Defence Equipment 2009 - Defence Committee Contents


Conclusions and recommendations


Overview of DE&S progress

1.  DE&S was created on 1 April 2007 following the merger of the Defence Procurement Agency and Defence Logistics Organisation. Some 20 months after the merger, DE&S appears to have made good progress and is considered to be "heading in the right direction". The progress made has been achieved against a backdrop of supporting current operations in Afghanistan and Iraq. We commend the Chief of Defence Materiel and DE&S staff for their achievements to date. (Paragraph 10)

2.  While industry has generally welcomed the progress made to date by DE&S, it has also called for this progress to be accelerated and considers that the establishment of programme boards will be particularly beneficial. In its response to our Report, we expect the MoD to set out its plans for accelerating the progress achieved to date, the key changes it expects to see implemented in 2009, its plans relating to the establishment of programme boards, including the benefits expected from such boards. (Paragraph 11)

Performance in supporting current operations

3.  It is extremely serious that the A400M transport aircraft programme, which is to provide much needed new tactical and strategic airlift for our Armed Forces, is now running two years late and further delays cannot be ruled out. We expect the MoD to press the contractor for a new delivery schedule for the programme and examine closely the assumptions and estimates in the schedule to ensure they are robust. Once the new delivery schedule is confirmed, the MoD needs to act swiftly to take the decisions which will prevent any capability gap emerging in the future relating to air transport. We expect the MoD, in its response to our Report, to provide us with an update on the forecast in-service date for the A400M programme and to update us on the action it is proposing to take once the new delivery schedule has been received from the contractor. (Paragraph 20)

4.  We consider that the Government has no choice but to consider the options referred to by the Chief of Defence Materiel. We call on the Government to set out its most up-to-date thinking on these options and to say whether it considers that there is a real risk that the entire A400M project might be so delayed that abandonment would be preferable. The costs and benefits attributable to any such decision should be clearly explained. (Paragraph 21)

5.  The Minister for Defence Equipment and Support has assured us that all the A400M transport aircraft which will be deployed into theatre will be fitted with a full Defensive Aids Suite, a fuel inertion system and explosive suppressant foam. Given that risks to aircraft are not restricted to operational theatres, we consider it surprising that a decision has yet to be made on whether the A400M aircraft not earmarked to be used in operational theatres will be fitted with all three systems. The safeguarding of our Service personnel should be paramount and the equipment they operate should have the maximum protection available. We note that the MoD considers that the risk of catastrophic fire on Chinook helicopters with pannier fuel tanks is low. We look to the MoD to ensure that its assessment about such risks is robust and is re-examined on a regular basis. (Paragraph 26)

6.  We note that the Urgent Operational Requirement process has continued to prove highly effective in enabling vital equipment to be provided in quick time to our Armed Forces in Afghanistan and Iraq. (Paragraph 29)

7.  We welcome the announcement on 29 October 2008 that a substantial number of protected vehicles are to be procured as Urgent Operational Requirements. The protection of our Service Personnel against continuously evolving threats must be the top priority. In its response to our Report, we expect the MoD to provide us with an update on its progress in acquiring these new vehicles and a breakdown of the procurement costs, including details of how much is to be funded from the MoD's budget. We also expect the MoD to provide us with details of which of the vehicles are expected to provide "longer-term benefit" beyond the current operations in Afghanistan and Iraq. (Paragraph 31)

8.  In November 2007 new arrangements for the funding of Urgent Operational Requirements (UORs) were announced. These new arrangements mean that, once the cost of UORs in a year have exceeded an agreed total with the Treasury, the MoD will have to contribute to half of the costs exceeding the agreed total and repay this two years later to the Treasury. In its response to our Report we expect the MoD to provide us with details of how the new arrangements have operated in practice, including its estimate of how much of the spend on UORs in 2008-09 will be funded from the MoD budget. We also expect the MoD to set out which of its programmes or activities will need to be re-prioritised in order to fund the cost of the UORs in 2008-09 which fall to the MoD's core budget. (Paragraph 36)

9.  While we are satisfied with UOR process, we remain concerned that the extent of UORs represents at least a partial failure by the MoD to equip adequately its forces for expeditionary operations which were anticipated by the Strategic Defence Review a decade ago. (Paragraph 37)

