FiReControl - Communities and Local Government Committee Contents


Examination of Witnesses (Question Numbers 60-79)

DR ROGER DIGGLE, MR ROBIN SOUTHWELL, MR SHAHID MALIK MP, SIR KEN KNIGHT AND MS SHONA DUNN

8 FEBRUARY 2010

  Q60  Mr Betts: There is not a single fire engine out there linked up to it, is there, operating on a day-to-day basis?

  Mr Malik: There is not. The go live dates are not until mid 2011.

  Q61  Mr Betts: What was the initial date when the project started?

  Mr Malik: We signed our contracts with EADS in March 2007. Since then I think the Committee will be aware that there have been two delays. In November 2008, there was a nine month delay and in July 2009 there was a ten month delay that I myself announced.

  Q62  Mr Betts: Is the 2011 date now guaranteed?

  Mr Malik: For any minister, after two delays, to give a 100 per cent guarantee would be rather foolish. We are confident based on all the information that we have that mid-2011 still is the date.

  Q63  Mr Betts: Are the contractors absolutely confident it is going to be up, running and working without any more hitches?

  Mr Southwell: We are committed to delivering in accordance with what the Minister has just mentioned. There is no reason, sitting here, that we do not believe we will meet that commitment.

  Q64  John Cummings: Are you saying there have been no commitments to that in the past?

  Mr Southwell: No, I am not saying that.

  Q65  John Cummings: What are you saying?

  Mr Southwell: I am saying, in answer to the question, my response which is we are committed to delivering in accordance with what the Minister has just said is the schedule.

  Q66  Mr Betts: What is the contractual commitment, because I understand the current contract that you have does not go beyond March 2010. Is that right?

  Mr Southwell: No. Our contractual commitment is as the Minister has just mentioned, to be delivered in accordance with the schedule mid-2011.

  Q67  Mr Betts: Is it actually set down in a new contract that has been signed by both parties though?

  Mr Malik: Let me just make the situation very clear. We have a draft schedule which indicates to us that mid-2011 is the date by which FiReControl will go live. We are currently looking at that schedule. We are going to finalise it very shortly. All the indications are that 2011 will be achieved and there are some very considerable reasons for having confidence in that because there have been some drastic changes within EADS and some significant changes within the CLG and CLG's capacity which give us much more confidence. I will probably allow Shona, with your permission Dr Starkey, to respond to that but we have had some significant changes with new project directors, new commercial directors, new heads of communication etc. That gives us confidence on the capacity side of the CLG. There have been significant changes on the side of EADS, including a new chief executive for the project in the UK which gives more confidence.

  Q68  Chair: Were any of you in post at the start of this debacle? No?

  Mr Southwell: I probably was in the job at the start of this project.

  Andrew George: 2007?

  Q69  Chair: No; 2004.

  Mr Southwell: I was probably just starting the job around then.

  Q70  Mr Betts: Is there a contract in place at present which states that this project will finish by mid-2011?

  Ms Dunn: There are a number of documents that were signed by EADS and by ourselves either in the run up to or just after the July 2009 rescheduling. There is a heads of terms agreement setting out the revised expectations and there are two contract change notes which set out a number of additional milestones and revised expectations, both in terms of what is to be delivered and how the relationship between the two organisations will work. That has not been fully taken through to detailed changes in the underpinning contract as yet and that will happen once the ongoing process of reviewing the revised draft schedule that EADS have provided to us is complete.

  Mr Malik: In a nutshell, the answer is no, but we have a draft schedule which we are looking at. It indicates a mid-2011 date which is the time period that we have already announced. We are confident that we are going to bottom that out and come to a conclusion over the next few days and perhaps weeks.

  Q71  Mr Betts: Presumably officials have been negotiating this. If it was July when this revised schedule and other revised documents were put to you and discussions began between the contractors and yourselves, why in February—I make that seven months later—has no revised contract been signed? That is an awfully long time. We are talking about two years from July 2009 to mid-2011. More than a quarter of that time has gone by and no contract has yet been signed. Is this another example of the problems that have beset the contract from the beginning at official level?

