FiReControl - Communities and Local Government Committee Contents


Memorandum from Lancashire Combined Fire Authority (FIRE 06)

1.  INTRODUCTION

  In response to the call for evidence for the Select Committee on FiReControl, Lancashire Combined Fire Authority provide a submission under the following main headings:

    — Project Management.

    — Costs.

    — Staff issues.

  The Authority continues to actively engage with the CLG to discharge its responsibilities under the Fire and Rescue Services National Framework to deliver the best solution forward for the Regional Control Centre. However, it believes increasing costs, together with numerous slippages, threaten the viability and credibility of the project.

2.  PROJECT MANAGEMENT

2.1  Business Case Approval

  Ministerial leadership and key CLG staff has regularly changed throughout the project. This has resulted in a lack of continuity, particularly with verbal commitments. One example of this was the Senior Responsible Officer (SRO) committing at a North West Seminar, that Authorities would be presented with the full business case to approve or otherwise. This was originally due in spring 2005 but delayed until October 2006. On her departure this commitment was remembered by elected members, but lost to the FiReControl Project.

  With the presentation of a full business case in 2009 and lease and infrastructure service contracts signed, the CLG has in essence delivered a fait accompli to Authority Members. This is reinforced by the £320 million committed to the project to date, over 75% of the expected cost.

2.2  Slippage

  The project has been blighted by slippage. It is understood that in a project of this type unforeseen events may cause some change in timescales. However, most recent issues revolve around the infrastructure services contract. Part of this procurement would have included agreeing specification and delivery to an agreed project plan, with financial remedies for non-compliance. It would be helpful for the contractual cause and consequences of any slippage to be explained to Authorities.

  Timing and communication of slippage has also been disappointing. Little regard has been given to the dedicated, professional staff working in Control Rooms across the country whose careers are deeply affected by these changes. Announcements as Parliament recess with little notice to FRA has become a common approach.

2.3  Accommodation

  Although FRA's have had some input on the accommodation workstream they were not provided with the proposed design until after construction contracts had been let. By any measure the accommodation is too big for solely a Regional Control Centre. For example in the North West the maximum number of staff handling calls will be less than 20, yet there are 47 potential office spaces, 80 parking spaces and a refectory for 30 (albeit any breaks would be staggered). The opportunity to provide a fit for purpose, more economic and efficient Regional Control Centre has simply been missed by the CLG. It will be for FRAs to pick up these additional costs through the lease and facilities management contracts.

2.4  Central Project Delivery/Resources

  It is evident that the different workstreams in the project have been delivered at very different rates. Hence many of the RCC buildings were nearing completion before the infrastructure service contract was let and available nearly 4 years before the programmed cutover date. It is also worrying, given the project has been running since 2004, that the detailed requirements of the technical solution is still being developed. It is not clear what the Central Project Team with significant numbers of secondees have been progressing throughout the project to date. Slippage has meant that some FiReControl work has not been available to action. Within FRA, resources can be redirected onto other necessary work when not required to work on FiReControl issues. However, this is not the case with the Central Project. It is only recently that FRS secondees have been released from their role within the Central team and returned back to FRS to reduce costs when workflow has been interrupted by blockages in the project

2.5  Sustainability

  It is understandable that following terrorist attacks in London and abroad there will be an increasing emphasis on resilience. However resilience must be coupled with sustainability. The building lease for the RCC is for 25 years (possible two years extension), the infrastructure services contract is for eight years (possible three years extension); the FM contract is for seven years (possible two years extension) and the Firelink Contract for 10 years. However all the emphasis is on initial delivery not how these contracts will be aligned, renewed or refreshed in the future. It remains unclear who will fund the next generation of the system and how replacement will be managed whilst maintaining resilience and interoperability.

3.  COSTS

3.1  Financial Assumptions

  A weakness of the FiReControl project is it is continually working against an uncertain financial backdrop. The business case is difficult to follow as there is not clear trail about the project costs and benefits included since the inception of the project, without cross referencing to at least three other substantial documents dating back to 2004. Despite the presence of the Finance Working Group, financial assumptions are not agreed before publication. This results in a full business case being issued when assumptions made are still in dispute.

  For example, it is assumed in the business case that the current cost incurred in running existing controls will automatically be saved on transition to RCCs. This is simply not the case. With the efficiency agenda most FRS are seeking to downsize so extra office space is not required. Furthermore a commercial let of a control room which is normally integrated within a wider premise is not feasible.

3.2  Cost Apportionment

  Lancashire CFA would also contend that the CLG's apportionment of infrastructure service and central support team costs is flawed.

  The CLG has stated their intention to apportion should have been:

    — Simple, transparent and easy to understand.

    — Relatively stable over time.

    — Reflects the region's ability to pay.

  Their preferred method was apportionment based upon the relative share of tax base and they went out to consultation on that basis. This is the method for apportionment that was used in the Full Business Case. The Authority would argue, given that all RCCs will have identical IT specifications and requirements, that shared costs should have been split equally between regions. This would also have avoided the situation where local tax payers in one region subsidise tax payers in another. This approach fulfils the first two CLG criteria in the bullet points above. Also given the CLG has already agreed the concept that resilience payments will be made to regions incurring net additional costs, the regions ability to pay will be taken into account by this provision.

3.3  Critical National Infrastructure Requirements

  The requirement for RCC to be part of the Critical National Infrastructure is obviously a CLG requirement based on enhancing national resilience. It is well in excess of current standards. The business case does not highlight clearly what elements of the costs are attributable to national resilience and Critical National Infrastructure requirements. Lancashire Combined Fire Authority believes that in line with the New Burdens doctrine such costs should be clearly identified and centrally funded. One example of these costs is the 24/7 security required at the RCC. FRA will be liable for these costs through the facilities management contracts. Clarity regarding how these costs have been allocated is required.

4.  HR ISSUES

4.1  Over prescription of Structure and Staffing

  It is recognised that HR solutions rests with the employer in this case the respective RCCs. It has taken time to resolve the governance issue to enable the employer to become a legal entity and all parties must accept some responsibility for any delays.

  However the FiReControl Project has generally adopted a utopian approach to HR issues.

  The papers provided are largely theoretical best practice, detached from the reality of existing terms and conditions and TUPE tensions. Much of the work that has driven efficiencies has been commissioned on a regional basis. It is unfortunate that the Project could not have been more proactive in this respect.

  The supervisory structure was devised when staff numbers were estimated to be 100-130 and has never been adjusted despite operator numbers being reduced. This provides a level of supervision particularly at a senior level unparalleled anywhere else in efficient Fire and Rescue Authorities. This is just another example of lost opportunity to optimise the RCC.

4.2  Communications

  Over the duration of the project Communications has generally been poor. There have been some good examples such as the locations release but the FiReControl Communications leads have been many and short-lived. The problem is less to do with individuals and more to do with the priority Communications commands in the FiReControl Project.

  Most recently there have been some encouraging signs, with the appointment of a new Communications Lead with the recognition of who is responsible for which messages to which stakeholders.

  Part of the frustration is the consistency and credibility of the messages we give our staff. Fire and Rescue Authorities relate to their dedicated and professional staff whose careers will change dramatically as a result of these proposals. Within an ever changing environment they remain surprisingly patient with remarkable levels of morale considering the challenges they are facing. Only certainty with the project will provide the firm basis upon which local release of information can be planned.

January 2010





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 1 April 2010