Ministry of Defence Annual Report and Accounts 2007-08: Government response to the Committee's Fifth Report of Session 2008-09 - Defence Committee Contents


Government response


Introduction

The Government welcomes the Committee's report on the Ministry of Defence Annual Report and Accounts 2007-08. The Government's response to the conclusions and recommendations contained in the Committee's report is set out below.

The Joint Personnel Administration programme: the Qualified Audit Opinion

1. (Recommendation 1). It is difficult to exaggerate the magnitude of the failure of the Joint Personnel Administration programme. At a time when the Department is seeking, in many cases successfully, to deal with areas of dissatisfaction in service personnel life, this failure, which affects pay, entitlements and service records, is unacceptable. (Paragraph 10)

We are determined to identify and address areas of dissatisfaction with Service life, and have recognised that the Joint Personnel Administration (JPA) interface with Service personnel has been such a source of dissatisfaction. The then Under Secretary of State (Mr Twigg) therefore commissioned a comprehensive and independent review of JPA in mid-2008.

The Review Report concluded that improvements were needed in a number of key areas including: governance; training; and a reduction in complexity to improve the user experience of the system. At the same time, the Review concluded that JPA has been "a considerable strategic success".

We have taken determined and systematic action to meet the Review's recommendations. A comprehensive analysis of JPA business functionality - that will identify gaps between what has been required and what has been delivered - is nearly complete. On the one hand, the initial findings of this stock-take of JPA show that there are problems with system access, some aspects of functionality and with the provision of management information. On the other hand, they show that JPA is largely fit for purpose.

The Service Personnel and Veterans Agency (SPVA) has achieved a 97.89% level of accuracy against its Key Targets for Financial Year 2008-09 for the delivery of pay to Service personnel. 99.99% of personnel were paid on time.

2. (Recommendation 2) We express our serious concern that the MoD's Resource Accounts for 2007-08 were qualified by the Comptroller and Auditor General, as a result of their lacking financial controls, arising from the recently introduced Joint Personnel Administration system. We are also concerned by the number of weaknesses in financial control identified by the NAO. We look to the MoD to address these weaknesses as a matter of urgency. (Paragraph 15)

We are addressing the National Audit Office's concerns with urgency and are working to complete:

  • A Payroll and Allowance Control Framework Project;
  • A JPA Finance Improvement Project; and
  • The implementation of the relevant recommendations made by the Independent Review (and other business improvements).

The SPVA and the Services have worked very effectively together to make good progress. This has been very detailed and time-consuming work - and there is still more to be done. Working closely with the NAO, SPVA and the Services have demonstrated that financial controls are in place. The Control Framework Project is scheduled to finish in December 2009. The JPA Finance Improvement Project was concluded in Apr 2009.

3. (Recommendation 3) In developing JPA, the MoD placed insufficient emphasis on financial reporting requirements or the requirements for management information. A system was put in place, presumably with the approval of the Department's Finance Officer, that provided insufficient evidence of payments and which could have such adverse impacts upon Departmental Accounts. We consider this to be a basic and fundamental error which is unacceptable on a project of this scale and importance. (Paragraph 16)

We acknowledge that errors were made early on in the development of JPA. Failures on the financial accounting side have been investigated. The investigation report concluded that, at the outset of the project, there was a failure to recognise fully the financial dimensions of the work involved. Specifically, the financial users' needs were not adequately reflected in early key documents. It followed that:

  • Robust financial user requirements were not developed;
  • Consequential risks were not identified sufficiently; and
  • JPA project work did not address adequately the financial and accounting functions.

Lessons have been learned and changes have been made to ensure that dependencies with the financial process are correctly considered by the Department's change programmes. With hindsight, in paying such close attention to project timescale and the costs and benefits to be delivered, focus on the Department's financial reporting requirements was lost.

