Examination of Witnesses (Questions 1-)
LORD COE,
MR PAUL
DEIGHTON, MR
JOHN ARMITT
CBE AND MR
DAVID HIGGINS
15 DECEMBER 2009
Q1 Chairman: Good morning. This is the
Committee's annual session at which we take evidence on the preparation
for the London 2012 Games. I would therefore like to welcome the
Chairman of the London Organising Committee, Lord Coe, and the
Chief Executive, Paul Deighton, and the Chairman of the Olympic
Delivery Authority, John Armitt, and the Chief Executive, David
Higgins. If we could start off with LOCOG: the LOCOG budget was
intended to be fully funded with only a very small public sector
contribution covering the Paralympics. Are you confident still
that you will be able to meet the budget without further recourse
to public funds?
Lord Coe: Chairman,
I think I will ask the Chief Executive to report on our sponsorship
progress.
Mr Deighton: Good morning everybody.
In terms of our budget, yes, you are absolutely right; the financial
model for the Organising Committee is for the expenses and the
revenues to come in together around about the £2 billion
mark. £2 billion continues to be our target for both revenues
and expenditure. On the revenue side, our principal activity in
this early part of our lifecycle is on our domestic sponsorship
programme, which I have updated you on in previous sessions; and
our target for that, as originally set, was between £600-£700
million: with the announcement of our 25th sponsor approximately
two weeks ago, we are virtually at the £600 million mark,
so the bottom end of our original range. Our target for the remaining
just over two and a half years is £100 million and I am confident
that we will be able to come in at the top end of that range,
because we have identified the specific sponsorship categories.
I think the programme has been very, very successful so far; and
I think as we get closer to the Games people's anticipation and
willingness to be associated with the biggest event that is going
on in the country will be very, very strong. We also have approximately
£700 million of procurement to use as an enticement for people
to become sponsors. In other words, one of the conditions for
getting some of those big contracts will be that they also become
sponsors; and that is a very powerful piece of leverage in these
relatively difficult economic times as well. So perversely, even
though the economy is having a relatively hard time, if you are
offering contracts alongside the sponsorship that, strangely,
works to your advantage; because many companies have excess capacity
both in terms of their production capacity and their people, and
so the marginal cost of providing them to us in terms of value
in kind in return for the sponsorship is actually quite a powerful
economic case for them. That is where we are on the principal
revenue exposure. The biggest item of revenue that we have yet
to contract is naturally our ticketing revenue; and of course
we do not begin to sell tickets until 2011, so that is to be expected.
We are confident in the work we are doing on ticketing; that our
target for that sector, which is approximately £375 million
net of VAT, is a realistic target. Again, on the revenue side,
we are in good shape. On the cost side, which of course is the
other half of the equation which we similarly have to keep under
control, there are the three most significant components of expenditure:
what we spend on workforce; what we spend on technology; and what
we spend on venues and infrastructure, which is really the temporary
facilities we put in place and the overlay we add to existing
facilities to turn them into Olympic facilities. We are very focussed
at the moment on driving down the costs in each of those three
areas as we move into our delivery programme.
Q2 Chairman: So there has been no
escalation in projected costs of staging the Games?
Mr Deighton: On both the revenue
and the cost side there are both risks and opportunities, which
we monitor in a very aggressive way to continue to try to bring
them into balance. So there are risks on both sides and opportunities
on both sides. There are things we will absolutely have to manage
as we go through these last two and a half years.
Q3 Chairman: What do you see as the
principal risks?
Mr Deighton: The principal risks
on the revenue side are that we will fail to collect the amount
of money of between £600-£700 million; because that
is a lot of sponsorship money that we will have gathered over
a five-year period, in a period of economic recession; but, as
I say, I think we have targeted the sectors very effectively.
There is always a risk on ticketing revenue because, again, we
are in a difficult period. We have to make sure people want to
come to the Games. We will be selling tickets for sports where
there has never been a ticket sold before, for example handball;
so we have to get our marketing programme right; we have to get
the excitement about the Games right. On the cost side, our challenges
will be around managing our workface, so we can absolutely keep
within our workforce budget; and there is always a need for more
people, so we have a very, very clear discipline on how many people
we hire. On the technology side, we have to deliver quite a complicated
technology system, particularly with respect to how we record
results, how we do timing, for example; and delivering that, together
with the existing Olympic partners, is a significant technology
project. As you know, technology projects always have some risk
of overrun if not managed tightly. On the venues and overlay,
just as the ODA have done in their budget, some of these venue
projects present considerable delivery challenges. Again, project
by project, we have a strict budget and will look to drive it
down; but those I think are the balances of the risks and opportunities.
Q4 Chairman: Thank you. I am sorry,
I should perhaps have asked you, Sebastian, whether you wished
to say a few words at the start. Before I bring in Adrian just
to explore some of the more detailed elements of revenue projections,
perhaps you would like to give us a quick overview.
Lord Coe: Chairman, we did actually
have some opening statements
Q5 Chairman: Which you have now lost!
Lord Coe: which are now
buried! Would it be for the convenience of the Committee to take
you through a quick romp across the landscape?
Q6 Chairman: Yes.
Lord Coe: I was literally going
to thank you, Chairman, for the opportunity to meet with you and
give you a progress update. We are now just 955 days until the
opening of the Games, that is 988 days until the opening of the
Paralympic Games; and our teams at LOCOG, as Paul has quite rightly
said, are keenly aware of the challenges that we face to stage
two of the largest sporting events in the world. If there is anything
I guess I would like the Committee to leave with before Christmas
it is the nature and scale and sheer complexity of this project
management. We open on 27 July in 2012; we stage 26 simultaneous
world championships; we take about two weeks working day and night
to transfigure, transform London from an Olympic into a Paralympic
city and then we do pretty much the same with 20 Paralympic world
championships. Our progress and our momentum have been, to date,
extremely strong. Since winning the bid, as Paul as just said,
we have raised nearly £600 million in private funding; we
have 25 domestic business partners in place; we continue to recruit
a world-class team as the organisation, bid-time, has grown from
70 to, Games-time, just over 2,000. We have informed our preparations
by our learnings from Beijing, and next February from the Vancouver
Games; and we have focussed our operational planning and delivery
in over 50 venues across London and the UK. Millions of people
are now benefiting being inspired by or delivering this project.
You will hear from John in a moment about the progress being madeextraordinary
progress being madein the Olympic Park. As we finalise
our plans, we at LOCOG now move centre stage. 2010 is a critical
year; the decisions we make now will, in large part, shape the
Games that we deliver to this country. We will submit over the
course of the coming year 117 planning applications; we lock-down
our venue operational plans; we will recruit over 400 new staff
to build the capacity of the teams, as Paul has said; we also
go to the marketplace as an Organising Committee with £700
million worth of business opportunities that will resonant within
businesses the length and breadth of the UK. We will continue
our planning for LOCOG's in-venue security responsibilities, while
working in partnership with the Home Office, the Metropolitan
Police and other agencies who lead in London and across the UK
security at Games time. We will also be introducing what I have
always considered to be the face of the Games next year, the volunteer
programme; and a new face in the form of a mascotyes, I
thought that would raise an eyebrow; and we continue to finalise
our ticketing strategy. During this time it is a very simple process
really: we plan; we refine costs; we make savings; we raise the
money; in 2012 we deliver; and then we dissolve. I will hand over
to John to just give you a quick overview of the development in
the Park.
