Spend, spend, spend?-the mismanagement of the Learning and Skills Council's capital programme in further education colleges - Innovation, Universities, Science and Skills Committee Contents


Memorandum 6

Submission from the Learning and Skills Council (LSC)

1. INTRODUCTION

  This memorandum refers to the FE capital programme, the events relating to its funding and administration up until the Foster review and the steps now in place to continue the programme.

2. BACKGROUND

  2.1 The purpose of the FE capital programme is to support the refurbishment and renewal of the FE college estate. The LSC is responsible for the administration of this programme.

2.2 During 2008 it became clear there was an unsustainable rise in demand from colleges for capital funding. In December 2008 the decision was taken to defer all approvals of capital projects until detailed work had been undertaken with colleges to establish a fuller understanding of the situation.

  2.3 On 23 March Mark Haysom resigned as Chief Executive of the LSC. Geoffrey Russell was immediately appointed as acting Chief Executive with the immediate task to increase the certainty and clarity around the capital programme.

  2.4. Geoffrey Russell appointed an external team from Grant Thornton to review the financial data held by the LSC about capital projects. He also appointed a new Director of National Projects to take responsibility for the capital programme and to work with a new sub group of the Council charged with overseeing the programme.

3. THE FOSTER REVIEW

  3.1 When concerns were raised about the future of the funding project the chair of the LSC and the Secretary of State, DIUS, jointly commissioned Sir Andrew Foster to conduct an independent review. Sir Andrew was asked to consider the causes of the increased demand for funding, LSC's internal processes and the lessons to be learnt for the future.

3.2 Sir Andrew Foster reported his findings on April 1st. He concluded with eight recommendations:

  3.3 Recommendation 1 called for immediate "agreement on how the present demand-led approach can be supplanted by a needs-based approach with explicit priorities and choice criteria." The LSC support the move to a needs-based approach. We have now worked with stakeholders to develop new criteria and designed a process by which future bids for capital funding will be prioritised. We expect the first stage of the prioritisation process to be finished by the end of June in order for the LSC to approve a small group of college projects to proceed this summer. Further information about this process can be found in section 5.

  3.4 Recommendation 2 called for "an early and open process of engagement and consultation between DIUS, the LSC and the college sector." Since the report the LSC have already started a consultation process including the use of a reference panel of college principals and representative college groups convened by the AoC and we are also consulting widely with Regional Development Agencies and local authorities.

  3.5 Recommendation 3 called for processes to be "grounded in fully accurate and detailed information about capital schemes in the pipeline." He also suggested "there should also be a preliminary mapping of potential needs indicators to assist the discussion process." The LSC now has detailed information on all existing capital schemes and those in the pipeline. We have engaged Grant Thornton to independently verify the accuracy of the information currently held. We have also worked with specialist advisers who will independently apply the agreed criteria to projects in the pipeline to provide confidence that the resulting proposals will be fairly determined.

  3.6 Recommendation 4 focused on a realistic assessment being required of individual colleges that have incurred expenditure, with high expectations, but have no guarantee of final approval for their proposals." An initial assessment of costs already incurred by colleges with Approval in Principal has been carried out. LSC regional finance teams are working with these colleges to establish their financial position and to address any cash flow issues. The LSC has given a commitment that no college will become insolvent as a result of capital project delays. The LSC and DIUS are developing a policy position on how to deal with the legitimate costs incurred by colleges where their project may not now proceed in the near future.

  3.7 Recommendation 5 stated that in "order to achieve speedy implementation, it will be essential to have a blended approach of open consultation with the sector, matched by a small dedicated project management group which drives a highly organised programme across LSC and DIUS levels." In response a joint project team involving LSC and DIUS staff was set up with David Hughes appointed to take personal responsibility for LSC's capital programme, with the additional support of a senior finance director within the LSC. The LSC will be making further changes to the way the capital programme is managed which will help in this transition year from the LSC to the SFA and YPLA. We hope to be able to announce these changes, along with wider management arrangements shortly.

  3.8 Recommendation 6 involved talks being held with HM Treasury. The Budget on April 22nd saw an announcement of further funding for capital projects.

  3.9 Recommendation 7 called for "future development to take place in the context of a comprehensive and competent financial strategy that supports needs-related planning." The LSC is working with DIUS, colleges and stakeholders to assess the priority needs for the future. This assessment will provide, by Spring 2010, clarity on future needs and funding requirements. On this basis, a new financial strategy will be developed for the SFA, YPLA and local authorities to take forward in the discussions for the next spending review.

  3.10 Recommendation 8 asked for "active consideration to be given to the future working arrangements of the Skills Funding Agency and the Young People's Learning Agency." Discussions are underway with DIUS, DCSF and local authority representatives about the future arrangements for capital in the Skills Funding Agency and the Young Peoples Learning Agency. The new arrangements include regulation and oversight of capital by DIUS and DCSF, a new financial strategy and best practice procurement methods.

4. BUDGET 2009

  4.1 The Budget announced additional capital funding of £300m in the current CSR period. This will allow the LSC to give approval to a limited number of projects starting in 2009-10. Recognising the long-term nature of capital projects, the Government is planning to continue FE capital investment programme in future years, with a planning assumption of £300 million a year from 2011-12 to 2013-14 to be confirmed at the next Spending Review. This provides a provisional £1.2 billion in total to 2013-14. Following the Budget announcement the LSC has written to all College Principals detailing the new funding and how this will be allocated.

