Ministry of Defence Main Estimates 2009-10 - Defence Committee Contents


Supplementary Memorandum from the Ministry of Defence

ANSWERS TO THE HOUSE OF COMMONS SELECT COMMITTEE'S MOD ESTIMATESRELATED QUESTIONS

Set out below are the MOD responses to the questions raised in the Select Committee's letter dated 11 June regarding:

    1. The Government response to the HCDC report on the 2008-09 Spring Supplementary Estimate;

    2. The Departmental Minute of 8 May 2009 (dealing with the gifting of infrastructure in Iraq);

    3. The 2009-10 Main Estimates.

1.  Can the MOD confirm in which FY, 2008-09 or 2009-10, the costs of £96.476 million, set out in the Departmental Minute of 8 May 2009 (for the gifting of infrastructure in Iraq), fall?

  This represents the whole cost of the project; Tranche 1 (4 dining halls); and Tranche 2 (accommodation and hospital). £61.270 million of the costs fall in FY 2008-09 with £34.749 million falling in FY 2007-08 and the remaining £0.457 million relating to Disposal Sales Agency's (DSA) valuation for the contents of the dining facility areas, such as walk in refrigerator units and food preparation areas. As the buildings came on line at different times and this was a DSA valuation we are not able to split this £0.457 million into different financial years.

2.  Can the MOD confirm when the business case for the accommodation units and the hospital in Iraq referred to in the Departmental Minute of 8 May was submitted to HM Treasury and approved? Can the MOD also confirm what the costs cited within that business case were?

  Following approval of the Business Case for Tranche 2 (3 accommodation blocks and hospital), the Secretary of State wrote to the Chief Secretary in December 2007 seeking Treasury approval for Reserve funding of £64.563 million. The Chief Secretary replied, approving the build, on 18 December 2007.

3.  Can the MOD set out a more comprehensive breakdown of those costs touched upon in the Departmental Minute and explain why those costs, for dining facilities, accommodation units and a hospital, the latter two incomplete, were so high?

  Since the site was under continued rocket attack, time was of the essence. Delay could have cost lives. Extensive threat analysis concluded that a clear risk of a mass casualty event existed. This analysis identified a need to rapidly deliver protection for the deployed force in areas which were particularly at risk from such attacks. These were areas where large numbers of personnel congregate, such as during dining periods, sleeping accommodation, and bringing the Role 2 (enhanced) hospital under cover. The approximate unit cost of the buildings was £10 million each, of which £4 million was for the major reinforced concrete plinth on which the building stands. The Tier 3 protected structure programme build delivered football pitch size hardened buildings capable of defending against rocket attack. The technical specification, and performance against ballistic weapons, is classified. These buildings form the final line of various layers of defensive measures fielded at the Command Operating Base .

4.  Can the MOD provide an assessment to the Committee of the stage of completion achieved in the construction of the accommodation units and the hospital to be gifted in Iraq?

  The initial four dining facilities were completed to their full intended operating capability. The remaining buildings were constructed to a waterproof and weather-tight standard before handover to US Forces for reconfiguration to alternative uses. The modular hospital and accommodation units which were intended to be incorporated into the structures were held in Kuwait when UK intentions at the operating base became clear. These assets have now been reassigned to OP HERRICK and are awaiting shipment to support other operational requirements.

5.  Can the MOD provide a breakdown of drawdown costs for Iraq in Financial Year 2008-09, showing the extent to which the extra £455 million allocated in the Spring Supplementary Estimate has been used, and if so, on what?

  The Department requested a contingency of £455 million in anticipation of the draw down costs of Iraq to cover potential non cash costs of depreciation, write-offs, and gifting of equipment and other capital assets. The provisional Indirect DEL outturn for 2008-09 indicates a lower figure. However, these figures are still subject to final audit confirmation. Work is ongoing to ascertain the final impairment costs of fighting equipment deployed in Iraq.