  Ms Dunn: The negotiation that led up to the July 2009 delay was set down in the heads of terms agreement and subsequently in the two contract change notes. The reason that has then not flowed through to the contract is because of the uncertainty that started to build post the July announcement around whether EADS wished to stick with their original, main subcontractor or whether they wanted to shift their main subcontractor. We are now looking at a draft, revised schedule which takes account of the implications of the shift of main subcontractor. Once we have completed that process with EADS, we will be able to flow those expectations through to the contract. The decision was taken there was no point in flowing them through to the contract until that issue was resolved.

  Q72  Sir Paul Beresford: Was there a contract first with the original subcontractor and, if so, what was the deadline on that?

  Ms Dunn: There is a contract that does exist. I would have to go back and check. I do not want to give you an inaccurate answer on that.

  Mr Malik: We can write to you on that[2].


  Q73  Mr Betts: If there is not a contract then and EADS fail to hit this new target of mid-2011, are there any penalties that they have to pay?

  Mr Malik: One of the improvements that we have made is on the commercial contracts side. We have carrots and sticks built into that now in a way that patently did not exist in the past. We have key milestones and many more milestones that EADS have to meet. Payment is on the basis of meeting milestones. Where key milestones are missed, there are penalties by way of liquidated damages. We are in a very different position than we were in a year or so ago or perhaps even less.

  Q74  Mr Betts: If you have not signed the contract, surely none of those penalty payments or rewards is—?

  Mr Malik: We have agreements.

  Q75  Mr Betts: Are they legally binding agreements that actually mean something if they fail to hit the deadlines?

  Mr Malik: That is my understanding. I am trying to paint a picture where—

  Q76  Mr Betts: What do EADS think about this? Do they agree that they are going to face penalties if they do not hit the targets?

  Mr Southwell: If it helps, we are very comfortable with the situation, notwithstanding what you are hearing. We are comfortable because firstly we are in the process of delivering against the schedule which the Minister mentioned, notwithstanding that we are in the final stages of securing the documentation. There is no delay and there is no confusion on our side as we move forward to seek to secure that delivery. The second thing we mentioned, as the Minister alluded to, is we have offered and agreed to put in place a regime whereby if we are delayed beyond that we will take a commercial hit to ensure that everyone is aware that we are serious that this will happen. In the context of where we are now, nothing that we are talking about is delaying us getting on with the job. We will deliver this. We are committed to delivering this by mid-2011 and we will subsequently be prepared to pay damages associated with any further delay.

  Q77  Chair: If EADS are so terribly satisfied with this, where is the delay in signing the thing that was first negotiated in July 2009? Is it with the department?

  Mr Malik: No. This is obviously quite a complex matter. Do you want me to deal with the schedule issue or do you want me to just explain?

  Q78  Chair: We need to know why, if everybody agrees with it, it was not signed.

  Ms Dunn: There are a number of issues in relation to the shift to Intergraph. There are potential implications for various aspects of the schedule. We are working with EADS to really get into the nitty-gritty of what those implications are, to understand where additional risks are arising and where those risks are falling. We are working together with EADS to get a lot of very detailed information. This is an incredibly complex schedule and complex plan. There are over 200 individual lines within this and within each of those there are many, many more. We need to understand in great detail the exact implications before we can advise the Minister on whether or not he should sign off on that. To answer the point about the penalties and liquidated damages though, the penalties and liquidated damages in the original contract and the penalties and liquidated damages that we have agreed as part of the change control notes are absolutely still extant. They are legally binding and we can call upon them.

  Q79  Mr Betts: Have there been any penalties and liquidated damages so far on the original contract?

  Ms Dunn: Both around the November 2008 and July 2009 rescheduling there have been negotiated agreements with EADS.


2   Additional information provided in FIRE 26A Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 1 April 2010