FiReControl - Communities and Local Government Committee Contents


8  Conclusions and recommendations

98. In May 2009 the Public Accounts Committee criticised CLG for poor performance in contracting and managing the New Dimension project. CLG responded by asserting that it had learnt lessons and was improving its delivery, citing the FiReControl project. Our inquiry shows that this is not the case.

99. The FiReControl project has been inadequately planned, poorly executed, and badly managed. The original contract was ill-suited to the nature of the project. Relationships both with the major stakeholders and with contractual partners have been mishandled. High staff turnover in CLG, especially at a senior level, has compromised the Department's ability to manage the project effectively. Costs have escalated and projected savings plummeted. The history of the project is a catalogue of poor judgement and mismanagement.

100. There are now considerable doubts about whether the project can be delivered. CLG needs to take this opportunity to consider carefully the points and concerns raised in this Report to review its options and make an informed, clear, open decision about the future of FiReControl.

101. On balance, given the investment of public funds already committed, and the benefits that will accrue, we conclude that CLG should press ahead with the FiReControl project. However, this recommendation is conditional on the assumption that CLG addresses the significant concerns and issues raised in this Report relating to its project management and the relationship with its main contractor and with its stakeholders. In particular, it is conditional on the urgent agreement of a viable project plan, in which the main stakeholders can have confidence, which will ensure that the target 'go-live' date of mid-2011 will be met. This project plan must include interim milestones which will allow progress to be assessed on a regular basis and decisions to be taken about whether alternatives need to be considered.

102. CLG should also put in place a communications plan that aims to shift the negative perception of the project and to influence FRSs to make the positive decision to switch to the system. Each FRA has the legal right to make the final decision on whether to accept FiReControl. CLG must respect that right and must work hard to unite all FRAs in supporting FiReControl. Any failure to ensure that all FRAs use the new system would be a significant blow to the ultimate aims of the project.

103. Meanwhile, CLG should urgently draw up and consult on contingency plans for any further failures. As a priority, those contingency plans should ensure ongoing safe and effective fire and rescue cover across the whole country whether or not FiReControl is implemented. They must also ensure that all regions involved will have adequate fire and safety measures in place during the 2012 Olympic and Paralympic Games. The plans should include provision for the maintenance and, where necessary, upgrading of existing control room technology, and CLG should meet the full costs of that to FRAs where it has become necessary as a result of delays in the FiReControl project.

104. We recommend that CLG inform our successors in the new Parliament in July 2010 that a viable project plan has been agreed with EADS, and report on progress against that plan, in particular the early version of the modified Intergraph product.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 1 April 2010