European Scrutiny Committee Contents


16 Global navigation satellite system

(a) (30745) 11614/09 COM(09) 302

(b) (30786) 11860/09 —

Commission Report on the implementation of the GNSS programmes and on future challenges pursuant to Article 22 of Regulation (EC) No 683/2008

European Court of Auditors Special report No. 7/2009 concerning the management of the Galileo programme's development and validation phase together with the Commission's replies

Legal base
Documents originated(a) 26 June 2009

(b) —

Deposited in Parliament(a) 3 July 2009

(b) 14 July 2009

DepartmentTransport
Basis of consideration(a) EM of 20 July 2009

(b) EM of 2 September 2009

Previous Committee ReportNone
Discussion in CouncilNone planned
Committee's assessmentPolitically important
Committee's decisionCleared

Background

16.1 The Community has a two-phase policy for developing a global navigation satellite system (GNSS). The first phase, GNSS 1, is the European Geostationary Navigation Overlay System (EGNOS) programme. The second phase, GNSS 2, is the programme, named Galileo, to establish a new satellite navigation constellation with appropriate ground infrastructure. Galileo is based on the presumption that Europe ought not to rely indefinitely on the GPS (the US Global Positioning System) and GLONASS (the Russian Global Navigation Satellite System) systems, augmented by EGNOS. Galileo is being carried out in conjunction with the European Space Agency[54] and there are a number of agreements in place or being negotiated with third countries about cooperation in the project. From early in 1999 we and previous Committees have reported to the House on many aspects of the Galileo project, most recently in June 2009.[55] The matter has been debated four times in European Standing Committee, most recently on 26 November 2007,[56] and once on the Floor of the House.[57]

16.2 In September 2003 the Galileo Joint Undertaking was set up to take forward the development and validation phase of the Galileo programme. It remained in place until the end of 2006 when its responsibilities were handed over to the European GNSS Supervisory Authority (GSA), established in 2005, by Council Regulation (EC) No. 1321/2004, as an arms-length body to own Galileo on behalf of the Community and to regulate and oversee it as a public private partnership.

16.3 Following collapse of public private partnership negotiations the Transport Council agreed in November 2007 a revised timetable for Galileo, to be completed by 2013, and for the funding to come wholly from the Community budget. The Council agreed a €3.40 billion (3.29 billion) cap on costs in the Financial Framework to 2013 and confirmed general principles for public sector governance and the procurement strategy for the programme. The subsequent Council Regulation (EC) No. 683/2008, in addition to confirming the new funding arrangements, addressed issues of programme governance (with the Commission identified as programme manager) and the procurement strategy and, with the Commission being placed in overall control of the programme, confirmed the GSA as a body to provide support to the Commission. The Regulation also requires the Commission to prepare an annual report to the Council and the European Parliament on the progress of the Galileo and EGNOS programmes.

The documents

16.4 Document (a) is the first of the reports from the Commission required by Council Regulation (EC) No. 683/2008. It sets out the activities undertaken by the Commission since the adoption of the Regulation and the work it has taken forward with the European Space Agency and the GSA.

16.5 On EGNOS the report shows that:

  • on 1st April 2009 the Commission took on ownership of EGNOS from the European Space Agency;
  • it has ensured continuation of operations by agreeing a temporary six month contract (April to October 2009) with a service provider to operate EGNOS;
  • the operator is a private company, ESSP (EGNOS Satellite Services Provider), created specifically for this role, which has been formed by a conglomerate of European air traffic service providers (including NATS from the UK);
  • negotiations are underway to agree a more detailed long term contract with ESSP — to operate the system for a period of five years, to 2013;
  • on 31 March 2009 the Commission also signed a Delegation Agreement with the European Space Agency, under which the latter will act as the Commission's agent for the design and procurement of EGNOS equipment and software renewals;
  • the Commission has concluded a contract for the replacement of the EGNOS satellite navigation transponders, which are nearing the end of their operational life; and
  • the Commission is embarking on further activities to ensure the full certification of EGNOS for aviation use, to extend EGNOS coverage in Europe and further afield, notably to Africa, and to pursue activities to develop the market for EGNOS beyond those of aviation.

