Memorandum submitted by the Environment Agency (LCT 47)

Comments on Small Hydropower Company response to the Energy and Climate Change Committee call for evidence Low Carbon Technologies in a Green Economy

Summary

1. The Environment Agency has launched a major programme of work aimed at streamlining the permitting process for hydropower developers, and improving the evidence base. This will address most of the concerns raised by the Small Hydropower Company (SHC).

 

2. The SHC highlight some important issues in their evidence, but they also make some unsubstantiated claims relating to their permit applications, our role as a consultee in the planning process, and the Environment Agency's approach to hydropower more generally.

 

3. The Environment Agency has issued 23 permits to hydropower schemes so far in 2009, taking on average 130 calendar days from receipt of a formal application. Applications from the SHC are taking considerably longer than we would like because they lack the necessary information and the schemes themselves are inherently complex.

Background

The Environment Agency supports the deployment of sustainable small-scale hydropower, and is committed to helping England and Wales meet their renewable energy targets. We also have statutory duties to protect the water environment, and to ensure that flood risk is not increased by new developments.

 

Poorly designed hydropower schemes can have serious impacts on the local river environment, particularly on fish populations, such as salmon and trout, and on flood risk for properties downstream of the installation. Our permitting process seeks to minimise these risks and, as well protecting the environment, it helps schemes to be accepted by other river users and stakeholders. We also provide advice to Local Authorities as a statutory consultee in the planning process.

 

In August 2009 we published Good Practice Guidance (GPG) for small-scale hydropower, which we developed in partnership with the British Hydropower Association (BHA), and with angling and conservation groups. The BHA is the main industry group for hydropower in the UK.

General comments

 

The SHC is developing a number of sites in England on behalf of British Waterways. Following an initial meeting in January 2009 to discuss their plans, we have been working with SHC and British Waterways to support their permit applications.

 

We accept some of the criticism from the Small Hydropower Company (SHC), particularly relating to the administrative delays they have experienced and the consistency of approach within the Environment Agency. However, we have been working with the hydropower industry, including the SHC, to improve this, and have launched a major programme of work to ensure we support the deployment of sustainable hydropower schemes in England and Wales. The SHC is aware of this work, is actively involved in some of it, and has participated in the stakeholder group we have established to steer it.

 

The SHC evidence highlights issues at particular sites, but fails to recognise the improvements that we are putting in place. We do not believe that their evidence provides an accurate reflection of the permitting process.

Better regulation for hydropower

The Environment Agency is committed to enabling the deployment of sustainable small-scale hydropower schemes in England and Wales. We have recently launched a cross-organisational programme of work that will deliver this, including:

· Publication of the Good Practice Guidance for small-scale hydropower schemes in England and Wales in August 2009. This provides clear guidance for developers on how schemes should be designed to meet environmental and flood risk legislation.

· A review of the permitting process for small-scale hydropower, with the aim of streamlining the process and reducing administrative burden. A public consultation will be launched in April 2010, and the review will conclude by September 2010.

· A training programme for our staff is being trialled to ensure they have the expertise required to deal with hydropower scheme applications. The programme should go live in January.

· A hydropower 'hub', with the support of DECC, is being developed to ensure better coordination and consistency between staff working on hydropower applications across England and Wales.

· A major evidence programme to refine and improve the Good Practice Guidance is in hand.

 

This work has been launched as part of an overall effort to ensure the Environment Agency is supporting the sustainable deployment of all forms of renewable energy, and in response to a significant increase in interest in hydropower over the last 18 months. This programme of work will ensure we are able to deal with these permit applications rapidly and efficiently in the future.

 

The Small Hydropower Company's permit and planning permission applications

 

We met with the SHC in January 2009 before they submitted any permit applications to advise on their applications and what they would need to consider. To date, the SHC has submitted five planning applications for hydropower schemes that we have been consulted on. These applications have been for schemes of varying size using different technologies, but the information provided with each application has often been inadequate, with little scheme-specific information.

 

The lack of sufficient information in the planning applications, particularly relating to flood risk assessments, has led to delays, with similar delays holding up the permit applications. The time taken to process permit applications from the SHC is in contrast to the overall average of 130 calendar days between developer's application and issue of permit for the 23 schemes we have permitted so far in 2009. We also note a number of major inconsistencies between our own records and the SHC evidence to the Select Committee. Further details are provided in the attached annex.

 

We are concerned that the 'economies of scale' (paragraph 2.2) that the SHC are attempting to achieve has led them to make assumptions about the appropriateness of their schemes on specific sites. Our view is that SHC appear to be assuming that our acceptance of one scheme on one site means the same scheme would be accepted on another. However, every site is different, and there is considerable variation in hydrology, terrestrial and aquatic ecology, fisheries and flood risk between the sites proposed so far. This means that a one-size-fits-all approach to managing their impacts is not possible.

