NHS Pay Modernisation in England: Agenda for Change - Public Accounts Committee Contents


Supplementary memorandum from the Chief Executive, NHS Department of Health

"NHS PAY MODERNISATION IN ENGLAND: AGENDA FOR CHANGE": DELIVERY OF AT LEAST £1.3 BILLION NET SAVINGS OVER THE FIRST FIVE YEARS

  Thank you for giving me the opportunity to provide further information relating to whether we delivered "at least £1.3 billion" net savings in the first five years of Agenda for Change.

  The £1.3 billion savings, as were to come from:

    — gains from increased productivity;

    — gains from increased staff resources ("participation rates"), for example because this would reduce the need to use expensive agency staff;

    — a reduction in pay drift from its historical average of 1.6%. Pay drift is the rate at which average earnings increase above the rate of the annual pay award; and

    — higher quality care.

  As I said at the hearing, it is difficult to separate out the savings that could be attributed to one programme when a range of other initiatives were also being introduced at the same time. In the event, the approach to measuring savings was overtaken and subsumed in the cross Government efficiency programme (Gershon), the priority being to deliver savings, not assign them to different programmes.

  The methodology used to assess the extent to which savings were being delivered, was set out in our Productive Time programme, part of our contribution to the cross Government efficiency programme.

  As was explained by Clare Chapman, Director General, Workforce At DH, Productive Time involved the integrated impact of the following three workstreams:

    — the new workforce contracts, of which Agenda for Change was one;

    — process redesign which aimed, for example, to encourage a reduction in variation in length of stay for common surgical procedures; and

    — the introduction of new technology. I referred in the hearing, for example, to the handheld computers that community nurses use to record their visits to patients, saving administration time and paperwork.

  The Productive Time programme, which was published in our Departmental Autumn Report 2008, shows that we have exceeded our target of delivering £2.9 billion of annual savings by March 2008, building cumulatively over the four years of the Productive Time programme to achieve nearly £3.1 billion.

  In the attached paper, I include examples of how the introduction of the Agenda for Change contract has contributed to delivering savings and provide an assessment of the extent of those savings.

  In addition, the NAO report identified that other savings contributing to this £1.3 billion figure include "a reduction in the likelihood of equal pay claims". Neither we here, nor the NAO in their report, have sought to estimate the value of this reduction, due to the uncertain outcome of ongoing legal action. However, it is worth noting that the NAO reported "There is a widespread view in the Department and amongst NHS Employers and other commentators that Agenda for Change has made it easier to show that NHS pay is fair and equitable".

  I would also like to take this opportunity to remind you that we are continuing our work to improve measures for quality that should more fully reflect the gains I believe we have made over the past years.

  The Office for National Statistics (ONS) include a partial measure of quality in their estimates of NHS productivity, but this is crude and almost certainly understates the gains we have made. Nonetheless their most recent article did conclude that NHS quality, on their narrow measure, was increasing by 0.5% a year from 2001 to 2005. This quality improvement has a value of around £370 million a year. The Agenda for Change "share" of this quality improvement (based on Agenda for Change spend as a proportion of total NHS spend) would be around 36% or £133 million a year.

  I explained that we have commissioned work from York University to improve the quality measure. The York study is a three part research project that will first refresh and update the output measure, then improve the measurement of inputs before going on to suggest improvements to the quality adjustment. The report expected at the end of this month reports on the second stage. Once Ministers have had the opportunity to consider their work, I will provide you with a copy.[4]

  In conclusion, my assessment of the savings attributable to the five years of the Agenda for Change contract, is within a range of between £1.1 billion and £2.2 billion.

25 March 2009

Annex

Q.109:   Did we deliver "at least £1.3 billion" net savings over the first five years of Agenda for Change?

1.  INTRODUCTION

  The Productive Time programme, part of the Department of Health's contribution to the Gershon cross Government efficiency programme, has been used to assess the impact of Agenda for Change, providing the most appropriate measurements available.