6.  Can the MOD explain the reason for the decision for Protected Mobility Package costs to be classed as UOR costs in FY 2008-09 but to be not so classified in 2009-10? Can the MOD yet set out what category these costs will fall in for 2010-11? Can the MOD set out what the MOD's contribution to the PMM is expected to be in FYs 2008-09, 2009-10 and 2010-11?

  The Protected Mobility Package, announced on 29 October 2008, will deliver nearly 700 vehicles urgently required for operations in Afghanistan. HM Treasury has agreed to provide £500 million of funding over three financial years, and their contribution is programmed to be £53 million in FY 2008-09, £424 million in FY2009-10 and £23 million in FY2010-11. The MOD will fund the remainder; the spend figures will vary over the course of delivery of the programme because of cost growth and exchange rate variance, and therefore it is not possible to give the exact costs or MOD contribution at this stage. While this package will deliver crucial and urgent capability for current operations in Afghanistan, it is also relevant to the MOD's longer-term equipment plans, so it is appropriate that the MOD should contribute towards the package.

  The Protected Mobility Package was agreed between MOD and HM Treasury in the middle of the financial year 2008-09, and the in-year spend was counted towards that year's UOR estimate to reflect delivery of the theatre specific aspects of the package. As financial years 2009-10 and 2010-11 were still some way off at the time that the package was agreed, and because elements of the package have utility for long-term Defence requirements, the costs for those two financial years are being dealt with separately from the UOR estimates.

7.  The reduction in administration spending between years is 2.5% (RFR1, Section M) compared to the 5% year on year savings set in the Spending Review for departments (see paragraph 1.1 of explanatory memorandum). What progress has been made in administrative efficiencies and reductions in back office/admin staff and is MOD on target to achieve the 5% savings required?

  The MOD is required to reduce expenditure on administrative costs by 5% per annum in real terms. There is a 5% reduction between 2008-09 and 2009-10, once inflation (at 2.7%) has been taken into account. Significant change programmes are in place to deliver the required savings—most notably the Streamlining reductions in Head Office, and the PACE programme in the Defence Equipment and Support organisation. On current plans, the savings targets are forecast to be achieved.

8.  Last year the AME budget for Defence Equipment and Support (RFR1, Section O) was negative (-£114 million) although it is not clear why. This year a budget of £27 million is sought. This may be a technical, accounting, change but could the MOD can explain what has changed?

  The AME credit scored against the Defence Equipment and Support organisation in 2008-09 related to a reduced cost of capital charge accounting adjustment. This adjustment resulted from lower total nuclear provisions than originally provided for in previous years, following a review of the level of nuclear provisions. The level of the creation of new nuclear provisions in 2009-10 is broadly in line with previous years.

9.  In 2008-09 there was a provisional overspend on the net capital budget of £81 million, due to lower than forecast capital receipts (exp memo paragraph 3.6). As a result, HM Treasury are deducting this from the 2009-10 capital budget. Are MOD budgets for 2009-10 and beyond being adjusted for anticipated receipts shortfalls as a result of the downturn in the property market? What impact will this have on spending plans?

  The level of receipts anticipated from the disposal of the MOD estate is reviewed during the planning round. The figure for 2009-10 was revised downward by £70 million in the 2009 planning round to reflect an expected reduction in the volume of the estate sold. The potential effect from 2010-11 onward will be considered in the 2010 planning round.

10.  Overall, capital (DEL) spending is still budgeted to rise by 9.7%, from £8,313 million to £9,121 million (+9.7%) (comparison of DEL tables in Main Estimates 2009-10 and Spring Estimates 2008-09). Around half of this appears to be going on Urgent Operational Requirements in Afghanistan. What are the main components of the increases in RfR1 (Provision of Defence Capability) and what are these designed to achieve?

