ARA 01
Memorandum
from the Ministry of Defence
1. The fourth quarter of 2008-09 showed a
large rise in forecast cost increases in military equipment procurement (figure
1.5, p 15) compared to recent quarters. The report identifies four major
drivers of such cost overruns (p107). What is being done to mitigate forecast
cost increases and improve performance against DSO
3? What is being done to improve the reported current slippage rate of 26% and
63 months and what level of slippage does the Department
believe it acceptable to bear?
As the Defence
Secretary indicated in his statement of 15 October on publication of Bernard
Gray's review of Defence Equipment
acquisition, the Department has
implemented a succession of initiatives to improve acquisition processes,
including Smart Acquisition, the Defence
Industrial Strategy and the Defence
Acquisition Change Programme. The statement included further steps which we
will be taking, in the light of the Gray report, to build on earlier reform and
deliver a radical improvement in performance.
The factors affecting the performance
of military equipment projects within the scope of Departmental
Strategic Objective 3 ( DSO 3) were
discussed in the essay on pages 107-108 of the Annual Report and Accounts. This
notes that Defence acquisition faces
significant challenges in procuring and supporting some of the most complex
engineering projects available, to be capable of operating in some of the
harshest global environments. In considering projects monitored for DSO 3, the 14 projects initiated after the 2004
Smart Acquisition reforms have demonstrated better controls than those that
preceded them, and show a net reduction in cost of £4m against their approved
levels. Looking at the whole DSO population of 41 projects, just under half the
total cost variation (46%) in 2008-09 was attributable to factors that are
largely outside the Department's
control, such as foreign exchange rates, as well as inflation. Just under a further half was due to
deliberate decisions taken by the Department
to reflect changed circumstances or priorities. Technical issues accounted for
the remaining element, some 9%, and covered problems such as cost or time
overrun.
The 14 projects initiated after the Smart
Acquisition reforms contributed 63 months time slippage (26%) against the total
slippage of 242 months for the DSO
project population as a whole.
DE&S continue to embed
the principles of Smart Acquisition to improve performance against cost and
time targets. Achieving the balance of
military superiority in an intrinsically unpredictable environment means that
many projects sit permanently at the most advanced edge of technology and are
therefore inevitably technologically risky. We seek to share these risks in the
most appropriate manner and strive to deliver within the required cost and time
envelopes. DE&S
is committed to up-skilling key
professional staff, including through the achievement of professional
qualifications, to ensure they have the skills necessary to continually improve
performance.
DSO 3 recognises that
realistically, given the scope and complexity of the Defence
equipment programme, some project cost growth and time slippage is inevitable.
The targets of 0.4 months per project and 0.2% cost growth per year agreed with
HM Treasury reflect.
2. General
Sir David Richards, the new Chief of
the General Staff, is reported as saying in August that "I believe that the UK will be committed to Afghanistan in
some manner - development, governance, security sector reform - for the next 30
to 40 years". What are the MoD's
assumptions about the likely trajectory of costs for operations in Afghanistan
over the next few years, given the likelihood of operations continuing for a
significant period into the future?
As we highlighted in our response to the
Committee's comments on our 2009-10 Main Estimate (HC773), the increase in
costs for this financial year include the additional security costs
required for the local elections, the costs of personnel providing counter
improvised explosive device (IED)
expertise, additional capital costs for Urgent Operational Requirements (UORs),
and the provision of increased airfield and associated support infrastructure.
The changing nature of operations means that we
cannot predict their cost in future years with any confidence. We will provide
a further estimate for 2010-11 in our Main Estimate submission early next year.
3. Combat
operations in Iraq
have now ended. Troops have been withdrawn, and you plan to retain only around
100 personnel in the area. How much do you expect the drawdown process to cost
in total?
We have now successfully completed drawdown from Iraq with the
extraction and remediation of all personnel and equipment. All UK occupied or
managed facilities have been passed over to US forces, or handed back to Iraqi,
or Kuwaiti authorities. The completion of the operational closure phase ensures
that data collection is now fully underway and the full cost of the drawdown
will be clearer once this activity is completed and all receipts collected.