Mr Armitt: As Seb has just indicated,
we have made good progress in the last year in partnership with
Seb and his team. The photographs I think you have got in front
of you give you some sort of images to show the progress that
has been made in the way that the Olympic Park is starting to
take shape. Today in fact we are announcing that the cable net
roof structure for the main stadium is now up and in place; and
that is against backgrounds of some not particularly helpful weather
over recent weeks, but we remain on-track and will next be putting
the lighting towers on top of that cable net structure, so that
will protect the stadium up to its full height in the new year;
and then after that we will put the fabric covering on the structure.
The infrastructure across the Park is continuing to take place:
bridges, utilities, underpasses and so on; landscaping has now
started; power is now on in the substation across the Park. Indeed,
it was particularly pleasing to have Her Majesty the Queen on-site
recently to plant the first of the trees, and that is being followed
up by a number more being planted. In a sense, what we see ourselves
doing with this infrastructure is creating the first phase of
Legacy75p in the pound. I have said it before but I think
it bears repeating, what we are spending is long-term infrastructure
for the benefit of that part of London; and of course we have
now got the Olympic Park Legacy Company established under Margaret
Ford, which is a further step forward in ensuring the long-term
legacy. When we were here last year, last summer, we were still
facing the difficulty of the credit crunch and its impact on the
Olympic Village and the Broadcasting Centre; that was resolved.
It was resolved by using some contingency but also by taking savings
which we have been able to make elsewhere across the other aspects
of the project. We continue of course to put a high level of emphasis
on containing costs, particularly in the current environment;
but I remain confident that we will continue to complete within
our overall budget. Part of what is happening of course is that
we are filling order books up and down the country for suppliers
and many thousands are involved; and, again, part of the benefit
I think of us hosting the Games is that that work and contract
opportunities are happening at this particular time. We have got
companies from Belfast to Bolton, and Perth to Poole, participating
in the project. A lot has been achieved, but we are not complacent;
we have still got a lot to do; a good few challenges yet to come,
I am sure; but I remain confident that we can continue as we have
started and we have got a solid foundation in place.
Q7 Chairman: Thank you. We obviously
wish to explore some of those aspects in more detail. Before I
bring in Adrian Sanders, I cannot resist: how are you going about
choosing the mascot?
Lord Coe: This is understandably
a long and detailed process; it includes various discussions the
length and breadth of the country; it involves our creative teams;
it involves our commercial teams; it involves a good chunk of
our communications team as well; and, as it says on the tin, a
mascot is something that people of all ages, of all backgrounds,
can feel some affiliation with; and of course, as Paul will tell
you, it is a chunk of our revenue as well in terms of our merchandising
proposal. Watch this space!
Q8 Chairman: How much are you spending
on the mascot?
Lord Coe: I think that is all,
at the moment, being scoped-out in terms of what it is we are
actually finally going to deliver to you.
Q9 Chairman: You will presumably
have in the front of your mind the controversy of the choice of
the symbol a few years ago?
Lord Coe: Yes, but I also have
to say that the controversy you talked about has now placed that
symbol not only as one of the most recognisable features of this
Games but one of the most recognisable global symbols as well.
Q10 Mr Sanders: I am intrigued. Is
it going to be animal, vegetable or mineral?
Mr Deighton: I will take that
as a rhetorical question!
Q11 Mr Sanders: Too much detail!
Are you still pursuing sponsorship deals with a supermarket, given
the problems with Coca-Cola and their complaint that such a deal
might damage their own promotional campaigns?
Mr Deighton: This is a very interesting
question. The essence of every sponsorship agreement is that each
company seeks exclusivity within its own category. Our role is
to protect their rights around that exclusivity in that category.
The complexity comes from when you introduce potential retailers,
because of course we have a number of existing sponsors who sell
products and they sell products through different retailers. If
we create a retailing category of course those retailers also
sell the products of competitors to our existing sponsors. What
we have to establish is a transaction which protects our existing
sponsors yet would also allow the retailer to be able to activate
its rights with the Games. We continue to have discussions to
try and make that a possible compromise. Our primary objective
is to make sure that the rights of our existing sponsors are properly
protected, because of course that is what they have paid for.
Q12 Mr Sanders: In this instance,
Coca-Cola is already the sponsor; so the difficulty is negotiating
a supermarket and protecting the interests of the existing sponsor?
Mr Deighton: Correct.
Q13 Mr Sanders: In terms of doing
that is there not a danger that you might lose the sponsorship
of the supermarket; and, if that was so, where would you then
go, because that could be quite a big gap?
Mr Deighton: When I discussed
earlier the risks and opportunities, the chance of doing a deal
in this category is what I would regard as an opportunity; and
therefore we are working very hard to try and come up with a structure
that will work both to protect our existing sponsors and one that
could work effectively for a potential grocery or retail partner.
Q14 Mr Sanders: Every little helps,
as they say?
Mr Deighton: We are very focussed
on that opportunity.
Q15 Chairman: Just whilst we are
on top-line sponsors, they do appear to exert quite a lot of power.
Can you assure us that we will not have a repeat of Beijing where
the only food outlet anywhere in Beijing Olympic Park appeared
to be a McDonald's?
Mr Deighton: I can absolutely
assure you, and this was a primary part of our food strategy which
was only recently released, that there will be a wide range of
food available in the Olympic Park and at our other venues; and
that wide range of food will include many fine examples of British
cuisine.
Q16 Chairman: Are McDonald's comfortable
with that?
Mr Deighton: They are absolutely
comfortable with the concept that the catering experience for
all people who attend the Games should be an outstanding one;
that they are an important part of it but so also is choice.
Q17 Chairman: But it is the case
that the only branded food will be McDonald's?
Mr Deighton: They will be the
only branded restaurant food there, yes, but there will be very
significant unbranded food choice.
Q18 Philip Davies: Before I move
on to ticketing, and following on from Adrian's theme, I want
to explore how many of these tickets will be sold at Asda price.
Back in 2005, Paul, LOCOG submitted to the Committee that of the
9.6 million tickets that would be sold for the Olympics and Paralympics,
4.3 million would be available at £20 or less at 2005
priceswe have got negative inflation at the moment so presumably
they will be even cheaper than that!with 6.2 million priced
at £30 or less, and 7.6 million at £50 or less. However,
not long ago, a couple of months ago, at a conference to confirm
Thomas Cook as a LOCOG sponsor, you said that a pricing strategy
would not be in place until 2010?
Mr Deighton: Yes.
Q19 Philip Davies: Is that an indication
that you are slightly backtracking on what you said in 2005?
