Ministry of Defence Main Estimates 2009-10 - Defence Committee Contents


Our Scrutiny of the Estimates

1.  The Treasury's Main Supply Estimates 2009-10 by which the Government requests resources from Parliament to meet its expenditure plans for the Financial Year ahead were laid before the House of Commons on Thursday 18 June.[1] The House will be asked to agree them on Thursday 2 July.

2.  The Main Supply Estimates contain an Estimate for each Government department and, separately, for each public service pension scheme. Our focus this year, as in the past, is on the Ministry of Defence (MoD) departmental Main Estimate. The MoD has as usual provided us with a memorandum which explains key elements of the Estimate. This is attached to the Report.[2]

3.  Shortly before the Main Estimates were laid, the Government sent us its response to our Report on the Spring Supplementary Estimate 2008-09. We have taken the opportunity in this Report to comment on important elements of this response. Further information was also sought from the MoD on both the Main Estimate and the response to that earlier Report. Both the Government response to our Report and the MoD's supplementary memorandum responding to our request for further information are attached to this Report.[3]

4.  This year the Main Estimates were laid relatively late. There was also an unexpected delay of sixteen days between their intended laying date and the date on which they were finally laid. However, the date on which the House will be asked to agree the Main Estimates was not changed as a consequence of this delay. There is thus significantly less time this year in which thorough and detailed scrutiny can be carried out by departmental select committees and Reports to the House can be drafted and agreed—indeed, only the absolute minimum period permitted by the Standing Orders of the House of Commons. We have commented before on the very tight schedule which committees such as ours have to adopt if they are to report on Supplementary Estimates before they are taken in the House.[4] It is highly regrettable that this year such a very tight schedule should apply also to the Main Estimates. We expect the Government in its response to this Report to set out the reason for the delays and the actions it intends to take in future years to ensure such delays do not happen again.

5.  We are grateful to the MoD for replying so promptly to our request for further information supplementary to its response to our Spring Supplementary Estimate Report and its Estimates memorandum. We also wish to thank the Committee Office Scrutiny Unit for its help with regard to the particularly tight deadline to which we had to work in preparing this Report, and for its regular assistance in scrutinising the Estimates.

Ministry of Defence Request for Resources

6.  The MoD's Main Estimate requests resources of £39.7 billion, with a net cash requirement of £37.7 billion. The MoD's Estimate is split between three Requests for Resources (RfR):

The headline figures are set out in the table below:Table1: The Ministry of Defence's Request for Resources (£million)
2009-10 Provision 2007-08 Outturn
Final ProvisionForecast Outturn
RfR1: Provision of Defence Capability 35,83334,637 34,53632,415
RfR2: Peace Keeping and Operations 2,8723,468 3,3262,196
RfR3: War Pensions and Allowances 1,0241,015 1,0141,014
Net resource requirement 39,72939,120 38,87635,625
Net cash requirement 37,74635,552 36,10632,787

Source: HM Treasury, Main Supply Estimates 2009-10, p 307

Provision of Defence Capability

7.  RfR1 covers by far the largest proportion of requested resources: its ambit includes personnel, equipment and support costs for the Armed Forces (including, for example the nuclear warhead programme). The departmental Main Estimate breaks this down by Top Level Budget Holder (TLB). After a number of changes to the TLBs over recent years they have this year remained more or less the same as last year, excepting some name changes. If this remains the case, it will make comparisons easier than has been the case for the last few years. The RfR1 provision for 2009-10 is £2,412 million more than the RfR1 provision at the time of the 2008-09 Main Estimates. Of particular note is the resources expenditure in the Chief of Joint Operations TLB which has risen 17% from last year's Main Estimates provision, from £396 million to £464 million. Changes in other TLBs are less striking. We request the MoD in response to this Report explain the reasons for the significant increase in resources allocated to the Chief of Joint Operations TLB.

