FiReControl - Communities and Local Government Committee Contents


Memorandum from Buckinghamshire and Milton Keynes Fire Authority (FIRE 09)

EXECUTIVE SUMMARY

    — Whilst Buckinghamshire and Milton Keynes Fire Authority (BMKFA) has expressed concerns on a number of occasions regarding the FiReControl Project (the Project) Members and Officers of the Service have worked to support it throughout its life.

    — The deadlines required by the Project have been demanding at times but officers of the Service have consistently met these in order to avoid causing further delay often at the expense of local initatives.

    — The delays in providing a credible solution mean that Buckinghamshire Fire & Rescue Service (BFRS) Officers struggle to "sell the concept" to staff groups.

    — Project credibility has been further affected by regular slippage.

    — BMKFA has serious concerns regarding the manner in which costs will be met in the future and information offered by CLG has provided little reassurance.

    — At this time BMKFA is predicting that an additional £350,000 per annum will be required to support the discharge of duties under Section 7 of the Fire and Rescue Services Act 2004 (FRS Act 2004) following cutover to the Regional Control Centre (RCC).

    — Continued uncertainty over the Project increase the risk to this Authority created by loss of Control room staff.

    — At present the costs associated with provision of national infrastructure will fall to local Fire and Rescue Authorities.

    — The initial project scope has now been altered resulting in the removal of some elements such as the optimal resource location software, the result being that the Project now offers little that is not already available in many existing Fire and Rescue Service (FRS) Control rooms.

    — Provision of equipment such as Mobile Data Terminals (MDTs) is welcomed but the delays associated with the Project mean that the technology offered is now considered out of date in many FRS.

INTRODUCTION

  1.  This report is submitted on behalf of Buckinghamshire and Milton Keynes Fire Authority and supports the South East Regional Management Board response. It is intended to offer a more local perspective for the consideration of the Committee.

  2.  Within this submission reference is also made to the Firelink Project which, whilst not part of the direct Select Committee remit, is fundamentally linked to the Project and is quite obviously a key enabler.

BFRS PROJECT INVOLVEMENT

  3.  BFRS has resourced the Project from its earliest stages and remains well placed to meet the deadlines and milestones set. This organisation believes that the concept itself is a valid one if somewhat utopian. However throughout the Project BMKFA has expressed concerns regarding the removal of local control rooms in favour of an untried and untested concept. Indeed throughout the Project slippage and technical difficulties have further reinforced this perspective.

  4.  At this stage, and with budgets likely to be adversely affected by the current financial climate, this Authority is more concerned that ever regarding the lack of clarity on Project costs. At this time there are no clear costs for either the FiReControl or Firelink Projects upon which the Authority is able to base its future cost projections.

  5.  The limited functions that will be carried out by the RCC's will almost certainly result in a large number of activities that are currently carried out by existing control room staff having to be undertaken elsewhere within FRS. This will undoubtedly dilute any possible cost savings and indeed many FRS, including BFRS, have real concerns that any savings will be realised.

  6.  At Project start BFRS had an old but reliable mobilising system. In the early stages of the Project it was felt inappropriate to begin a replacement project for that system given the impending RCC's. However following a number of Project delays and the ageing system that we were using it became apparent that there was a need to consider a replacement. BFRS has had that replacement system in place since mid-2009 and has had to do so in order to ensure that it can continue to meet its statutory duties under the FRS Act 2004.

  7.  BFRS has chosen to upgrade some elements of its existing mobilising system, but has not carried out a total refresh as might have been undertaken had FiReControl not been underway. There will therefore be further work to be undertaken should the FiReControl Project not deliver a system in the near future.

  8.  Despite the slippage BFRS has, to date, managed to maintain a technically capable and appropriately staffed control room but the continued uncertainty will undoubtedly begin to take its toll in the near future as staff look for increased job security.

  9.  Dorney Lakes in South Bucks is within a mile of the border with Royal Berkshire and is one of the 2012 Olympics venues. Had the project delivered according to a number of the earlier deadlines then the upgrade would have been completed prior to the Olympics with the obvious advantages of integration that this would have provided should a response be required to the events. However BFRS is now scheduled to cutover just after the Olympics in late 2012 creating a double negative: BFRS will not be part of the integrated FiReControl solution; we will also have to balance a significant amount of preparatory work required immediately prior to cutover whilst managing the risks associated with supporting an Olympics event.

THE CAPABILITIES BEING PROVIDED

  10.  The delays now mean that what may have been a viable advance in technical capability a number of years ago is now common place within many FRS. This means that a vast quantity of public money will now be spent with little hope of any real advances. Granted the ability to mobilise across borders will be an advantage but this assumes that there is cross-border mobilisation on a large scale, this is not the case and therefore the advantages that this offers are limited.

  11.  The technology that is being offered in terms of vehicle mounted MDTs to facilitate data transfer and improve availability of risk information to crews are now in wide use within many FRS including this Service. The proposed software provision is already in use by a number of FRS but in a far more integrated way than is currently available via this Project. It should also be noted that a number of Services already have a more advanced MDT solution in use meaning that at cutover to RCC's they may have to accept a reduction in functionality.

