Memorandum from the Fire Brigades Union
(FIRE 27)
1) The Fire Brigades Union
(FBU) represents approximately 45,000 members covering all ranks and duty
systems in the fire & rescue service including approximately 4,000
officers, 11,000 firefighters working the retained duty system and 1,500
firefighters (control). This represents over 85% of all uniformed operational
personnel currently serving in the fire & rescue services. The FBU welcomes
the opportunity to submit evidence both written and verbal to the Select
Committee and this submission deals with some of the key issues. We would also welcome the opportunity to
appear before the Members of the Select Committee to support our submission and
to attempt to answer any questions they may have upon it.
OVERVIEW
2) The Government originally
'sold' the FireControlProject on Invest to Save principles. The result, it was
asserted, would be a much better and more resilient system which would be delivered
in a staged cutover between 2006 and 2007 and pay for itself within 5 years.
3) FireControl is now
massively over the original cost estimates, there are significant problems and doubts
about the technology, what it can deliver and whether the system will be
'resilient'. The Project will not be complete, even on current timetables until
the end of 2012 at the earliest, if at all. There will be no savings, it will
cost more.
4) The problems must be put
down to lack of foresight, major errors at the beginning and since, poor
project management, lack of stakeholder engagement or genuine 'sign up', an
inability to take proper note of real concerns and the dismissal of doubters and
sceptics out of hand.
5) Costs and timescales
became totally out of control, leaving some FRS's with ageing systems that
require imminent replacement. Many had not upgraded because of the expectation
that a new RCC system would be in place by 2006/2007 and then later 2008/2009.
6) Many have no planned
Control facility going forward. The responsibility of the fire authority
remains to ensure control systems are fit for purpose to fulfil its statutory
duty irrespective of the FireControl Project which may or may not be concluded.
7) Such is the state of the
Project and lack of confidence in it that a fundamental independent review must
be undertaken involving all stakeholders and utilising and upgrading current
controls, the FBU's preferred option, must be considered as part of that
process.
8) Assertions about the
resilience of the new system are now central to the new Government 'spin'.
There is no evidence to support claims of greater resilience or that the end
result will be a much better system.
9) It is important to temper
the Government 'spin' with a dose of realism about what has been achieved and
what could be achieved.
PROGRESS SO FAR
10) The RCCs buildings are
nearly all built. None are close to being operational and their costs are a
significant drain on the Project.
11) Supposedly 'resilient',
they are red brick construction with considerable areas of glass situated
behind wire-fencing in open business parks. Some are based on flood plains,
flight paths or close to airports and major motorway junctions, all of which
undermine claims of 'resilience'.
12) There have been numerous delays
and cost-overruns. Morale has plummeted, confidence in the Project has nose-dived
across the service. There has been immense pressure on senior operational
managers. Some key staff have left.
13) The adoption of the LACC
model has created major problems and a whole cottage industry of additional
FRS/Regional Management Board advisors replicated across every region in England. A
simpler, and cheaper solution would be a secondment model for control staff,
that would be real progress instead of the current uncertainty for staff and close
the gold mine for consultants giving HR and legal advice on the employment
issues.
14) All RCC Directors have been
appointed. The first four appointed had no fire service background, let alone a
fire service control background. This was the preferred outcome of CLG.
15) In 2008 there were 130
project risks on the FireControl Risk Register, eight of which were rated
'high' or above. On 16 December 2009 in a Parliamentary Answer in response to a
question from David Drew, fire minister Shahid Malik said there were 176
project risks, "of which sixteen are rated 'high' or 'very high'."
16) There are major concerns
with the technology.
Command
and control
17) FireControl was intended to
produce a 'stripped down' version of our current emergency fire controls. The
FireControl concept was based, as we pointed out, on a roadside assistance
control model - call-handling, mobilising and limited incident monitoring and
support.
18) The lack of a proper
command and control role or function in the RCCs started to become more
obviously apparent to the wider fire service from 2008 onwards. Command and
control is what ensures the safety of firefighters and the public at incidents
and goes well beyond basic incident monitoring and support.
19) It is central to fulfilling
several statutory duties placed on fire authorities, including ensuring the
health and safety of their firefighters. A proper command and control function
was not included in the specifications for FireControl.