16.6 On Galileo the report first shows that the Commission has set up a new and clear governance structure for the delivery of the Galileo programme as required by Council Regulation (EC) No. 683/2008. This has involved:

  • setting up a European GNSS Programme Committee, a management committee with Member State participation, which assists the Commission in the management of the Galileo programme;
  • establishing a Galileo Inter-institutional Panel, comprising representatives of the Council, the European Parliament and the Commission, as a forum for sharing information — a first meeting took place in February 2009;
  • creating a new security board through which Member States' security experts can assist in the security activities on the programme — it replaces the security board previously set up in relation to the Galileo Joint Undertaking;
  • signing a delegation agreement with the European Space Agency, in December 2008, for the latter to act as the procurement agent for the six work packages that will deliver the Galileo infrastructure;
  • preparing a draft legislative instrument to bring the duties of the GSA, in Council Regulation (EC) No. 1321/2004, into line with those of Council Regulation (EC) No. 683/2008;[58] and
  • appointing an independent project management team to provide external advice on the Commission's project management of the Galileo programme.

16.7 Secondly on Galileo, the report shows that:

  • the Commission and the European Space Agency have taken forward procurement of the full 30 satellite constellation of Galileo and the accompanying ground segment;
  • they have commenced negotiations with interested bidders for the six work packages set out in the Council Regulation (EC) No. 683/2008 (system support, ground mission systems, ground control systems, satellites, launchers and operations), which will deliver Full Operational Capability (launch of satellites and completion of all infrastructure by 2013); and
  • the Commission and the European Space Agency will evaluate the candidates for the tenders and hope to have the majority of the contracts concluded by the end of 2009 with any remaining ones being completed early in 2010.

16.8 On Galileo the report discusses, thirdly, the continuation of the development and validation phase of the project, showing that:

  • the two experimental satellites are currently operating effectively;
  • the subsequent launch of the four In Orbit Validation (IOV) satellites, to allow comprehensive testing of fully operational Galileo satellites in a space environment, is still planned to begin in 2010;
  • in 2008 the European Space Agency identified the need for additional funding to meet an expected shortfall in funding for the IOV phase;
  • reasons for the shortfall include increase in industrial costs, increase of launch costs and increases in the European Space Agency's own administrative costs because of the delay;
  • the net shortfall amounted to €376 million (£320.39 million), which the European Space Agency was unable to find a way of meeting these additional costs and the Commission therefore agreed to fund the shortfall from its budget for Galileo; and
  • the Commission will continue to monitor the situation, because in funding the shortfall, it has used the entire contingency fund set aside for Galileo to 2013 and there is now little margin left in the current Financial Framework.

16.9 The Commission also uses the report to highlight a number of issues and activities on which it is currently engaged and which it expects to bring before Member States for consideration by the end of the year. These include:

  • a Communication and action plan on Galileo applications;
  • the Commission's international activities such as those aimed at addressing compatibility and interoperability issues with other GNSS providers (the USA, Russia, China), those aimed at ensuring cooperation with third countries on satellite navigation and those to address global standards and the control of the trade in sensitive GNSS technologies; and
  • preparing a report setting out the Commission's budgetary and governance proposals for the operational and exploitation phase of Galileo from 2014 onwards, in the next Financial Framework and beyond.

16.10 Document (b) is a special audit report from the European Court of Auditors. It concerns the Community's involvement in satellite navigation, that is EGNOS and Galileo (referred to collectively as Galileo), in the period 2003-2006. The report includes a response from the Commission to the Court's recommendations.

16.11 The Court recognises that:

  • Galileo was the first of its kind in many areas for the Commission;
  • it was the first time that the Community and the European Space Agency had collaborated on a space programme of this magnitude; and
  • it was the first industrial programme to be managed at Community level and it would have been the first public private partnership for the Community.

16.12 Collapse of the public private partnership negotiations in early 2007 led the Court to examine the events leading up to it, principally;

  • what factors accounted for the failure of the concession process;
  • what factors accounted for the reported delays and cost overruns;
  • how much has Galileo benefited from spending on research and development;
  • how well did the Galileo Joint Undertaking integrate EGNOS and Galileo; and
  • whether the governance of Galileo was adequate.

