FiReControl - Communities and Local Government Committee Contents


Memorandum from Yorkshire & Humberside Regional Management Board (FIRE 12)

  In response to the Communities and Local Government Committee's decision to undertake a brief inquiry into the FiReControl programme, the Yorkshire and Humberside Regional Management Board wishes to offer the following comment with respect to the terms of reference set:

  The Committee will consider the progress with the project so far; the reasons for the cost and time overruns which the project has experienced; and what, if any, changes need to be made to the Government's plans for proceeding with the project. Written submissions to be received by Friday 8 January 2009.

  The Yorkshire and Humberside Regional Management Board is comprised of members from the region's four fire authorities, West, South and North Yorkshire together with Humberside FRA and exists to deliver various important national goals that were defined in the 2004 White Paper "Our Fire and Rescue Service".

FIRECONTROL PROJECT—BUSINESS CASE

  The final Business Case, published in Spring 2009, brought together both the national and regional cases for the first time. Elected members up to that point had received information and made decisions at a local level against the original strategic case, which presented the rationale for the project across a range of policy areas. The strategic benefits that the project aims to achieve have been supported by fire authority councillors and officers across the region, however, the critical matter of the project's final cost to individual fire authorities and therefore the communities they serve had not been presented until the regional case was published.

  The original concept predicted national savings on current control room costs of up to 30%, whereas it appears that nationally savings will only be achieved when the network is operating fully in, say 2015. CLG's calculations suggest that 21 FRA's will achieve savings, while 24 will face increases, which are to be covered by a new Resilience Grant. CLG, however, have made it clear that it will not commit the Government to maintaining the grant beyond three years; it will be reviewed in each Comprehensive Spending Review.

  That statement alone has created nervousness and confusion at a local level. Firstly, how has CLG been able to secure the millions required to cover the first three years of operation of each RCC when that will probably, if not, definitely fall within a subsequent CSR period. Secondly, it appears that when it is advantageous to do so CLG can organise longer term financial support as is the case with the New Dimension assets it wishes to transfer to local government and will financially assist the Service in maintaining national resilience for the duration of the asset's operational life, the contract we believe is for a duration of 16 years. If indeed national resilience continues to be paramount and the RCC network forms part of the critical national infrastructure, surely long term financial assurance is not an unreasonable expectation or request of individual fire and rescue authorities?

FIRECONTROL PROJECT—GENERAL

  Each of the four constituent Fire Authorities that make up the Yorkshire & Humberside region have committed significant resource and time to both the planning and implementation phases of the project. Members of the Regional Management Board have received updates of national, regional and local progress on a quarterly basis. A range of issues, problems and concerns have remained fairly constant throughout, namely:

  Limited user engagement in the development of technical requirements; the difficulties associated with separate procurement processes for the building accommodation and the technical solution; security arrangements and the specification and size of the accommodation itself; limited consultation in the development of the project meant an opportunity was missed to learn from the service's existing control rooms; lack of clarity with regard to new burdens settlements for the life of the project; lack of genuine partnership working between CLG and the FRS; and ongoing delays with the technical solution.

  From the early stages of this project there has been a lack of effective user engagement and consultation. This has led to a lack of understanding within the central project team of the technical requirements needed to procure a system that would satisfy the operational requirements of individual fire services. The procurement process was undertaken despite the majority of user requirements lacking definition. These apparently were to be resolved post contract award.

  At the time, both the Chief Fire Officers Association (CFOA) and fire service representatives voiced concerns that this would bring uncertainty and risk to the development of a state of art technical solution. It remains unclear why CLG were so confident that the successful bidder would be able to develop a system that would meet all of the yet undefined requirements. The ability of the mobilising system to be able to reflect FRS's individual IRMPs remains a central requirement of the project and if not delivered it would leave FRS's to further question CLG's approach.

  Fire Authorities have a duty under section 7(1) Fire and Rescue Services Act 2004 to make provision for the purpose of extinguishing fires in its area and protecting life and property in the event of fires in its area. Also, under section 7 (2) (c) it must, in particular "make arrangements for dealing with calls for help and for summoning personnel". Should confidence in the final system remain low it will be the local Chief Fire Officer who is responsible for undertaking a risk based operational judgement whether to migrate from their current mobilising arrangements to the one offered.

  Statutory responsibility will not change once the network of Regional Control Centres become operational even with the contractual arrangements and service level agreements between FRSs and the LACCs in place, it remains with individual FRAs.