Our response to the Committee's comments on our
Main Estimate (HC773), noted current costs associated with the drawdown from Iraq. The main
asset impairment (during 2008-09) is a charge of some £63m for
accommodation/infrastructure (Tier Three); and there was also a constructive
loss of £48.9m for the transfer of four incomplete permanent structures
following drawdown. Both were reflected in the 2008-09 Annual Report and
Accounts (HC850).
Our total outturn in non-cash proved lower than the
provision sought in the Spring Supplementary Estimates, reflecting the
considerable uncertainty in the potential impairments at the time the estimates
were drawn up.
4. Could you give us more detail about
the outcome of the exercise to assess recorded assets to determine whether they
should be recovered, gifted, sold or written off, under Operation BROCKDALE? What value of assets (equipment and
infrastructure) is covered by each category? What key equipments have, or will
be, sent from Iraq to Afghanistan?
(Answer to follow)
5 You
have now spent over £4bn on Urgent Operational Requirements for both
operations. Have you made any assessment of what will happen to this equipment
once operations are complete? The net additional costs to the Department for operations in Afghanistan
continue to be met from the reserve. What assessment have you made of the
future impact on the Department's
budget, if Urgent Operational Requirement purchases become part of the Department's core equipment fleet?
Urgent Operational Requirements (UORs) are
specific to operations and hence not part of the core Defence
equipment programme. After UOR procured equipment has been in service for one
year, or at the end of the operation, (whichever is sooner) its effectiveness
is reviewed against the original capability requirement. Following this review
there are four possible options for the UOR:
· If it has proved effective in
its intended operational context and demonstrated potential utility elsewhere
it may be taken into the core equipment programme.
· If it has proved operationally
effective but has not demonstrated potential utility elsewhere it will be
maintained for the duration of the operation.
· If it has proved only
partially operationally effective it will be run into obsolescence
without further investment prior to end of life disposal.
· If it has proved ineffective,
or the capability is no longer required and it offers no other utility, it will
be disposed of.
As outlined in a closed session with Committee in
May 2009, we are taking a number UOR projects into
core, at a total cost of around £50m. The general areas covered include
military vehicles, communications and medical equipment. We continue to keep
all UORs under review, and, where appropriate, consider whether to bring them
into the core programme
6. Why does your Annual Report no longer
give any information on the target for readiness as has been the case in
previous years? What figure are you aiming for and how is this calculated? Are
you satisfied that the lack of a visible target does not hinder the
transparency of MoD performance in
this area?
The
2004 Spending Review Public Service Agreement set a target of a weighted
average of 73% of Force Elements reporting "no serious" or "critical
weakness". This target was not carried forward into the 2007 Spending
Round agreement, reflecting the fact that such a target had become largely
irrelevant when the Armed Forces have been operating at high tempo and for a
sustained period. The target related to readiness for the entire range of
contingent capability and the Armed Force have simply not been able to maintain
readiness across such a broad spectrum whilst ensuring they deliver the highest
priority, success on current operations. The focus is now on recuperation; internal
targets are being set to recuperate specific capabilities rather than a very
general measure which does not relate to any specific type of operation.
Further detail is classified at this stage.
7. You
were unable to generate the full contingent capability of trained forces for
the Joint Rapid Reaction Force in 2008-09. When do you expect to be able to
provide a limited capability, and when do you anticipate being able to provide
the full capability?
Defence continues to generate and sustain high
quality, properly trained Force Elements for all programmed operations.
We have also made the regeneration of specific elements of the force structure
to deliver a bespoke contingent Small Scale (SS) Focussed Intervention (FI)
capability a priority, in particular the ability to conduct FI for Counter
Terrorism (CT) and complex Non-combatant Evacuations Operations (NEO).
Whilst many of the elements that we plan to have available for this task are
not involved in current operations and remain ready, others within the Joint
Rapid Reaction Force (JRRF) have been affected by the high operational tempo
sustained over the last seven years and need to be recuperated; this will take
time and resource.
The current estimated timescales for recuperation
are classified and Committee has been given them in closed session, together
with an explanation of how they relate to the scales of effort and associated
military tasks, as part of the Inquiry into Readiness and Recuperation on 28
April 2009.
8. How far do you expect contingent
readiness to improve following the drawdown of personnel from Iraq, and when
do you expect to see the improvements reflected in improved readiness figures?