  12.  The MDT hardware offered under the Firelink Project is now also showing its age before it has even been fitted, a number of Services having now taken the decision to replace fixed MDT's as provided under Firelink with demountable units which have many advantages in terms of functionality for the support of Fire Service operations.

  13.  The Firelink project has provided an improvement to inter-brigade and inter-service communications, however many FRS have seen their wide area radio costs multiply by a factor of 10. Whilst Firelink is a key enabler for the FiReControl Project there has been a lack of standardised provision with each FRS allowed to specify its own requirements. The FiReControl Project has also, to date, failed to clearly detail the methods that will be used to mobilise resources. This has resulted in no standardised provision for FRS and as such it is entirely possible that some FRS will have to incur further costs involved in the provision of further communications equipment in order to ensure that an RCC is able to mobilise their resources.

  14.  On a purely emotive issue one of the assumptions of the FiReControl Project is that technology is able to deal with any local issues and as such there is no need for local knowledge in local control rooms. This is a flawed concept since technology may be able to deal with locality issues but it will struggle to support people who are genuinely in distress and for that there is no substitute for the human factor. Concentrating on meeting caller demand based upon purely quantity factors completely misses the need to appreciate that when people are under significant stress in an emergency quality of call management becomes a more important factor. The demand to handle calls quickly will place considerable pressure upon RCC Control Room Operators to concentrate on quantity not quality.

  15.  Project reviews have resulted in some elements being removed. For example the proposed resource optimisation system based upon the FSEC algorithms has been removed. This was designed to ensure that risk to the public was appropriately managed, but this has been removed to be replaced by a system whereby Brigades simply nominate key stations based upon a set of simple, but arbitrary rules. The ability for CRO's and the RCC to balance risk at times of high demand is therefore removed in favour of a basic set of rules simply because it became apparent that this was too difficult and/or too expensive to achieve.

  16.  There are also a number of performance issues relating to the prime contractor; to date the DCMT1 terminal has failed to deliver anything useful to BFRS. Both it and DCMT2 have experienced significant delays and MDT1.0a is now faced with a significant credibility issue due to the difficulty in transferring data to the terminals and no immediately available network capability.

  17.  At this time the main system known as the Mobilising and Resource Management System (MRMS) does not appear to exist and the schema required to allow FRS to develop interfaces to this and other critical systems is not yet available prompting further fears of impending delay.

PROJECT GOVERNANCE

  18.  The current RCC premises costs (£160,000 per month) are significant, the total project cost predictions, £43 million (as detailed in parliamentary questions), is a significant sum and one which many members of the public may feel is disproportionately high. With a general election due to take place in the next year, and with the suggestion that other parties may take a different view to the existing Government, project credibility is further undermined.

  19.  The contracts themselves have remained an area of contention with many FRAs. Whilst BFRS would like to support the Project and in particular to ensure that the systems and services provided meet contractual obligations a lack of visibility has hampered this.

  20.  Members of this Authority and Officers of the Service do not believe that either the contractor, nor CLG, have properly engaged with us as key stakeholders and perhaps more importantly it is felt that there is in many cases a lack of true understanding of the business needs associated with the receipt and handling of emergency calls.

  21.  The recent consultation on in-service contract management has further undermined the relationship between this Authority and CLG by not providing useful information or alternative options with the circular. Indeed it appears that prior to the consultation deadline work was already underway to recruit Board members for the Non-Departmental Public Body making the consultation process appear as a paper exercise.

  22.  The lack of stakeholder engagement at an early stage in respect of the RCC building, in the South East at least, has created concerns over the specification process used. It is felt by this Authority that the building is over-specified and will cost considerably more than needed. This cost will have to be borne, at least in part, by the residents of Buckinghamshire and Milton Keynes. There remains no route through which these costs can be challenged by this Authority.

CONCLUSION

  23.  Within BFRS there is a very real concern that staff have lost faith in the project and there is no doubt that after a further three years our project team will be suffering a considerable degree of scepticism over whether the project will ever reach fruition, whilst project credibility is probably now at its lowest ebb.

  24.  BFRS is confident that the quality of our data is high and that we will be in a position to provide what is required by an RCC. However the large scale automation required within the RCC environment is an area that historically FRS have not utilised simply because emergencies, by their very nature, are difficult to predict accurately and whilst there may well be some similarities many require a more flexible approach that would be difficult to achieve through automation, hence the need for experienced, well trained staff who have the time to make quality decisions not be forced to achieve a quantity target.

  25.  It is accepted the Project has demonstrated that in the event of large scale and/or widespread emergencies there is a need for a greater integration. As such a local control room in each FRS may not be the ideal approach but consideration to simply integrating existing facilities (where they remain suitably robust) must now be reconsidered.

  26.  Whilst this Authority will continue to resource the Project to the best of its ability the pressures being placed upon the Service to deliver in so many other areas will undoubtedly begin to impact on FiReControl deliverables. Given the almost inevitable further delays and this Authorities stated position that it supports local control rooms staffed by local operators it is the recommendation of BMKFA that the continuation of this Project must be carefully considered.

January 2010





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 1 April 2010