FiReControl - Communities and Local Government Committee Contents


7  Costs

94. The following table, taken from the NAO's memorandum, shows how the delivery timetable and anticipated costs and benefits of FiReControl have changed since the project's inception:
  Strategic outline business Case Outline Business Case Full Business Case version 1.0 Full Business Case (Parts 1 and 2) Revised Full Business Case version 1.1 Current forecast
Published July 2004 November 2004 June 2007 July 2008May 2009 n/a
Cost to the Department £120 million £160 million £340 million £380 million£380 million £423 million[2,4]
Efficiency savings per annum for Fire and Rescue Authorities (£22 million)[3] 30%

(£25 million)

28%

(£23 million)

11%

(£8 million)

9%

(£6 million)

9%

(£6 million)

Overall project savings/(Cost) in NPV[1] £86 million £42 million (£50 million) £(211 million) £(218 million) £(240 million)
IT operational n/a n/aOctober 2009 July 2009May 2010 May 2011
Cut over to Regional control centres 2007-2009 2008-09 2010-2011 2010-2012 2010 onwards2011 -2012

Source: NAO analysis of FiReControl business cases[121]

Note 1: Period under consideration for overall project savings / (cost) is 2004-05 to 2020-2021.

Note 2: In addition the Department has a contingency of £17 million.

Note 3: Efficiency saving not provided in percentage terms.

Note 4: These figures exclude any potential royalty income from future sales of FiReControl technology.

95. CLG's written evidence notes that the FiReControl project "represents £420 million of investment in the Fire and Rescue Service".[122] It goes on to describe the changing financial costs of the project:

  • The first indicative cost figure given to Parliament for project implementation was £120 million, which did not include costs of meeting local and regional implementation work, nor costs for installing equipments in all fire stations. At that stage, CLG thought that the IT system would be delivered by commercial off-the-shelf solutions and the integration requirements had not been fully defined.[123]
  • In 2007, the first comprehensive assessment of the total cost to deliver the project was announced. The project cost was estimated at £340 million, based on a schedule for the first RCC going live in October 2009. The business case forecast national level savings of 28 per cent. compared with the costs of running the current control rooms.[124]
  • In 2008, CLG announced that the total implementation cost would be £380 million. The increase in project costs "followed engagement with stakeholders to further develop understanding of the local and regional costs of implementation including the revision of estimates on training and redundancy costs in particular".[125]
  • CLG commissioned an independent review of the current local control room costs during 2007-08, which found that their running costs were lower than previously estimated. "As a result of that review the annual savings which were reported at 28 per cent. in 2007 were reduced to 11 per cent. in the 2008 Business Case".[126]
  • The final version of the Full Business Case, published in May 2009, estimates the annual national savings once the network goes live to be £6 million (9 per cent.).[127]

96. It is disappointing that the estimated efficiency savings achieved through FiReControl have been revised downwards significantly during the course of the project. It is particularly unhelpful that one such reduction was caused by CLG's inaccurate data about current running costs of existing local control rooms.

97. The NAO states that the Department currently predicts that the FiReControl project will cost £423 million. Whilst the Department originally expected the project to realise efficiencies and save costs locally that would be in excess of the costs of the project, the Department now expects the overall project to cost £240 million[128] more than the local savings forecast. Not every Fire and Rescue Authority will make net annual cost savings locally as a result of the project. The Department plans to make annual payments of £8.2 million to these Fire and Rescue Authorities.[129]


121   Ev 128 Back

122   Ev 95 Back

123   Ev 97 Back

124   Ev 98 Back

125   Ibid. Back

126   Ibid. Back

127   Ibid. Back

128   Net present value. Back

129   Ev 128 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 1 April 2010