16.13 The Court, noting that by the autumn of 2007, when the Council and the European Parliament decided to redirect Galileo, the development of the programme had been set back five years to 2013, is critical of the handling of Galileo by the Galileo Joint Undertaking in a number of key areas. It recalls that:

  • the original timetable had envisaged that the deployment phase, that is the launch of the full satellite constellation and the building of the ground infrastructure, would be completed by the end of 2007; and
  • as it was, by 2008, no operational satellites had been launched (although two test satellites had) and the original cost estimates for the preceding development and validation phase of the programme had doubled to €2.10 billion (£1.79 billion).

But the Court also says that, whilst the Galileo Joint Undertaking did not achieve most of its objectives, the majority of these were due to factors outside of its control. The Court's criticisms were that:

  • the Commission failed to actively direct the programme. Although between 1999 and 2004 it had actively played its role in initiating the programme and getting it started, when it became apparent during 2005 that there would be delays and the project would overrun on costs no corrective action was taken until March 2007;
  • the Galileo Joint Undertaking was required to negotiate a public private partnership that had clearly been inadequately prepared. Despite there being considerable experience within Member States on managing and running public private partnerships, the Commission failed in its preparation to allow sufficient time and provide sufficient and appropriate management resources;
  • the Galileo Joint Undertaking allowed the two competing consortia to merge into a single consortium and in doing so lost any competitive element that could have led to cost savings and greater value for money;
  • the Galileo Joint Undertaking's regular reports identified several risks but it reported the progress in an unduly positive light. Crucially it never reviewed the feasibility of the programme or provided strong management but continued to agree to postponements in its contract discussions with the bidders;
  • by continuing to report in such a positive light, the Galileo Joint Undertaking denied Member States the knowledge to request corrective action;
  • Member States acted in their own national interests and intervened on behalf of their own national industries regarding the composition of the consortium that was bidding for the concession contract as well as the location of the various centres, ground infrastructure and headquarters needed for the Galileo programme;
  • an absence of a comprehensive market development approach limited the usefulness of the Galileo research programme;
  • this was further compounded by a lack of relevant projects under the Community's Sixth Framework Programme for research and development and the general delays that Galileo experienced;
  • integration of Galileo and EGNOS was only partially successful due to the Galileo Joint Undertaking's mandate being unclear;
  • this particularly affected the delivery of the EGNOS programme and the Galileo Joint Undertaking spent little time in developing the market for EGNOS;
  • in relation to governance, the division of the roles and responsibilities of those involved in the development and validation phase of the programme, Member States, member countries of the European Space Agency, the Commission, the Galileo Joint Undertaking and the European Space Agency, was poorly defined; and
  • the Commission did not providing adequate leadership in the development and management of Galileo.

16.14 The Court makes five recommendations. These are that the Commission:

  • needs to have more authority as a programme manager. To do so it should adapt its resources and its legal and financial instruments to the specifics of the development and management of the programme, a cooperative framework between the Community and the European Space Agency should be created and the Commission should ensure that it has the financial ability to commit itself to the costs of the infrastructure over a long timeframe;
  • should clarify the political objectives behind Galileo and translate them into strategic and operational objectives to provide a robust road map that goes from now to beyond its full deployment;
  • should allow sufficient time to prepare the commercial operational phase, drawing on best practice guidance from Member States and taking into account experiences in comparable sectors;
  • should address analysis, consolidation and validation of relevant user requirements, development of enabling actions (that is a legal and regulatory framework), promotion of EGNOS as a showcase for Galileo and development of a clear pricing policy or revenue model for Galileo and EGNOS and of a third party liability policy; and
  • should ensure, for any future joint undertakings and industrial programmes, that there are clear and compelling reasons for such action and establish a governance structure that does not impede proper programme management by the Galileo Joint Undertaking.