Mr Deighton: No, it is not an
indication that we are in any way backtracking. Our plan on ticketing
has always been that we will begin to sell tickets in 2011, and
that we will announce our full ticketing strategy in 2010. We
have always said that and we are precisely en route to do that.
We are absolutely committed in our ticketing strategy with respect
to pricing to making sure that significant numbers of tickets
are available at highly affordable prices. Indeed, if you are
trying to sell 9.2 million tickets to such a range of sports,
a number of which are not that well known in the UK, the only
way we are going to get full stadia, full of enthusiastic fans,
is to make them highly affordable, and that is our objective.
It is our objective; it is certainly the objective of the Olympics
Minister; it is certainly the objective of the Mayor of London;
and those stakeholders are actually defining our final pricing
strategy over the months ahead. The only reason it is difficult
at this point to talk in such specific terms, as we have with
our bid promise, is that of course back then the Games actually
had a different portfolio of sports: we had baseball and softball,
where you would have had 700,000 tickets at the very low end of
the pricing. We just want to make sure we have got a very precise
grip of the supply side of the tickets. What we have been working
on is our competition schedule, so we know exactly what sport
is going to be when; what is in the morning; what is in the afternoon;
how many sessions we have. Just last week the IOC confirmed for
example the format of the cycling competitionswhere they
redistributed some events towards the sprints and equalising events
between men and women. You have to know what events you are putting
on before you know what tickets you have got to sell. We are also
looking very specifically at the seating bowl, so again I know
how many seats I have to sell. We are working with the broadcasters,
for example, on camera positions. If you have lots of camera positions
you have fewer seats left to sell. All that work, on the schedule,
the seats, is what you need to know for how many you have got;
and then on the demand side, we are building up a sport-by-sport
plan for who the fans are, and who is going to come and watch
these sports. It is a very different proposition to get somebody
to come to the final of the 100 metres in the main stadium, compared
to someone to come, as I mentioned earlier, to the preliminary
rounds of the handball competition where handball has not been
regularly played in the United Kingdom. We need a sport-by-sport
analysis of where that demand is. When you have got that supply
and you have got that demand we will then be in a position to
very precisely define the pricing we think we need to fill those
stadia and to meet our commitment to provide a very significant
number of highly affordable seats within that 9.2 million tickets.
Q20 Philip Davies: Republic of Ireland
football fans might disagree with your fact that people have never
paid for tickets to watch handball in the past! I am still puzzled
really by your answer, because all of those issues that you went
through, and complications, they were all issues and complications
back in 2005; but back in 2005 there was a clear commitment that
4.3 million tickets would be available at £20 or less, 6.2
million priced at £30 or less. That seems to me like a very
descriptive ticket pricing strategy, as far as I can see. I do
not think anyone could really ask for much more than that in terms
of a pricing strategy. I still get the impression from what you
have just been saying that you are actually backtracking on those
figures. Just for the avoidance of any doubt, will you reiterate
today that 4.3 million tickets will be available at £20 or
less?
Mr Deighton: I will reiterate
today that when we take you through our pricing strategy next
year we will be able to demonstrate to you that we have fully
met our commitment to making these tickets highly affordable.
Q21 Philip Davies: So that is, no;
you are not going to make that commitment?
Mr Deighton: No, it is not. We
are not comparing like with like, because we have different tickets
available. We have got dollars; we have got constant prices; there
are current prices; the ticket will include a free travel pass
in London; so when you put all those things together I think we
need to have a proper understanding of what you are getting for
the ticket. This team, together with our stakeholders, are absolutely
prepared to stand by the commitment that when you see those prices
you will say, "These people have lived up to the commitment
of making sure they are affordable". At this point, two and
a half years out, we really do not want to get more specific about
pricing. You would not set prices with that degree of specificity
with the changes in the economy, this wide range of sports, this
far outit would be a mistake.
Q22 Philip Davies: You set them seven
years out, so why would you not set them two and a half years
out?
Mr Deighton: Because we want to
get this absolutely right.
Q23 Philip Davies: How are you going
to enforce the law preventing ticket touts at the Olympics?
Mr Deighton: I think the first
thing is in the next one and a half years or so anybody presenting
themselves as selling new tickets we want to make quite clear
to the general public that cannot be possible, because tickets
only go on sale in 2011. Any attempt by anybodyand this
is something I think we would like the Committee's help onif
you are hearing about this in your constituencies where they think
they are being offered tickets, let us know; we are trying to
be as public as possible saying, "Anything that happens pre-2011
before our formal ticket launch can't be possible". Anyone
trying to do that is effectively trying to take advantage of the
public. I think that is the first thing. Secondly, of course,
with Olympic tickets, like Premier League tickets, the law is
very, very clear; they cannot be resold at a profit. We will be
working with the police to follow up on any instances where we
think that is happening; whether it is tracking it down on the
internet, or whether it is happening in practice. I think the
other thing that is really important, as I suggested earlier,
we are very keen in our business plan for ticketing to make sure
that we get those tickets initially into the hands of the people
who most want them, so the opportunity to create this kind of
secondary market is as limited as possible. That is why we are
really building a very carefully constructed book for each sport,
so once those guys have got that ticket it is not going to come
back onto the market. If they do want to resell the ticket, we
have a plan to develop a London 2012 ticket exchange so they will
be able to resell it through us, so they will have no excuse.
For whatever reason they cannot go, we will be able to resell
it for them; not at a profit but we will be able to take care
of their original purchase price. That again is a small facility
which should constrain the supply of potential tickets that could
represent a touting risk if not controlled.
Q24 Philip Davies: So everyone would
be able to get a refund if they could not go?
Mr Deighton: If we can resell
it.
Q25 Philip Davies: What if you cannot
resell it?
Mr Deighton: Then we will not
buy it off them; but if we cannot resell it I cannot imagine someone
else is going to pay ten times as much for it. So that should
not leave us with a touting risk.
Q26 Philip Davies: The ban will undoubtedly
stop people like ebay selling them and that kind of thing. I am
not entirely sure what you are going to have in place to stop
some spiv in a raincoat around the corner from selling them on.
Is there going to be any technology used to try and prevent ticket
touting, or are you going to be expecting a police officer stood
on every corner around London?
Lord Coe: Raincoat protection!
Mr Deighton: There is obviously
the risk that that kind of activity could certainly happen, just
as it does with the Premiership football tickets; which is why
we are focussed on getting these tickets in the hands of people
who are not going to resell them; providing liquidity for those
who do; and we will work with the police to determine how active
they can be about preventing that kind of activity.
Q27 Philip Davies: Seb, have you
found the medals that I read you had lost?
Lord Coe: It does seem to have
raised a few eyebrows, but I genuinely am now busy tracking them
down, with any number of promptings from Sunday newspapers!
Q28 Philip Davies: You have mentioned
about volunteering in your opening piece. I just wanted to ask
where you are in ensuring that every part of the country gets
the opportunity to get a fair lick of the sauce bottle in terms
of sending volunteers down to participate in the Olympics?