The successful conclusion of
operations in Iraq will, on
current assumptions, following recuperation, return overall commitments to
within existing concurrency assumptions but, crucially, while Afghanistan
remains a Medium Scale (plus) operation, some force elements such as enablers
will continue to operate beyond those routine concurrency assumptions.
The benefit of the TELIC drawdown is being taken firstly in putting the
current Operations Commitments Plot on a more sustainable footing, reflecting
the main effort of success in Afghanistan.
Beyond that the drawdown should, over time and subject to sufficient resource,
enable an increase in readiness and we are focussing initially on recuperation
of key Small Scale capabilities.
9. Why does your annual report not contain
any quantification of the costs and timescales of the main NEIP projects
compared to budgets and plans? (DSO
3 PI 3.2) Can you give us more information on your NEIP projects, for example
on the scale of the investment?
The Non
Equipment Investment Programme (NEIP) is a central programming tool comprising
approximately 70 funding provision "lines" for a diverse selection of
infrastructure programmes. This approach enables informed judgements to
be made on projects looking out over 10 years and by balancing estate
rationalisation costs with the related disposal receipts.
The scale
of the NEIP is of the order of £30bn over 10 years. The Plan covers high
value (greater than £50m) estate rationalisation projects and Information
System-enabled business change programmes, including PFI projects. Programmes
vary considerably, from the delivery and long term support of Information
Infrastructure, long term (up to 30 years) service provision of serviced office
accommodation. Examples illustrating the diversity of the Plan include:
· Project
Allenby Connaught. In addition to a major £1.4bn, 10-year, construction
programme involving the new build or refurbishment of 550 buildings and the
demolition of 447, the 35 year project encompasses a wide range of support
services including catering, cleaning, transport, estate management, document
production and handling, stores and waste disposal. The Project has a total
through life value of some £8bn and covers Army Garrisons across Salisbury
Plain and at Aldershot.
· The
Royal School of Military Engineering (RSME), a 30-year Public Private
Partnership, worth some £5.6bn, which will improve essential training and
provide significant investment for new and refurbished soldier accommodation.
· Defence
Information Infrastructure (DII), a
£4bn 10-year programme to provide and support a
single information infrastructure comprising a standard, consistent platform
for Defence applications and deliver
a more effective, modern environment for the sharing of information and the
transmission of messages. Ultimately, it will provide 300,000 user
accounts, on 150,000 terminals, spanning 2,000 MoD sites worldwide.
· Main
Building Refurbishment (MBR), a £750m 30 year programme to provide the Ministry of Defence with secure, modern and
efficient working accommodation in Whitehall
Following an evaluation of this work we have
introduced a more structured and granular approach. We have completed some initial work on how to
best collect, evaluate and report information on the progress of individual
programmes against their specific targets against DSO3,
given the potential to be misleading by applying a single performance target or
metric across the various programmes.
This will be included in further reporting.
10. In relation to nuclear deterrent, what
was the outcome of the two year concept phase, originally due to finish in
September 2009? Is this now complete and what decisions have been taken as a
result?
The Defence
Board and Ministers will consider the future deterrent Concept Phase work later
this year.
11. What
progress have you made in implementing the recommendations from the strategic
review of reserves? What is the status of the 47 recommendations subject to
further consideration and resourcing? Do
you expect that these will be implemented at a later date?
The implementation of the Strategic Review of
Reserves (Programme CITIZEN) is now well underway involving the MoD, single
Services and other key stakeholders. All programme activity is being
co-ordinated under the direction of the Vice Chief of Defence
Staff and is on track with some significant progress already having been made. The
Review of Reserves made 89 detailed recommendations. 46 of these are
being taken forward in the first tranche' with the remainder (mainly those with
resource implications) requiring additional research and consideration prior to
being taken forward. Of the 46 first tranche' recommendations, six have
been assessed as completed, 31 are making good progress with nine requiring
significant additional work. Two small
implementation teams, Personnel Policy and Volunteer Estate have now been
established and are leading on the key the areas of Terms and Conditions of
Service and the rationalisation of the Volunteer Estate respectively.
12. In relation to the Departmental Capability Review, Are you on track to
achieve a reduction in the size of Head Office under your streamlining
programme by April 2010? How have these reductions been achieved?