16.15 It its responses to the Court's observations the Commission:

  • says that the public private partnership took account of studies of best practices, but concedes that these were primarily in established business fields where risk factors would already be known;
  • argues that the nature of Galileo made it very difficult to apply best practice and that it was impossible to use a comparator;
  • argues that the time pressures meant that in its view it took the correct path in opting for competitive dialogue as a procurement model;
  • says that there were no knowledge gaps in the Galileo Joint Undertaking staff and that they were highly experienced in their relevant fields;
  • says that the merger of the two consortia was not encouraged or supported by the Galileo Joint Undertaking, but after careful scrutiny it was believed that the single consortium would offer better value for money;
  • makes it clear that Member States were also represented on the Supervisory Board of the Galileo Joint Undertaking and therefore did not have to rely only on the Commission for information on the programme;
  • asserts that it fulfilled its political responsibilities and sought agreement between Member States by asking former Commissioner Karel van Miert to mediate and says that in doing so it managed to progress the negotiations on the concession contract;
  • says that, with further support from the European Investment Bank, the differences were narrowed down to a few substantial issues that subsequently were to prove intractable — these related primarily to a continuous and unresolved dispute over the share of industrial work and the private sector's liability for design and market risks, that is potential revenues, because of the technical complexity of the programme;
  • points out that EGNOS was an European Space Agency programme and its development had been funded primarily by European Space Agency member countries and industry — it had suffered from delays due to technological issues and difficulties in the relationship between the industrial parties;
  • says that it believes that the roles of each party involved in the governance of Galileo were clearly defined and that, in its opinion, the European Space Agency was clearly accountable for technological development, and the Commission was responsible for all political responsibilities.

16.16 In response to the Court's recommendations the Commission says that:

  • it has already taken steps to adapt its resources and its legal and financial instruments to allow it to act as a programme manager — in addition to internal recruitments, it has arranged for the transfer of 30 experienced staff from the European Space Agency to provide a dedicated Galileo team and it is already planning for adequate budgetary cover in the next Financial Framework;
  • the Communication on the future of Galileo beyond the deployment phase, which Council Regulation (EC) No. 683/2008 requires of the Commission in 2010 and on which it has already started work, will also cover the strategic and operational objectives of Galileo, integration of EGNOS into Galileo, the actions necessary to encourage the use of GNSS technology and a proposal for an appropriate regulatory framework; and
  • it has set up and may set up other joint undertakings — each of these has and will continue to be planned and assessed against criteria relevant to the activity on a case by case basis.

The Government's view

16.17 On the Commission's report, document (a), the Parliamentary Under-Secretary of State, Department for Transport (Paul Clarke) says that it contains no new policy implications for the Government, but goes on to comment that:

  • in the discussions that led to the adoption of Council Regulation (EC) No. 683/2008 the Government had pushed for such reports and it therefore welcomes the document;
  • the Government remains fully engaged in the GNSS programme through various Community fora and as a member of the European Space Agency;
  • its focus on Galileo remains to ensure the delivery of a system to time and within the budget of €3.4 billion (£3.29 billion) agreed by the Council and the European Parliament;
  • it remains committed to the delivery of an economically useful and commercially viable system as the best means of delivering benefits for Community economies;
  • in doing this the Government's focus remains on cost control, mitigation of risks and value for money, through effective programme management with clear lines of responsibility, open procurement and regular reviews of likely revenues;
  • it therefore fully endorses the Commission activities in setting out a clearer and more transparent governance structure for taking the programme forward; and
  • it agrees with the Commission that there are significant challenges ahead for the programme and therefore supports the its intention to bring forward a review of the programme in 2010 and to set out proposals for the operational and exploitation phase of Galileo after 2014.

16.18 The Minister then discusses in more detail some of the issues arising from the document. First, on EGNOS he says that:

  • the Government understanding is that all the relevant parties involved in the negotiations to agree a contract for a permanent service provider to operate EGNOS are optimistic that an agreement will be reached over the summer of 2009;
  • the certification process to ensure that EGNOS can be certified for aviation use is already underway and it is currently expected that it will be achieved in the first half of 2010;
  • NATS is involved in all these negotiations; and
  • the Government supports the process as it agrees that EGNOS can offer users enhanced accuracy that will make it suitable for safety critical users, in particular the aviation community.