20) At a FireControl workshop
at the BAPCO conference on 22 April 2009 concerns were openly acknowledged. A
very senior advisor to EADS on FireControl faced a number of probing questions
from FRS control officers who raised the issue of command and control at
incidents.
21) EADS made clear the system
being provided to RCCs was call-taking and mobilising, with some limited
incident monitoring because those were the contract specifications. There is NO
command and control function, "it is not part of the specifications".
22) The contract
specifications, he said, meant that at incidents officers would have laptops or
MDTs and apart from that they would be "on their own". The EADS advisor said it was only now that
FRSs were starting to realise the lack of a command and control function in the
contract specifications for the RCC technology and there needed to be "debate"
about what happens.
23) Our clear understanding is
that on this point the contractors delivered to the specifications demanded of
them. This serious omission was made by those who set out the contract
specifications.
24) The issue is not fully
resolved and is of grave concern. At the very least, remedial work causing
further delays and costs will have to be undertaken and a whole new area of
"out of scope" work has been identified.
25) It has significant
implications for the staffing model, the technology, cost and delays. In our
view this played a very significant role in the further delays which have
emerged and at least some of the additional costs which have arisen as a
result.
26) The matter of how command
and control is maintained in a practical sense with the breaking of the link
between local FRSs and their local emergency controls is still not resolved. In
answer to a Parliamentary Question from John McDonnell MP, about the transfer
of operational command and control arrangements to regional controls the fire
minister Shahid Malik replied: "The responsibility for operational command and
control will remain, as is now, with local Fire and Rescue Services".
Unproven
Technology, Under Development
27) Until recently the proposed
mobilising system from Ericsson - CoordCom - had never been deployed in the UK fire service
market. To state that it was proven off the shelf technology was misleading and
inaccurate.
28) It is also worth noting
that the FireControl Updates contain 2 items which are "to be costed by EADS"
relating to mobilising officers and dynamic mobilising, both standard features
in existing suppliers' systems. This again indicates that the original system
specifications would be functionally less than the systems currently in use in
some areas.
29) It has now publicly emerged
that Ericsson is to be dropped altogether in favour of Intergraph I/CAD as a
mobilising system. Intergraph I/CAD has been tried and tested and failed in the
UK
fire service.
30) In the proposed Cleveland tri-centre tests,
Intergraph I/CAD failed. In any event, no system has been tried and tested in a
national network of regional fire service controls, as none exists anywhere in
the world.
31) We anticipate the
FireControl specification may be more demanding than those specified a few
years ago and we will need some convincing that a product - albeit an updated
version - which failed a lesser test can now succeed in a more demanding one.
32) We anticipate knock on
effects including potentially on DCMT1 and DCMT2 which we mention later in this
submission. This may lead to further delays.
Resilience
33) Another major feature cited
as essential was that of resilience. The choice of 9 different systems does not
in itself guarantee resilience, neither does 46 systems. The system
architecture chosen by CLG for 9 Systems is then compromised further by only
having 3 Data Centres, all of which are housed within 3 of the existing
controls.
34) Currently to render the FRS
in England
inoperable a considerable number of FRS's would have to fail or be taken out by
terrorist attack (as well as their backup facilities). Under the new scheme
taking out the 3 Data Centres will render the whole RCC infrastructure
unusable.
35) Without the Data Centres
then the Gazetteer options become unusable and dispatching impossible for such
large areas. Current localised systems, even without Gazetteers, can mobilise
with area knowledge to generate responses to an emergency situation.
36) The call-handling capacity
is appallingly low because of very low staffing numbers. As a result individual
RCCs will hit spate conditions much more quickly.
37) At times the national
network will have very, very low numbers of staff on duty - less than 60. The
entire national system could hit spate conditions when several RCCs hit spate
conditions at the same time. This would happen during, for example, widespread
weather events such as flooding or widespread snowfalls.
Database
Generation
38) The current proposal is
utilising the NLPG dataset. This is meant to be another benefit of the proposed
RCCS.
39) This is utilised by many
organisations and is a substantial database for mobilising. However it is
somewhat different to the databases that FRS currently use. Many FRS have
started to switch their existing systems to use the NLPG database and are
finding out at first hand the problems it poses.