4. (Recommendation 4) It remains unclear whether the ability of the MoD to recover such a small proportion of the monies it paid out to EDS for JPA reflects the nature of the contract, a just assessment of the proportion of responsibility for JPA's weaknesses or both. The decision to implement the JPA programme through an existing contract, which was clearly insufficient to deal with problems that might arise, was short sighted. The lack of clarity in the design in the system at the outset has led significant costs being incurred by the Department which ought to have been entirely avoidable. (Paragraph 19)

Charges are raised by SPVA for service delivery failures. These vary according to the nature of each failure and take into account:

  • The share of responsibility for the failure between MOD and EDS;
  • The extent of the impact of the failure on customers; and
  • Any other mitigating factors.

The JPA Procurement Strategy Review concluded that early implementation offered significant additional value, and that earliest benefit could be realised by contracting with EDS for JPA implementation.

5. (Recommendation 5) We recognise that considerable work has been undertaken recently to enable JPA to support the MoD's financial performance. We note that more work will need to be done. We will return to this subject in our next inquiry on the MoD's Annual Report and Accounts. In its response to this Report the MoD should set out what the current state of JPA is, what current satisfaction levels within the service community are with regard to JPA, and what progress has been made in implementing the NAO's recommendations. (Paragraph 22)

JPA is a major change programme which has revolutionised the way in which the Armed Forces are administered. We accept that there have been issues with the JPA, including with accounting mechanisms and associated audit trails and are working hard to correct these.

JPA is however now closer to delivering the comprehensive, flexible and simplified administration service that was envisaged. Since roll-out Service Personnel have received their basic pay without interruption, almost without exception. For the first time some 300,000 self-service users can now view pay slips, submit on-line expenses and leave requests, and change personal details direct onto the system. And by saving of around 1400 administrative posts we have been able to devote more resources to the front line.

Overall satisfaction with SPVA has now risen to 80% - an increase of 12%. Satisfaction with the JPA system has risen by 7% to 77%. Whilst it remains a particular area for further improvement, customer service satisfaction with the Enquiry Service has nearly doubled from 28% to 55%.

Efficiency savings

6. (Recommendation 6) As we noted in our last Report, the MoD has exceeded its efficiency targets by a wide margin. We commend the MoD for its focus in maintaining its core programme. We must however express some concern that these cuts come at a time of considerable change in the MoD, and of continuing high operational commitments. Inevitably, such reductions in staff have placed greater burdens upon personnel and hindered performance. (Paragraph 27)

Identifying new efficiencies can be challenging and it is important that, where possible, we do not place greater burdens upon our people or hinder performance. We are, therefore, fully engaged in the cross government Operational Efficiency Programme (OEP) where we are undertaking a self-assessment of MOD performance and costs against best practice benchmarking in key back office and shared service functions. We will only identify efficiency initiatives where there are true savings to be made or where performance can be improved.

7. (Recommendation 7) We are concerned that there has been a significant cost to the achievement of the MoD's efficiency programme. We consider that the difficulties Service personnel experienced using the JPA system were in part due to the MoD's pursuit of its efficiency targets. The fact that the MoD has exceeded its efficiency targets while the JPA system has performed so badly raises questions about the management of the MoD's extensive change programme and about a possible conflict of priorities. (Paragraph 29)

As the Committee notes, a focus on efficiency has been important in maintaining the MOD's core programme. Benefits management is also an important component of best practice programme management. This does not mean that efficiency has been pursued at the inappropriate expense of other factors; indeed a saving that accrued as a result of a diminution of capability would not be classed as an efficiency.

There is no evidence that the efficiencies that were achieved are linked to initial problems with service delivery and the programme is now delivering significant business benefits with evidence that it is meeting the majority of business requirements.

8. (Recommendation 8) We are concerned that MoD's headcount reductions, office closures and consequent move towards contact centres have together proved a source of frustration to Service personnel. We note that the MoD has no method of measuring whether the quality of the service it provides to Armed Forces personnel has deteriorated as a result of the efficiency programme. We recommend that the MoD develop a system to monitor the effect of its efficiency programme so as better to enable it to manage its impacts on Service personnel. (Paragraph 30)

We recognise that efficiency savings should not normally impact on delivery performance or quality of service. A range of measures are been used to monitor the effect of projects in the efficiency programme, e.g. the Service Personnel and Veterans Agency undertake regular surveys (twice per year) to measure the quality of the service provided to the Armed Forces which then informs ongoing work to improve services offered.