Lord Coe: We are pretty advanced
actually in that area. As I said, we launch our recruitment programme
next year. You are quite right it is a key principle; that volunteering
is something that we looked at very, very strongly actually. Even
as far back as the bidding process we recognised this was a huge
opportunity to engage people the length and breadth of the country
in that. We have a volunteering team based at LOCOG headed up
by our Director of HR, Jean Tomlin, who again has worked extremely
closely not just with our LOCOG needs but also across some of
the other groups that we need to work closely with for our volunteer
programmes obviously within London and our venues around the UK
as well. That is ongoing work.
Q29 Philip Davies: Will there be
any provision for paying people's expenses to go down to London
to volunteer?
Lord Coe: No, we cannot. As an
Organising Committeeand no organising committee has ever
done that in the pastwe are not in a position to pay people
to volunteer; nor are we in a position to contribute expenses
to housing. What we do think will take place, and we are looking
at this in terms of a sort of home-stay approach, is that actually
the experience of volunteering in cities is that people go to
cities and link up with friends, sleep in houses, even on floors,
to do this. We will provide proper facilities for them during
the dayregular food, shelter and all the other things you
would expect us to providebut we cannot be responsible
for dealing with them outside of their volunteering hours.
Q30 Philip Davies: So if you do not
know anyone in London, poorer people need not apply, is that the
case?
Lord Coe: No, that is not true.
The very nature of volunteeringchoosing my words carefully
herethey do tend to be slightly more enterprising people;
and I have little doubt at all that if you want to volunteer and
you are based in Sheffield, and you are really keen to do that,
this will happen; this will work.
Q31 Mr Sanders: Is there not an opportunity
here for a sponsor, perhaps a transport company, coach, train,
A N Other, to actually help with tickets for volunteers to get
them to and from London? Has that been explored?
Lord Coe: Paul talked about the
ticketing strategy a few moments ago; the price of a ticket is
one important aspect; actually the ability to get to that city;
to find the right kind of accommodation; that is why we are delighted
that we have got an organisation like Thomas Cook on board; so
we will be looking at opportunities, as you have said, Super Savers,
all those sorts of things, to make sure that we can get our volunteers
to London in the most cost-effective way.
Mr Deighton: Of course there are
some venues around the country. The football tournament in particular,
as you know, is distributed around the country so there will be
some local opportunities there, and down in Dorset for the sailing
of course. The volunteer opportunity is not solely restricted
to London.
Q32 Adam Price: Moving on to broadcasting
and particularly the Paralympics, one of the very positive developments
in recent years has been a rise in public interest in Paralympic
sport. I am sure one of the shared objectives is to use the Olympic
Games to leverage that even further. Philip Lane, the Chief Executive
of the British Paralympic Association, has laid his cards very
clearly on the table that he wants to see the Paralympic Games
available free-to-air, the same way the Olympic Games will be.
What is your view on that?
Mr Deighton: Yes, indeed. We talk
to Phil Lane of the BPA, a great partner of ours, and we hope
they deliver as many medals in London as they did in Beijing;
that would be very helpful for us, particularly for our TV viewing
figures. We are currently conducting a tender to sell the Paralympic
broadcast rights, as I think you know. The criteria we will use
for selecting the winner are really twofold: firstly, it is all
about the amount of coverage; and the quality of that coverage.
I think your observation was spot on: there has been significant
emerging interest in the Paralympics. This is a great opportunity
because it is coming homeStoke Mandeville having been the
origins of the Paralympics. We have a brilliant team; and really
now is the chance to take it to another level in terms of generating
broader interest, and TV is key to doing that; both the breadth
of the coveragehow much of the Games we can getand
how good the coverage is. You need to get people interested in
the Paralympicsboth the sport itself and the stories behind
some of the competitorsand that is what will make people
watch. We are also seeking commitments from broadcasters to do
a lot of work leading up to 2012not just at Games timeto
create that opportunity. I am absolutely confident that we will
have a level of coverage of the Paralympic Games which is quite
unprecedented in its range and quality. I am happy to tell you
that. The second componentthere is a value component, of
course there istraditionally with the Paralympic Games
the cost of the broadcast production is not covered by the revenue
that anybody is prepared to pay for it; so it is a net cost to
the Organising Committee. Of course that impacts your point of
view on the range of coverage. If the revenue is not covering
the costs it impacts your view on the amount of investment you
are prepared to make in that coverage. Of course our job is to
protect the taxpayers' purse by raising as much money through
the LOCOG organisation as we canbalancing everything else
we have to balance. I do not think money is the primary objective
here but it is always an important consideration. Those are the
things we are balancing. I think we are in a position to do a
really, really good transaction which will provide exactly the
kind of boost and coverage to the Paralympic Games which you would
like, which I would like, and which Phil Lane of the BPA would
like too.
Q33 Adam Price: What are you saying,
that the overriding objective has to be to maximise the audience
figures et cetera? If Sky, for example, produces a better proposal
in terms of creating excitement and viewer interest then that
will score heavily?
Mr Deighton: Making the Games
a spectacular success; generating as much interest as possible;
building that audience for the long-term; giving their athletes
and their sport as much exposure as possible is absolutely our
objective.
Lord Coe: I think also it was
absolutely central to our vision that there were a number of legacies
we really wanted to drive towards; clearly improvements in the
levels of sporting participation; but in the Paralympics, not
just an improvement in the level of Paralympic participation but
actually using the Games to change public attitudes towards disability.
Paul is quite right to say that the amalgam of issues for me weighs
very heavily on the ability to actually not just create great
coverage around the Games, but the kind of creativity that enshrines
the original concept of the vision as early as possible. I think
that is not just the BPA, but that is also something that is really
sacrosanct for the International Paralympic Committee based in
Bonn.
Q34 Adam Price: To what extent do
you think that having the Paralympics there as part of the core
really of the Games helps you to get another wider message across,
which is that sport is for all?
Lord Coe: I think it is absolutely
central. We have just appointed Chris Holmes, the champion Paralympic
swimmer, as Director of Paralympic Integration. We are the first
host city to have the Olympic Games and the Paralympic Games legally
enshrined. We are fully integrated. I chair the Organising Committee
for the Olympic and Paralympic Games; Paul is the Chief Executive
of that organisation. We see no difference at all in the way we
go about our daily business in bringing both of those to the table.
For us, this is just the way we do it. We would be open about
this tooif you look at some of our business partners that
we have brought to the table, those business partners, particularly
organisations like British Telecom, are actually activating much
of their sponsorship in the Paralympic platform; so for us this
has been the right thing to do. Organisationally it makes much
more sense; and actually commercially there are some big advantages
in this too.
Q35 Adam Price: Could we move on
to the venues and the ODA. You mentioned the progress that you
have madethe substation was the first building to be completed.
As you complete more and more venues, who will fund their maintenance
through to 2012?
