FiReControl - Communities and Local Government Committee Contents


Memorandum from Derbyshire Fire & Rescue Service (FIRE 05)

SUMMARY

  The perceived benefits of the Regional Control Centre programme were largely as follows:

    — To create Control Rooms capable of dealing with very large incidents, especially cross border.

    — To have Control Rooms with a great deal of technological resilience with commonality of controls to facilitate fall-back arrangements.

    — The accrual of cost savings in moving from 46 to nine Control Rooms.

    — Enhanced collaboration between the emergency services with such cross border and standardised entities.

    — Enhanced service delivery benefits with more regional working with common procedures, practices, naming conventions and common key datasets with efficiencies in information accessibility and resources.

  1.0  For the above to be realised, however, it would appear essential in the first place, purely from an operational perspective, to sort out common procedures, practices, naming conventions and common key datasets, certainly across a region and probably nationally upon which the technological solution would be based given that the Control Room would no longer be based within a single FRS but would need to service a number of FRSs.

  1.1  Secondly, it would also appear essential to sort out the political and legal relationships that would have to pertain between the RCCs and the individual FRSs and the Government so that everyone was fully aware of their rights and responsibilities under the law and within the wider political landscape.

  1.2  Thirdly, given the nature of the technological resilience envisaged for the RCCs with their specified need to be able to fallback to each other in the event of any serious failure and the data rich environment that would be needed to overcome issues of lack of local knowledge etc a tried and tested "end to end" technological solution needed to be specified which could support the procedures, practices, naming conventions and datasets detailed above.

  1.3  The Mott Macdonald report of 2003, The Future of Fire and Rescue Service Control Rooms in England and Wales, puts forward what it sees as a good example of how a new integrated regionally based Control Room could realistically be achieved wherein it cites the example of The South Wales Fire and Rescue Service which was created from three existing Fire Services, Gwent, Mid Glamorgan and South Glamorgan.

  1.4  The new regional service was created with all of the appropriate political backing and legal underpinning in place. Procedures and practices were then rationalised and common naming conventions and key datasets created for the new service. Obviously the relationship between the new Regional Control Centre and the South Wales Fire Service was made clear as the Control Room was firmly established as part of the new command structure with the appropriate technology specified to underpin all of this and put in place with a high level of positive user engagement.

  1.5  It would appear that the FiReControl project has attempted to do items 1.1, 1.2 and 1.3 in parallel to each other in a rather jumbled fashion rather than in the logical order pursued in the South Wales Fire Service scenario with the establishment of a new political framework of responsibilities followed by a related legal framework, followed by new common procedures and practices and consequent common naming conventions and datasets, followed by the specification of appropriate, resilient technology to underpin all of this with the appropriate user involvement. Thus we still do not have clear common practices and procedures in place across the region or nationally and have not established common naming conventions to any great degree, apart from the single instance of national call signs. Nor have we identified key datasets which we all can utilise and appear to be some way in the distance.

  1.6  Although LACCs have been formed to oversee the RCCs it is still not clear what the legal framework is and how individual FRSs will relate to the RCCs. What can FRSs legally expect from the RCCs and what can the RCCs legally expect from the FRSs. Are indeed the RCCs the agents of the FRSs who thus far have the legal responsibilities for Fire and Rescue activities or will there be some other arrangement.

  1.7  There is also no clear political framework in place that encompasses the relationship between the Government, the LACCs, the RCCs and individual FRSs. However, with all of that up in the air, a contract has been signed between CLG and EADS to put in place a technological solution for a national network of nine RCCS. The FRSs have had no direct sight of this contract and so cannot comment upon its suitability directly, CLG being the customer and EADS the contractor with FRSs being some vague "end user". However as the contract was signed in 2007 it has become apparent to FRSs that there would appear to be no tried and tested technological "end to end" resilient solution ready to be rolled out but merely a core system which is being constantly added to and refined.

  1.8  The related Firelink project which supplies the radio communications is also a little semi-detached from the FiReControl project with often unforeseen anomalies when the two projects coincide. For FRSs it is often difficult to know where responsibility lies between the two for any specific product or activity.

  1.9  From the FiReControl project, software products already released have left a lot to be desired in terms of their quality and appear to be constantly being worked upon. To the FRSs, therefore, the perception has gained ground that CLG have signed up to a generalised functional specification which will be translated down the line into a more refined technical specification as needs must.

  1.10  The cost savings promised also do not appear to be now realisable with deadlines being continuously abandoned and with all costs spiralling from their predicted base possibly as a result of the lack of legal, political, procedural and technological resolution alluded to above.