10.  We are concerned that the MoD appears to have made little progress with regard to its examination of the impact of current operations on equipment. While the MoD appears to have robust data on the cost of equipment procured through the Urgent Operational Requirement process, it does not have information on the cost of recuperating equipment returning from current operations nor on the impact of those costs on other areas of its budget. Such costs must be substantial given the length of time that UK Armed Forces have been involved in current operations in Afghanistan and Iraq. The MoD must identify accurately the costs to date of recuperating equipment and the likely future costs of recuperation. Without such information, there is a real risk that these costs will fall on the Defence Budget, which is already under pressure, rather than on the Reserve as they rightly should be. (Paragraph 44)

Equipment procurement performance

11.  We are concerned to learn that, once again, the Nimrod MRA4 programme has experienced further cost growth and in-service date slippage. In its response to our Report, we expect the MoD to set out the findings from its examination of the extent of further cost increases, to provide us with the latest position on the current forecast in-service date, and to outline the "mitigation measures" it has identified and what it expects these to deliver. We have not been satisfied by the explanations for these delays given by the MoD to date, nor by the Department's assurances as to how performance would be improved. We will return to this matter in the future. (Paragraph 48)

12.  In its first year of operation, DE&S failed to meet its Public Service Agreement target to "Deliver the equipment programme to cost and time". We note that the National Audit Office examined the procurement performance relating to the 20 largest projects and found that the aggregate forecast cost for these projects increased by £205 million and the aggregate in-service date slippage increased by eight years in 2007-08. We are concerned that DE&S has failed to control delays on equipment projects with almost half of the 20 largest projects experiencing in-service date slippage in 2007-08. We have not been satisfied with the explanations given by the MoD as to what it intends to do to rectify this decline in performance, and we will be returning to this matter in the near future. (Paragraph 50)

13.  Financial Year 2008-09 saw the introduction of new Departmental Strategic Objectives (DSOs) which include a Performance Indicator under DSO 3 covering "Procuring and Supporting military equipment capability through life". The MoD's performance, six months into 2008-09, has been disappointing with average in-year forecast in-service date slippage and average in-year forecast cost increases both exceeding the targets set. The MoD considers that exchange rate changes account for most of the forecast cost increases reported in 2008-09. In its response to our Report, we expect the MoD to set out its estimate of how much it anticipates exchange rate changes will add to the cost of equipment programmes in 2008-09 and what action it is taking to minimise the risk of such cost increases. (Paragraph 55)

14.  In its response to our Report, we expect the MoD to set out what specific action it is taking to reduce the Demonstration and Manufacture timescales of equipment projects by 50% from 2009 onwards, a target set out in the DE&S Business Strategy 2008-12 and how such reductions will be measured and reported. (Paragraph 56)

15.  The MoD does not consider it possible to assess how, if at all, support to current operations has impacted on performance against its procurement targets. We consider that, while it would appear that only a small proportion of DE&S staff have been involved on Urgent Operational Requirement projects, support to current operations has had an adverse impact on its procurement performance, although we doubt that this factor alone is responsible for the state of parts of the equipment programme. DE&S staff involved in UOR projects have had to be transferred from longer-term equipment projects and, given the importance of UOR projects, more experienced project staff are likely to have been transferred. We would hope that as work supporting current operations begins to reduce, and staff are transferred back to the longer-term projects, that this will have a positive impact on procurement performance. (Paragraph 58)

16.  We note that the MoD considers that a key contributor to cost increases or delays on equipment projects is "the realisation of unplanned or low level / high impact risk". The MoD states that it was placing greater emphasis on investment prior to Main Gate to address this risk. In its response to our Report, we expect the MoD to set out, for the current projects which have passed Main Gate, the proportion of such projects where 10-15 per cent or more of the forecast project budget was spent in the Assessment Phase. (Paragraph 61)

17.  We note that DE&S has made good progress in improving the skills of its staff across a range of key acquisition disciplines. We note also that the Defence Commercial Director has recently been announced as the new Comptroller and Auditor General, but we consider it essential that the MoD build upon the progress he and the Chief of Defence Materiel have achieved to date. (Paragraph 66)

18.  Equipment programmes have often experienced delays at various points in their life cycle. We note that the MoD is looking at training programmes which focus on the "value of time". In its response to our Report, we expect the MoD to set out what consideration it has given to such programmes and its future plans in this area. (Paragraph 68)

19.  By 2012, DE&S plans to have reduced its staff by 25% compared to the number in post at the start of April 2007. At the end of September 2008 the number of staff had been reduced by some 15%. Given that procurement performance declined in 2007-08 and that DE&S is supporting two operations, we find it surprising that DE&S is pushing ahead with its streamlining programme. DE&S must monitor closely the morale of its staff and recognise the uncertainty that such programmes create. In its response to our Report, we expect the MoD to provide us with its rationale for reducing staff at a time when procurement performance has declined and when DE&S remains busy supporting two overseas operations. We also expect the MoD to provide us with details of the costs incurred to date, including redundancy and early retirement costs, as a result of the streamlining programme. The response should also set out how many consultants have been employed to undertake work previously undertaken by DE&S staff who have left under the streamlining programme, and the costs of these consultants. (Paragraph 71)