 

If SHC had engaged us more consistently through pre-application discussions, as is recommended in our Good Practice Guidance, many of these issues could have been overcome early on.

 

Of the five applications, one has been granted permission, one has been refused and we are working with SHC to resolve issues with the other three. Of these, the scheme at Linton-on-Ouse has proved the most complex and further details are given in the Annex.

 

 

 

 


 

 

Annex - detailed response to issues raised in the Small Hydropower Company evidence to the Climate Change and Energy Select Committee

 

1 SHC's application for a hydropower scheme in Gunthorpe, River Trent

Gunthorpe raises particular concerns relating to flood risk as the area is very sensitive to flooding and the village of Gunthorpe does not benefit from flood defences. A number of properties in the village regularly flood. The River Trent upstream and downstream of Gunthorpe weir is also of significant importance for both fisheries and ecology. This is therefore a complex proposal that must ensure that it does not increase flood risk to others, allows the safe passage of the maximum number of migratory fish and protects the wider aquatic environment.

 

We have identified a number of inconsistencies between the SHC's evidence and our own records.

 

1. The SHC claim not to have received a response to their permit applications. The SHC applied for permits on 17 June 2009, and we acknowledged the applications formally by 2 September. We were in contact with British Waterways, the nominated contact in the application, throughout the interim period. Delay was due to the application being in the name of the Agent rather than the occupier, which is highly unusual and led to concerns about how the permit could be enforced.

2. The SHC assert that the Environment Agency had not read their documentation prior to a meeting with the SHC on the 8 September 2009. By this time we had scoped the requirements of a planning submission (our letter of 10 February 2009); met with SHC to discuss the Flood Risk Assessment (16 February 2009); reviewed the planning submission and outlined our objection to the detail of the planning application (our letter of 15 July 2009).

 

In addition:

 

1. The presence of the weir pool is a very important feature of the fishery habitat on this reach of the Trent. Whilst a fish pass is extremely important for the passage of adult fish, it cannot mitigate for the loss of a significant spawning and nursery area.

 

2. We recommended the installation of a vertical bar fish screen to SHC in line with Good Practice Guide. SHC have offered an alternative design using horizontal bars. As this is a new and untested technology suggested by the developer we would normally expect the company to provide the supporting information that enables us to assess it fully.

 

3. The type of turbine used in a hydropower scheme has implications for the level of the fish screening required. This is outlined in our Good Practice Guidance. Archimedes screw turbines do not require fish screens as fish can pass safely through. Other turbines, such as Kaplan, require screening to prevent fish mortality as a result of entering the turbine.

 

2 SHC's application for a HEP installation at Linton-On-Ouse

We were first consulted on the Linton-on-Ouse scheme by the Local Planning Authority (LPA) on 22 June. Some of the supporting information submitted with the application was not specific to the site, and in some cases made reference to conditions in different regions. We were therefore forced to object to the application. This was based on concerns over the impact on fisheries and flood risk, and was until acceptable details were submitted. Due to the complexity of the application we needed to extend our statutory timescale to respond, but this was agreed by the local authority.

 

We were not approached for pre-application advice from SHC regarding this scheme. Had we been contacted, we would have been able to let SHC know what information we needed to see to assess the environmental impact of the scheme adequately. This may have negated the need to object to the proposals, and is why we always recommend developers approach us early on in the process.

 

On 17 August we received a highly critical response from SHC via the local authority. We provided a thorough response to this, which sought to clarify to SHC exactly what was required to overcome our objections. This response was issued within our 21 day statutory timescale. We therefore contest the point raised in paragraph 4.5.4.1 stating that our response suffered from 'tardiness'.

 

Agents acting on behalf of SHC subsequently submitted a draft Flood Risk Assessment which addressed our concerns. We advised that this information be submitted formally to the local authority so that we could remove our flood risk objection. This is needed to ensure it becomes part of the planning conditions, but to date this has not yet been submitted.

 

In reference to the letter of 17 September (4.5.4.1), this was addressed to the local authority and not sent directly to the Environment Agency. We have consulted our records and are unaware of a formal consultation from the local authority on this information.

 

The Linton-on-Ouse scheme has the added complication that there is already an existing permitted scheme on the other bank of the river, where the operator has recently received planning permission to extend the works. The applicant, Mr Throup, has permission to construct an additional Archimedean Screw turbine on the west bank of the river.

 

3. The Environment Agency's hydropower scheme on Romney Weir

The SHC evidence suggests that the Environment Agency has abused its statutory power for commercial gain in the permitting and development of Romney Weir (4.5.3.2.2.3).