Peace Keeping and Operations

8.  When we began our regular scrutiny of the MoD's Estimates after the 2005 General Election, forecast costs of operations for each Financial Year were first set down in the Spring Supplementary Estimate towards the end of that Financial Year. They would be voted on by the House shortly after that Estimate was laid. During Financial Year 2006-07, we made the case for the House receiving earlier notice of operational costs each Financial Year and recommended that the MoD bring forward forecasts of operational costs at an earlier point in future Financial Years.[5]

9.  In response, the MoD signalled its intention in future to bring forward operational costs to the House for agreement in its Winter Supplementary Estimate which is laid before the House some two to three months earlier than the Spring Supplementary Estimate each year.[6] We welcomed this move but pressed for some indication to be given to the House at the time of the Main Estimates of what operational costs were expected to be.[7] We acknowledged that such forecast costs were likely to change on account of the volatile and uncertain nature of operations, and that further sums would probably need to be sought at the time of the Supplementary Estimates later in the Financial Year. However, we were aware from information submitted to us by the MoD that the time-lag between MoD forecasts and their publication of forecast costs based upon them in the Supplementary Estimates was sometimes so great that earlier public notification of forecast costs to the House was desirable, notwithstanding the possibility of later changes to those costs.[8]

10.  We were very pleased when, in its memorandum accompanying the MoD Main Estimates for 2008-09, the MoD presented a forecast cost for operations.[9] In our Report on the 2008-09 Main Estimates we thanked the MoD and asked for this total to be broken down in future in the same way as the figures presented for operational costs in the MoD's Supplementary Estimates memorandum.[10] In this year's Main Estimates, the MoD has done this for the first time.[11] Moreover, the MoD has included, again for the first time within the body of the Main Estimates, the formal request for operational resources under RfR2. These operational costs will of course continue to be resourced from the Reserve. We welcome the MoD's willingness to share increasing amounts of information on operational costs with the House at this early stage in the Financial Year, and likewise for seeking formal approval from the House for these funds earlier than before. These are not insignificant steps in allowing our Committee and the House improved financial scrutiny.

11.  The MoD, in its memorandum accompanying the 2008-09 Main Estimates, included a forecast for operational costs for that Financial Year of "at least £2Bn…[to be] split between Afghanistan and Iraq"[12]. In our Report on those Main Estimates we commended the MoD for this but pointed out that, while welcome, this information was not as detailed as we had hoped.[13] The information provided by the MoD in the 2009-10 Main Estimates memorandum is a great advance on what was provided last year. The Table (reproduced below) setting out forecast costs under RfR2 for 2009-10 breaks down an overall sum—such as given the previous year—into the same elements as feature in previous Supplementary Estimates memoranda. We are grateful to the MoD for this provision of more detailed information.Table 2: Estimated cost of operations in Afghanistan and Iraq at Main Estimates 2009-10
Cost Type Iraq £M Afghanistan £M
Direct Resource DEL
Civilian Personnel 916
Military Personnel 37148
Stock/Other Consumption 189480
Infrastructure Costs 69216
Equipment Support Costs 231485
Other Costs and Services 93423
Income Foregone/ Generated (-) 1-12
Total Direct Resource DEL 6291,756
Indirect Resource DEL 165258
Total Resource DEL 7942,014
Capital DEL
Capital Additions 831,481
Total Capital DEL 831,481
Total Estimated Costs 8773,495

Source: Ev 4, Table 8

12.  In our Report on the 2008-09 Spring Supplementary Estimate, we noted that, at that late point in the Financial Year, the MoD was expecting to spend "over twice the amount it set down as a likely minimum for operational costs at the time of the last Main Estimate". We expressed the hope that the 2009-10 forecasts would be more robust.[14] We are pleased to note that the figure for expected operational costs in Afghanistan for 2009-10 set out in the memorandum accompanying the Main Estimates is not only usefully broken down but more precise and, importantly, greater in size than the figure of £3 billion which the Prime Minister announced to the House on 29 April 2009.[15] The MoD has clearly not kept complacently to the sort of forecast outline minimum it placed within the memorandum accompanying the Main Estimates for the last Financial Year but has set out what we expect to be a more realistic and thus more robust figure.

13.  Current forecasts suggest that the cost of operations in Iraq this Financial Year will be £877 million, and in Afghanistan £3,495 million, a total of some £4,372 million.[16] We do not yet have an out-turn for Financial Year 2008-09 for those theatres, but on the basis of the latest forecast included in the Spring Supplementary Estimates (of £1,958 million and £2,559 million for Iraq and Afghanistan respectively—in total, £4,517 million),[17] these sums represent a decrease of 55.2% and an increase of 36.6% respectively against expected costs for Financial Year 2008-09. The overall reduction, adding together both theatres, is 3.2%. This is the first reduction in overall costs of operations in Iraq and Afghanistan since those operations began to be carried out in both theatres, although Supplementary Estimates this Year might negate that reduction.

