DE 11
Supplementary memorandum from the Ministry of Defence
TLCM
(i)
At the evidence session on 18 November 2008, industry witnesses
emphasised the importance of the Through Life Capability Management (TLCM)
approach. Is the Mo
Good
progress has been made in implementing Through Life Capability Management
(TLCM). Since the publication of the
Enabling Acquisition Change report in 2006, the
TLCM will take time to implement as it requires different ways of thinking and working rather than just process change. The basic elements are already embedded across defence, principally to support the way we approach our capability planning. As part of the next phase, we are focusing on how we deliver military capability more effectively. In line with the Office of Government Commerce's guidance on Managing Successful Programmes, we will introduce a programme approach; aggregating many individual delivery projects, both new and in service, into broader through life capability based programmes. This next phase commenced in early November 2008 and is expected to be embedded by March 2010, although experience from similar changes in other public and private sector organisations suggests a need for continuous improvement over time.
Spending
Review 2007 provided the
Programme Slippage
(ii)
The Mo
Low probability but high impact risks
are more likely to occur during the testing and evaluation phase of a
project. Of the major contributors to
the reported forecast slippage in 2007/08, three projects - Terrier (Combat
Engineer Tractor) (27 months), General Service Respirator (22 months) and
Precision Guided Bomb (18 months) - were at this stage.
To reduce both schedule and cost risk, greater emphasis is being placed on investment prior to Main Gate decisions, the aim being to ensure greater technical, financial and commercial maturity of solutions. Evidence of this comes from the Future Carrier programme where the assessment phase was extended to further mature the design and carry out additional risk reduction work aimed at reducing both schedule and cost risk. Other examples are the Search and Rescue Helicopter (SAR H) project and Maritime Airborne Surveillance and Control (MASC) project.
Armoured Vehicles / FRES
(iii) What will happen to the 400 vehicles that will be
removed from current operations when the new vehicles, which were announced on
29 October 2008, come into service? If they are to be retained, will the storage
and / or recuperation costs be funded from the Mo
A decision has yet to be made on this issue. The
(iv) Has a contract for the package of risk reduction work relating to the FRES Utility Vehicle programme been let and, if not, when is it expected to be let? When is the risk reduction work expected to be completed by?
As the Secretary of State announced on 11
Separately, as the Secretary of State also announced, in the context of current operations and bearing in mind the considerable recent investment in protected mobility, we have concluded that the highest priority should now be accorded to delivering the Warrior Capability Sustainment Programme and the FRES Scout vehicle as quickly as possible. Whilst this will mean a delay to the FRES Utility Vehicle programme, we recognise the importance of the Utility Vehicle and are now looking at the best way to take this procurement forward.
Nimrod MRA4
(v) In 2007-08, the Nimrod MRA4 programme experienced an additional cost increase of £100 million and an additional three months time delay. Has the programme experienced any further cost increases or delays in the current financial year? If so, of what order? If there are further delays on the programme, are there other aircraft which might meet the required capability and, if so, are they being considered?
In Spring 2008 further potential cost increases were identified by BAE Systems on the procurement aspects of the Nimrod MRA4 programme. Work is underway to scope the extent of these increases and identify potential mitigation measures. The programme has not experienced any additional time delays.
15 December 2008
|