  The "Productive Time" programme covers two of the four contributors to the savings set out in paragraph 2.20 on page 18—"(i) gains in increased productivity" and "(ii) gains from increased staff resources". In terms of the effect of Agenda for Change on the pay bill, of which "(iii) reduction in pay drift" is a part, the NAO report concluded that the effect of Agenda for Change was more or less neutral. One of the NAO's scenarios gave a saving (£604 million over five years), and the other a cost (£186 million over five years)—the details are set out in Figure 5 on page 18 of the report.

  Finally, a partial measure for "(iv) higher quality care" has been included in the calculations but will need to be revised in due course once the York work on quality measures has been concluded.

2.  PRODUCTIVE TIME

  The Productive Time programme ran from April 2004 to March 2008 so broadly mirrors the Agenda for Change period the PAC is interested in.

  Three main areas of opportunity for savings in productive time were identified:

    — IT (the National Programme for IT, "Connecting for Health").

    — Process Improvement (the NHS Institute for Innovation and Improvement's High Impact Changes and subsequent developments of this work).

    — Pay Modernisation (Agenda for Change, Consultant Contract and GP Contract).

  DH recognised that the measurable outcomes overlapped across the three programmes. Within the NHS, it was anticipated that changes would be planned and managed in an integrated way with these three programmes acting as enablers to organisational improvement. Out of this thinking, the Integrated Service Improvement Programme (ISIP) was developed. This was referred to in the hearing.

  This is the key reason efficiencies were not monitored separately to pay reform. The NAO endorsed this approach in their first study of Gershon efficiency in 2005.

  This rationale is documented in Appendix 1 pages 23-37 of the Efficiency Technical Note (ETN), which accompanied the published Productive Time Measurement Templates. The templates, where Agenda for Change was identified as having contributed to delivering efficiency savings, have been used as a basis for calculating the contract's contribution over the period of the Productive Time programme (see section 4 below).

  The ETN can be found on the DH website at:

http://www.dh.gov.uk/en/Publicationsandstatistics/Publications/PublicationsPolicyAndGuidance/DH_081430

  The savings from our Productive Time programme were published in our Autumn Performance Report 2008 and can be found in Chapter 4: "Value for Money" at:

www.dh.gov.uk/en/Publicationsandstatistics/Publications/PublicationsPolicyAndGuidance/DH_091854

3.  PRODUCTIVE TIME EXAMPLES

  Below I set out some examples of how the NHS has delivered productive time improvements through the use of the Agenda for Change contract. The following show how employers have improved service delivery by using Agenda for Change.

 (i)   Reduction in length of stay for elective in-patients

  Aintree University Hospitals NHS Foundation Trust has adopted a partnership approach between management and staff, to create new roles, made easier by the Agenda for Change job evaluation process. The establishment of a breast link nurse in cancer services has supported patients returning home, improving productivity by reducing length of stay (190 bed days in 17 weeks) and patient experience.

 (ii)   Reduction in emergency bed days

  Dartford and Gravesham NHS Trust improved its stroke service by using the NHS Knowledge and Skills Framework to strengthen staff competencies. Agenda for Change enabled the service to be redesigned and a new role to be created. The introduction of the Stroke Pathway Nurse means that patients are now treated on a dedicated rehabilitation ward, with better therapeutic input. Care has become more consistent, resources used more effectively and length of stay, bed occupancy and incidence of healthcare associated infection all reduced.

 (iii)   Reduction in "did not attends"

  Waiting times for the audiology service provided by Central Manchester PCT have been reduced to zero. Using the NHS KSF, staff have been trained to decide which audiology tests to apply, improving the efficiency with which diagnosis is reached. Agenda for Change out of hours arrangements have enabled an extended working day and longer working week. New roles have been created using the Agenda for Change job evaluation process. Assistants set up rooms allowing audiologists to concentrate on serving patients, improving skill mix.