 

Romney Weir is an Environment Agency owned weir upon which we are developing a hydropower scheme in partnership with a developer. It is a pilot scheme in which we are leasing the site to the developer who will design, construct, operate and maintain the development. The aim is both to demonstrate best practice and to generate renewable energy, in line with Government's ambition to generate more renewable energy on the public estate.

 

The developer is responsible for obtaining planning permission and the necessary statutory consents rather than ourselves, and the application will be treated as any other. There are some differences to the SHC's own applications, mostly because the developer is using an Archimedes screw turbine, which is fish-friendly and therefore does not need screening. The scheme also includes a fish pass and a system to ensure there is variation in the flow over the weir gates to protect the ecological value of the weirpool.

 

4.Our regulatory responsibilities

The SHC accuse statutory organisations including the Environment Agency to have "on occasion little or no understanding of their duties under Law and what a reasonable person may expect of them" (4.5.6.1.1) and to fail to "exercise their duty and operate within the law" (4.5.1).

 

Our regulatory requirements for hydropower schemes are consistent with the environmental legislation, particularly the Water Resources Act 1991, the Land Drainage Act 1991, the Salmon and Freshwater Fisheries Act 1975 and the Water Framework Directive (2000). This legislation requires us to ensure that new developments within the river environment, including hydropower, do not increase flood risk and do not cause unacceptable damage to fish or the wider environment.

 

We are also a statutory consultee in the Town and Country Planning process for developments at flood risk, or for operations in or adjacent to a Main River. Our role is to ensure that all proposals comply with Planning Policy 25 "Development and Flood Risk" (PPS25). Developers are required to submit a Flood Risk Assessment to demonstrate that their proposals comply with PPS25 and to inform the scheme design.

 

Where we have objected to hydropower schemes through the Town and Country Planning process, it has usually been due to insufficient information being supplied, particularly in relation to the Flood Risk Assessment. Since flood risk is a material planning consideration, Flood Risk Assessments will continue to be required as part of the planning process.

 

We accept that there have been a small number of occasions where our planning officers have objected to a scheme on other matters when we are also addressing them through the permitting system. We are addressing this issue, and will ensure better coordination between our planning and permitting roles.

5.Staff expertise and resourcing

The SHC accuse the Environment Agency of having "a lack of experience and knowledge (and in some cases inadequate numbers of qualified staff) in dealing with the technical aspects of renewable applications". (Section 4.5.6.1.3)

 

We have produced the hydropower Good Practice Guidance, which provides our staff and developers with detailed technical guidance. However, we accept that expertise within the Environment Agency is currently limited to a small number of staff. This is because until recently we have seen very few applications for hydropower. In response to increased interest we are training more staff throughout the organisation in hydropower.

 

6.Defining requirements for developers

The SHC complain that we do not state what environmental mitigation standards are adequate (4.5.6.1.4), but also that we should only define outcomes and not how they should be achieved (4.5.3.2.2.2). The Good Practice Guidance sets out a number of environmental mitigation options, but it also allows developers to propose their own mitigation measures as long as it is accompanied with an appropriate risk assessment. This is because default guidance is preferred by smaller developers, for whom the burden of providing detailed risk assessments would be onerous. Larger developers, such as the SHC, are able to deviate from the default guidance, but they must provide the evidence that shows their proposals will protect the environment and address flood risk issues.

 

7.The role of small-scale hydropower

The SHC's understanding of the potential for new small hydropower is not consistent with the available evidence. A recent report by ITPower on behalf of DECC estimates an available resource in England and Wales of approximately 250MW, whilst our own mapping of opportunities suggests a theoretical, unconstrained maximum of 1100MW. This would be equivalent to 1.5% of UK electricity needs, and would involve developing many tens of thousands of small sites. We are undertaking work to provide a better assessment of hydropower opportunities and potential win-win benefits when associated with provision of fish passes.

8.The evidence base for our regulation of small-scale hydropower

The Good Practice Guidance (GPG) represents the best science and expert opinion in drawing up its recommendations on fish screens, flows available for hydropower, and design of fish passes. The Guidance was developed in co-operation with the British Hydropower Association (BHA) and with other stakeholders, particularly fisheries interests. It is acknowledged by all parties that there is a need to obtain further evidence on the effectiveness of the mitigation measures installed on hydropower sites. However there is relevant information in the scientific and operational literature on hydropower and other abstraction processes that is directly applicable. We will be undertaking work to improve the evidence base, and this work was presented to hydropower stakeholders at a meeting on 18 November, which SHC attended. The first phase of this work will be completed by March 2010. If necessary, the Good Practice Guidance will be updated with the findings of these projects.

 

December 2009