40) To give some
examples:Business Parks that are currently built generally identify the
different premises as Unit 1, Unit 2 etc. This is how these buildings appear in
the NLPG Database. Once let the Building now has a name and may change hands
several times even 1 year. These names do not appear on the NLPG database for
some considerable time - if ever - and the company name provided will result in
no match against the gazetteer when searched by the operator at the RCC.
Invariably the Unit number will not be given or known and does not form part of
the new address. To overcome this each FRS will have to generate an "extra"
database containing this information, maintained by them, a not inconsiderable
task.
41) Another example is that
many towns and cities have areas within them, these areas form part of the
address to the local inhabitant. In one FRS there are that 9 areas in one town
which do not exist in the NLPG database, as such every property in those areas
will have to become part of a local database for that FRS to allow matching
against the supplied address. The only alternatives are to get the NLPG
database amended (only allowed through Local Government request and a lengthy
procedure) or to get the residents to change the way they report addresses. It
is our belief that it is almost certainly impossible to do either within the
timescales involved.
42) There will be many similar
examples that will come to light as the Database generation continues and
practical use of NLPG emerges, these items should have been known and dealt
with at the outset.
43) The transfer of information
is time consuming and cumbersome. It also has to be provided by FRSs and is out
of scope work.
DCMT1
AND DCMT2
44) These are the toolkits for
converting and transferring the FRS's existing data into a format that EADS can
use to link the FRS related data to the NLPG database and also to generate the
"extra" databases that contain the entries that do not exist in the NLPG
database.
45) Problems with the DCMT1
toolkit became apparent to fire and rescue services in the summer of 2008 and
has played a major role in the delays. We understand these problems only became
apparent after CLG, as the Project Managers, had signed off the toolkits as
meeting the contract specifications and it was then rolled out FRSs.
46) Up to that point CLG at
imposed itself as the go-between linking EADS to the FRS. We understand it made
a point of ensuring there was little or no direct contact between the
contractors and other stakeholders meaning the problems only became apparent
after the toolkits had been cleared for release to FRSs.
47) This issue of direct
collaboration was addressed - belatedly - in the summer of 2009 with the
creation of Solution Establishment Workshops, the first attempt at genuinely collaborative
working. But what it highlights is that this was not happening before and only
started when the Project ran into serious trouble with delays mounting.
48) The DCMT1 toolkit may now
be substantially complete, albeit nearly 2 years late. Some of the issues have
been inexcusable. But in the absence of close contact between EADS and the FRSs
- a decision taken by CLG as Project Managers - it was perhaps inevitable.
49) Project Managers should
have known that the larger authorities would have enormous data sets and for
the initial releases to appear to have problems handling large data sets is
ridiculous. The other reported issues shows the poor quality systems at Departmental
Project Management level that allowed these to get to the end user.
50) Again the Project
Management systems and methodology (Prince 2) should have picked these items up
and managed them rather than supplying poor quality tools - albeit to
specifications agreed and signed off by CLG - within the project life cycle.
51) Switching the mobilising
system from Ericcson to Intergraph/ICAD may produce further problems with the
DCMT1 toolkit. That remains to be seen.
52) CLG has consistently
under-estimated the amount of work needed to be completed by FRSs to identify,
cleanse and capture the data even with the toolkit working perfectly. This is
at least 3 to 5 years of work.
53) There is limited and
reducing capacity within the fire service to deliver this quickly - the ability
is there, simply not the number of control personnel needed to carry out the task
in addition to their existing workloads.
54) Whilst DCMT1 is used to
identify what FRS address data is contained within NLPG, and what is not, it is
the more complicated DCMT2 that "binds" this information together. Only time
will tell whether similar issues will emerge with DCMT2 as did with DCMT1. It
is imperative that mobilising arrangements for a life-saving emergency service
such as that for the fire and rescue service aren't changed without being fully
validated and tested beforehand. Testing "in the field" is not a professional
option to adopt.
55) It would be surprising,
given the complexity of the technical challenges, if they did not. There may
also be issues relating to the switch to Intergraph I/CAD as the mobilising
system.
56) We are aware, given the
delay to the roll out of the DCMT1 toolkit, that many FRS's have not completed the
work and some are only at the early stages of starting the work relating to the
use of DCMT1. Without this data it is difficult to conceive how any meaningful
testing of the system can take place.