  RFR1 CDEL expenditure increased from £7,687 million in Spring Estimates 2008-09 to £7,861 million in Main Estimates 2009-10 (as shown in the table below). This represents an increase of £174 million (around 2¼%), broadly in line with the Defence budget. The additional resource has been allocated across the MOD's entire capital investment programme, primarily to equipment and support.


2008-09 £M 2009-10 £M
RFR17,6877,861
RFR21,1281,565
Non-operating A-in-A-501 -305
Total£8,314M £9,121M




11.  The comment at Paragraph 4.5 of the explanatory memorandum suggests that expenditure is expected for the Balkans but has not been included in the Main Estimate. If it is known that some expenditure will be incurred, why is no Balkans funding included in the Main Estimate, particularly as last year Balkans funding was included in the Main Estimate?

  As we stated in our 2009-10 Main Estimates Memorandum, Balkans funding will be requested in the Supplementary Estimates once any planned drawdown arrangements have been finalized. We wish to be in the position only to ask Parliament to vote on a request for resources which is sufficiently robust.

12.  Are there any significant increases to provisions (for liabilities) being made in the Main Estimate? (paragraph 12 of the explanatory memorandum)

  There are no significant increases to the planned creation of provisions in the 2009-10 Main Estimates. Any subsequent change in the level of provisions will be reflected in the Supplementary Estimate round.

24 June 2009



DEPARTMENTAL MINUTE REGARDING THE GIFT OF UK PERMANENT STRUCTURES WITHIN SOUTH EAST IRAQ TO THE US ARMED FORCES

  It is the normal practice, when a Government department proposes to make a gift of a value exceeding £250,000, for the department concerned to present to the House of Commons a Minute giving particulars of the gift and explaining the circumstances; and to refrain from making the gift until fourteen Parliamentary sitting days after the issue of the Minute, except in cases of special urgency.

  The gift in question is to the US Armed Forces and consists of four permanent protected structures currently used as UK dining facilities located within the Contingency Operating Base (COB), Basra. The COB has been occupied by the UK Armed Forces since May 2003 as part of Operation TELIC. The UK's planned transition within Iraq will see our Armed Forces, during the early part of 2009, hand over responsibility for the military operation within Multi-National Division (South East) to the US. In order to enable this transition the UK Armed Forces will be required to vacate the COB to allow a US Brigade Unit under the command of HQ 10th Mountain Division to infill.

  In accordance with Departmental Gifting policy, the MOD Disposal Services Authority (DSA) and Defence Estate Land Agent (DLA) have provided asset valuations. DSA have valued the contents (non-fixed assets) of all four permanent dining facilities at £456,885. The contents comprise sinks, walk-in refrigeration units, food preparation areas, catering equipment and furnishings. The permanent structures have been given a zero value by the DLA as they sit on Iraqi soil and cannot be sold on the open market. UK investment over financial years 07/08, 08/09 is £45.399 million, which through impairment (a technical write down in value) is reduced to a nominal sum of £1. The US intention is to use the four permanent structures as dining facilities, although should this change the MOD will instruct DSA to sell the removable contents from each. The structures and their contents will eventually transfer to Iraq when the US Armed Forces no longer have a use for them. In total, the gift is worth £456,886.

  Although not a gift, an additional four incomplete structures have been handed over to the US Armed Forces, which will eventually transfer to Iraqi control. The total value of these structures was £50.620 million, which has been treated as a constructive loss. The combined value, therefore, of all buildings and contents is £96.476 million-£45.399 million (hardened structures gifted, impaired to £1), £0.457 million (the gifted contents) plus £50.620 million (the constructive loss on the incomplete structures).

  The Treasury has approved the proposal in principle. If, during the period of fourteen parliamentary sitting days beginning on the date on which this Minute was laid before the House of Commons, a Member signifies an objection by giving notice of a Parliamentary Question or of a Motion relating to the Minute, or by otherwise raising the matter in the House, final approval of the gift will be withheld pending an examination of the objection.

8 May 2009





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2009
Prepared 2 July 2009