FiReControl - Communities and Local Government Committee Contents


5  Lack of consultation and collaboration in the FiReControl project

68. The CLG memorandum maintains that engagement with primary stakeholders has occurred during the six years that FiReControl has been in existence:

    The FiReControl project has been running since 2004. Since that time, we have engaged very closely with the Fire and Rescue Service to understand their needs and to establish their requirements for the Regional Control Centre network.[79]

69. However, contrary to CLG's views, the general lack of consultation by CLG is a major theme running through both the written and oral evidence. During most of the FiReControl project's existence, up until about a year ago, there was a lack of consultation and collaboration between CLG, EADS, the FRAs and the LACCs, despite the legal responsibility of FRAs to prevent or deal with fires and the safety risks connected with this.[80] Written evidence from the South East Region supports this view:

    CLG owns the contract and commercial processes for FiReControl. FRAs are unsighted on the detailed obligations and outputs of the main contractor, EADS. The FRAs represent the main user and only customer for this contract yet have no contractual relationship with the supplier. Other Government Departments deliver large and complex projects by having a partnership between effectively 2 'customers' as the interface with the provider of operational capability. This has not been the case for FiReControl (nor FireLink) leading to the perception of disenfranchisement of the regions and individual FRSs. Too often, FRS involvement has been too little, too late when early engagement would have offered better support to EADS and increased project ownership by the end user community.[81]

70. This point is reinforced by the London Fire and Emergency Planning Authority (LFEPA), whose written submission highlighted the feeling of disempowerment by FRSs:

    The difficult challenges in the project such as defining all of the use requirements should have been addressed at an early stage; this may have led to much more clarity during the delivery phase. Again we would emphasise that early user engagement would have helped in this area but it is not only the engagement process but also listening to what the users have to say that is important. There needs to be a greater emphasis on partnership working between CLG and the FRS rather than the customer/client relationship which appears to exist at present.[82]

71. FRAs retain the statutory duty to make arrangements for dealing with calls for help and for summoning personnel for the purpose of extinguishing fires and protecting life and property in the event of fire, under Section 7 of the Fire and Rescue Services Act 2004. This statutory duty will not change when the new Regional Control Centres become operational. Despite this fact, the CFOA highlights the lack of consultation with those involved in the front-line services of Fire Control:

    Throughout the project the Government have failed to recognise and plan in accordance with the democratic and legal processes within which Fire and Rescue Authorities (FRAs), operate. This frequently results in inadequate time being allowed within the project plan for proper consultation and local decision making. Moreover it reinforces continually the perception within the service of being "railroaded" by central government at the same time that CLG publicly promotes the idea of partnership within the project. This has been a significant factor in eroding the confidence of key stakeholders and FRAs.

    Notably, in the early stages there was a gross misunderstanding on the part of Government about the legal and democratic status of Regional Management Boards and their ability, or otherwise, to make collective decisions on behalf of Fire and Rescue Authorities. This resulted in unrealistic expectations about local decision making processes.[83]

The FBU goes further, stating that CLG actively dissuaded consultation and collaboration with the main players, up until the point when technical IT problems occurred in the summer of 2008:

    Up to that point CLG [had] imposed itself as the go-between linking EADS to the FRS. We understand it made a point of ensuring there was little or no direct contact between the contractors and other stakeholders [...][84]

End-user requirement

72. The NAO memorandum describes how progress was delayed in breaking down end-user requirements:

    The Department set out approximately 2,000 requirements for the IT system in its contract with EADS. These needed to be broken down further into 8,000 more detailed sub-requirements in consultation with Fire and Rescue Services end users to ensure that the system's design, development and testing activities are aligned to end-user requirements [...] Little real progress was achieved in breaking down the system's requirements until summer 2009 when the Department agreed with EADS and the Fire and Rescue Services that joint workshops would be held to achieve this. Until this point there was uncertainty as to the design approach to be followed.[85]

The FBU goes on to describe complications with technical specifications of FiReControl:

    There were clearly major issues with the technical specifications the contractors were asked to deliver too. The Project scope has been changed before, after and since the IT contract was signed. There also appeared to be no 'real world' assessment of the true complexity of the project nor of realistic timescales to deliver what was being demanded.[86]

73. The exclusion of staff from any involvement with the specification and development of FiReControl led not only to delays, caused by a failure to appreciate the end-user needs of the system, but also to the demoralisation of staff and their sense of alienation from the project. The Fire Protection Association submitted written evidence that illustrates low staff morale in the fire community:

