London 2012: Lessons from Beijing - Culture, Media and Sport Committee Contents


Examination of Witnesses (Questions 125-139)

LORD COE, MR PAUL DEIGHTON, MR JOHN ARMITT AND MR DAVID HIGGINS

9 DECEMBER 2008

  Q125 Chairman: This morning's hearing is a further part of the Committee's inquiry into preparations for the 2012 Olympic Games. We have a lot of ground to cover in the course of this morning's session. To start the first part, I welcome Lord Coe, chairman, and Paul Deighton, chief executive, of the London Organising Committee of the Olympic and Paralympic Games and John Armitt, chairman, and David Higgins, chief executive, of the Olympic Delivery Authority. Now that we are approximately half-way between the point at which we were awarded the games and the event taking place perhaps I may ask what progress has been made and whether or not we are on schedule.

  Lord Coe: Thank you, Chairman. We have 1,326 days and 189 Wednesdays to go to the opening ceremony. I am delighted to be able to report to you that we are on schedule. Before making my remarks it would be remiss of me if I did not compliment the extraordinary performances this year of Team GB, Paralympic and Olympic, which I think all of us around this table would agree have given the whole project an exceptional platform for the next four years. Beijing was centre stage for a large part of our nation, for the organising committee and our learning. We had 100 observers there across all operational areas. This year very good progress has been made not just in Beijing learning which is central to the way we drive the project forward. We had to deliver two ceremonies in Beijing in the Olympic and Paralympic fields. We made it very clear when bidding that we were doing so for a Games in the new era of legacy and sustainability, and you certainly know the views of our teams on that. This is probably a more appropriate model now given the economic challenges that lie ahead than we recognised when bidding in Singapore. Over the past year we have delivered the launches of the Cultural Olympiad, our educational programme and our sustainability plan, and we have brought nine world-class companies to the table as business partners going forward. Hindsight is a wonderful thing but I am glad we started that process extremely early. We can genuinely say we are on track and on budget and the real task going forward is to seek efficiencies in the planning areas in everything that we do. Perhaps Mr Armitt can update you on Olympic Park progress.

  Mr Armitt: Chairman, 2008 has been a good year for us and has seen strong delivery on site. We have started on schedule and we have seen the successful completion of two major projects. Today we shall announce completion of demolition of the 52 pylons that run across the site. Those overhead power cables are now in tunnels beneath the site. That was a very unusual and complex project costing £250 million which was completed on time and budget. A couple of weeks ago we announced that the Weymouth facility was complete for the sailing. If you go to Olympic Park today the stadium steel is visible from a long distance away. We have also started work on the aquatics centre and major infrastructure across the project. It is worth remembering that for all the work we do on the Olympic site 75p in every pound represents major regeneration and long-lasting benefits to London. There are always challenges. Last year when we were in front of you we were concerned about contamination, obtaining the site and site clearance. That is all successfully behind us now. Today we face things like the credit crunch and the impact that has had on the private finance required for the Olympic Village and the IBC and MPC media centres, but we have not allowed that to slow us down and construction work has started. In the mean time negotiations continue to try to find an acceptable financing package from the private sector. I just remind everybody that there are lots of benefits to the work we are doing. A lot of contracts are going to many companies across the country. Local people who were previously unemployed benefit from jobs on the site. We are also introducing a good deal of training for people in the area, so there are jobs for unemployed people and training and business opportunities across the UK. There is still some way to go. We have three years of very intensive activity, but we believe we have got off to a good start and have good foundations in place.

  Q126  Mr Evans: Do you foresee having to draw down on any further contingency funds in the coming months and, if so, for what?

  Mr Armitt: The contingency is largely in two parts: £1 billion of what is called programme contingency and £1 billion of funders' contingency. As to the former so far we have drawn down £21 million of the £1 billion and we are 25% through the work, so there has not been too much drawdown. In the past I have always made the point that given the nature of the works, life being what it is, we would expect to expend the bulk of that first £1 billion. The second £1 billion is the funders' contingency which was set aside for unexpected events. So far the most unexpected event has been a problem with financing the Olympic Village, and in order to start construction the government has released £95 million for the first six months which will take us through to the spring when we hope to have financing in place. If not, it will require a further drawdown of the funders' contingency, but overall I am confident that we shall be able to complete the whole project within the overall budget that has been set.