57) Performance of this system
will depend on the volume of data searched and a system that works with a small
data set may not even work, or work as well, with a large data set if the
hardware is not specified correctly.
Current
System Capabilities in Business Case inaccurate
58) One of the main reasons
cited by numerous Ministers for the Project was that the current systems did
not support the latest technology. There were 9 Technology items cited in each
Regions Business case Part 1, being:
MDT's / VMDS
Information Available to Fireground
AVLS
Status Updates
Dynamic Mobilising
EISEC
GIS (Ctrl Only)
GIS (Integrated into Service)
Full Premise based Gazetteer
59) This information is
inaccurate, misleading and has never been corrected.. Some items are incorrect and
others are inaccurate in that the facilities were available but the FRS chose
not to purchase them eg Dynamic mobilising, EISEC and Premise based gazetteer.
60) Ministers then used this
data to cite one of the reasons for the justification for the project was
ensuring all fire controls had the most up to date functions. Had the correct
information been established from knowledgeable sources then this justification
would have been non-existent.
61) Since the project award all
the items listed above are available on all the existing suppliers systems,
most as standard items if local fire and rescue services judge them to be
important enough to purchase them.
62) The Department could have
amended GD92 which sets out requirements for control systems to ensure all systems
could have been gradually upgraded in the normal way to meet these
requirements. They have not done so, they still could.
HOW DID WE GET TO WHERE WE ARE NOW?
63) The approach and Project
management were flawed from the outset. The entire Project was bundled into a
single contract with a Prime Contractor leading a Consortium. Such was the
scale of the Project, there were probably no more than a handful of companies
worldwide which could have bid for a project of this size with a realistic
chance of success.
64) This approach effectively
meant that every existing experienced supplier of control systems to the UK
fire service market eg Fortek or Remsdaq, would be excluded. They were.
65) It also meant there was a
very high likelihood that the Prime Contractor chosen would have no experience
in delivering a control system to a fire service in the UK or, possibly,
anywhere in the world. This is what transpired.
66) Project Management was
supplied by a series of Departments with little historical knowledge of the
fire service, informed - if that is not putting it too strongly - by transient
civil servants and consultants with no experience of delivering any fire
service control system of any size, anywhere. It was overseen by a series of
transient ministers.
67) There were some FRS
secondees in various numbers at various stages. Of the 60 people assigned to
the Project in the first few years, only 12 were from a fire service
background. What weight was attached to their work, opinion or views is not
known.
68) Once the decision had been
taken to 'bundle' the contract in such a way - with the inherent flaws we have
outlined - the use of a Consortium or Prime Contractor to facilitate such a
large and ambitious project is entirely in order.
69) However, the project differed
from the fire service norm at that time in that the Prime Contractor (EADS)
appears to have largely a supply/ install contract only. Central Project
Management was and is being carried out by CLG using their own staff along with
some seconded FRS staff and consultants.
70) There were clearly major
issues with the technical specifications the contractors were asked to deliver
too. The Project scope has been changed before, after and since the IT contract
was signed. There also appeared to be no 'real world' assessment of the true
complexity of the project nor of realistic timescales to deliver what was being
demanded
71) The results are clear for
everyone to see: no clear and consistent understanding of how emergency fire
controls work, lack of leadership, controls, objectives and relevant technical
expertise. Even with such a flawed
process, a single 'Turnkey' contract could have removed some of the issues and
led to a clear target to be achieved or penalties to be levied.
72) Instead, CLG FireControl
Project managers were a barrier between the contractors EADS tasked with
delivering the technology and the end users -fire and rescue services. Direct
collaborative working between EADS and the FRS was blocked by CLG until the
creation of Solution Establishment Workshops (SEWs) in the summer of 2009.
73) The central point of the
creation of the SEWs is not that the process started, but that it took until
the Project was on its knees before CLG allowed this method of direct
collaborative working to be put in place.
74) Poor CLG Project Management
was compounded by what should have been the close relationship between the
FireControl and Firelink projects. Delays to the FireLink Project have had a
knock-on effect on FireControl and vice-versa.
75) It is clear from our
discussion with a number of those involved in both projects that there was a
lack of transparency, openness and communication between the two projects for
prolonged and critical periods. The responsibility for that lies heavily at
Departmental and ultimately ministerial level.