  As already mentioned the decision to procure the accommodation and technical solution separately, rather than by way of an integrated approach, has been questioned at a local level. The buildings appear to be over specified and are too large. The security arrangements incorporated into the premises appear to be in excess to the threats potentially posed to the buildings, both of which have increased costs that will result in a long term revenue burden to fire authorities in Yorkshire & Humberside. Resilience and security requirements were designed to meet Government standards but once again consultation was not undertaken with Fire Authorities at a local or regional level.

  FiReControl and Firelink Projects have operated simultaneously but separate of each other with their own management structures despite many similarities and a requirement to bring about integrated solutions. This has not only led to delays to the overall programme and problems associated with technical aspects of the two projects but also once again excessive back-office costs to the programme itself and inevitably to FRA's in the longer term.

  The project is being delivered by a team within CLG that consists of civil servants, seconded fire service staff and consultants. The team appears to be very large for a project of this nature. One would have expected the risks and the resources required to deliver the project to have sat with the supplier, however, in this case CLG seem to be bearing much of the responsibility and resource burden of delivery.

  The impact of this on the service in general is that it has drawn a lot of the technical expertise from fire services into the centre. From one perspective this is to be welcomed, as it is only by engaging with users that a viable product will be produced, but this has led to a significant risk emerging which is that the fire services themselves will no longer have the in house capability or capacity to deliver their transition activities that are required prior to being able to accept FiReControl into service.

  Supposedly there remains a commitment from Government that the FiReControl Project will not be a net new cost burden on fire authorities. The main concern for fire authorities is the ongoing revenue costs of the project post implementation. The most recent business case has set out the projected annual payments that are to be made to authorities incurring additional costs because of the project.

  Concern regarding the long term future of resilience payments has not diminished. CLG have only been able to give an undertaking to review these payments after three years, which is confusing as it has been able to direct funding to the New Dimension programme for long term maintenance and servicing contractual arrangements. While it is accepted that a review is required once steady state has been reached to ensure that payments remain accurate there is a fear that the review could lead to these payments being reduced or discontinued. This would lead to an increased burden for local tax payers. In order to ensure that fire authorities are willing to commit to this project, a clear commitment is required that the principal of new burdens funding will apply for the full term of the project and not just the first three years.

  The numerous delays in the delivery of this project have led to a lack of confidence in the ability of CLG to deliver a complex project of this nature. The problem stems again from the lack of user engagement at early stages of the project. From the beginning CLG seem to have failed to grasp the complex nature of this project. If this project is to deliver its objectives there needs to be a new culture of working in partnership with the FRS, more realistic goals and timescales need to be set. This has not always been the case to date.

  The impact of delays to the project on the FRS is not insignificant. Dedicated project teams have to be kept in place with a lot of expertise either being seconded to the national project team or committed to the project internally. This takes away valuable expertise for delivering other projects and programmes that are essential to maintaining a first class service to the public.

RECOMMENDATIONS

  The final arbiter of whether the FiReControl system is acceptable to any individual FRS should remain with the respective Chief Fire Officer, otherwise CLG may need to consider the use of directive powers.

  There needs to be more effective user engagement if the project is to be delivered successfully with all user requirements captured and clearly defined.

  The FiReControl and Firelink projects should be consolidated with significant savings in consultants fees.

  Less reliance should be placed on the use of consultants for specification purposes when there are reliable sources of advice readily available within other government departments.

  More regular external project reviews should be undertaken and there should be a greater willingness to accept change within the project as circumstances change.

  There may need to be a clearer definition of responsibilities between the CLG and the supplier as it appears that there is a large central team having to support the supplier and so taking on a greater burden of the risks involved.

  Ongoing impact on the FRS should be closely examined by CLG and communicated in a transparent and informed manner.

  The defining of user requirements should be addressed immediately.

  The financial settlement to cover the net new burden to the FRS needs to be a transparent process that is based on the real impact to authorities and not on the cash available to the project.

  There needs to be a very clear message from the government to fire authorities that new burden payments will continue for the life of the project and not just the first three years.

  If the government should decide to change either the project in its entirety or any aspects of its delivery strategy the service itself should be offered the opportunity to manage the implementation itself, either by refreshing existing systems or by collaboration with partners. The government should provide full funding for this to be implemented.

  An Options Review should be undertaken and communicated to all 46 FRAs as part of a formal consultation exercise.

January 2010





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 1 April 2010