14.  Resource expenditure on peacekeeping is down 17.2%, as against the forecast from the 2008-09 Spring Supplementary Estimate, from £3,400m to £2,800 million. Within this, the Iraq resource spend is down from £1679m to £794 million (-52%) and the Afghanistan resource spend is up from £1710m to £2014 million (+18%). Capital expenditure on peacekeeping is on the same basis up 38% from £1,128m to £1,564 million, of which the Iraq net capital spend is down from £273m to £83 million (-70%) and the Afghanistan net capital spend is up from £849m to £1481 million (+74%).

15.  The reduction in costs for Iraq is of course largely a result of the drawdown of UK forces. Continuing costs in this theatre reflect specific drawdown costs and the costs for the main UK military presence in the first part of the Financial Year and for the remaining, much smaller, elements for the rest of the Year, the majority of UK Forces leaving Iraq by the end of July 2009. The MoD memorandum is helpful about the grounds for the increase in Afghanistan costs:

"Operations in Afghanistan include the additional security costs required for the local elections, and the costs of around 200 personnel providing counter improvised explosive device (IED) expertise. Capital costs for Afghanistan include Urgent Operational Requirements (UORs) such as further force protection (e.g. tactical support vehicles and surveillance equipment), and ongoing further modifications to military equipment for use in the operational environment (e.g. further adaptations to Tornado aircraft and Lynx and Merlin helicopters). UORs by their very nature reveal a capability gap in a specific operational environment and are therefore sensitive. We therefore cannot provide precise details. There is also an additional capital provision for increased airfield and associated support infrastructure in Afghanistan."[18]

16.  As this will be our last opportunity in this Parliament to scrutinise the MoD's Main Estimates, we have taken the opportunity to put side by side the costs of operations in Iraq and in Afghanistan for each Financial Year since we began our scrutiny of these costs in 2005. We have set these out below for Iraq, for Afghanistan, and then for both theatres combined. These tables help provide a sense of the scale of these operations in the last five years, of the changes in the scale of the component costs and of their overall trajectory.

    Figure 1: Overall cost of operations, Iraq and Afghanistan, 2005-06 to 2009-10

Source: previous Defence Committee Reports and Ev 4, Table 8

Table 3: Iraq: cost of operations, 2005-06 to 2009-10 (£ million)
Cost Type Iraq outturn

2005-06

Iraq outturn

2006-07

Iraq outturn

2007-08

Iraq

forecast

2008-09 (Spring)

Iraq

forecast

2009-10 (Main)

Resource - Direct
Military personnel 80100 98116 37
Civilian personnel 1415 1418 9
Stock/other consumption 219218 237240 189
Infrastructure

Costs

8183 130150 69
Equipment support costs 220206 278356 231
Other costs and services 111137 162175 93
Income foregone / (generated) 105 4(1) 1
Indirect Resource 6223 131625 165
Total (Resource) 797787 10541679 794
Capital Additions 160169 403279 83
TOTAL 957956 1,4571,958 877

Source: previous Defence Committee Reports and Ev 4, Table 8Table 4: Afghanistan: cost of operations, 2005-06 to 2009-10 (£ million)
Cost Type Afghan

outturn

2005-06

Afghan

outturn

2006-07

Afghan

outturn

2007-08

Afghan

forecast

2008-09 (Spring)

Afghan

forecast

2009-10 (Main)

Resource - Direct
Military personnel 850 8573 148
Civilian personnel 24 912 16
Stock/other consumption 57164 301521 480
Infrastructure

Costs

11101 149167 216
Equipment support costs 24112 200422 485
Other costs and services 3789 160305 423
Income foregone / (generated) 8(2) (11)(15) (12)
Indirect Resource 142 156225 258
Total (Resource) 148560 1,0491,710 2014
Capital Additions 51178 433849 1,481
TOTAL 199738 1,4822,559 3,495

Source: previous Defence Committee Reports and Ev 4, Table 8Table 5: Iraq and Afghanistan: cost of operations, 2005-06 to 2009-10 (£ million)
Cost Type Iraq /Afghanistan outturn

2005-06

Iraq

/Afghanistan outturn

2006-07

Iraq

/Afghanistan outturn

2007-08

Iraq

/Afghanistan

forecast

2008-09 (Spring)