Mr Armitt: The ongoing maintenance
and basically looking after any of the venues and the Park is
something we have always recognised is part of the activities
which we have to undertake. Between ourselves and LOCOG we have
sufficient money within our budgets to cover that. At the moment
we are just finalising with them the details of precisely who
looks after what in the run-up to the Games. As I have said, it
is an issue which we have always recognised as something which
will be there because we always planned to actually complete venues
well in advance, in order that LOCOG would have the opportunity
to run trial events.
Q36 Adam Price: So those discussions
are still ongoing?
Mr Armitt: Yes, they are not difficult
ones; it is just a matter of refining the detail.
Q37 Adam Price: You are not having
a fight over it?
Mr Armitt: No.
Q38 Adam Price: If we go to the other
end of the calendar, at what stage will the Park be handed over
to the Olympic Park Legacy Company?
Mr Armitt: Again, that is something
which we have to finalise with the Legacy Company; but it is likely
to be 2013. The ODA itself is expected to cease by 2014 so, again,
it is just a matter of refining the time which suits them as the
Legacy Company, when they have got the resources and organisation,
to pick things up. There are alterations to be made; transitioning
the Park as it is for the Games time; transitioning it towards
something which is ready for the Legacy Company to take over;
and, as I say, that will take us a year or so post-Games to complete.
Q39 Adam Price: With land value still
falling, they have got a debt to repay. It is a bit of a hospital
pass to be Chair of the OPLC, is it not?
Mr Armitt: It is four years away.
I think we all are (and need to be) optimistic about the economy;
and therefore one would hope that by then land values would certainly
be picking up.
Q40 Adam Price: I admire your optimism.
When will the public have free access to the Park so they can
enjoy the investment they have put in?
Mr Armitt: Again, that will be
post the Games and it will depend on particular locations, particular
venues, and the degree of alteration which we have to make to
them in order to prepare them for public use. The velodrome probably
will be one of the earlier ones, because we do not have significant
changes to make; whereas on the aquatics there are more significant
changes to make it ready for legacy use.
Q41 Adam Price: You mentioned, and
Seb mentioned as well, the opportunities that will still be there
next year for companies the length and the breadth of the UK.
I saw the latest figuresand it was a question by Pete Wishart,
my SNP colleaguewith a breakdown of the direct suppliers
by nation that you have engaged on construction, and there were
a whole range of contracts. Up until the end of October this year,
of the 1,063 businesses then that had won contracts only four
came from Wales. It is a pretty poor showing, is it not?
Mr Armitt: That is four of the
main contracts which the ODA have letand I could probably
recite which four they areand I know they are all quite
substantial contracts. Equally, you will find that where we have,
for example, placed a contract with somebody in Manchester, they
in turn will let subcontracts to people in Wales. All you are
seeing is the tip of the iceberg really with the ODA direct contractsabout
1,100 compared with the tens of thousands literally which would
sit below those prime contracts which we let. There is no doubt
that different parts of the country have taken different levels
of business interest. The key thing is that the opportunities
are open in the way that they should be for public contracts let
by ourselves. At the end of the day you deal with the people who
come forward; the people who put forward competitive prices.
Q42 Adam Price: Will it be possible
for you to do some kind of supply chain analysis. If what you
are saying is right maybe there are companies lower down, so we
can get a sense of whether we have had value for our £100
million of Lottery money we have lost in Wales?
Mr Armitt: We have done an analysis,
particularly for the main stadium. These analyses are quite difficult.
You are relying on information coming through from several tiers
of subcontracts; and it is quite a costly business to just keep
pursuing different companies and saying, "To whom have you
let contracts?" In the case of the McAlpine Team Stadium
contract for the main stadium, there are more than 100 sub-contracts
flowing from that which are across the country. We published a
map a few weeks ago of contracts around the UK which showed several
thousand; but it is not our plan to try and do a detailed analysis
of the whole of the development of the Park to identify whether
Yorkshire had had more than Wales or whatever.
Q43 Adam Price: Of the contracts
that you are yet to offer in the next year, will they become smaller,
do you think? Will there be more opportunities for smaller companies,
because presumably you have let the major construction tenders?
Will there be other opportunities for servicing companies?
Mr Armitt: Yes, they are more
likely to flow through LOCOG. We are getting towards the back-end
of our contracts now. The next phase of procurement is essentially
a LOCOG one.
Lord Coe: We are going to market
with about £700 million worth of business next year.[1]
In reality that is about 75,000 business opportunities. We have
just appointed a Head of Procurement, so this is a big part of
what we do over year 2010.
Q44 Paul Farrelly: I always seem
to get landed with the boring figures sectionor land myself
with it! Beforehand, just following up on Adam's points, one of
the issues that I raised with all of you in regular meetings as
we have gone on was the importance to local areas, that actually
it is a Games of nations but which is felt on the ground. I think
it was LOCOG who said there was a contract that was given out
for an initial 1,000 mugs for LOCOG to use and it was given to
a company that actually imported them from China.
Mr Deighton: No, that was not
true.
Q45 Paul Farrelly: Could I follow
up separately from this sessionwith your £700 million
worth of business you are going to placehow are you looking
at the ceramics industry in particular in Britain and helping
it make the most of the Olympics?
Mr Deighton: Actually it will
not simply be in the £700 million procurement; I think the
ceramics industry will also have an opportunity to participate
in our licensing programme. If you look at the precedents within
our licensing programme you will find that we have been really
focussed on using the best of British, so the licensees we have
signed upfor example, for our diary and personal organiser,
some are giving out diaries with "2012" on them, we
are using Letts which is in Scotland; that is the kind of licensing
deal we are doing. In ceramics I am sure that we will come up
with licensing arrangements which allow us to present the best
of the British ceramics, because that is what people want to buy
when they come to the UK to celebrate 2012
Q46 Paul Farrelly: Indeed, but not
just for the commemorative opportunities, but your own opportunities.
I think I have said before, I was really pleased to see in Vancouver
and at Google in Seattle that the companies there value the quality
of British products so much that if you turned the cups over they
were made by Steelite or Dudson; it happens in the House of Commons;
it happens on Virgin trains when I travel back up from London
to Stoke-on-Trent. I would hope that every time that someone turns
a cup or a plate over at the 2012 Olympics it is going to be made
in Britain, made in Staffordshire. Can you give us that promise?
Mr Deighton: We will take you
through how we are procuring everything that will have an impact
on Staffordshire ceramics. I do not have all that information
in my head.
Q47 Paul Farrelly: Fantastic. I will
take you up on it. Before numbers, I do not think any discussion
of Legacy is going to be complete without you being able to say
where you are on the future use of the stadium?
Mr Higgins: Clearly the stadium
now is the responsibility of the Legacy Company.
Q48 Paul Farrelly: I thought you
might say that.