 (iv)   Reduction in staff sickness

  The National Blood Service used Agenda for Change to standardise working practices across the country, its harmonised terms and conditions providing the basis for reviewing regional differences. The NHS KSF and Agenda for Change job evaluation supported the introduction of new and extended roles to support service redesign. Outcomes included "round the clock" working, where needed; reduced medical input; reduced courier costs; and improved staff morale reflected in reduced sickness absence.

 (v)   Reduction in Cancelled Operations

  Preoperative assessment can be carried out by telephone for fit patients having minor procedures. Hospitals that assess six weeks before admission have reduced postponement rates to 5% through better skill mix. Many hospitals use the NHS KSF to ensure nurses with the appropriate clinical expertise and experience have the skills to undertake telephone pre operative assessment. If consultants do pre operative assessment, they often do them too near to the procedure date, increasing the chance of cancellation.

 (vi)   Reduction in Use of agency Staff

  Avon and Wiltshire Mental Health Partnership NHS Trust has been using Agenda for Change job evaluation and the NHS KSF to tackle recruitment and retention issues in nursing by creating new roles including associate mental health practitioners, community mental health workers and advanced practitioners. These new posts are designed to attract a wider range of applications. Partnership working with trade unions ensures that staff are able to develop, progress and move into other posts over time. This initiative has reduced the reliance on agency staff.

 (vii)   Better skill mix—introduction of Emergency Care Practitioners

  Agenda for Change helps support new roles which improve efficiency and develop careers eg Emergency Care Practitioners (ECPs).

  About 900 ECPs are employed by ambulance trusts, supporting urgent and emergency care. They are able to work independently, treating at the scene adding value to services delivered in the community, out of hours and primary care.

  Agenda for Change supported recommendations in "Taking Healthcare to the Patient: Transforming NHS Ambulance Services" (2005) offering a career structure up to ECP.

  Since then, Agenda for Change has enabled a better skill mix to provide a greater range of mobile healthcare including a new role of Emergency Care Assistant (ECA) and increased use of Emergency Care Practitioners (ECPs).

  These changes help to develop a career structure in the ambulance service that more closely mirrors that of the wider NHS, with an emphasis on a range of roles that local ambulance trusts can draw on to respond to local demand.

4.  ATTRIBUTION OF PRODUCTIVE TIME AND QUALITY SAVINGS TO AGENDA FOR CHANGE STAFF

  The following tables look at the key deliverables of the Productive Time programme and attributes them first to the Agenda For Change workforce and second to the Agenda For Change contract.

  Table 1 estimates, in the penultimate column, what proportion of the realised efficiency saving is attributable to Agenda for Change staff. The % estimates follow the following logic:

    — the reduction in length of stay reflects the efforts of staff working in hospital (Agenda For Change is 75% of hospital staff costs);

    — the reduction in emergency bed days reflects the efforts of all staff, hospital, community and primary care (Agenda For Change is 67% NHS staff costs); and

    — the reduction in Did Not Attends is a whole system effect, not simply attributable to staff effort (Agenda For Change is 36% of total NHS spending).

Table 1

ATTRIBUTION OF PRODUCTIVE TIME AND QUALITY SAVINGS TO AGENDA FOR CHANGE STAFF
Key Performance Indicator Start point (April 2004)End Point (Mar 2008) Cumulative savings over the period April 2004 to Mar 2008 (£million) Estimated contribution from AfC staff Cumulative Savings attributable to AfC staff (£ million over the period April 2004 to March 2008)
Reduction in length of stay for elective in- patients 3 days2.5 days2,000 75%1,500
Reduction in emergency bed days33,508,608 28,293,9112,90067% 1,950
Reduction in Did not attends11.52% 10.60%9036% 30
Reduction in cancelled operations1.19% 0.91%3536% 10
Reduction in staff sickness4.71% 4.50%20075% 150
Reduction in use of agency staff5.2% of paybill 3.1% of paybill30075% 225
Better skill mix eg introduction of Emergency Care Practitioners (ECPs) 0 ECPs900 ECPs80 100%80
Quality£370pa£370pa 1,48036%500
Total 4,445
Rounded Down 4,400
Notes:



(i)  Figures rounded down. Those up to a 100, to the nearest five, those above a 100, to nearest 50.