16.19 On Galileo, more generally, the Minister tells us that:

  • discussions have started and are continuing in Working Groups on the draft legislation to bring Council Regulation (EC) No. 1321/2004 into line with Council Regulation (EC) No. 683/2008;[59]
  • the Government's fully accepts and supports the Commission's aim of addressing the legal inconsistencies between the two Regulations and agrees that it has to be done as soon as possible;
  • a first reading deal with the European Parliament would help in avoiding costly delays — however it is essential that the Regulation is fit for purpose and discussions are ongoing with a view to ensuring its provisions, particularly those relating to security (and on how the Commission proposes to oversee security accreditation) are appropriate;
  • the Government shares the Commission's concerns about the funding the IOV shortfall, particularly about the likely effect of this on the overall longer term budgetary envelope for Galileo;
  • in line with its priority objectives for Galileo, the Government will remain vigilant in its aim to ensure value for money through disciplined project management, open procurement and effective financial management to ensure the project is brought in within the agreed €3.40 billion ceiling;
  • the Government is keen to see competition in the procurement for the Full Operational Capability phase — such competition is essential if costs are to be controlled;
  • UK industry is already benefiting from contracts in the current development phase of Galileo and a number are well placed to gain contracts in the open procurement phase for Full Operational Capability and thus ensure maximum benefit for the UK from the programme;
  • it is of utmost importance that the procurement is successfully concluded as soon as possible in 2010 if the challenging timetable for Galileo is to be met and the Government will continue pushing for this objective;
  • the Government looks forward to the Commission's paper on GNSS applications and its proposed Action Plan — a successful Galileo can be expected to further stimulate the market for satellite navigation applications in a wide range of economic sectors and the Action Plan will be very important in launching further discussion on the wider commercial opportunities for Galileo;
  • on the Commission's activities with third countries, the Government fully supports the need to ensure compatibility and interoperability with other GNSS and to ensure the non-proliferation of sensitive technology;
  • the Government agrees that there are potential advantages for the Galileo programme and benefits for Community industry in extending formal cooperation between the Community and third countries, to increase the commercial potential and market development opportunities; and
  • the Commission is close to concluding a cooperation agreement with Norway to cover its involvement in the Galileo programme and will shortly be seeking a mandate to pursue a similar agreement with Switzerland, both of which initiatives the Government supports.

16.20 On the European Court of Auditors' Special Report, document (b), the Minister says that:

  • given that it is a historical perspective of the Galileo programme during the period 2003-2006, there are no policy implications for the UK;
  • the report is welcomed by the Government for providing an independent review of Galileo and it should be noted that several of the issues reported by the Court were in accord with concerns raised by the Government at the time;
  • the Government has always argued within the Galileo arena for improvements in its governance, advocating the need for effective political oversight and transparency, with clear lines of responsibilities for all parties and arguing that in any public procurement of the system there needs to be more robust estimate of costs and risks, with better budget discipline, better cost control and better project and risk management and that all procurement should be robust, open and fair;
  • these concerns have been addressed, for the present, by the adoption of Council Regulation (EC) 683/2008, which sets out the strategy for achieving Full Operational Capability, confirms the new funding arrangements, is addressing the issues regarding programme governance and has set out a procurement strategy that is open and transparent and which the Government supports; and
  • the Regulation also addresses issues regarding the role of the GSA that arose following the collapse of the public private partnership — its role is now one of supporting the Commission on the Galileo programme, but it has also retained its specific responsibilities for technical certification, security accreditation and the development of markets and the commercialisation of Galileo.

Conclusion

16.21 These documents provide useful information on the evolution and present situation of the Galileo project. Although we clear both of them we note that:

  • the European Court of Auditors' special report, document (b), confirms the doubts we and our predecessors have held about both the conception and management of the Galileo project; and
  • we will continue to take a close interest in developments, for the immediate future particularly in relation to the draft Regulation on the GSA, which continues under scrutiny,[60] but subsequently also on the Commission's proposed Action Plan and on financial provision and management.






54   See http://www.esa.int/SPECIALS/About_ESA/SEMW16ARR1F_0.html and http://www.esa.int/esaNA/index.html.  Back

55   (30514) 6257/09: see HC 19-xviii (2007-08), chapter 6 (3 June 2009) and chapter xx of this Report. Back

56   See Stg Co Deb, European Standing Committee, cols. 3-40. Back

57   See HC Deb, 2 July 2007, cols. 763-87. Back

58   (30514) 6257/09: see HC 19-xviii (2008-09), chapter 6 (3 June 2009) and chapter 3 of this Report. Back

59   Ibid. Back

60   Ibid. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2009
Prepared 23 September 2009