Firelink/FireControl
76) The original timetable to
complete FireControl by December 2007 was tied to the completion of FireLink,
the new digital radio system, which had a delayed completion date of December
2007. FireLink is providing the vast majority of the benefits claimed for RCCs
and is very technically challenging in its own right.
77) While we know FireLink
radio technology can work for brigade level controls there has to be a question
mark over its capacity to work across several fire services region-wide. There
are already genuine question marks about the capacity of Airwave, which is now
a private monopoly supplier to the emergency services, given the increasing
burdens being placed on it.
78) Delays to FireLink do have
a knock-on effect on FireControl. Some of these were set out in a National
Project Manager's Update, FireLink Strategic Snapshot- December 2007. This
acknowledged that a number of fire services did not update their existing
controls - known as legacy systems - because the new RCCs were meant to be in
place by the end of 2007.
79) Delays to both the FireLink
and FireControl Projects meant "interim solutions" had to be put in place to
cope with the late-running of both Projects. Additional work had to be carried
out with for what was described as the "longer extended interim solution".
80) Problems identified in the
FireLink Phase A operational Rollout included: Fit out of 8 'pilot vehicles in
each FRS: "temporarily stalled in the early regions due to delays by Airwave in
providing test scripts." Issues with training "eg lack of training equipment."
81) Problems were identified in
the Phase B launch date (the fit out of the main vehicle fleets). This was
"progressively delayed as a result of....over ambitious forecasting and inadequate
groundwork by Airwave....delays in submission of test scripts for Phase A
acceptance work....knock-on effects of the (preceding) Police resilience
programme."
82) These issues meant "Airwave
roll out forecasts have been drifting increasingly out of synchronisation with
events on the ground since the late summer". The result was a "realism
adjustment" - a euphemism for a further delay. FireLink Project managers
reported they had been able "to persuade Airwave fully to reflect the reality
of where we are and their track record to date by adding a significant amount
of contingency to their forecasting."
83) This strategic snapshot is
also revealing in a number of other points. Concerns about the fitting of
aerials to officers cars threw up other concerns about "the evolving FireControl
Concept of Operations appears now to be shifting beyond the current FireLink
scope of supply based on a wider interpretation of the term 'resilience'.
Separate work is therefore now in hand...to clarify the FireControl Concept of
Operations..."
84) The Concept of Operations
would play a major role in setting out the technical specifications for the
contract agree with EADS. That it was still evolving at this stage - there was
still no fixed Concept of Operations - would make it much more difficult to
establish the technical solution.
85) The same report includes
part of a letter from Richard How, the senior civil servant heading up the
FireControl Project on a day to day basis. This letter, to the FireLink team,
reveals there were already concerns about delays for FireControl arising a
matter of months after EADS secured the contract.
86) It revealed that Mr How had
written to the FireLink team at the end of August 2007 about "concerns that the
release dates for a number of products - in particular Convergence and Data
Schema - from EADS were later than planned." Mr How told the FireLink team,
operating from within the same Department and upon which FireControl depended,
that EADS provided some information but that it would "be counter-productive"
to share that with them at that time.
87) By November Mr How could
still not share the information. He could say that "Since then we have been
working closely with EADS to develop a comprehensive set of robust plans in
which we all have confidence....However, EADS is not as far advanced as they and
we hoped they would be....this lack of information is preventing the FRS from
developing their detailed activity and resources plans....the failure to deliver
to date is inevitably creating concerns about the capability to deliver as they
have contracted.....the delay in providing information is compressing the time
available that that (sic) the FRSs have to complete their activities...."
88) It would be unfair to
Airwave and EADS not to point out that these documents only set out the views
of CLG Project Managers. These comments may be unfair to one or both
contractors, may not fully set out the full picture or be self-serving in other
ways
89) What is clear is the
Department was not ensuring the proper flow of full information between the key
personnel and the key contractors working on two closely related Projects. If
anything, the Department was a barrier to the flow of critical information
between and within both Projects.
OVERVIEW - GETTING IT WRONG FROM THE START
90) The project is defined to
operate under the Prince 2 project management process. Like all Project
management processes these define tasks, timelines, costs,
checkpoints/gateways, actions, personnel, risks and should include for
contingencies. The documented hierarchy published in the Business cases (Part 1
and Part 2) provides for the accountability.
