Defence Support Group - Defence Committee Contents


Supplementary memorandum from the Ministry of Defence

Q1.   To what extent will continued reliance on separate land and air IT systems (on the operating side) restrict the possibility of realising future synergies within DSG?

  A1.  DSG does not anticipate that operating two bespoke IT systems across the land and air businesses will impede or restrict its ability to realise future synergy benefits.

Q2.   In Q13 there is reference to the activity of "land supply" now being carried out by staff at Sapphire House. The Committee would appreciate a short note setting out where this activity was carried out before, and what happened to those staff who carried out this activity when Sapphire House was brought into DSG. It would also like to know how much money was saved from this development within DSG.

  A2.  Staff undertaking the procurement and provisioning activities in Sapphire House, Telford transferred internally from DE&S to DSG on 1 September 2008. This followed DSG's proposal to take on these activities with the aim of delivering future synergy benefits and savings to the MOD customer, and this proposal was accepted and endorsed by Ministers in December 2007. This meant that staff based at Sapphire House would not have to relocate to the South West as originally planned under the DE&S Collocation Project but would instead transfer to DSG. Part of the transfer process included a Voluntary Early Release scheme which helped realise staff reductions of 94 with subsequent savings of £3.88 million.

Q3.   In Q13 there is also reference to savings of a "fair amount of money in material costs and things of that nature". To what specifically does this refer, and how much was saved?

  A3.  DSG anticipate savings of £2.2 million on its planned material spend in 2008-09. Further non-staff related savings of £1.9 million are anticipated in Information System expenditure and an additional £1.1 million from areas such as HR, finance and consultancy expenditure.

Q4.   The Committee would appreciate a note setting out DSG's possible participation in the Equipment Sustainability Solution in Camp Bastion, and when the full extent of this participation is likely to be confirmed?

  A4.  The Equipment Sustainability Solution (ESS) at Camp Bastion will be delivered in two distinct phases; construction followed by the delivery of a repair capability. The project is being managed by PJHQ with their prime contractor for both phases being KBR.6 DSG are being invited to participate in a very small way for the construction phase by giving specialist advice to the project on infra-structure and facilities aspects. The construction phase is due to complete in Apr 2010. Negotiations continue on aspects of the commercial contract for the repair capability phase, and KBR as the prime will be required to run a sub-contract competition for the various elements of delivering the repair capability. Due to their position within MoD; their proven track record; their knowledge of the equipments, and their security status in regard to repairing certain sensitive equipments, DSG will be invited to participate in that competition, however, successful award of a sub-contracting role in providing a repair and maintenance capability at the ESS, is predicated on DSG's ability to provide an overall value for money and affordable solution. It is anticipated that sub contract elements to the prime contract will be awarded later in 2009.

Q5.   In Q87, Mr Hughes says that "about 20% of what I do is contracted via industry at any rate". The Committee would like confirmation of the proportion of DSG's work for which it is the MoD's prime contractor, and the proportion of DSG's work for which it is a sub-contractor to industry. It would also like confirmation of whether this proportion is by turnover or by capacity.

  A5.  81% of DSG's work, by turnover, is contracted directly to the MOD with 17% as a sub-contractor to industry and the remaining 2% of turnover comes from wider market customers.

Q6.   The Committee would also be grateful for an indication of when DSG expects to submit its five year strategic plan to Ministers and when it expects this plan to be agreed by Ministers. The Committee would also like to know when DSG expects to publish its first Annual report.

  A6.  DSG plans to present its Corporate Strategic Plan to the Minister in March when its next Owner's Advisory Council meets. DSG anticipates publishing its first Annual Report and Accounts once they are laid before Parliament, which it expects will be in early summer 2009.

18 February 2009



6  KBR is a US engineering and construction company.




 
previous page contents

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2009
Prepared 22 June 2009