The Department
remains on track to reduce the size of the Head Office by 25% by April
2010. This has been achieved by a combination of re-deploying
approximately 250 military personnel back to front line posts, a civilian Early
Release Scheme, relocations out of Central London
and natural wastage. The majority of these posts were removed on 1 April
2009 and we are currently working on the redeployment of surplus staff. We
are also focussing on materially improving the way the business operates. A
small team has been trained and is supporting business units to improve the way
they make decisions, prioritise their work and measure and continually improve
their performance.
13. Table 3.21 (p91) shows defence outturn
against the DEL
budget. Defence
Equipment and Support shows a Resource under-spend of £507 million against a
budget of £15.195 billion. Paragraph
3.103 (p88) suggests that the under-spend was in large part the result of
favourable reassessments of asset lives which reduced depreciation costs. This
reduced depreciation cost may also have contributed to a £1.6 billion dip in DE&S Resource expenditure in 2008-09 compared
with the year before (see page 22). What other factors account for the £1.6
billion lower DE&S Resource
expenditure in 2008-09, compared to 2007-08 and indeed to 09-10?
Question
|
Response
|
The military pay process
On ensuring that accurate data is held
within the JPA system
· The
Department should establish a task force to systematically correct pay and
personnel records. There have been some improvements seen, and more are
planned, but a systematic cleansing exercise should be undertaken with clear
targets for the required levels of accuracy to be obtained and deadlines for
the completion of this work;
|
The
Joint Personnel Administration (JPA) Assurance and Compliance Working
Group has been established to provide coherence across initiatives to improve
and maintain data accuracy. The Group has already confirmed the areas of
concern that led to the qualification, established a baseline of existing
initiatives and initiated additional work. This will lead to
improvements in the quality of data held on JPA.
|
· Particular
attention should be paid to ensuring that the Department can meet its
statutory requirements for reporting to Parliament on Votes A manning levels
|
The
ongoing work on the validation of JPA data will support both in year and annual
reporting of Territorial Army and Royal Naval Reserve strengths
including Vote A requirements. In addition we are in the processes of
both improving data and cleansing the contract types for the TA. This
work will be completed during 2009.
|
On
access to the JPA system
· A formal
review should be undertaken of the existing levels of access to the JPA
system and whether they are sufficient to allow the processes to be operated
as intended. Where access is insufficient, alternative arrangements should be
introduced;
|
The
review into the infrastructure and application access problems is to report
in January 2010, to enable issues and perceptions to addressed. In
addition, a review of how self-service users, HR and accounting specialists
are trained and remain up to date is taking place to ensure that users have
the skills and competences to prevent errors arising and to improve data
quality.
|
· The
ability of the Department's main IT platform to support the JPA system going
forward should be reconsidered in light of the other applications which are
also dependent on this IT platform;
|
The
Department is engaging with all
appropriate parties to ensure that, for the future, JPA has an adequately
supported capable IT platform.
|
On
military pay process controls:
· The
Department should complete the review of controls begun last year to identify
those that are key and to consider if further controls are
needed. This review should take account of the need to reduce the
level of error and fraud in relation to basic pay, allowances and expenses to
an acceptable level and should ensure that there is a proper balance between
preventative and detective controls. More specifically:
|
The
review of controls, which includes the involvement of the Department's
internal auditor, is continuing. The JPA Assurance and Compliance
Working Group is coordinating a number of initiatives; a review of the
control framework, end to end assurance, closer working with finance staff
from across the different budget areas within the Department and regular
reporting on any suspected fraud. A wider review of training for users
and JPA documentation is also underway.
|
o consideration should be
given to activating the JPA system's capacity to allow line managers to
see each expense claim at the time it is input. Whilst they would not be
required to authorise the claim, this would provide visibility of the claims
being made and would provide an early alert on incorrect or ineligible
claims;
|
The
JPA assurance and compliance working group will consider this option.
|
o as
recommended in my predecessor's report, the Department should revisit the
level of payments above which a manual check is made. The current level
is all net payments over a set limit of £10,000;
|
The
Service Personnel and Vetting Agency (SPVA) is reviewing options for the
development of enhanced controls to cover potential erroneous payments.
