carbon dioxide leak from storage tank
|
27 October
|
Oldbury
|
Carbon dioxide leak from fuelling machine
|
| | |
2008
| | |
19 February
|
Oldbury
|
Carbon dioxide leak from storage tank
|
20 February
|
Torness
|
Carbon dioxide leak from gas bypass plant
|
26 June
|
Heysham 2
|
Steam leak in gland steam drain line
|
26 July
|
Heysham 1
|
Carbon dioxide leak from storage tank
|
7 October
|
Wylfa
|
Carbon dioxide leak from storage tank
|
23 December
|
Torness
|
Carbon dioxide leak from valve in the fuel machine standby CO2 coolant supplys
|
| | |
2009
| | |
24 April
|
Hartlepool
|
Hydrogen leak from Unit 2 alternator frame
|
26 May
|
Heysham 1
|
Turbine cooling water leak
|
28 May
|
Hinkley Point B
|
Pressure vessel cooling water leak from Reactor 4 sump
|