Documents considered by the Committee on 10 June 2009 - European Scrutiny Committee Contents


11 Trans-European Transport Network

(30421)

6135/09

COM(09) 44

Green Paper TEN-T: A policy review towards a better integrated Trans-European Transport Network at the service of the common Transport policy

Legal base
DepartmentTransport
Basis of considerationMinister's letter of 3 June 2009
Previous Committee ReportHC 19-viii (2009-09), chapter 5 (25 February 2009)
To be discussed in Council11 June 2009
Committee's assessmentPolitically important
Committee's decisionCleared

Background

11.1 In 1996 the Community adopted Guidelines for the development of the Trans-European Transport Network (TEN-T) — defined as road, rail, inland waterways, motorways of the sea, seaports, inland waterway ports, airports and traffic management and navigation systems. The Guidelines provided that the TEN-T, should be a single multimodal network, with corridors of common interest and integration of land, sea and air transport infrastructure networks. They identified 14 priority axes deemed to be of European significance in supporting trans-national trade and cohesion. In 2004 the Guidelines were revised — changes made included:

  • extension of the deadline for completing the TEN-T to 2020;
  • extension of priority axes from 14 to 30 (the United Kingdom is involved in five of these); and
  • the possibility of coordinators (termed European coordinators) to be appointed for cross-border priority axes.

11.2 Responsibility for implementing the network rests with Member States. TEN-T projects are mainly financed by them and to a lesser extent by private investors. The Community also provides support, primarily through instruments adopted under the Trans-European Networks Finance Regulation, as well as from the Cohesion and European Regional Development Funds, and other non-financial instruments, such as coordination initiatives.

11.3 Completion of the TEN-T network has been slow. Of the 30 priority corridors, only four[42] have been completed to date. The lack of funding and the complexity of some TEN-T projects have been identified as the main reasons impeding timely implementation. The Guidelines require the Commission to report on their implementation every two years. The latest report was published in January 2009.[43]

11.4 With this Green Paper the Commission sought to open a debate questioning not only whether the objectives of the 2004 Guidelines have been achieved, but whether or not those objectives are still sufficient to meet future TEN-T challenges. The Commission summarised developments on the TEN-T and took stock of three main issues:

  • the design of the future TEN-T network;
  • its objectives and priorities; and
  • its financial needs.

The paper interspersed the discussion with twelve questions for stakeholders to consider and concluded with a set of three options for TEN-T development, for future network design, on which it asked for comment also. The options were:

  • maintaining the status quo — that is keeping the TEN-T corridor approach, including the wider objectives and principles as set out in the current Guidelines, updating axes as necessary;
  • maintaining the priority axes only — that is abandoning the wider objectives and priorities as set out in the current Guidelines given the difficulties in applying true Community level planning, but maintaining the priority axes approach (the approach used in the Trans-European Energy Network programme); or
  • a priority or core network approach — that is adopt a flexible approach to the TEN-T, with geographical and conceptual pillars. The network would have to facilitate co-modality, by being fully integrated (including intelligent transport systems) and able to meet future transport and environment demands, for example contributing to emission reduction objectives.

The Commission invited responses by 30 April 2009.

11.5 When we considered the Green Paper we heard from the Government that:

  • the Government was still formulating its position on the issues outlined by the Commission, but as a general principle it agreed that there was a need to revise the TEN-T programme;
  • it would not wish, however, to see a revision that moved too far away from the principles and objectives agreed under the existing Guidelines;
  • the Green Paper first option, and to a lesser extent the second, were continuations of the principles set out under the present Guidelines, whilst the third would provide a more radical review of the TEN-T programme, both in scope and in definition; and
  • the Government expected that this review of TEN-T policy would, in due course, lead to a legislative proposal amending the 2004 TEN-T Guidelines.

We commented that clearly the consultation initiated by this Green Paper might lead to important changes to efforts to develop the TEN-T network. Before considering the document further we asked to see the outcome of the Government's planned informal consultation and its response to the Commission. Meanwhile the document remained under scrutiny.[44]

The Minister's letter

11.6 The former Secretary of State for Transport (Geoff Hoon) first tells us that the Government's response to the Green Paper was submitted on the 30 April 2009 and he encloses a copy of the response. We annex the summary of this and the answer to the Commission's final question (on the options). The full text can be seen on a Commission website.[45] The response makes clear that the Government is looking for a fundamental review of the TEN-T programme and would prefer an approach based on the Commission's second option.

11.7 The Minister comments further that:

  • in preparing the response, an informal consultation with interested stakeholders was conducted;
  • given the nature of TEN-T, this was limited mainly to Government bodies, sponsored agencies and the Devolved Administrations;
  • limited contributions were received — however the Government was aware that a considerable number of UK stakeholders, including the Welsh Assembly and the Scottish Executive, decided to respond directly to the Commission;[46]
  • the consultation exercise did not throw up any real surprises;
  • there was a general agreement that the TEN-T programme should be reviewed;
  • there was a general concern that the new design should not overlook the peripheral needs of the Community; and
  • an issue which attracted significant comment was the Commission's initial options for the future design of the TEN-T network — most of the responses favoured the second option for its simplicity or the third for its potential wider-Community benefit.

11.8 The Minister continues that in considering those responses there were points of principle which the Government felt it was important to stress in its response to the Green Paper, such as the need for TEN-T to demonstrate value for money. On this, it specifically expressed its opposition to inclusion of new TEN-T corridors without a compelling case for Community value-added. He says that key points which were emphasised were:

  • the objectives of the TEN-T programme need to be clarified and more focused on both scope and outcome;
  • any TEN-T funding from the Community budget must be better focused on priority projects, and combined with a European Investment Bank loan and private finance as a general rule;
  • the existing TEN-T maps would need to be reviewed — no further "priority corridors" should be set up without a compelling case for Community value-added;
  • fundamentally, TEN-T needs to be better focused on projects that provide genuine Community value-added and value for money;
  • only those transport corridors and transport components (such as major ports or airports) that are of strategic interest to a number of Member States should be part of the TEN-T network;
  • in order to obtain a true network effect, the network needs to be fully integrated and multimodal and promote sustainable modes of transport;
  • the peripheral needs of the Community should also be taken into account; and
  • the review should address sound financial management, project scoping and TEN-T management which have each been inadequate in many cases — for instance, the Government would wish to see a clear definition of what defines the TEN-T network as complete.

11.9 Finally the Minister tells us that the Presidency hopes that at the 11 June 2009 Transport Council it will be possible to agree Council Conclusions, which the Government expects to invite the Commission to continue discussing the TEN-T review and to submit a proposal amending the TEN-T Guidelines before the end of 2010.

Conclusion

11.10 We are grateful to the Minister for this information about the Government's consultation on and response to the Commission's Green Paper. We have no further questions to raise and clear the document.


42   Oresund Bridge, Malpensa airport, the Betuwe line, the high speed line PBKAL (Paris Brussels Cologne/Frankfurt Amsterdam London). Back

43   (30376) 5620/09 + ADD 1: see HC 19-viii (2008-09) chapter 22 (25 February 2009). Back

44   See headnote. Back

45   See http://ec.europa.eu/transport/infrastructure/consultations/2009_04_30_ten_t_green_paper_en.htm.  Back

46   Such responses can also be seen on http://ec.europa.eu/transport/infrastructure/consultations/2009_04_30_ten_t_green_paper_en.htm.  Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2009
Prepared 19 June 2009