Mr Higgins: We did have it until
the end of 2007 but, given that we do not own the land, we were
unable to sign a 20-year lease with any club or any organisation
because it is not ours to give. We have a short-term lease that
runs out in 2013. What we did design, the white structure you
see there, is very flexible. That can have a roofing structure
there for 20,000, 30,000, 50,000 or 80,000 seats and I think it
is inevitable it should remain there; and therefore it gives a
capacity that in 50 years' time if they want to bid for the Olympics
again, once again they can reconstruct an 80,000 seat stadium
and rebuild it again. The great thing about that is that it is
very flexible. The seating is the same: we can take it back to
what it was planning approved for, which is back to athletics,
a 25,000 or 30,000 seat bowl in the ground, or you can have flexibility
as multipurpose sports. The biggest thing we did was to leave
that and the 700 rooms that are underneath built into the stadium
with sufficient flexibility for the Legacy Company then to determine
the use. They are working on it; and we have done further studies
over the last few months for them, so there is no point in me
giving my personal opinionsthey are worthlessit
is really up to the Legacy Company and their Board to make a decision.
Q49 Paul Farrelly: Prior to the incorporation
of the Legacy Company, who was conducting negotiations with football
clubs, with the Saracens Rugby Club?
Mr Higgins: We were; that was
us. That was in 2006 and 2007. It was a lot more interesting than
what we are doing now.
Q50 Paul Farrelly: Who was conducting
negotiations between 2007 and May 2009?
Mr Higgins: The ODA took over
in January 2008, and now the Legacy Companywhich is a joint
venture between the Department of Communities, local government
and the Mayorhas been established in the last few months;
so a combination of the ODA and now the Legacy Company.
Q51 Paul Farrelly: Are the people
who are conducting these negotiations the same, or have they all
changed?
Mr Higgins: Some of them are similar.
Q52 Paul Farrelly: Some of them are
similar?
Mr Higgins: But there is of course
a new Chair in Margaret Ford and a new Chief Executive in Andy
Altman.
Q53 Paul Farrelly: What legacy is
handed over from one set of negotiations by one body to another
body?
Mr Higgins: We can assure you
there are files everywhere, stacks of files, and stacks of consultants'
reports. The main thing is, the Legacy Company commissioned the
ODA to re-look at the design in the last six months and come back
to convince them that there is the flexibility built in the stadium
to be able to handle multiple sports, which we have done.
Q54 Paul Farrelly: Do you know where
we are on Legacy?
Mr Higgins: No, we finished that
report a couple of months back. They are only having their first
Board meeting this week, so they have just been established. It
is not going to be on the first meeting, I am sure; but soon after
I am sure they are going to be coming back with a recommendation.
Paul Farrelly: Chairman, are we seeing
the Legacy Company?
Chairman: Yes, we are.
Q55 Paul Farrelly: Just on figures,
the main stadium, how does the final anticipated cost compare
with the original baseline budget?
Mr Higgins: In our November 2009
report, our quarterly report, we say the forecast is around the
same; it is 537, so we do not see that changing.
Q56 Paul Farrelly: The aquatics value?
Mr Higgins: Again, the aquatic
centre comes in at 245; and again, since July that has only changed
a million, so we do not see major changes on that.
Q57 Paul Farrelly: That is with the
roof back in?
Mr Higgins: The roof has always
been on there. Of course, that is with the temporary roof taken
away.
Q58 Paul Farrelly: On the final budget,
am I right in sayingand I am sorry to go back over old
ground but we keep refreshing the numberswithin the original
8,099 maximum available budget there were no anticipated receipts
from the Olympic Village in that original figure?
Mr Higgins: That is right. The
Olympic Village is going to be privately financed, as was the
Media Centre. The Media Centre was going to be partially privately
financed.
Q59 Paul Farrelly: There were no
anticipated receipts from the Village in that baseline figure?
Mr Higgins: That is correct.
Q60 Paul Farrelly: To just compare
like with like, we should be ignoring the 324 million?
Mr Higgins: The 324 million of
course is a net figure, because clearly you can see the Village
construction on that figure there, the 664, from which then the
324 is taken away from that to give a net cost for the Village.
There are a number of receipts coming in because part of the Village
deal is the pre-sale of the affordable housing to Triathlon Homes,
which is money that is coming in to help fund the Village. The
total cost of the Village is clearly above 664 million.
Q61 Paul Farrelly: I am concentrating
on the 324; you say that is a net figure?
Mr Higgins: That is a net figure;
that is right.
Q62 Paul Farrelly: Net of, what?
Mr Higgins: It is a figure from
private sector sales, and it is private sector sales that we have
built into this budget that we expect to be able to return to
our funders. There will be some other sales revenue we will expect
to come in to help finance the fit-out.
Q63 Paul Farrelly: That is a gross
figure from private sector sales?
Mr Higgins: There is a gross figure
that is higher than the 324. The 324 is a net figure we expect
to be able to return to funders from the sales.
Q64 Paul Farrelly: In terms of just
assessing the figures like-for-like, 324 is not in the original
baseline decision?
Mr Higgins: Correct, and neither
was the 664 in there either.
Q65 Paul Farrelly: No, but the contingency
was, which you are using?
Mr Higgins: Correct.
Q66 Paul Farrelly: Which you are
using. If we include the £324 million, we are then adding
on an extra amount of contingency as a quid pro quo for using
contingency, if you see what I mean.
Mr Higgins: Some of the contingency
is drawn down to fund the village, because you draw down £664
million and then credit £324 million.
Q67 Paul Farrelly: I understand that,
but the contingency we are using was in there.
Mr Higgins: That is right.
Q68 Paul Farrelly: I am not misunderstanding
that.
Mr Higgins: No, that is right.
Q69 Paul Farrelly: John, you are
nodding.
Mr Higgins: The original budget
of £8 billion and £99 million included two pots of contingency:
one of funders around £1 billion; one of programme around
£1 billion. Money was drawn from both those pots of £1
billion to cover the cost of the Village.
Q70 Paul Farrelly: In the table that
is in my briefing notes that has been very helpfully provided,
we have a figure of £683 million for assessed programme risks.
What is that?
Mr Higgins: That is on the third
line from the bottom. Programme risks are risks outside the direct
project risks, so they cover issues from cost inflation or industrial
disputes or co-ordination costs or planning risks that may come
through. They are the remaining risks in the project to complete
the project.
Q71 Paul Farrelly: Costed risks.
Mr Higgins: They are estimates.
Q72 Paul Farrelly: They are estimates.
Mr Higgins: They are estimates.
Q73 Paul Farrelly: That is an estimate
like in future use of contingencies.
Mr Higgins: Yes.
Q74 Paul Farrelly: To completion.
Mr Higgins: Correct.
Q75 Paul Farrelly: With no particular
timing when they fall.
Mr Higgins: That is right.
Q76 Paul Farrelly: How much of the
original contingency of £1.972 million is still not allocated?
By my calculations, I make it £534 million. Is that correct?
Mr Higgins: Certainly in the funders
that sounds the right figure.
Q77 Paul Farrelly: That takes you
to £683 million. Then £53 million for net future cost
pressures and what has already been allocated, so there is £534
million left.