This will include enhanced reporting of the results of those checks.
|
o the monthly 5% check on
expenses should be reviewed in order to determine whether there needs to be
an increase in the % level of checks;
|
The
effectiveness of the percentage level of the monthly check is reviewed on a
rolling basis by the single Services to ensure an optimal balance is achieved
between the deterrent effect of local checking and the workload thereby
engendered.
|
o the data mining techniques
currently being developed should be considered for wider use by budget
holders to assist in targeting their checks on the amounts with most risk
which are being charged to their budgets;
|
SPVA
are working with both Defence
Internal Audit and Top Level Budgets to engage budget holders to target
charges based on different risk profiles.
|
o the Department should
introduce a more formal system to monitor the effectiveness of preventative
and detective controls and a mechanism to enable enhancement of training
and/or controls in areas where errors are being identified;
|
Options
for the development of enhanced controls to cover potential erroneous
payments are being reviewed.
|
· reporting
of allegations of fraud and misuse of JPA and any underlying trends as well
as the subsequent outcomes should be enhanced and formalised;
|
The
Department has a zero tolerance for fraud. The single Service assurance teams
are working together to develop a common assurance regime. They will
also use new data interrogation technology to detect unusual patterns of
transactions and potential cases of fraud. The instances of investigated
cases of potential JPA fraud will be specifically monitored over the next two
years to establish trends and improve control.
|
· the
responsibilities of all parties, for example the TLBs, should be clear
and agreed,
|
The JPA Assurance and Compliance Working Group consists of
representatives from the Services, Top Level Budgets, SPVA and Defence internal Audit. to ensure consistency in
all areas of military pay and allowances across the Department; including a
common understanding of roles and responsibilities.
|
· the
adequacy of resources available should be reassessed in the light of the
evolving control environment;
|
In some areas resources have been increased and the overall adequacy
of resources against changing requirement is being closely monitored.
|
On
the provision of management information
· the
management information available should be reviewed to ensure it meets the
requirements of all stakeholders including budget holders on whom the
Department is relying for checks on out-turn most notably the TLBs;
|
The adoption of standard reports, already released, will achieve
greater coherence in reporting. In November 2008 new budget management
reports were delivered. Training in the use of these reports has now
been completed and as a result they are now being used to better affect in
the front line Top level Budgets.
|
On
achieving the JPA vision:
· the
Department should revisit the timetable for harmonisation of pay and
allowances to ensure the results are achievable and consistent with its
ability to amend the JPA system to cope with the resultant changes;
|
A detailed review of options to address harmonisation and
simplification is underway. In addition, the Future Pay Structure Study
which reports to the Service Personnel Board in March 2010 will consider
options for a future pay structure including greater harmonisation and thus
simplification of pay and specialist pay.
|
· Service
Personnel have a wide range of abilities, education and needs. The
Department should consider the range of support needed both at the existing
call centre and in Units is sufficient to ensure Service personnel receive
their entitlements;
|
The
JPA Training and Documentation Working Group is seeking to review and where
necessary improve JPA training and documentation. A review of how self
service users and HR specialists are trained and kept up to date is taking
place to ensure that users have the skills and competencies to prevent errors
and improve data quality.
|
· the
Department needs to begin its assessment on whether to upgrade to Oracle 12
and make the necessary preparations to review the current extensions to the
COTS product or make provision for further maintenance costs from 2012
onwards;
|
Oracle 11 will be fully supported until April 2013. SPVA are
already reviewing the costs and options for the Oracle upgrade.
|
Inventory
management
· the
Department should analyse the reasons for the increasing discrepancies in
stock counts and introduce appropriate additional controls to ensure that
stock systems are sufficiently robust and efficient to support operational
requirements, ensure efficient stock management and provide sufficiently
accurate information for financial reporting requirements;
|
Stocktaking
across the Defence Storage and Distribution Agency (DSDA) is now conducted by an independent team.