Iraq

/Afghanistan

forecast

2009-10

(Main)

Resource - Direct
Military personnel 88150 183189 185
Civilian personnel 1619 2330 25
Stock/other consumption 276382 538761 669
Infrastructure

Costs

92184 279317 285
Equipment support costs 244318 478778 716
Other costs and services 148226 322480 516
Income foregone / (generated) 183 (7)(16) (11)
Indirect Resource 6365 287850 423
Total (Resource) 9451,347 2,1033,389 2,808
Capital Additions 211347 8361128 1564
TOTAL 1,1561,694 2,9394,517 4,372

Source: previous Defence Committee reports and Ev 4, Table 8

Drawdown in Iraq

17.  Given that most UK forces will have withdrawn from Iraq by the end of July 2009, four months into the Financial Year, it is perhaps not surprising that the estimated costs of £877 million for this Financial Year are under half of the amount forecast for the whole of the preceding twelve months. Clearly there were always going to be specific costs relating to drawdown which would be additional to the general operational costs for UK forces for the first part of 2009 during which the main bulk of UK forces remained in Iraq. The Spring Supplementary Estimate for 2008-09 included an additional £455 million to cover some of these specific drawdown costs within that Financial Year.[19] The Government response to our Report on those Estimates, however, fails to set out to what extent this allocation was used during the Financial Year.[20] An additional request for this information has also been met by the statement that the figures cannot be given as they are "still subject to final audit confirmation" and that "work is ongoing to ascertain the final impairment costs of fighting equipment deployed in Iraq".[21] The supplementary memorandum from the MoD does however say that "the provisional Indirect DEL out-turn for 2008-09 suggests a lower figure" than £455 million.[22]

18.  The Government response to our Report on the 2008-09 Spring Supplementary Estimate did however set out in some detail expected drawdown costs for Iraq for 2009-10. Component parts of these costs will be:

  • £13 million for hire service contracts to replace equipment returned to the UK;
  • £97 million for mechanical handling equipment (e.g. cranes) and other equipment support costs;
  • £21 million infrastructure, accommodation and other costs of withdrawal;
  • £56 million for transport (through Defence Supply Chain Operations Movement and Vehicles Group; and
  • (£10 million) stock return from theatre.[23]

19.  These component costs aggregate to £177 million. Consequently, the remaining £700 million cost for 2009-10 is to cover the presence of the main UK force in Iraq until its withdrawal by the end of July 2009 (for four months of the Financial Year) and the smaller force of some 400 personnel whose role in Iraq will be maintained for the rest of the Financial Year. However, the sum of £700 million is nearly half the cost of maintaining the full UK force in Iraq for the previous twelve months (excluding the extra £455 million drawdown contingency). We expect the MoD, in its response to this Report, to set out more clearly why the cost of operations in Iraq in Financial Year 2009-10 is still so relatively significant when for most of that Year only approximately 400 UK personnel will remain in theatre.

20.  Given that drawdown cost for Iraq for 2009-10, set at £177 million, is significantly lower than the contingency set aside for 2008-09, most of the drawdown cost for Op TELC as a whole clearly fell within that earlier year. It is therefore frustrating that the response to our request for a breakdown of drawdown costs for 2008-09 has twice met with no substantive response. This is unsatisfactory. We expect the MoD in its response to this Report, or within its Annual Report and Accounts to set out clearly, comprehensively and in appropriate detail the specific drawdown costs in Iraq for Financial Year 2008-09. If these costs significantly exceed or fall under the £455 million allocated for the purpose, we also expect the MoD to explain why this is so.

21.  A Departmental Minute laid before the House on the same day that we received the Government response to our Report on the 2008-09 Spring Supplementary Estimate provides an insight into some of the drawdown costs of Iraq. This Minute concerns the gifting to US forces infrastructure consisting of four dining facilities and four other incomplete structures (three accommodation units and a hospital unit). This infrastructure (which will in turn be passed on to the Iraqi Government) is valued at some £96.476 million in total—some £45.399 million for the dining facilities and some £50.620 million for the incomplete structures. (The total also includes a small sum of £456,886 to cover the contents of the completed buildings.)[24] Their cost of construction fell in Financial Years 2007-08 and 2008-09, some £61 million in the former and some £35 million in the latter, under RfR2 in each year.[25]