MOD's Value for Money (VfM) programme aims to deliver £3.15Bn of sustainable, cash releasing gains by 2010-11, all of which are being recycled to ensure that maximum resources are focused on delivering Departmental objectives.

The VFM programme is subject to annual internal audit to validate that robust structures are in places as well as confirming the actual savings made are compliant with Treasury VfM methodology - this includes ensuring that output performance is not negatively impacted. Our savings will also be reviewed by the National Audit Office, which will report on each Department's claim during the Comprehensive Spending Review 2007 period.

Capability Review

9. (Recommendation 9). It is probably too early to determine the success of these changes. We hope that the MoD will, in its next Annual Report and Accounts, describe in some detail the positive impact of the programme stemming from the Capability Review. We do remain concerned, however, that the Streamlining Programme, coming on top of the efficiency programme and accompanied by changes to processes and structures, may inadvertently affect the quality of performance within the MoD. (Paragraph 34)

We have taken action to implement this recommendation. The 2008-09 Annual Report and Accounts will contain a detailed description of our progress in implementing the programme stemming from the 2007 Capability Review. This is in addition to a summary of the results of the second Capability Review of the MOD, which took place earlier this year. This Review found that the Department has a sound platform to build on for the future and recognises the efforts we have made to implement the recommendations of the 2007 Capability Review.

MOD has made good progress on creating a Head Office that is cheaper, simpler, clearer and more effective, through the Streamlining programme.  To ensure that the quality of performance does not suffer, we will drive forward a programme to help Head Office business areas improve their performance through the use of flexible resourcing, work prioritisation and decision-making tools.  We are committed to continued development of the senior leadership group and to better exploiting IT and technology.  And from April we will introduce a comprehensive induction and training package for head office entrants.  We will measure progress through the use of pulse surveys and maturity models.

Data security

10. (Recommendation 10) We are concerned to learn that the MoD has been involved in separate incidents where significant amounts of personal data have been lost. We are pleased that the MoD has since then put in place firm measures markedly to reduce if not prevent similar incidents happening the future. While we agree with Sir Bill Jeffrey that preventing any reoccurrence of data loss is impossible, we emphasise that the MoD must show no complacency in this area. We are pleased to see that the matter is being overseen by the Defence Board, at the very highest level within the Department, and we expect clear and full information on progress to date in limiting or preventing such incidents in the next Annual Report and Accounts. (Paragraph 41)

Information on progress to date in limiting or preventing incidents will be presented in the next Annual report and Accounts. We have recently reported on progress in meeting the recommendations of the Burton Report: 41 out of a total of 51 have now been actioned. Significant progress has been made against the 10 remaining recommendations. Sir Edmund Burton has always been clear that a number of his original 51 recommendations would involve a longer term programme of change, and the Information Commissioner's Office (ICO) have recently reconfirmed that they see these 10 in that light and did not expect completion of them by 31 March 2009.

Overall performance

11. (Recommendation 11) We commend the MoD for the efforts it clearly puts into supporting the Armed Forces and attempting to deliver its SR2004 PSA targets. However, we are disappointed by the quality of the MoD's forecasting during the 2004 Spending Review period. We are concerned that institutional over-optimism might in some areas significantly impact on efforts to improve performance. We look to the MoD to make improvements to the accuracy of its forecasting in future and to inject a greater sense of realism into how its personnel carry out forecasting in future, and to report progress on this in its next Annual Report. (Paragraph 44)

12. (Recommendation 15) We find it perplexing that the MoD thought for so long that it would not fail against this readiness target, especially since it understood that the Armed Forces were "continuing to operate above the overall level of concurrent operations which they are resourced and structured to sustain over time" (Paragraph 55)