Results are reviewed at One star rank and scrutinised to identify trends and
to allow for remedial action to be taken at an early stage. The
combination of preventative quality checks, a strict stocktaking programme,
monthly analysis of stock adjustments and management snap checks will
identify problem areas and lead to corrective action. In 2009-10 40%
more items will be checked than in 2008-09.
|
· a review
should be carried out to confirm and clarify ownership of systems and to
identify ways to ensure existing systems and any new systems are
comprehensive and meet the identified needs of key stakeholders;
|
The
Material & Financial Accounting Programme Board will direct the
development of essential improvements to current processes, Information
Systems, policy and practice that will enable the implementation of effective
solutions to material and financial accounting problems within the End to End
Joint Supply Chain.
|
· a
review should be carried out to examine the interfaces between the various
stock systems, including the MEFAR, to ensure that an appropriate programme
of reconciliations is conducted which will confirm the completeness of
records and the robustness of data underpinning the figures in the
Department's Resource Accounts;
|
The
Inventory Optimisation Team will revise and republish Stock Accounting
Reconciliation Requirements. This document will detail the end to end
reconciliation process, from the Inventory Stock Management Systems through
the Stock Collation systems to MISA and the accounts' General Ledger.
New
processes for stock system data extraction and comparison between systems are
being introduced. Full reconciliations are anticipated to be carried
out quarterly, the first to be completed as at 30 September 2009, and these
will be made available to the NAO.
|
· all
stakeholders including the FAPC should be consulted as part of these reviews
and before any major changes to the current systems are introduced, and
· where
there are significant changes in key experienced personnel whether due to
rationalisation or other factors, the Department should put in place
strategies which support knowledge and skills transfer;
|
The
Material & Financial Accounting Programme Board will direct the
development of essential improvements to current, Information Systems, policy
and practice processes that will enable the implementation of effective
solutions to material and financial accounting problems within the End to End
Joint Support Chain.
|
Assets
accounted for using the MERLIN/MAESTRO systems
· The
Department should complete the census exercise and investigate surpluses and
deficiencies to ensure that its records can be updated;
|
The
census process has been supported with a personal letter from Chief of
Defence Material. A dedicated team has been established to ensure all
returns are received. All discrepancies will be cleared and the systems
updated to reflect an accurate position of assets held. Systems changes aimed
at improving asset reporting will be investigated.
|
· review
the timing of the census exercise and consider if it could be carried out
more effectively to allow the Department time to be able to investigate any
reported deficiencies and for these to be reflected in the financial
statements.
|
The
census date has been brought forward from January to September, allowing more
time to ensure returns are received and discrepancies followed up.
Instructions have been updated to ensure clarity at Unit level, where the
details are being recorded. An annual assurance report on the census will be
produced by 31 March 2010 to inform NAO's audit.
|
BOWMAN
communications equipment
· the
stocktake of BOWMAN equipment should be completed to establish as accurate a
record as possible and missing equipment should be formally written off;
|
Bowman
And Tactical Communication and Information Systems (BATCIS) provide
BOWMAN baseline information to facilitate HQ Land Forces physical asset
verification census. This is being conducted quarterly in 2009-10. Visibility
levels of around 90% are being achieved. The balance comprises stock in
transit to/from theatre and assets in the repair loop, both temporarily out
of sight of HQ Land Forces.
|
· procedures
should be developed to recognise the different types of equipment to enable
more effective asset management;
|
The
recommendation concerns L class items. BATCIS has published a business case
to update Joint Service Publication 886, Volume 4. The change will allow L
class items to be accounted for as consumption on issue from warehouse to
reflect the high value single use nature of the equipment.
|
· working
with the Army and their contractor, the Department should review the
procedures for accounting for BOWMAN assets including purchases, issues,
assets in the repair loop, losses, write-offs and assets in transit.
These procedures should be designed to provide the robust management
information required for operational deployment, stewardship and financial
reporting;
|
Defence
Equipment & Support has developed a Bowman Asset Management Improvement
Plan to address governance and accounting issues. A working
relationship has also been established with General Dynamics with a view to
enabling them to deliver regular quality management information to support the
MoD's materiel and financial accounting requirements. The project team is
working with HQ Land Forces to establish a process to report
damaged/destroyed assets, particularly those arising in operational theatre
and processes to reflect in the Accounts Fixed Asset Register.