22.  This Minute, and the related letter from the then Secretary of State for Defence, the Rt Hon John Hutton MP, to Edward Leigh MP, the Chairman of the Committee of Public Accounts, reveals that the £96.476 million loss of these buildings will need to be covered in this year's Estimates. As there is no evidence that it has been covered in the Main Estimates as laid on 18 June, it will presumably be covered at the time of the Winter Supplementary Estimates. It seems odd that the Government did not make reference to this information in its response to our Report or in the memorandum accompanying the Main Estimates. Indeed, the drawdown costs for Iraq set out in the Government response for this Financial Year are entirely silent on this loss. We expect the MoD to set out for us when the costs of the loss represented by the gifting of infrastructure to US forces in Iraq will be accounted for, and when the House will formally be asked to vote monies as a consequence. We also request an explanation of why this drawdown cost does not feature in the broken down costs set out in the Government response to our last Report on the Spring Supplementary Estimates.

Urgent Operational Requirements

23.  In our Report last year on the 2008-09 Main Estimates we expressed some concern at the future impact on the MoD's main Budget of the substantial sum expected to be spent on Urgent Operational Requirements (UORs) in that Financial Year.[26] At the time of those Main Estimates, the MoD expected the cost of UORs in 2008-09 to amount to £1.065 billion. By the time of the Winter Supplementary Estimates this figure had been refined to £1.063 billion[27]—and by the time of the Spring Supplementary Estimate it had fallen very slightly to £1.054 billion.[28] The formal outturn cost on UORs for that Year is yet to be made available to us.[29] We accept the assurances of the MoD in the Government response attached to this Report that the cost will not go beyond the £1.065 billion originally cited, not least because 50% of any sums spent on UORs beyond this limit would fall partly on the MoD main Budget for 2010-2011, in line with the agreement between the Treasury and the MoD announced to the House by the then Secretary of State, the Rt Hon Des Browne MP, on 12 November 2007.[30]

24.  In the memorandum accompanying the MoD Main Estimates for 2009-10, the MoD helpfully broke down UOR costs for each theatre and by resource and capital. This is set out in the Table below: Table 6: Forecast UOR expenditure breakdown in 2008-09
Type of Cost Iraq £M Afghanistan £M Total UOR £M
Resource 116128 244
Capital 147663 810
Total 263791 1,054

Source: Ev 13

The MoD also pointed out in that memorandum that the additional capital request in the Spring Supplementary Estimate included new UOR costs of £13 million for Iraq and a combination of £17 million new costs, some forecast UOR reductions of £18 million and £53 million for the Protected Mobility UOR package for Afghanistan.[31] That this additional UOR cost of £65 million is likely still to permit the total UOR cost in the outturn to come in lower than the total set at the time of the Winter Supplementary Estimate presumably means that there were other savings earlier in the Year or that the original forecast was generous. We would be grateful for confirmation of UOR costs for 2008-09, accompanied by a note explaining the changes to the composition of these costs over the period concerned.

25.  We note that the MoD in its response to our earlier Report and in the later supplementary memorandum also points out that the estimate for UORs in Financial Year 2009-10, as agreed with HM Treasury, is £635 million, considerably less than for the previous Financial Year. Any UOR costs over and above this agreed sum of £635 million will fall in full on the Defence budget in Financial Year 2011-12.[32] We would be grateful for an explanation of why UOR costs beyond the limit agreed between the Treasury and the MoD are now to fall in full upon the MoD two Financial Years later: this seems to go against the agreement announced to the House by the then Secretary of State, the Rt Hon Des Browne MP, in November 2007, which stated that such costs would be split 50:50 between the Treasury and the MoD. One reason for the reduction in UOR costs is that the Protected Mobility Package (PMP) for 2009-10 will not be taken as part of the UOR spend as it was in 2008-09. (Arrangements for 2010-11 are not yet settled.) While £53 million of the PMP was covered by the total UOR estimate last Financial Year, the £424 million of Treasury contribution to this Financial Year's PMP costs is being dealt with separately, out with the UOR allocation.[33] However, even taking into account the amount of PMP costs within UOR costs last year, UOR costs this year will still be below non-PMP UOR costs for Afghanistan last year. We request the MoD, in its response to this Report, to break down the projected 2009-10 £635 million UOR costs in the same way as it did for 2008-09, by theatre and by capital or resource type. We are concerned that this limit on UOR costs may be an indication that the key ingredients of UORs, namely that they are required, urgently, for operational reasons, may be seen taking second place to cost considerations. We also request the MoD to give an explanation of why UOR costs are expected to be so much less than for the previous Financial Year.