  1.11  Thus the conclusion appears to be that major legal, procedural, political problems still exist and even the technological solution is not settled two years after contract signing. FRSs, therefore, have little confidence left that all of these issues can be resolved in a reasonable timeframe and are already having to look to other possible solutions to prop up their existing, ageing mobilising systems. This is all the more galling to FRSs as they perceive that if the one billion pounds plus, which it is considered will be the cost of the FiReControl project, had been divided amongst the individual FRSs, perhaps with some central guidance on levels of resilience and cross border collaboration, then there would have been more than enough money for technological resilience and enhanced functionality based upon existing control room structures. Needless to say staff morale would also have been rather more enhanced than it is at the present time.

2.0  ISSUES

2.1  Political and legal framework for RCCs

  2.1.1  As expressed above it is crucial for FRSs to know where they stand in relation to the RCCs. In the main it is understood that RCCs will carry out the wishes of the individual FRS when mobilising resources within the FRS's boundaries, as expressed by the business rules etc formulated by the FRS and sent across to the RCC. However in exceptional circumstances the RCC reserves the right to mobilise resources as it sees fit especially regarding very large incidents, cross border etc by passing FRS rules in those instances. Thus the RCC by implication has legal responsibilities in its own right, separate from the FRSs. At present it is only FRSs which have statutory duties to undertake fire and rescue operations and to mobilise appropriate resources in a timely fashion. Statutory duties, it would appear would need to be extended to include the RCCs. Thus there would have to be a clear legal demarcation between the rights and responsibilities of the RCCs as opposed to those of the FRSs.

  2.1.2  At present the political and legal governing bodies of the FRSs consist of Fire Authorities based upon local authority boundaries. The RCCs are going to be governed, politically and legally it would appear, by LACCs consisting of councillors from the region in which they operate. However if a FRS has a problem with the RCC which it cannot work out using the normal channels it would have to appeal to the Fire Authority to take that forward to the LACC for resolution. But as the same councillors sit on both bodies is there not something of a contradiction in their respective roles.

  2.1.3  Undoubtedly at present there is an implied overlapping of responsibilities between FRSs and RCCs which could potentially be dangerous. If the RCCs were wholly subordinate to the FRSs in their legal obligations, operations etc then there obviously would be no such problem but with the RCC's perceived responsibility to act regionally or even nationally if it needs to then there is a de facto authority embedded within the organisation which sooner rather than later needs to be translated into a legal reality.

3.0  COMMON PROCEDURES, PRACTICES AND DATASETS

  3.1  The need for common procedures, practices, naming conventions and common key datasets is a high priority if the RCCs are to function properly across borders. However after more than five years since the inception of the FiReContol project, after numerous workshops and seminars at all levels there is perhaps only one firmly agreed common way of working which has been promulgated across FRSs and that consists of the establishment of a set of national call signs. Everything else is still being worked upon.

  3.2  All of the above needs to be established so that FRSs can embed these new procedures, practices, naming conventions etc into their organisations and this is extremely time consuming. Once these have been embedded within the FRSs then mechanisms need to be formulated whereby key datasets related to these procedures and practices can be sent across to the RCCs.

  3.3  Because of the detached nature of the RCCs (detached from individual FRSs) their ability to operate effectively will depend to a very large extent on the quality of the data sent from the FRS so it is essential to ensure that information rich data is sent across in a timely fashion and that the integrity of that data is maintained. Similarly data needs to be received from the RCCs at the FRSs so that the FRSs can be in a position to know how their resources are being deployed and how their resources are performing over time (all of which FRSs are aware of now).

  3.4  We appear to be a very long way off from establishing these things and if the RCCs are not going to become very poor quality call centres then these things are essential. The richness and quality of the data used and outputted will to a large extent dictate the quality of the RCC operation.

4.0  THE TECHNOLOGICAL SOLUTION

  4.1  At contract signing in 2007 the FRSs were under the impression that CLG had signed up to a tightly specified "end to end" nationwide mobilising system which just needed to be rolled out and installed at each station within each FRS. However as the months and years have rolled by it has become apparent that the specification has not been that tight. Initially no station end mobilising kit had been specified there was merely the core system at the individual RCC.

  4.2  The provision of the station end kit was presumably to be the responsibility of the FRS plus the negotiated attempt to interface with the RCC's core system. As the difficulties of that became apparent eventually the powers that be relented and station end kit was included in the scope of the project. But this still does not include one key system. FRSs at present, via a mobilising cabinet, send mobilising messages to stations which appear on printers and which set off lights and alarms, alert officers using paging systems or similar and alert retained fire fighters using proprietary alerter systems consisting of small range vhf transmitters based at stations, connected to their control rooms.