|
· establishing
the levels of visibility required using an effective management information
system and mapping out how to achieve this with appropriate allocation of
responsibilities and deadlines;
|
Defence
Equipment & Support will continue to develop and roll out Bowman And
Communication Management System (BACMS) and Joint Asset Management and
Engineering Solutions (JAMES) systems which will enable serial number
tracking and accounting for Bowman assets. BATCIS will develop a database of
serial numbers as part of the Bowman radio baseline data supplied quarterly to
HQ Land Forces. As BACMS develops, serial numbers will be progressively added
with physical locations to improve visibility. Ultimately, JAMES will hold
the Master serial number and location library.
|
· as
costs have not been updated since 2006, the Unit Production Cost (UPC) of
each BOWMAN asset should be reviewed to ensure that the value of BOWMAN
assets reported in the Department's Resource Accounts is materially correct;
|
BATCIS
have conducted a re-costing exercise which confirms the present UPCs. The
evidence has been presented to NAO for their review.
|
More
widely:
· the
Department should ensure that no further equipment is issued without NATO
stock numbers, where this is the key identifier to enable effective
management of the assets, and
· the
Department should review other key equipment lines to ensure that the bespoke
inventory systems provide adequate records to support operational,
stewardship and financial reporting requirements.
|
The
Material & Financial Accounting Programme Board will direct the
development of essential improvements to current processes, Information
Systems, policy and practice that will enable the implementation of effective
solutions to material and financial accounting problems within the End to End
Joint Support Chain.
|
The reduction in
expenditure from 2007-08 to 2008-09, in addition to the reduction in
depreciation is due to Administration Costs being included in the 2007-08
outturn (Table 31 pg 214, Annual Report & Accounts 2007-08), but excluded
from 2008-09 return. These costs are now reported centrally for the Department
as shown in Table 3.21 (p91). The actual outturn of £14,688m is also shown in
this table. The 2008-09 figure on page 22 was only an estimated figure.
The 2009-10 Plan figure is higher than the 2008-09 outturn as a result of the
plan reflecting the normal level of expected non cash costs (depreciation etc)
as opposed to the one off reductions last year. This was due to a re assessment
of asset lives and capital spares as stated in paragraph 3.103(p88) in the
Annual Report & Accounts.
14. Para
3.139 (p99) refers to a £195 million shortfall in estate disposal receipts
compared with CSR plans. What discussions has the Department
had about the scope for the MoD's
budget being compensated for the impact of lower estate disposal receipts from
the depressed property market? What impact would this otherwise be likely to
have on the department's spending plans?
As pointed out in the
Report, the shortfall was caused by delays and the lower than expected receipts
due to the depressed property market. The impact of depressed market
conditions has been discussed with the Treasury, with the conclusion that the Department
should absorb the loss, on the grounds that it had benefited from gains in
earlier years when conditions had been more favourable than expected. The
receipts for delayed disposals will eventually be realised, although they are
still likely to be depressed by the market conditions. The resulting financial
pressures were addressed in the Department's annual planning round.
15. The National Audit Office has qualified
its audit opinion (p183) on the Resource Accounts due both to material error in
military specialist pay, allowances and expenses and to inadequacy of evidence
related to certain income and expenditure and asset holdings (as well as 'Votes
A' control). The Committee would like to
have a point-by-point analysis of what action the Department
is taking on each of the recommendations listed in the bullet-points on pp196-198
of the C&AG's audit report.
The answers are as follows:
16. Does
the Department accept all of the
findings of the NAO and proposed actions in relation to the Resource Accounts?
What action plans and timescales for implementation have been formulated, and
can these be shared with the committee?
The Department
has accepted the audit findings and the Defence
Equipment & Support Top Level Budget and Deputy
Chief of Defence Staff (Personnel)
area have major improvement programmes underway to resolve the issues
identified.
17. Also on the qualified accounts, what is
the Department's current estimate of
the likely extent of specialist pay and allowances payments that will be
recovered, and how much might have to be written off?
The National Audit Office results were extrapolated
from a sample of the overall population. Further work to identify the
actual number of errors is in hand. Where overpayments are identified
corrective action will take place in accordance with Joint Service regulations
18. What is the Department's
current estimate of the value of undocumented assets that might have to be
written off? How much of the 11% of Bowman assets not visible to stores
accounting systems does the MoD
consider are in the repair loop rather than missing?