26.  The supplementary memorandum from the MoD attached to this Report helpfully sets out that while the Treasury is providing £500 million for this PMP over three Financial Years (£53 million in 2008-09, £424 million in 2009-10 and £23 million in 2010-11) it is not clear yet what the costs to the MoD will be and when they will fall. The estimate given in the Government response to our Report on Defence Equipment 2009 (received on 27 April) suggested that the total cost of the PMP would be £680 million, £180 million thus falling to be paid for by the MoD.[34] This overall sum has already risen by 9.7% since the original estimate. As the £500 million Treasury contribution is already set and not subject to change, the MoD will have to carry 100% of any continuing increase in costs for the PMP. We are concerned that there might still be significant increases in the cost of the Protected Mobility Package, all of which will fall to be paid in full by the MoD. We request the MoD in its response to this Report set out its latest assessment of the cost to it of this Package, when this cost is likely to fall, and when the House will formally be notified of this cost.

Conclusion

27.  We recommend that the House of Commons approve the MoD's Main Estimates, and have identified no issues which require a debate before it does so. The House should note that for the first time these Estimates contain a formal request for resources for operations in Iraq and Afghanistan which means that, while they cannot directly be compared to previous Main Estimates, they do represent a more realistic assessment of operational costs and of monies for which the MoD is responsible for the whole Financial Year.


1   HM Treasury, Central Government Supply Estimates 2009-10, Main Supply Estimates, 18 July 2009, HC 514 Back

2   Ev 1-10 Back

3   Ev 11-14 and Ev 14-15 respectively Back

4   Defence Committee, Eighth Report of Session 2007-08, Operational costs in Afghanistan and Iraq: Spring Supplementary Estimate 2007-08, HC 400, paras 2 and 3 Back

5   Defence Committee, Fourth Report of Session 2005-06, Costs of peace-keeping in Iraq and Afghanistan: Spring Supplementary Estimate 2005-06, HC 980, para 15 Back

6   Defence Committee, Fifth Report of Session 2005-06, Costs of peace-keeping in Iraq and Afghanistan: Spring Supplementary Estimate 2005-06: Government Response to the Committee's Fourth Report of Session 2005-06, HC 1136, paras 3 and 4 Back

7   Defence Committee, Third Report of Session 2006-07, Costs of operations in Iraq and Afghanistan: Winter Supplementary Estimate 2006-07, HC 129, para 8 Back

8   Defence Committee, Eleventh Report of Session 2007-08, Ministry of Defence Main Estimates 2008-09, HC 885, paras 17-27 Back

9   ibid., Ev 3, para 6.6 Back

10   ibid., para 15 Back

11   Ev 4, Table 8 Back

12   HC (2007-08) 885, Ev 3, para 4.4 Back

13   HC (2007-08) 885, paras 14, 15 and 17 Back

14   Defence Committee, Fourth Report of Session 2008-09, Spring Supplementary Estimate 2008-09, HC 301, para 7 Back

15   Ev 12, response to recommendation 6 Back

16   Ev 4, Table 8 Back

17   HC (2008-09) 301, p 9, Table 2 Back

18   Ev 4, para 4.4 Back

19   HC (2008-09) 301, paras 8 and 9 Back

20   Ev 12, response to recommendation 7 Back

21   Ev 15, response to question 5 Back

22   ibid. Back

23   Ev 13, response to recommendation 8 Back

24   Ev 16 and 17 Back

25   Ev 14, response to question 1 Back

26   HC (2007-08) 885, para 14 Back

27   Defence Committee, First Report of Session 2008-09, Winter Supplementary Estimates 2008-09, HC 52, para 17 Back

28   HC (2008-09) 301, para 15 Back

29   Ev 13, response to recommendation 10 Back

30   HC Deb, 12 November 2007, col 500 Back

31   Ev 13, response to recommendation 9 Back

32   ibid., response to recommendation 10 Back

33   Ev 13, response to recommendation 10, and Ev 15, response to question 6 Back

34   Defence Committee, First Special Report of Session 2008-09, Defence Equipment 2009: Government response to the Committee's Third Report of Session 2008-09, HC 491, p 5, response to recommendation 7 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2009
Prepared 2 July 2009