Mr Higgins: I think that is the
figure, of remaining funders contingency that has not been allocated.
Mr Armitt: I would simply draw
a distinction between allocated and released. In terms of budget,
contingency which has not been released, then it is still £1.2
billion.
Q78 Paul Farrelly: I am just trying
to get a picture of your anticipated headroom towards the end,
before the mechanical and electrical engineers go awry.
Mr Armitt: Yes, the emphasis on
those M&E risks will be in the £643 million.
Mr Higgins: Our best estimate,
which is the forecast to complete, is the £7,241 million,
which is a forecast at the end of the project, after receipts
have come in from all quarters.
Q79 Paul Farrelly: If you wanted
like for like, it would be £7,241 million add £324 million,
presumably, because you would have taken out what was not there
before. It would be £7,565 million.
Mr Armitt: Before the £324
million receipts, that is correct.
Mr Higgins: Yes.
Q80 Paul Farrelly: How much are you
anticipating that CLM is going to be paid by the time we have
finished the project?
Mr Higgins: We have not put in
our details, our forecast. It was released in the annual report.
I think the figure was £140 million that has been paid to
CLM in the last period. I do not have the exact figure, but we
could certainly come back to you on those.
Q81 Paul Farrelly: Yes, it would
be interesting to see what your anticipated payments to CLM are
by the end of the project, how they are compared with what you
forecast at the beginning.
Mr Higgins: We let the work orders
with CLM in stages. We are just in the final stages of negotiating
one of the last tranches of that work order. CLM would bid competitively.
They were chosen on value and expertise, but they also coincidentally
happen to be the cheaper of the various international consortiums
that came in and bid for that. That original tender process set
their profit margins. As we set each work order, we then have
it externally validated by external auditors and consultants.
All of our payments to CLM are signed off by the National Audit
Office.
Q82 Paul Farrelly: A final figure
against what you anticipated in the future, and if there is any
difference, whether that is going to add contingency, what
Mr Higgins: A reasonably substantial
part of their final payment will be dependent on performancefinal
performance on cost in particular.
Q83 Paul Farrelly: We have discussed
with CLM whether they are getting bonuses on like for like costs
or whether get a bonus by reducing the costs because you take
a big item out.
Mr Higgins: If we have taken substantial
scope outthere were some savings on inflation, for example,
which then, taken away, reduced their available headroom. There
are adjustments for scope within the contract.
Paul Farrelly: If you could let us have
some figures that would be helpful.
Q84 Chairman: You will be aware of
the comments of the Mayor of Newham that the borough has not seen
great benefit in terms of the skills and jobs, and that although
21% of the workforce (the figure you quote) come from the five
boroughs, a lot of these are transient workers. How do you respond
to that?
Mr Armitt: I have some difficulty
with it. As you say, 21% of the workforcewhich is a higher
percentage than we expectedare coming from the boroughs.
Newham has a substantial proportion of that. We have put several
hundred people already through training courses. Nearly all of
them were local people, people who were previously unemployed.
We have established a new construction training school, not just
for the Games but for the longer term in Newham. If you look not
only on what is happening on the Olympic Park but the Westfield
development, which is clearly going to create thousands of jobs
in the longer term within the shopping centre there, and we have
worked very closely with the various Newham organisations whose
job it is to help people into work. As I say, we have exceeded
the expectations, so I would have to disagree with the Mayor's
interpretation that Newham had been particularly ill served, as
it were. I think they have been well served.
Q85 Chairman: Have you done any research
into the extent to which the workforce from the host boroughs
are genuine long-term residents or temporary residents?
Mr Armitt: We rely on the permanent
address which they give in the same way as any other public sector
body determines where people are living. The more important thing
is that people are living there, and therefore the income which
they receive is being spent locally, so that local businesses
and so on are benefiting from their expenditure for the period
which they are there. That, in a way, is the important point and
the jobs are open to anybody who is legally entitled to seek a
job on the Olympic Park. As I say, we are pleased with the proportion
and the diversity of the people who have come forward. The diversity
statistics also demonstrate that they are very much in line with
the general diversity of the local boroughs.
Mr Higgins: The other point we
would make is that 631 of the jobs on the site have come through
the job brokerage programme. The people that are put forward are
put forward by the local borough, so Newham have selected these
people from their community and put them forward and said, "We
want you to offer these priority jobs to these people." It
is up to Newham to decide whether they think they are permanent,
short term, or whatever in terms of their residency status.
Lord Coe: From a LOCOG point of
view, we have an education programme within the organisation called
Get Set. We have 70 schools in the borough of Newham at the moment
taking part in that. We have 14 pre-Games training camps in the
borough as well. Of course Newham is the focus for the extraordinary
venue legacy that London will be left with and all the skills
potential for the future management of that as well. This is a
very good story.
Chairman: The Committee is considering
having a public meeting in the borough, so we will hear whether
that is confirmed by local residents.
Q86 Paul Farrelly: Do you have similar
statistics for all the boroughs?
Lord Coe: Yes, we do.
Q87 Paul Farrelly: Including Hackney.
Could you let us have them?
Lord Coe: I am very happy to do
that, yes.
Q88 Alan Keen: Paul has talked about
the Village, but what about the press and broadcasting centre?
What forecasts do you have for that?
Mr Higgins: With the press and
media centre, there are two main buildings there, one being in
media, which is essentially an office building, and then there
are the broadcast facilities, which is a large two-storey structure.
Originally the plan was to get around £160 million worth
of private investment into that project, but, as we approached
the end of 2008, the Government and the ODA board took the decision
that we were just chasing the market down and that it made no
sense, that it was much better to focus on building a fit-for-purpose
facility for the Games, making sure that structurally the building
had enough investment in it that was flexible enough for legacy.
That is what has been built now. The building has been built on
land owned by the LDA, which we expect to be transferred to the
Legacy Company. The building will be transferred to the Legacy
Company without any debt and with a 1,500 car park next to it.
I would have thought that with a car park, next to the A12, with
those sorts of facilities and without any debt, it should be attractive.
We have had a number of potential tenant users who have approached
the ODA, but once again, like the stadium, we are unable to sign
long-term leases. We have passed those leads onto the Legacy Company
and I know they will continue. There is also the chance to take
the advantage of the substantial fit out that LOCOG and the Olympic
broadcaster and BT will put into both those buildings.
Q89 Alan Keen: It sounds optimistic.
Are you optimistic?
Mr Higgins: I would have thought
there are not going to be many buildings of that size and scale
built in London, East London, in the next few years. Also, if
you look at occupation, this is a building which will be occupied
end of 2013/early 2014. You are not going to get someone to commit
to that today, but you start doing the work now, particularly
if are going to leverage that investment by LOCOG and BT.
Q90 Alan Keen: I am sorry, I missed
Desert Island Discs, and this is more of a question that you could
have been asked there, but if you had recorded a graph of happiness,
I am sure it would have been ten when we won the bidand
we were dancing in the tearoom here at lunchtime
Lord Coe: I thought we did that
all the time!
