Flooding: the Government's response to Sir Michael Pitt's review - Environment, Food and Rural Affairs Committee Contents


Letter from the Managing Director—Networks at Ofgem to the Chairman of the Environment, Food and Rural Affairs Committee, 24 March 2009

GOVERNMENT RESPONSE TO THE PITT REVIEW

  Thank you for your letter of 4 March 2009 seeking Ofgem's views on the above subject. You queried specifically the work being undertaken by the energy networks to implement the Pitt Review's recommendations. As you know, these recommendations related to the protection of critical national infrastructure. In your letter, you also sought Ofgem's views of the funding arrangements for such protection work.

  Following the floods in the Midlands and South Yorkshire in summer 2007, an industry task group "Substation resilience to Flooding" was set up under the Energy Emergencies Executive Committee (E3C). This group, led by the Energy Networks Association (ENA), was tasked to carry out a comprehensive assessment of the electricity substations' resilience to flooding and the steps that may be taken to mitigate current and future risks. Ofgem has taken an active role in the group. At the end of March 2008, the task group submitted to E3C and the then Energy Minister, Malcolm Wicks, the report of its Phase 1 work. Subsequently, the task group initiated a further phase of work to oversee the implementation of the recommendations put forward in the Phase 1 report. This includes the production of an Engineering Technical Report containing a risk based methodology to improve the electricity substations' resilience to flooding to a level that is acceptable based on a cost/benefit assessment of each site.

  Funding for the network operators to carry out protection work to achieve adequate level of resilience to flooding, will be an element of the expenditure to be taken into account in the five yearly Price controls that Ofgem sets for the electricity transmission and distribution operators. In line with our duties (including our principal objective to protect the interests of energy customers), we seek to set price controls at levels which would allow efficient network operators to collect from customers at a level that allows an efficient business to finance their activities. We also place incentives on the network operators to improve their efficiency and quality of service.

  For the 14 distribution network operators (DNOs), their current price control expires on 31 March 2010 and Ofgem is now undertaking the fifth Distribution Price Control Review (DPCR5) to set the controls for 2010-15. As part of that process, the DNOs have submitted forecasts of works to be carried out, and associated costs, relating to improving flood defence at about 450 (of some 5800 in total) of their grid and primary substations. In evaluating sites to protect and the level of protection to employ, the DNOs have taken into account the recommendations from the industry task group on flood resilience, and have based their forecasts on detailed site survey and societal risk via the inclusion and weighting of "critical customers". My team is examining in detail the need, case and efficient costs for works at each of the at-risk substations within each DNO and across the DNOs, including the number of customers connected, types of critical customers connected, the nature and level of defences to be installed as well as the costs and timings to complete the works, and the benefit such defences would bring. We will determine funding allowances in the light of our analysis, current statutory requirements and ensure it achieves best value for consumers.

  The transmission companies have taken part in the industry task group on flood resilience and have also been assessing the need for any works at their substations. The same principle of funding adopted in DPCR5 will be applied for the consideration of funding for the transmission licensees, but with some variations in timing. This is because the current transmission price control runs from 1 April 2007 to 31 March 2012; as a consequence, the expenditure to step up flood defence was not anticipated at the time of setting this price control. Should we become aware of any unanticipated costs which arise during this price control, we will consider a range of approaches including flexing the revenue allowance for the current control period and making allowances in the future price control.

  I hope you find the above helpful. However, if you require any further information, please do not hesitate to contact me again.

  Yours sincerely,

Steve Smith

Managing Director—Networks

The Office of Gas and Electricity Markets

24 March 2009





 
previous page contents

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2009
Prepared 21 May 2009