Significant progress has been made
over the past two years to improve the visibility of Bowman assets. The Bowman and
Tactical Communications and Information System (BATCIS) project continues to
develop and roll out a system to track and account for Bowman assets, which are
designed to be easily transported and are widely dispersed and heavily used on
military operations This will enable us to better identify the number of
assets in service and in the repair loop and demonstrate full fleet
visibility. It is considered unlikely that any asset write offs due to
lack of visibility will be necessary.
19. Page 256 includes a 'claim waived or
abandoned' in respect of EDS non
recovery of costs, amounting to £9m. Why can the Department
not recover costs from EDS for JPA
non-performance?
Under the Service Provision Agreement a maximum
charge, that could be invoked, is calculated. Discretion exists for a
smaller sum to be charged where the maximum charge is deemed inappropriate, for
example when the reason for a service delivery failure cannot be
apportioned solely to EDS.
Additionally, the charge can be waived in total, for example when a service delivery
failure is judged to be as a consequence of circumstances outside EDS' control.
The £9m represents the maximum sum which may be
waived against service delivery failures under the Service Provision during the
Financial Year 2008-09. A significant proportion of the charges were not
invoked because service delivery failures were due to factors beyond EDS' control. Imposing failure charges for minor
breaches would both adversely affect the partnering relationship between the Department and EDS, and could be open to legal
challenge.
20. The Accounting Officer's Statement on
Internal Control (p178) and the C&AG's audit report note that the
complexity of the specialist pay and allowances system was an important
underlying cause of the breakdown in controls on these payments. What
consideration is being given to the scope for simplifying and/or rationalising
payments and allowances across the Services?
The Service Personnel Operating Board
(SPOB) has considered the issue and a detailed review of options to address
harmonisation and simplification is underway. In addition, the Future Pay
Structure Study which reports to the SPOB and Service Personnel Board in March
2010 will consider a number of options for a future pay structure including
greater harmonisation and thus simplification of pay and specialist pay.
21. What is the cause of the large reductions
in the assessed cost of the submarine force elements and Army field units in
2008-09 compared to 2007-08, as noted at p240?
The main reason for fall in the cost attributed to
the submarine force is the reduction in the value of provisions for nuclear
decommissioning following a review. There were also falls in the value of
submarine related stocks and capital spares consumed as well as a benefit from
the attribution of a share of the fall in departmental overhead costs resulting
from the movement on derivative financial instruments associated with the
forward purchase of foreign currency.
The costs allocated to Army Field Units have
reduced in 2008-09 (compared to 2007-08) partially as a result of more of the
Army's 2008-09 costs being allocated to Operations under Strategic Objective
1. There were also falls in the value of stocks and capital spares
consumed by Army Field Units as well as the benefit of the attribution of a
share of the fall in departmental overhead costs resulting from the movement on
derivative financial instruments associated with the forward purchase of
foreign currency.
22. The
Report notes that under the CSR's 'Value for Money' savings programme £114m has
been saved from the drawdown in Northern Ireland (para 3.123). The VFM savings
are scored on a counterfactual basis. To what extent do these savings represent
a faster and/or more extensive drawdown than that envisaged at the time of the
CSR in October 2007?
The drawdown in Northern Ireland
proceeded in 2008-09 as planned in the 2007 Spending Round and achieved the VfM
savings envisaged. The additional measures mentioned in the Report will
materialise from the final year of the Spending Round period.
23. The Report notes that the MoD is reviewing the 'business models' of the Met
Office, DSDA
and Oil & Pipelines Agency (para 3.128).
What is the latest position on that work?
Substantial progress has
been made since the Operational Efficiency Programme final report was published
in April. A detailed update on each review will be published in the Pre-Budget Report
in November.
24. What assessment has the MoD made of the levels of transparency and
accountability provided by the new system of objectives and targets in use in
this reporting period? Do you have
any plans to change this system?
The Department
now supports a number of cross governmental Public Service Agreements while
measuring success against three Departmental
Strategic Objectives. Assessments of these objectives and targets is
supported by use of the Defence Balanced Scorecard (as, indirectly, were the
previous Departmental PSAs) and responsibility for delivery of objectives is
clear within the related Defence Plan. A comprehensive review of
Performance Management is ongoing in parallel with related internal work on
strategy.
Ministry of
Defence
2 November
2009
|