We recognise the Committee's disappointment with the quality of MOD's forecasting and at the potential for some institutional over-optimism.  With respect to readiness (PSA Target 3), in the 2005-06 Interim Assessment MOD reported that it was on course to achieve the readiness target.  This assessment was fair at the time because at that point the Armed Forces were not as heavily committed to Operation Herrick in Afghanistan; had this remained the case, there is no reason to suspect that the PSA target would not have been achieved.  By the time of the next interim assessment, a year later, the Armed Forces were committed at above planned levels and the impact of those current operations on contingent readiness was beginning to bite. The assessment of "some risk" reflected this.  By the end of the SR04 period, with success on current operations being the clear highest priority for the Armed Forces, the contingent readiness target was not met.  We regard the progressive change in the PSA 3 assessment as reflecting the reality of operations that were not part of the assumptions that underpinned the SR04 target.

13. (Recommendation 12) We do not consider the MoD's current system of reporting its progress against its targets to be sufficiently transparent. The response we received from the MoD to our queries on this issue only emphasises the unsatisfactory way in which the headlines of the Annual Report were constructed. When targets comprise many sub-targets, when subjectivity is key to measurement, when no metrics are provided to assess what is meant when a sub-target is 'partly met', there is clearly insufficient transparency. We understand the need sensibly to balance clarity and accuracy with brevity. Nonetheless, we recommend that the MoD develop a more accurate method of measuring its progress against targets for next year's Annual Report and Accounts, and at the very least make performance against sub-targets a much more prominent part of that Report's headlines in future. (Paragraph 49)

We recognise the Committee's concern. Parameters for reporting performance against Spending Round targets are set centrally by HM Treasury and all departments are expected to work with these when providing assessments. In addition, the MOD has to take cognisance of security and that some performance indicators are not susceptible to quantative treatment. In recognition of these factors, the MOD in the 2007-08 report sought to provide a thorough narrative on qualitative performance indicators. 2008-09 performance indicators were set before the start of that year, but we have noted the Committee's desire to see the assessment of performance given more prominence in the Annual Report and Accounts.

Operations

14. (Recommendation 13) We encourage the MoD to look into making publicly available as many of the unclassified elements of assessment within this area as possible, but we understand the operational sensitivities will mean that this area of performance will necessarily remain less accessible to the public than other areas of the MoD's performance. (Paragraph 51)

We note and are sympathetic to this recommendation.

Conflict prevention

15. (Recommendation 14) We accept that a number of the outcomes set out in the MoD's Public Service Agreements for the period from 2004 to 2008 and in its Departmental Strategic Objectives for the period from 2008 to 2011 are not subject to easy measurement. We also accept that the MoD's own direct influence in relation to some of its international objectives will be necessarily limited. However, we reiterate the need for the MoD to try to develop more rigorous and objective methods for assessing performance. (Paragraph 53)

The MOD now shares targets for conflict prevention with FCO and DfID under PSA 30 for CSR07. We have developed more rigorous and objective measures for assessing performance for PSA 30 as a whole, which are applied across the three Departments, although specific responsibilities for each Department, as appropriate, have been allocated by the PSA 30 Delivery Board.

Readiness

16. (Recommendation 16) We welcome the openness that the MoD has shown in explaining the complex metrics for measurement of performance with regard to readiness. We expect an assessment in the Spring Performance Report of how the MoD considers the new metrics to be working. (Paragraph 57)

We continue to improve our performance metrics and will provide an assessment of the revised metrics once there is sufficient data to analyse.

17. (Recommendation 17) This continuing poor performance against readiness targets is serious. As the MoD's recent Autumn Performance Report accepts, it limits "the ability of force elements to engage in new contingent operations and military tasks". It also reveals the significant stresses which exist currently upon manpower, equipment, training and logistics. This puts into stark perspective the UK's capacity to sustain current operations into the medium term. (Paragraph 59)

We have continued to meet all mandated force generation activity to sustain the capability needed to conduct current and enduring operations and Military Tasks. Although performance against readiness goals is below the target, there have been small improvements in the overall readiness picture throughout the current reporting year. Operating for a sustained period above the overall level of concurrent operations for which Defence is resourced and structured to sustain, has reduced the capacity to be ready to react to the full range of contingent operations articulated in the planning assumptions. Whilst we acknowledge that meeting the sustained level of concurrent operations has impacted on the future capability of the Armed Forces to conduct contingent operations, this will be mitigated as concurrent operational commitments reduce.