  Q127  Mr Evans: There have been changes in circumstances over, say, the past six to eight months. You mentioned "credit crunch" but to the rest of the world it is "recession". Sadly, there have also been terrorist incidents in Mumbai and banks and firms have gone bust. I am just wondering whether anything has happened over the past six to eight months that have caused any expenditures or concerns that you did not foresee.

  Mr Armitt: No. So far the release of contingency has been very much under control. Apart from the issues around financing we have not had any significantly unexpected events. That is why we have had to release only a small proportion of the programme contingency so far. Inflation in the construction industry has remained fairly high in the past 12 months. Some statistics that I saw only a couple of days ago showed a 7% increase over the past year, but clearly there has been a slowdown in the past quarter. Looking ahead, potentially that could benefit us if there is continued slowdown in inflation. On the other hand, the very point you make about companies getting into financial difficulty and perhaps going bust is a risk to us. The nature of the contracts we have let means we have very good sight of the sub-contracts particularly placed by the major contractors and through that process we hope to be able to keep a reasonable eye on the state of health of the companies that supply us so that if somebody starts to get into difficulties we can perhaps take action to mitigate the impact of it, but you are quite right to highlight it as a risk going forward.

  Q128  Mr Evans: Six months ago £1 was worth about $2 and was riding high against all other currencies. Since that time the pound has gone into free fall. Has that had any impact on costs?

  Mr Armitt: It will have an impact on any materials that are bought from overseas. We have ordered quite a lot of materials in the past 12 months and clearly the devaluation of the pound is one of the factors that has kept up inflation within the construction industry because to a large extent inflation is made up of materials costs.

  Q129  Helen Southworth: Perhaps you would share with us your analysis of the impact of the economic downturn on the construction areas within the village and explore with us what you believe will be the balance between the issues around private financing and changes in cost in relation to that?

  Mr Armitt: As we have seen in the house building sector in particular there is a significant slowdown in the volume of construction now taking place. By "house building" I do not mean simply traditional houses but obviously blocks of flats as well. That slowdown increases pressure on all the companies in that sector and makes those companies hungrier for work. As developers slow down the rate of building they carry out potentially it could provide some softening in the market for us in procuring for the Olympic Village. That has to be set alongside other pressures on the market which I described in my previous answer. As far as concerns financing, it is an ongoing negotiation which is being handled by Mr Higgins. We are making progress but, as you would expect, in the current circumstances I would describe it as slow but steady progress. Clearly, we do not want to be driven into completion of those discussions if that comes early and therefore costs more than it might otherwise cost if we delayed it by a few months.

  Mr Higgins: That is right. We have an asset. The most important thing is to separate delivery from funding and not make compromise decisions on delivery and so maintain the quality of design, sustainability and management. That is what we are doing. We have to ensure that the athletes' experience is enhanced. Over the past six months we have enhanced the village from the point of view of athletes' experience. I believe that it is better than the bid book now and better than it was a year ago. We are building for games time less high rise which will mean more public open space. It is a bigger plot than at bid time, but we should not be forced into making short-term decisions which destroy public value in the funding. The funding market is extremely difficult. There is huge uncertainty as to the price at which these apartments will sell. The government has that risk in any case. We have a committed partner in Lend Lease and its board is very supportive. We have good support from two banks and we need to work through those processes. There will be government funding and investment required in the village and that results from reduced expectations about the sale price of the housing. That is just the reality as a result of the decline in forecast sale values when these apartments go on the market in 2013 and 2014. But if we ever let programmes slip behind we will spend a lot which will not be decent value for money and make compromises and we are not doing that. Four of the apartment blocks already have foundations well under way. There are planning approvals for five of the projects. An enormous amount of effort is going into the design quality of the apartments at the moment.

  Q130  Helen Southworth: Therefore, you will not reduce the quality of what will go on site?

  Mr Higgins: Absolutely not. That would be very short-sighted. The government has direct exposure to £500 million to £600 million worth of market housing on this project just at the Olympic stage, let alone its long-term investment in land around Stratford as well as the LDA's landholding. It has a long-term interest in keeping the value of the whole estate sound.

  Q131  Helen Southworth: What opportunities arise because of the economic downturn on the site that you have with such a degree of security and size of project?