  4.3  The retained fire fighters have small pager-type receivers which receive the mobilising call notifying them to attend their stations. The retained alerter system is still not included under the FiReControl project, even though retained fire fighters comprise a substantial part of the FRS's workforce. It is the FRSs responsibility to supply and maintain such a system and interface it to the RCC system via the RCC network. This will complicate the operation of the RCC, obscuring system responsibility when it should be centred on a single entity (as it is in most FRSs now). Needless to say if FRSs were setting up a new mobilising system they would specify such a system end to end, including retained alerter systems and have maintenance responsibility operationally in one place.

  4.4  Furthermore, this late in the project, a key functionality of the system has not yet been determined. There is still no technical definition which defines how officers will be alerted and mobilised. The recently suggested switch from the Ericsson core mobilising system to an alternative Intergraph product this late in the day further enforces the doubts as to the suitability of the technological solution. CLG and EADS have suggested that switching systems should not greatly alter the findings of functional workshops which have attempted to determine how the system will operate but FRSs experience of system architecture suggests that each system has its own methods of doing things embedded within it and it is not so easy to change things.

  4.5  So far DFRS has received two major IT products from the project. These are MDT1a (Mobile Data Terminal software for holding risk-based data within the fire appliances) and DCMT1 (Data Collection and Management Toolkit software for collation of risk based data related to the existing mobilising gazetteer). Both of these products although based on commercial "off-the-shelf" software have displayed numerous quality flaws which have had to be rectified in ongoing and often acrimonious discussions with EADS and CLG. Indeed a number of issues are still outstanding.

  4.6  Major issues are also still outstanding regarding such matters as how we will connect to the RCC, how we will send data to them, how we will receive data from them, how we will maintain key datasets, how the station end kit which they are supplying will be installed and maintained etc.

  4.7  Thus the conclusion that FRSs have come to is that there was never a tried and tested technological solution ready to be deployed which could meet the aspirations of the correct levels of resilience and functionality detailed within the FiReControl literature and we are still a long way from achieving those levels. There is a danger that aspirations will be watered down as problems with the technological solution multiply to the extent that the functionality of the RCCs will be worse than the existing functionality based upon Control Centres in FRSs.

5.0  COSTS

  5.1  One of the benefits of the RCC network was going to be the savings accruing from the reduction of 46 to nine controls for the country. However it has become apparent that these predicted cost savings have largely evaporated. Even the FiReControl literature is not now predicting any substantive savings. FRSs would point to the time overruns and the still unresolved issues surroundings all of the above.

  5.2  There is still a massive discussion still to be had between the FRSs and the RCCs as to how much "back office" functionality will be undertaken in each organisation to replace what is undertaken now in FRS's control rooms over and above the simple mobilising process, all of which is not costed. Although CLG recompense FRS for various so called "new burdens" costs arising out of the Firelink and FiReControl projects nevertheless there are still substantial costs which are not met. Large parts of the extra, unforeseen, expenses incurred for maintaining the present mobilising system which in DFRS is well over three years beyond its original end contract date have had to be met by the FRS.

  5.3  A large part of the extra staffing costs are not met which includes the extra work other staff members have to undertake within DFRS beyond the core project team. Although some of these staffing and other costs can be seen to have brought some value to the FRSs in that they have allowed the FRSs to examine various procedures and processes, nevertheless it has to be admitted that much of this cost would be unjustifiable in the ordinary course of events. Thus there are substantial costs to the FiReControl project incurred by the FRSs which do not appear within the official project figures which if they were to be properly costed would definitely wipe out any proposed savings and would probably show that the FiReControl project taken as a whole was more expensive than the status quo with as yet unproven and unrealised benefits.

6.0  CONCLUSION

  6.1  Unless certain political, technological and legal barriers can be quickly overcome to expedite new ways of working and the appropriate use of common technology then the project as it now stands is probably not achievable to the quality standards envisaged in a reasonable timescale.

  6.2  As a good number of FRSs have mobilising systems now well beyond their contracted life it could be a good time for a number of neighbouring Fire Services to come together to jointly procure a new locally based but resilient mobilising system. Thus an alternative model needs to be considered, perhaps based upon existing control rooms with proper technological and procedural resilience designed in, between immediately neighbouring Fire Services.

  6.3  FRSs could be legally tasked with planning for very large incidents which crossed borders as this is primarily a procedural issue rather than a technological one. Such a project would involve between two and five services which would form a manageable project team and have a good chance of reaching some sort of conclusion in a reasonable timeframe.

December 2009





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 1 April 2010