18. (Recommendation 18) Restoring full contingent capability for our Armed Forces is one of the most pressing issue the MoD faces. It is essential that the MoD's programme of recuperation is effective and places no further strains upon our Armed Forces. We are particularly concerned that the programme is founded upon assumptions as to commitments which the UK Government may not be able to keep to over this period. We therefore stress to the Department the importance of this programme being able to take account of increased deployments in Afghanistan or new smaller operational commitments while still aiming to recuperate force elements to the required level in a reasonable time-scale. (Paragraph 62)

The restoration of contingent capability is one of the MOD's highest priorities after current operations and we have published our recuperation intentions internally within Defence Strategic Guidance 2008. Our commitment to Afghanistan is a strategic priority which does not diminish the importance of maintaining other operational commitments. The recent conclusion of combat operations in Iraq improves our capacity to alleviate further strains upon the Armed Forces.

The European Security Agenda, NATO and ESDP

19. (Recommendation 19) Other departmental select committees have in the past expressed concern about targets shared between departments, on the grounds that each department involved is tempted to believe that principal responsibility for action or success lies elsewhere. This is clearly unsatisfactory, and it is vital that areas of responsibility and sub-targets within each target are formally assigned to particular government departments so that lines of activity and responsibility are clear. (Paragraph 63)

PSA Target 4, to which the Committee refers, has now been superseded by CSR 07's PSA Target 30: 'Reduce the Impact of Conflict through Enhanced UK and International Efforts'.  Indicator 3 concerns more effective international institutions and covers NATO, the AU, the UN and the EU.  Whilst PSA 30 remains a joint target, sub-indicators for each organisation, with more clearly defined responsibilities for each Department, have been assigned by the PSA 30 Delivery Board.  The Government therefore believes that it has already addressed the HCDC's concerns with reference to PSA 30 about the value of shared targets and more clearly delineated departmental responsibilities and lines of activity.

Armed Forces personnel

20. (Recommendation 20) Personnel and manning issues are clearly another area of the MoD's performance that needs addressing as a matter of urgency. The recuperation programme which the MoD is about to put in place to assist in improving readiness levels following the drawdown in Iraq will have to focus not just upon equipment and training issues but also upon manpower issues. (Paragraph 69)

Personnel issues are invariably one of the most critical factors within our internal performance assessment. Recognising the importance of manning, we have initiated a comprehensive recuperation programme which will include the readiness levels for Manpower and Equipment and Training. Recruiting performance indicates that Manpower levels are being restored which should, in time, allow the Recuperation programme to address shortfalls in skill sets and readiness.

Equipment

21. (Recommendation 21) We are not satisfied with explanations that have been given by the MoD as to what it intends to do to rectify this decline in performance with regard to defence equipment, and we will be returning to this matter in the future. (Paragraph 70)

Of the 42 projects reported for 2007/08, cost growth was confined to two projects, NIMROD MRA4 and the BEYOND VISUAL RANGE AIR TO AIR MISSILE, both of which were initiated before reforms to defence acquisition were introduced. Similarly, around two thirds of the reported slippage was focused on three projects, only one of which was initiated after the introduction of acquisition reforms.

Future DSO targets

22. (Recommendation 22) We will monitor the MoD's reporting under this new system and call upon the MoD to include reporting on its work under the FCO-led PSA 30 in quarterly reports in future. (Paragraph 74)

The PSA 30 Delivery Board produces six-monthly reports and we wish to continue reporting to that cycle. Many of the specific objectives are the subject of joint work with the FCO and DfID (although one Department may be in the lead), and it would be difficult to produce a report for one element of a collaborative approach. Moreover, as the PSA requires objectives to be achieved by 2010/11 and they are very strategic in nature, there are unlikely to be significant changes in results over a three month period.





 
previous page contents

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2009
Prepared 17 June 2009