European Scrutiny Committee Contents


5 Trans-European Transport Network

(30421)

6135/09

COM(09) 44

Green paper TEN-T: A policy review towards a better integrated Trans-European Transport Network at the service of the common Transport policy

Legal base
Document originated4 February 2009
Deposited in Parliament6 February 2009
DepartmentTransport
Basis of considerationEM of 17 February 2009
Previous Committee ReportNone
To be discussed in CouncilNone planned
Committee's assessmentPolitically important
Committee's decisionNot cleared; further information requested

Background

5.1 In 1996 the Community adopted Guidelines for the development of the Trans-European Transport Network (TEN-T) — defined as road, rail, inland waterways, motorways of the sea, seaports, inland waterway ports, airports and traffic management and navigation systems. The Guidelines provided that the TEN-T, should be a single multimodal network, with corridors of common interest and integration of land, sea and air transport infrastructure networks. They identified 14 priority axes deemed to be of European significance in supporting trans-national trade and cohesion. In 2004 the Guidelines were revised — changes made included:

  • extension of the deadline for completing the TEN-T to 2020;
  • extension of priority axes from 14 to 30 (the United Kingdom is involved in five of these); and
  • the possibility of coordinators (termed European coordinators) to be appointed for cross-border priority axes.

5.2 Responsibility for implementing the network rests with Member States. TEN-T projects are mainly financed by them and to a lesser extent by private investors. The Community also provides support, primarily through instruments adopted under the Trans-European Networks Finance Regulation, as well as from the Cohesion and European Regional Development Funds, and other non-financial instruments, such as coordination initiatives.

5.3 Completion of the TEN-T network has been slow. Of the 30 priority corridors, only four[22] have been completed to date. The lack of funding and the complexity of some TEN-T projects have been identified as the main reasons impeding timely implementation. The Guidelines require the Commission to report on their implementation every two years. The latest report was published in January 2009.[23]

The document

5.4 With this Green Paper the Commission seeks to open a debate questioning not only whether the objectives of the 2004 Guidelines have been achieved, but whether or not those objectives are still sufficient to meet future TEN-T challenges. The Commission summarises developments on the TEN-T and takes stock of three main issues:

  • the design of the future TEN-T network;
  • its objectives and priorities; and
  • its financial needs.

The paper intersperses the discussion with twelve questions for stakeholders to consider and concludes with a set of three options for TEN-T development on which a final question is based.

5.5 In relation to the design of the TEN-T network, objectives and priorities the Commission:

  • says it is considering evolving from the existing priority corridor approach to a wider priority or core network approach;
  • suggests this new core network should include a geographical pillar (defined in concrete geographical terms) and a conceptual pillar (a more flexible, broader scope for setting out TEN-T objectives and priorities);
  • considers that this would introduce more flexibility into the concept of projects of common interest, making it possible to respond to market developments that are currently difficult to foresee;
  • touches additionally on how best to meet TEN-T and wider Community objectives (including single market, cohesion, and environmental objectives);
  • questions, in this context, how the TEN-T programme should address passenger and freight traffic, the role of airports and ports in connecting the Community with the rest of the world, the role of intelligent traffic systems and the role of waterborne transport in the Community; and
  • focuses on achieving environmental objectives by exploring the role of technological innovation in a TEN-T context.

5.6 On TEN-T funding and implementation the Commission:

  • recognises that achievements would depend upon the TEN-T budget available to complete the network and the role of the Member States and private investors in ensuring that implementation is completed on time;
  • is not, however, consulting on any budget increases;
  • is instead focusing on ways by which TEN-T efficiencies can be improved;
  • is exploring other options, in addition to the available Community funds, to encourage private investment and maximise all the available funds;
  • proposes building on existing instruments, for example, the TEN-T Finance Regulation already provides for public-private partnerships and loan guarantees;
  • touches on other non-financial instruments, such as the TEN-T European coordinators that help to stimulate the implementation; and
  • puts forward new instruments for consideration such as the open method of coordination, which could include benchmarking Member States as a way of encouraging investment in TEN-T corridors.

5.7 The Commission then outlines three options for future TEN-T network design:

  • maintaining the status quo — that is keeping the TEN-T corridor approach, including the wider objectives and principles as set out in the current Guidelines, updating axes as necessary;
  • maintaining the priority axes only — that is abandoning the wider objectives and priorities as set out in the current Guidelines given the difficulties in applying true Community level planning, but maintaining the priority axes approach (the approach used in the Trans-European Energy Network programme); or
  • a priority or core network approach — that is adopt a flexible approach to the TEN-T, with geographical and conceptual pillars. The network would have to facilitate co-modality, by being fully integrated (including intelligent transport systems) and able to meet future transport and environment demands, for example contributing to emission reduction objectives.

5.8 The Commission says the Green Paper initiates a consultation on the issues outlined within it and invites responses by 30 April 2009.

The Government's view

5.9 The Secretary of State, Department for Transport (Geoff Hoon) says that there are no policy implications at this stage. He comments that:

  • the Green Paper does not contain any proposals that would change the Government's existing policy;
  • the Government is still formulating its position on the issues outlined by the Commission, but as a general principle agrees with it that there is a need to revise the TEN-T programme;
  • it would not wish, however, to see a revision that moves too far away from the principles and objectives agreed under the existing Guidelines;
  • the Green Paper first option, and to a lesser extent the second, are continuations of the principles set out under the present Guidelines, whilst the third would provide a more radical review of the TEN-T programme, both in scope and in definition;
  • it is not entirely clear, however, how the Commission envisages the third option operating in practice;
  • the Government will be seeking clarification from the Commission and will consider all the options with view to responding to the consultation by the deadline; and
  • the Government expects that this review of TEN-T policy will, in due course, lead to a legislative proposal amending the 2004 TEN-T Guidelines.

5.10 The Minister tells us that the Government is consulting informally with stakeholders — given the Commission timescale a formal consultation is not possible. He adds, however, that interest in the Green Paper is limited mainly to Government bodies, sponsored agencies and the Devolved Administrations.

Conclusion

5.11 Clearly the consultation initiated by this Green Paper may lead to important changes to efforts to develop the Trans-European Transport Network. Before considering the document further we should like to see the outcome of the Government's informal consultation and its response to the Commission. Meanwhile the document remains under scrutiny.





22   Oresund Bridge, Malpensa airport, the Betuwe line, the high speed line PBKAL (Paris Brussels Cologne/Frankfurt Amsterdam London). Back

23   (30376) 5620/09 + ADD 1: see chapter 22 in this Report. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2009
Prepared 6 March 2009