91) The published delays do not
account for the difference in time from the original proposal and the current
end date. There must therefore have been significant delays during 2003, 2004,
2005 and 2006 prior to the first re-alignment date. It would not be
unreasonable for the Select Committee to request sight of the original Gantt
chart (project plan) and the current one.
92) This should show (under
Prince 2 guidelines) all of the slippages and the reasons and what corrective
action, if any, was taken. All plans should be reviewed at least monthly if not
more frequently and reports produced to show progress/issues/corrective
action/costs to date. There are timelines in the Business case documents but
these contain insufficient detail and were only produced in 2008/2009.
93) The FireControl Project was
based on a 2003 report from Mott MacDonald, updating an earlier report. It
purported to set out how a much better and more resilient system could be
completed within 4 years, would pay for itself and save money.It was clearly
flawed.
94) A key part of selling the
original decision to proceed with the project was undoubtedly based on the
financial information produced in the 2003 Mott McDonald which indicated there
would be significant savings (£20 Million year on year) to be made on a Project
costing £100 million. This produced the claim by then Minister Nick Raynsford
that the project would pay for itself within five years.
95) There would be on-going
savings, it was asserted, and these would be ploughed back into the fire
service. On paper, it was a formidable case - a much better system, delivered
in a few years, making massive savings using tried and tested technology.
96) As the Fire Brigades Union
repeatedly pointed out, this was obvious nonsense to those with hands on
experience of managing significant change in a control room environment. Even a
brief consideration of numerous Public Accounts Committee and Select Committee
reports would show national Government's inability to deliver projects that
worked, on time and to budget.
97) It is belatedly accepted by
Government that no national network of regional fire controls exists anywhere
in the world. The technology has never been tried and tested on this scale, if
at all, in a fire service environment. The technology is in development during
the course of the Project and remains so.
98) The 2003 Mott MacDonald
report also aligned FireControl with the Labour Government's Regional
Government Programme. It is only in the context of a regional fire service that
a regional control centre could make any sense at all, although there would
still be issues of resilience and operational practicality.
99) The original initial
capital one off costs, based over 10 years, were estimated as £100 million
(Mott McDonald Full Report 2003 page 143) which included new buildings (£25.2
million), systems (£36 million), project management (£12.2 million) and
redundancy costs (£27.1 million) with ongoing savings on costs of maintenance
(£28.1 million) and ongoing staff savings (£143.3 million).
100) Completion was
estimated to be 4 years after commitment, namely 2007. There is a major error
in the Mott McDonald report that calculates the savings to be £70.8 million
over 10 years. But they mistakenly had ongoing costs of maintenance as a saving
rather than a cost. Taking this into account, the actual estimated savings
should have been stated as £14.7 million, not £70.8 million.
101) Although the
Government has reconfigured its arguments to be based on assertions - although
not evidence - of better resilience, alleged cost savings have always been
central to the Business Case for FireControl. This is cynical. Other options
were and are being rejected on the basis they could show no savings.
102) The original
cost estimates bear no relation to the actuality which has unfolded. While we
have some sympathy to claims that further estimates are over different
timescales to different specifications, it remains that the Project was
originally pitched and sold on the basis of a very flawed report.
103) In our view it
is not a reasonable excuse that specifications and scope changed and a project
was adapted or added to. It is a consistent criticism of how things start to go
wrong in major IT projects.
104) Some of the
details of the promises on cost savings are set out in the FBU response to
Business Case, April 2009 at p11. That
document also sets out in some detail our major concerns about the Project
which we will not repeat in this submission but attach as requested.
105) We also attach
numerous independent reports commissioned from the Institute of public Finance
which detail the progression of the Business Case. These are also attached and
we will not re-visit all the detail within those reports.
WHAT THE GOVERNMENT CLAIMS THE PROJECT
COSTS
106) The Government
often uses figures which are different to or selectively chosen from those used
in their Business Cases. These also need to be addressed.
107) Given the detailed information they must hold, there is
little consistency in the Government claims of what the Project will cost.
Figures are quoted over different time scales - some to 2012, others to 2020.