(ii)  For length of stay, reduction in staff sickness and reduction in agency, the proportion ascribed to staff on Agenda for Change is based on their percentage of the overall Hospital and Community Services (HCHS) paybill, 75%.

(iii)  For emergency bed days, given the influence of GPs, their paybill is added to HCHS, reducing the influence of staff on Agenda for Change to 67%.

(iv)  For DNAs, cancelled operations and quality, all of which have a "system wide" impact, the influence of staff on Agenda for Change is less still and assessed as the Agenda for Change paybill percentage of overall NHS spend, 36%.

(v)  For better skill mix, the impact is adjudged to be 100%.

(vi)  The figures above except for quality are cumulative over the 4 year period of the productive time programme.

(vii)  Quality is an annual figure based on the ONS assessment of 0.5% pa (£370 million per annu,) as a proportion of NHS expenditure from 2001 to 2005. This has been extrapolated for the Productive Time period.


  Table 2, which provides a range within which it is estimated that the new Agenda for Change contract itself has delivered Productive Time efficiency savings, anticipating that some may have been delivered anyway ie without the introduction of Agenda for Change.

  The number and range of options illustrates the difficulty of allocating efficiency gains to one particular programme at a time when the focus of activity in the NHS was improving efficiency, not attributing it to different modernisation programmes.

Table 2

ATTRIBUTION OF PRODUCTIVE TIME AND QUALITY SAVINGS TO THE AGENDA FOR CHANGE CONTRACT
Key Performance IndicatorCumulative Savings attributable to AfC staff (£ million over the period April 2004 to March 2008) Cumulative Savings attributable to AfC contract (£ million over the period April 2004 to March 2008) [50%] Cumulative Savings attributable to AfC contract (£ million over the period April 2004 to March 2008) [33%] Cumulative Savings attributable to AfC contract (£ million over the period April 2004 to March 2008) [25%]
Reduction in length of stay for elective in-patients 1,500750495 375
Reduction in emergency bed days1,950 950640480
Reduction in Did not attends30 16108
Reduction in cancelled operations10 643
Reduction in staff sickness150 755035
Reduction in use of agency staff225 1157555
Better skill mix eg introduction of Emergency Care Practitioners (ECPs) 802013 10
Quality500250 165125
Total4,4452,205 1,4501,100
Rounded Down4,400 2,2001,450 1,100


  This methodology produces an estimated contribution from the Agenda for Change contract to efficiency savings of between £1.1 billion and £2.2 billion over the period April 2004 to March 2008 based on a range of assumptions that the Agenda for Change contract might have delivered between a quarter and a half of the benefits attributed to Agenda for Change staff themselves.

5.  CONCLUSION

  At this time, therefore, DH considers that between £1.1 billion to £2.2 billion might be attributed to the introduction of the Agenda for Change contract over its first five years from increased productivity, increased staff resources and improved quality. Although the methodology used here does not define the impact that Agenda for Change has made on the ground, we believe that on a number of reasonable assumptions it illustrates the likely scale of effect.

  The quality contribution will be reassessed once DH has seen the report from York University.

  Finally, one of the most important aspects of Agenda for Change is its ability to provide fair pay based on rigorous job evaluation. There was an estimate included in the business case to HMT of savings from fewer equal pay cases which was part of the "at least" £1.3 billion. DH is not in a position at this time, to assess the extent of any such savings given ongoing legal proceedings in which a number of key issues relating to Agenda for Change and preceding pay arrangements are being considered. At the moment, it is also unclear how long the legal process will take as that will depend on how the parties react to the Judgment expected at the end of this month.









4   http://www.york.ac.uk/inst/che/pdf/rp47.pdf Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2009
Prepared 18 June 2009