20.  We note that the Secretary of State has instituted a review to examine the progress in implementing acquisition reform and make recommendations for securing better value for money in the acquisition of major equipment programmes. There have been several such reviews over the last decade, yet major equipment programmes continue to experience cost increases and delays. It will be vital that the recommendations are implemented quickly and fully so that the expected benefits are delivered. We expect the MoD to provide us with a copy of the review once completed and to set out how the findings and recommendations in the review are to be taken forward. (Paragraph 73)

Progress with the short examination

21.  The FRES programme has been a fiasco. In February 2007 we concluded that the MoD's attempts to meet its medium-weight vehicle requirement had been a sorry story of indecision, changing requirements and delay. Two years later the story is, incredibly, even worse. We find it extraordinary that, some seven months after announcing General Dynamics UK as the provisional preferred bidder for the FRES Utility Vehicle, the MoD has announced that priority is now to be given to the FRES Scout Vehicle. Whilst we recognise that the MoD's equipment requirements need to reflect changing threats, that is no excuse for the MoD's behaviour in this programme; they have wasted their and industry's time and money. The FRES Utility Vehicle programme was, from the outset, poorly conceived and managed. The MoD must work out what its requirements are for medium-weight armoured vehicles and identify lessons from the saga of the FRES Utility Vehicle programme. In its response to our Report, we expect the MoD to set out the cost to date of the FRES Utility Vehicle programme and how it plans to take forward this programme in the future. (Paragraph 95)

22.  We welcome the announcement made on 11 December 2008 that the MoD will be further increasing helicopter capacity in Afghanistan over the next two years. Given our continuing interest in helicopter support for current operations, we plan to monitor closely the progress in delivering the commitments set out in the announcement. (Paragraph 97)

23.  The MoD's confirmation that some 60 Future Lynx helicopters are to be procured is to be welcomed. However, in his evidence to the Committee, the Minister for Defence Equipment and Support was unsure as to whether the programme had passed the main investment decision or whether the contract had been signed. This may have been what caused him to say that the programme had been brought forward. We recognise that the Minister had taken up post only two months before the evidence session, but we do note that this was one of the programmes referred to in the Written Ministerial Statement of 11 December 2008. In its response to our report, we expect the MoD to provide us with the latest forecast cost and in-service date for the Future Lynx programme. It is also difficult to judge on the evidence currently available whether these numbers are sufficient to meet all battlefield and maritime needs. (Paragraph 104)

24.   We find it very strange that, only six months after awarding the contracts to build the carriers and announcing the in-service dates, the MoD has decided to delay the entry into service of the two new aircraft carriers, the first by one year and the second by two years. We do not share the view of the Minister for Defence Equipment and Support that the delays to the in-service dates will result in "no loss to the defence capability of the nation at all". In its response to our Report, we expect the MoD to set out its latest forecast of when the two carriers are expected to enter service. (Paragraph 112)

25.  We were surprised to hear that HMS Ark Royal was due to be paid off earlier, despite it being the newest of the three Invincible Class Carriers. The Minister's evidence would seem to indicate that for a period prior to the introduction of the new Carriers only one Invincible Class Carrier will be in service, which represents a significant reduction in capability. (Paragraph 113)

26.  We are concerned that the MoD could not provide us with an estimate of how much the decision to delay the in-service dates for the Future Carriers will cost, as the estimates that the MoD has been given were not considered robust. We would expect DE&S to have the ability to produce robust estimates, given that one of its key roles is to be an intelligent customer. There will also be a cost in extending the life of either one or both of the existing Carriers, but the Minister for Defence Equipment and Support did not apparently consider this a matter of any importance. We consider that, while the delay to the entry into service of the two carriers may provide some short-term savings, the Future Carrier programme is likely to cost substantially more in the long-term. In its response to our Report, we expect the MoD to provide us with details of the additional cost of delaying the entry into service of the two carriers—both the additional contractual costs relating to the Demonstration and Manufacture phase and the costs of extending the life of either one or both of the existing Carriers currently in service. (Paragraph 114)