108) The fact that some of the leases, signed in 2007 onwards
are over 20 years and some over 25 years extend beyond both dates. There
appears to be no co-terminosity in the lease termination dates which are likely
to close out between 2027 and 2032.
109) When it suits, and to 'prove' alleged savings, staffing
costs of running the RCCs are included. At other times they are not.
110) It is an oft quoted comment from Government that critics
of the project are not comparing like with like, or using different timescales.
The Government appear to do this themselves, making it very difficult to tie
down what the full costs are or even details how the costings have changed in
the various Business Cases.
111) Differing language is used by Government to describe
various costs as "basic initial costs", or "set up" costs to "estimated full
cost of implementing FireControl". The Business Cases quote a figure of around
£1.4 billion, although that does include on-going staffing costs through the
life of the Project.
112) These are included by Government - it is their Business
Case - because alleged savings were always based on cutting the numbers of
emergency fire control staff. We will return to that issue later.
On 22 October 2009 the following question was
asked and answered:
Mrs. Spelman: To ask the Secretary of State for Communities and Local Government
what recent estimate he has made of the total cost of delivery of the FiReControl project; and what estimates were
made in (a) 2004, (b) 2005, (c) 2006, (d) 2007 and (e)
2008. [293319]
Mr. Malik: The current estimated overall cost of delivery of the FiReControl Project for (a) 2004 was
£120 million; (b) 2005-£160 million; (c) 2006-£190 million; (d)
2007-£360 million; and (e) 2008-£380 million.
On 2 November
2009 [source] Mr Malik answered in another question: The basic initial costs
and timescales of implementing the FiReControl
project, as originally estimated in 2004, were £120 million. Following more
detailed work, project costs were updated to include funding to fire and rescue
authorities for local and regional implementation activity, the costs of the
regional control centre building leases and the costs of equipment to be
installed in every fire station in England to support improved
mobilisation.
The
expenditure to date on the project is approximately £190 million. The estimated
full cost of implementing FiReControl
is £420 million.
113) Even on these figures
the cost of the Project has more than tripled.
WHY HAVE COST INCREASED?
114) The reasons
given in Mr Malik's reply for some of the increased costs show how
ill-thought the original estimates were.
Mott MacDonald's building costs estimates were £25.2 million and even over a
ten year period (as opposed to the longer leases) are well short of the reality
of the leasehold and other costs relating to the buildings.
115) The fact that
Station End Equipment - the 'cost of equipment to be installed in every fire station'
- were left out of the calculations - beggars belief. It meant the Project was
moving along on the basis they had worked out the cost of the equipment needed
to send a message, but not the fact there would need to be equipment to receive
the message and it would have to be paid for.
116) In a letter
dated 13 November in response to concerns raised by a constituent of Rob Marris
MP Mr Malik goes further in explaining the cost and time overruns: "the
FireControl technical solution has proved to be more complex than originally
anticipated, and the development stages have taken much longer than expected."
He asserted that the contract with EADS was signed with them having a full
"understanding of the technical solution required....[nor having full] information
about the amount of work that would need to be carried out by the individual 46
Fire and Rescue Authorities."
117) Only once the
contract had been signed - which was in 2007 - he asserted, did "it become
apparent that the Project scope needed to be broadened." No details of the
broadening of the scope are given.
118) The Outline
Business Case (OBC) November 2004 sets
out in some detail (at Appendix C) why the costings in original Mott MacDonald
report were wrong. The OBC identified some key areas of risks the Project would
face including that there was a very high risk of total project failure.
119) The OBC uses a
Private Developer Scheme (PDS) as its recommended method of supplying new
Regional Control Centre buildings. It is an expensive option and the OBC
underlines the catastrophic impact on any estimated savings of the buildings
being completed more than six months before they are meant to become
operational.
120) The OBC heavily
flagged up, as a significant risk, the financial impact of the buildings being
completed more than six months before they were to start becoming operational.
It also pointed out the importance of there being a degree of co-terminosity
for leases for the new RCC buildings which would become the national network of
regional control centres. That is they would all expire and have to be renewed
at approximately the same time or within a reasonable period of each other.
121) The OBC
identified that from the signing of the PDS contracts to building completion
would take around 18 months. Building in a six month rent-free period from
practical completion to becoming operational would deal with the issue of rents
being paid for empty buildings and is a sensible recommendation.