  Mr Higgins: I think there will be a decline in inflation. We do not see it at the moment because we are still awaiting inflation from Europe from where a lot of the materials come.

  Q132  Helen Southworth: Can you give us a little explanation of what that will comprise? Is it the lower price of raw materials?

  Mr Armitt: To take structural steel as an example, the cost has gone up by 300% in the past three years. It went from £350 to £400 per ton to £1,300 per ton. That will start to reduce, but there is no great evidence that it is happening quickly.

  Q133  Helen Southworth: In terms of the village itself, are you looking at different ways to structure it to take account of some of the changes that you need to make in relation to timescale?

  Mr Higgins: Absolutely. We have deleted the high rise. The early plans had four 30-storey towers. They are good from the point of view of value; they would be the highest value we would expect, but in a market like this it is not sensible to build four 30-storey towers. If you have very small pre-sales the whole market knows that you have to sell four large tower blocks. We are building more low rise and affordable housing initially. That is not outside the planning requirements which overall are about 30% affordable housing. It is just a much more sensible solution from the point of view of the government's risk and also it produces a better village for the games. It may be worth asking Mr Edwards later this morning about his experience of the games. We have presented the games plan to the BOA, IOC, the Olympic Board and also the Athletes' Commission.

  Q134  Chairman: Therefore, you are suggesting that even though the village has been scaled down by 30% it will not have any effect on the athlete experience?

  Mr Higgins: I think it will actually be better for athletes than it was at bid time a year ago, but I suggest that you ask Mr Jonathan Edwards as a former Olympic athlete about his views on the new plans—who I believe is to appear before you later this morning.

  Q135  Chairman: It slightly begs the question why you originally decided that you wanted 4,000 units if 2,800 would provide a better experience.

  Mr Higgins: Two years ago you would make a profit on every apartment you built. Therefore, the more you built the more money you made. That has completely changed. It is hard to believe but in July 2007 people camped out over night for two nights to buy apartments in Stratford so they could get at the front of the queue. In an apartment block directly adjacent to the Village the world has changed and therefore we need to be more efficient and build less. We certainly do not want an overhang in the private market.

  Q136  Chairman: Therefore, the original plan was based not on what was best for the athletes but on maximising future revenue?

  Mr Higgins: The original development was wholly privately funded and it was a plan to build around legacy and then to house athletes. When it became clear that there needed to be public subsidy for the project we then asked: what do we really have to build? What is the most efficient build for the games time? Why build extra houses on which we will lose money? Let us hold off on that; they can always be built later on when the market recovers, but it is silly to build 500 extra apartments when they are not required, in particular the more speculative but higher value high-rise apartments which obviously were very attractive two years ago but are more risky from the government's point of view and are less adaptable for games time.

  Q137  Helen Southworth: In terms of the return to the lottery at the end of this process, all of the payback is dependent on the profit that is made at the end of the games and in the following years. It is really important for Members of Parliament and the public who are financing the entire thing that there is focus on payback. Have you also made an analysis of the likely impact of these changes on that payback? Will you be keeping a very clear focus on ensuring that none of those opportunities is lost over the coming years because of the current downturn?

  Mr Higgins: We are very aware of and transparent about lottery investment in infrastructure. That deal relates to the LDA's own land which is public parkland, not the Stratford deal. That is land controlled by London and Continental Railways. That land deal is the subject of a relationship between the mayor, the LDA and lottery. They do their own analysis on the impact of the market surely, but what we do as the ODA is ensure that the infrastructure that we put into the park will facilitate the appropriate sustainable development. We have sized all the major utility infrastructure to legacy plus 25% and, therefore, the lottery and LDA should be able to get maximum value from the land receipts which will not be limited by the infrastructure we are putting in.

  Q138  Helen Southworth: Will you be able to provide continuing reassurance to us? You will have a very clear focus on it in the next period?

  Mr Higgins: We are very focused on legacy. 75% of everything we do is set into legacy. Accountability for the recovery of receipts from land sales is a contractual relationship between the lottery, mayor and LDA.

  Q139  Helen Southworth: But it will be determined to a very significant degree by the decisions that you take?

  Mr Higgins: We are very much focused on it.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2009
Prepared 29 June 2009