27.  The Minister for Defence Equipment and Support has assured us that the decision to delay the in-service dates of the carriers will not result in any job losses or loss of specialist skills. We remain to be convinced and will be monitoring the programme closely, in particular, the industrial implications of the decision to delay the entry into service of the two carriers. We are also puzzled as to why this decision was made so soon after Main Gate. The timing suggests that the decision had nothing to do with the carrier programme itself but with easing problems with other programmes identified in the short examination of the equipment programme. We expect from the MoD clarification of this change to plans so soon after Main Gate in response to this Report. (Paragraph 117)

28.  We note that the MoD considers that the Joint Strike Fighter STOVL programme is progressing well and that it plans to procure three aircraft for Operational Test and Evaluation. We also note that the MoD considers that technology relating to the programme was being transferred to the timescale originally agreed. We plan to continue to monitor the progress of this key programme. (Paragraph 124)

29.  We note that the MoD is considering alternative procurement approaches to the Military Afloat Reach and Sustainability (MARS) programme and that this is likely to result in the deferral of the fleet tanker element of the programme. In its response to our Report, we expect the MoD to set out what impact the expected delays on the MARS programme will have on defence capabilities such as Carrier Strike. We also expect the MoD to set out how the delay to the MARS programme will affect its ability to comply with International Maritime Organisation environmental standards which require the phasing out of single hull tankers by 2010. (Paragraph 127)

30.  The second objective of the short examination of the equipment programme was "rebalancing the equipment programme to better support the frontline". We note that the Minister for Defence Equipment and Support considers that this objective has been achieved. We consider that, while supporting current operations must be the priority, it is absolutely vital that the MoD continues to give sufficient attention to the longer-term equipment programme. We note that the Minister has set up a Committee to look at the longer-term priorities. The issue of keeping the equipment programme balanced is an issue we plan to monitor closely. (Paragraph 134)

Status of Equipment Programme

31.  We note that industry and the MoD appear to have radically different views on the status of the equipment programme. Industry refers to the equipment programme being paralysed, yet the MoD claims to be spending substantial amounts of money with industry and denies industry's claims. We doubt that the announcements about the equipment programme on 11 December 2008 will provide industry with much clarity about the MoD's future requirements. There is an impression of another shoe waiting to drop. We plan to monitor this issue closely in the future. (Paragraph 137)

32.  We note that any further major changes to the equipment programme will be announced in spring 2009 following the completion of Planning Round 09. We expect the MoD to keep Parliament informed of such changes as soon as they are known. (Paragraph 140)

Funding of Equipment Plan

33.  Many commentators have suggested that the defence equipment programme is under-funded, but the MoD was unable to give us a clear answer and could not provide us with an estimate of the level of any such under-funding. We note that, following the completion of the short examination of the equipment programme, the Minister for Defence Equipment and Support considers that the equipment programme is affordable, no significant equipment orders having been cancelled, although the timetables for some have been slipped. We are aware that, in the past, slipping programmes has resulted in increased costs. We plan to monitor the outcome of Planning Round 2009 which is expected to be completed in spring 2009. (Paragraph 150)

Pre-budget statement

34.  We note that there was no injection of funds for the UK defence industry in the Pre-Budget Statement of 24 November 2008. We are concerned to hear from industry that Small and Medium-sized Enterprises (SMEs) are "suffering" because money is not flowing down the supply chain. In its response to our Report, we expect the MoD to set out the extent to which it is aware that SMEs are experiencing problems and how it is proposing to address these in order to ensure that the current supply chain is retained. (Paragraph 154)

Defence research spending

35.  The UK's future military capability depends upon the investment made today in Research and Development (R&D) and the military advantage achieved at any one time depends upon the R&D investment made over the previous 25 years. We are extremely concerned to learn that defence research spending has been cut which, in our view, is short-sighted. We agree with the Minister that it is a matter of priorities and consider that it should be a very high priority. Sufficient funding for defence research needs to be ring-fenced. If not, the MoD must acknowledge that the role which our Armed Forces can play in the future will be substantially reduced. In its response to our Report, we expect the MoD to provide us with details of the extent of the recent cuts in defence research spending and set out the specific areas affected by these cuts. We also expect the MoD to provide us with its assessment of what impact the recent cuts in defence research spending will have on the UK's future military capability. (Paragraph 162)

Measures to limit DE&S spending

36.  We note that the Chief of Defence Materiel (CDM) sent a memorandum to DE&S staff in autumn 2008 setting out measures to reduce spending on equipment programmes. CDM calls the measures a "commitment regime" and considers this to be a routine practice. Whilst we support the need for robust financial control, it would appear to us that the measures taken by CDM to reduce spending on equipment programmes are a clear sign that defence funding issues are more acute than ever in the current financial year. (Paragraph 165)