122) Having
identified these two key traps to be avoided - and the mitigating steps needed
to be taken to avoid them - the CLG Project Managers then walked into both
traps. On 10 August 2005, without any further Business Case of any kind, CLG
announced it was proceeding with the PDS scheme, sites had been identified and
the contracts signed with the developers for between 20 years and 25 years and
which come to an end between 2027 and 2033.
123) The minister,
asked on 16 December in a Parliamentary Question by David Drew to make a
statement as to how a national network was to be kept in place after the ending
of the first set of leases in 2027 and the ending of the final leases in 2034, simply
referred to the Landlord and Tenant Act..
124) The signing of
the PDS contracts at such an early stage has been catastrophic. No update of
the Outline Business Case was produced before the decision and no more detailed
work had been done on costings, timescales or the prospects for the technology.
125) A draft Full
Business Case was produced in 2006 and another update in 2007. Another was
promised throughout 2008 and eventually appeared. The IPF reports on all of
these are attached.
126) The Institute of
Public Finance, in an independent report for the FBU, said in its assessment of
the Private Developer Scheme PDS scheme - the biggest price 'ticket' for the
whole project - did not demonstrate value for money. The IPF also identified a
£200 million increase in the total project costs in the FireControl Business
Case. The overall Project costs did not rise above the £1.4 billion identified
in the previous 2007 Draft Business Case because an assumption was made which
cut back on staffing costs by a further £200.
127) Having hastily
signed the property contracts, the IT contracts then waited for more than 18
months to be signed. There was therefore no chance of the RCC buildings being
operational six months after practical completion and rents becoming payable.
128) The IT contract
was signed in March 2007 after much delay. As we pointed out earlier, by August
2007 CLG were already complaining about delays to DCMT1 and Convergence work.
Why CLG expected such complex work to be completed within a few months has
never been explained, but it was from the summer of 2007 that concerns about
delays started to emerge.
129) Our own response
to the Full National Business Case is also attached. We will not go through
that in detail but attach it as requested. It does raise significant questions
about resilience, call handling capacity and call filtering by BT and Cable and
Wireless Operators.
WHERE
DO WE GO FROM HERE - basic principles
130) First, a
profound reality check is needed. There is little confidence left within the
fire service that this Project is going anywhere good and it's not going
anywhere soon.
That is an opportunity to re-think what
basic principles should underpin what happens next.
1. There are political limits to how far
local democratically controlled fire services are prepared to go towards
regionalisation;
2. There are technical limits to what can
be achieved at a regional level within a reasonable timescale and budget;
3. You should only be prepared to take
great risks and go to great expense if there is evidence - not assertion or
mere conviction - that the rewards are so great as to justify the level of risk
being taken;
4. There must be clear link between the key
strategic priorities of local fire services and any future Project
configuration, including agreed measures of success.
5. There must be clear ownership and
leadership driven by the needs of local fire services and not by the needs of
central Government;
6. There must be an effective engagement
with all key stakeholders and a re-building of confidence and co-operation;
7. End-users need to buy in to any future
project and not have it used as an opportunity to drive down their working
conditions or working environment;
8. Project managers must continue to
demonstrate skills and a proven approach to project management and risk
management.
9. There must be an agreed and realistic
timetable, greater co-operation with all stakeholders including contractors
with the aim of achieving a proper collaborative environment and not a return
to a blame culture and key players being kept apart;
10. Adequate provision of resources and
skills to deliver what is required.
The ten key principles we set out above
should apply to any future configuration of how the benefits required from
future systems are delivered. The key is delivering what local fire and rescues
say they need going forward, utilising at least some of the work, and possibly
some of the RCC buildings if appropriate.
131) Alternatives to
FireControl are already being explored with or without the knowledge or
co-operation of CLG. Our preferred option, on the basis of speed, cost and
confidence in it as a solution is to utilise upgraded existing controls.
132) This not a
'do-nothing' option. The union is also prepared to consider any Business Case
presented which considers other options. We would urge that under any other
options, including RCCs if Government does press ahead.
133) A decision to
press ahead regardless does not make success a certainty. The technology may
never be made to work in the way required of it.
January
2010
|