4.2 Although such commitments into the next spending round are provisional, this is welcome news and should allow us to develop around £750 million of new schemes. We feel there are three main areas of interest to the Select Committee moving forward.

  4.2.1 How we intend to use the needs based criteria in relation to the additional £300 million in 2009-10 and 2010-11 to identify those with the most urgent and greatest need projects, as well as the approach we intend colleges to take in prioritising projects for the next spending review period.

  4.2.2 How we support colleges which have incurred costs in developing their project proposal and in anticipation of their project being approved.

  4.2.3 How we ensure we deliver greater value for money on capital projects.

5. NEXT STEPS: PRIORITISING PROJECTS

  5.1 To maintain objectivity we have appointed PricewaterhouseCoopers (PwC) to assist in the drafting of the LSC's project selection criteria, as well as in the development of a scoring framework and assessment process which we hope to use for the first time in helping the Council select a group of projects at its meeting on 3 June 2009.

5.2 The Foster report made it clear that the criteria should be needs-based and set in the wider context of learning and skills. The LSC has therefore put together draft criteria to reflect that recommendation.

  5.3 The LSC proposes the following criteria are used to prioritise projects. We will be as inclusive as possible in consulting on this, but have very tight timescales to meet in order to deal with these urgent issues; our aim is to finalise by 15 May in order to have new projects selected at the 3 June National Council meeting.

  5.4 A key part of the consultation, based on the recommendations in the Foster report, has been discussions with a panel of college Principals convened with the support of the Association of Colleges. This panel met on 29th April and provided important input. We are also consulting with the Local Government Association and the Regional Development Agencies.

  5.5 The first stage of prioritisation is readiness, Colleges with project applications awaiting in-principle or detailed approval will be asked if they consider their projects can commence on site within three months or so. To meet this timetable we have appointed property consultants Lambert Smith Hampton (LSH), to review all of the capital applications currently extant. Their first priority is to identify those projects that are ready to be on site and building this summer. Projects which pass through the readiness gateway will then be assessed against the other criteria.

  5.6 Criteria. We propose that once readiness is agreed the following criteria are used to prioritise projects:

    —  Education and skills impact—this criterion assesses the extent to which the project addresses current and future education and skills need and supports industrial activism.

    —  Contribution to local economic and regeneration priorities—this criterion considers the wider economic and regeneration impact of the project.

    —  Co-dependency with third parties—this criterion looks at the practical implications of not proceeding with the project and the leverage ratios involved.

    —  Condition of estate—this criterion evaluates the condition of the existing estate and the impact on learners and the extent to which they are addressed by the project.

    —  Value for money—this criterion assesses the extent to which the project demonstrates that it has gone through a process to maximise value for money.

  5.7 It is clear that the urgent and greatest need projects will not include the majority of college projects which either have Application in Principle approval, or have been seeking such approval. We will therefore have a separate process for these and other new proposals from colleges which will provide us with a new needs-based priority list of projects. That priority list will be used to approve projects as and when funding becomes available in the next spending review period. We expect this prioritisation process to be based on the same criteria set out above.

  5.8 We propose a swift, streamlined and transparent selection process for the first round of project prioritisation. This process needs to be completed quickly so that projects can start on site as soon as possible.

6. NEXT STEPS: INCURRED COSTS

  6.1 The LSC recognises that colleges with projects that cannot go forward now for funding in this year or next may have to write off some development expenditures in their accounts. The LSC will work with each college with the help of independent property consultants to assess how the longer term value of expenditures can be maximised, as well as to understand the nature and extent of any liabilities. Through its normal financial intervention process, the LSC will ensure that no college is unable to meet its financial obligations as a result of decisions on capital projects.

6.2 Once we have a full analysis of the costs incurred and their nature, we will be able to identify those cases where a contribution to such costs from the LSC may be justified. The LSC has advised colleges that they should continue to avoid committing any further expenditure on the development of projects where there has not been full approval to go forward.

7. NEXT STEPS: ACHIEVING GREATER VALUE FOR MONEY

  7.1 As with the urgent and greatest need projects, there is no doubt that there has to be a new focus on achieving value for money as we go forward with this programme. The expectation is that all colleges will consider the scale, scope and costs of their projects very carefully; with limited funds we will want to ensure that we maximise the impact for learners, employers and communities in every project we approve.

7.2 We have instructed Lambert Smith Hampton to review all of the projects in the pipeline that are now unlikely to proceed for the time being so that we can review their scope, scale and timing. We want to have the best possible information to hand to inform the comprehensive spending review next year when there may be a further chance to seek additional funds.

  7.3 These college-by-college reviews will include detailed analysis of spending on project costs. This will be an extensive process, as there are potentially more than 150 projects to be considered. The process will include colleges completing a self-assessment questionnaire. Through bringing in consultants we aim to complete the work as quickly and as objectively as possible. In the taxpayers' interest, we will also be very hard nosed in driving for much better value for money.

May 2009


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2009
Prepared 17 July 2009