    The transition to the new arrangements for FRS mobilising has clearly created anxiety for a number of stakeholders in the fire community, including it would appear, some of those who will ultimately be responsible for its governance. That degree of uncertainty, dissent and project delay has done little to instil confidence in the wider fire community, particularly those who fear that the new arrangements will ultimately lead to a 'lowest common' denominator of service provision.[87]

74. The Minister confirmed that it was the responsibility of CLG to involve the FRS from the start of the project, to ensure that detailed end-user requirements was captured and used to develop the system:

    I think it was, absolutely. I take responsibility. We ought to have done that. We ought to have engaged key stakeholders in a way that was adequate. It was inadequate.[88]

75. Robin Southwell, CEO of EADS, also accepted responsibility for failures to involve the fire community from the start:

    I have to agree with the Minister that in hindsight we should have done a little bit more work earlier and we should have done a little bit more work after we had been selected in terms of bringing in the various stakeholders, defining their requirements, understanding the behavioural issues as to how it actually works on the ground, to allow us to gain the traction and momentum which we all wanted.[89]

Solution Establishment Workshops (SEWs)

76. After admitting that EADS and CLG had not taken account of stakeholders' views, Robin Southwell told us that they had learnt lessons and went on to describe the Solution Establishment Workshops (SEWs), which were created in the summer of 2009 and comprise of representatives from EADS, the FRS and CLG to address the issue of direct collaboration and stakeholder involvement:

    [...] we are having end user workshops, solution workshops, on a regular basis. In fact, I believe a few of them are working today, involving the end user on an operational basis so that we are real time ensuring that we have that dialogue which was missing at the beginning and which is now taking place.[90]

However, earlier in the same oral evidence session, the previous witnesses criticised SEWS, with John Bonney describing them as "not particularly well organised"[91] and explaining that not all representative bodies are invited to the meetings.[92]

77. When asked for supplementary evidence on the issue of satisfying end-user requirements, CFOA sent the following information about SEWs, describing what it considers to be a fundamental flaw in their approach:

    The Solution Establishment Workshops (SEWs) are a welcome improvement in user engagement but remain fundamentally flawed in their approach to system design. Each SEW has been focussed on developing a single thread of functionality in isolation. Where demonstrations of functionality have been possible, they have been on the basis of unrepresentative data and, when requirements are not apparently met, assurances are given that the functionality will be provided from "a different module" or by "workarounds". This gives rise to concerns that the system will be unnecessarily complex, unworkable and possibly fail to meet requirements when subjected to tests using real end-to-end scenarios and real fire service data.[93]

Responsibility for the lack of consultation

78. The issues of end-user requirement and stakeholder collaboration highlight the difference of opinion between CLG and EADS. Although in oral evidence the Minister and Mr Southwell appeared to share responsibility for the lack of stakeholder involvement, in its memorandum, EADS maintains that it is responsible for "deploying and transitioning the System to live operation, including loading the operational data", while CLG is responsible "for managing the whole 'business change' journey for stakeholders."[94] EADS continues to describe the changes that CLG has made in ensuring closer collaboration with the users of FiReControl:

    In order to ensure that the arrangements contracted with CLG satisfactorily represent the expectations of the FRS and RCC, these users must be involved at every step of the way. Close tripartite management is essential to enact this.

    We applaud the significant changes that CLG and FRS have made to the governance of stakeholder engagement and introduction of collaborative working which is essential to deliver the overall solution into use.

    The new operational processes are still being evolved by CLG with the FRS and RCC. Developing the processes alongside the system (as now in the new joint "SEW" workshops) will give a better result, but it does take significantly longer. This collaborative development will improve the chances of success, however, in particular for the FRS and RCC who need to undertake their implementation.[95]

79. However, as has been discussed earlier, CLG blames the project's delay—a delay that is largely due to an inability to address the end-user requirement—on EADS. [96]


79   Ev 96 Back

80   FRAs retain the statutory duty to make arrangements for dealing with calls for help and for summoning personnel for the purpose of extinguishing fires and protecting life and property in the event of fire, under Section 7 of the Fire and Rescue Services Act 2004.See paragraph 88 for further information on this. Back

81   Ev 46, italics added.  Back

82   Ev 65 Back

83   Ev 77 Back

84   Ev 103, italics added. Back

85   Ev 134 Back

86   Ev 105 Back

87   Ev 36 Back

88   Q 86 Back

89   Q 90 Back

90   Q 91 Back

91   Q 26 Back

92   Q 27 Back

93   Ev 80 Back

94   Ev 117 Back

95   Ev 119 Back

96   Ev 97 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 1 April 2010