Defence Inflation

37.  Defence inflation, and in particular defence equipment inflation, reportedly runs at a higher rate than the general rate of inflation. A recent research paper suggests that defence inflation may be running some 3% higher than the general rate of inflation. If true, this would seriously undermine the Comprehensive Spending Review 2007 settlement for defence which was reported as being a 1.5% annual real terms increase in the MoD budget for the period 2008-09 to 2010-11. The MoD is undertaking work, scheduled to be completed in April 2010, to produce a measure of defence inflation. We find the lack of urgency given to this project to be regrettable. The MoD must push forward this work as quickly as possible so that the results can feed into its negotiations with the Treasury in future spending reviews. We expect the MoD to work with organisations such as the Defence Industries Council to examine the issue of defence inflation and report back to us with its findings. (Paragraph 174)

Responsibility for implementing the Defence Industrial Strategy

38.  We note that the Minister for Defence Equipment and Support has overall responsibility for the Defence Industrial Strategy (DIS) and that the key official within the Department with responsibility for the DIS is the Defence Commercial Director. However, the Chief of Defence Materiel (CDM) is also responsible for "driving forward" the DIS. In its response to our Report, we expect the MoD to set out the specific responsibilities relating to the DIS which fall to the Minister for Defence Equipment and Support, the Defence Commercial Director and CDM. (Paragraph 182)

Progress in implementing the Defence Industrial Strategy

39.  We have heard mixed messages about the progress made in implementing the Defence Industrial Strategy (DIS). The MoD reports that good progress has been made in most of the industrial sectors. However, we have heard several concerns from industry, including concerns that the progress has been slower than hoped, that the expected transparency has not materialised, and that the DIS was "on hold". In its response to our Report, we expect the MoD to consider the evidence we have received from industry, and explain to us why there is a difference of opinion between the MoD and industry on the progress made in implementing the DIS. We are particularly concerned to hear from industry that the expected transparency has not materialised and expect the MoD to set out how it plans to address this specific issue. (Paragraph 194)

40.  We also look to the MoD to provide us with an update on the progress in negotiating a Long Term Partnering Arrangement in the fixed wing sector, including when it expects to have reached agreement on such an arrangement. (Paragraph 195)

41.  A key objective of the DIS was to move to a Through Life Capability Management (TLCM) approach to acquiring and managing defence equipment programmes. However, some industry representatives have raised concerns that the TLCM approach has not been fully embedded. In its response to our Report, we expect the MoD to set out its assessment of the extent to which the TLCM approach has been embedded across the department. (Paragraph 197)

Updated version of the Defence Industrial Strategy

42.  An updated version of the Defence Industrial Strategy was expected in December 2007, but the MoD did not meet this deadline, nor the next deadline of spring 2008. The MoD claimed that the original deadline was missed because of the need to finalise Planning Round 2008. More recently, the MoD has claimed the delay has been caused by the need to complete the short examination of the defence equipment programme. The short examination has been completed and both the MoD's Permanent Secretary and the Chief of Defence Materiel have told us they were confident that the updated version of the DIS would be published in 2009. (Paragraph 206)

43.  We find it astonishing that the new Minister for Defence Equipment and Support was "open-minded" as to whether it made sense to have an updated version of the DIS. The DIS is now over three years old and a key aim was to provide industry with clarity about the MoD's future requirements. In its response to our Report, we expect the MoD to tell us whether, or not, it plans to publish an updated version of the DIS. If it does plan to do so, we expect the MoD to set out when it plans to do so. If it does not, we expect the MoD to set out how it plans to keep industry informed of its future requirements and the industrial capabilities which the UK needs to retain. We condemn the failure to date to publish an updated version of the DIS and consider that its continuing absence increases the risk that the UK Defence Industrial Base will not be able to meet the future requirements of our Armed Forces. (Paragraph 207)

The Defence Industrial Base

44.  We are worried to hear from some industry representatives that they are concerned about the future of the UK Defence Industrial Base. However, the MoD does not appear to share these concerns. In its response to our Report, we expect the MoD to set out what assessment it has made of the health of the UK defence industry and, in particular, those parts of the defence industry where the MoD wishes to retain industrial capability in the UK. (Paragraph 211)

45.  We note that the MoD has signed up to the Supply Chain 21 programme which aims to improve the defence supply chain. In its response to our Report, we expect the MoD to set out the contribution it is making to this programme, its assessment of the progress of the programme to date, and what specific benefits if expects the programme to deliver. (Paragraph 215)





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2009
Prepared 26 February 2009