Q91 Alan Keen: We will be tomorrow
especially! Then it is going to be on ten at the beginning of
the Games itself and all the way throughmaybe even 11.
Have you had any downs, when you were down to two or three or
even zero during these first few years?
Lord Coe: What has been comforting
for me in this whole process is that we have escaped in large
part the famous curve of unhappiness that a lot of cities go through.
As you would remember, we did come off a peak quite quickly because
of the awful events in London the following day.
Q92 Alan Keen: Yes.
Lord Coe: But there are a number
of things that have been significantly different. First of all,
we have maintained extraordinarily high approval figures. Some
of those approval figures are at their highest the further you
get from London. That may beg other questions, about some of the
creativity that we are seeing in communities which know London
is not in their backyard, and therefore they really do have to
make these Games relevant. Some of the highest approval figures
we get consistently are from Northern Ireland. There is something
else that is fundamentally different as well. Usually at the time
when people are really beginning to question all sorts of things
about the Games you are about to go into the proceeding Games,
and often, on top of that, you get people saying, "We don't
have any medals to show for it, so why are we doing all this in
four years' time." Of course, we did. We came out of Beijing
with an extraordinary medal haul, both Olympic and Paralympic,
and it got people on to a very positive agenda. Most people I
spoke to immediately after Beijing just could not wait for this
all to take place in our own backyard, with all the potential
and legacy benefits that we have talked about. That is in large
part due to the quality of our communication teams as well. We
view communication not just as something you do during the bidding
process but as part of the daily DNA. You have to go on explaining
with transparency what you are doing and why you are doing it
and when you are doing itand, yes, sometimes where the
disruptions are going to occurand I think we have done
that well. It is also in large part due to the fact that we do
not genuinely view this as simply a London Games. I spend and
Paul spendsas do David and Johna lot of our working
month out of London, explaining what it is we are doing and visiting
projects that I know would not be taking place had we come back
empty-handed. We have done very well in that. We have three years
to go. We are, by nature, slow-burn people, I do not think we
get there quickly, but I recognise in communities now that there
is a greater understanding than there has ever been that there
is something in this for everybody.
Q93 Alan Keen: I was present when
the Speaker helped in handing over the torch for the Commonwealth
Games to India. Over 25% of my constituents originated in the
Punjab, so I was thrilled to hear that they are going to take
the torch around all the villages and then put funding for sport
into the villagesvillages which probably have nothing at
the moment as far as sport is concerned. What are we doing around
the regions? Apart from your visiting them and obviously thrilling
them when you go there, what else are we doing practically?
Lord Coe: We are using our programmes
in a very smart way. I talked a moment ago about our domestic
education programme, Get Set. That now has 10,000 schools in the
UK signed up. That is millions of students now involved in our
education programme, where they learn about the Olympic and Paralympic
values and make them relevant in their own schools and colleges.
We have what we call our Inspire brand. We are the first host
city to recognise that we want to be able to inspire organisations,
particularly in the non profit-making sector, to be able to tap
into that. As a very good example of that, I went to Northern
Ireland not long ago and witnessed an extraordinary programme
called the Pied Piper, driven by a messianic figure Brian Irvine.
He brought five schools from across the sectarian divide together
to create what in essence was an Olympic Opera. When they had
their public demonstration of this, it virtually brought Belfast
to a standstill He was able to use the Inspire brand in order
to bring sponsors that were not in conflict with the sponsors
and partnerships that we bring to the table. He got the Ulster
Orchestra, local support, political backing. These are the things
we are now beginning to witness. John quite rightly talked about
the impact, in a very difficult economy, of some of these contracts
that we will be letting next year and John is currently letting.
We have 600 or so pre-Games training camps, we have a budget to
support National Olympic and Paralympic Committees coming to use
those pre-Games training camps in all our regions. That is important,
because that is not just about driving some local revenue; it
is also about bringing world-class competitors into venues where
our local young people can be inspired to watch top judo players,
top swimmers. Paul witnessed the Australian swimming team up in
Manchester the other day. They were preparing for the World Championships
in Rome but at the same time coaching youngsters in swimming.
This is a very, very good story.
Q94 Alan Keen: I have mentioned this
a few times in the past, the great relationship that still exists
from 1966 between my own team, Middlesbrough, and North Korea,
because they played their three games there and knocked the Italians
out. Different from those days, we have masses of people in this
country now whose families originated from places all over the
world. It is thrilling. We want them to be UK citizens but we
want them to have their own roots as well. Are we doing anything
special to engage those people in supporting those nations from
which their roots come?
Lord Coe: Yes. It is a good opportunity.
Last night within our own organisation I spoke to what we call
our community advocates, from communities certainly London-wide
and more broadly. We are working on engaging those communities
in wherever it happens to be, North West Lancashire, the West
Midlands, but also through our international inspiration programme,
which is our commitment to get 12 million more young people involved
in high quality physical education and sport in 20 countries by
2012. I was in India literally a week ago to look at some of the
projects that we are funding in conjunction with the British Council
and UK Sport and Unicef, but, also, if you look at the Indian
community in London, 6% of London now is an Indian community,
so there are opportunities both domestically through our engagement
and advocacy programmes and internationally through our international
inspiration. When I was in Africa not long ago I was asked by
a head of state what it was I wanted out of the Games, and I said,
"As far as I am concerned, sitting here, I want your athletes
when they walk in to our venues to feel they are competing in
front of a home crowd." This is an important part of the
process.
Mr Deighton: I was in Middlesbrough
a couple of months ago. The training pitch for Middlesbrough is
a pre-Games training camp for football, and of course St James'
Park is a venue. The opportunity to rekindle some of those links
with themes from around the world is very much alive in the North
East.
Q95 Alan Keen: I always ask these
questions in these sessions. You have been struggling with costs,
and I think doing a great job. Obviously you could not match the
forecast that was made when we decided to bid for the Games by
a long, long way, but you are struggling with costs. You must
know how much we could have saved had it been a national Olympics,
so that we did not have to build a new centre completely in East
London. Then it would have involved people around the regions
and nations in the UK. Does the IOC listen and look towards adapting?
My main problem is not the money we could have saved but the fact
that nations less well off than us would never be able to bid
for a city Olympics and spend what we are spending, but we could
save a lot of money if it was a national Olympic bid. South Africa,
for instance, have facilities around the whole country, but to
build anything in Cape Town or Johannesburg would cost an awful
lot. Is the IOC continually thinking about adapting?
Lord Coe: It is fair to say that
the International Olympic Committee recognises that for the maintenance
of a global brand you have to be able to take that brand into
countries and continents that have not had the Games before. Rio
is an extremely good example of that. This is a country that has
never had the Games and a continent that has never had the Games,
which has the potential to impact and imprint on 180 million young
South Americans through the Olympic Movement. The movement is
fully conscious that you cannot keep taking it back to hotspots
and clusters; you do have to broaden this out. In doing that,
you would probably need in some ways to change the approach to
the way you support those countries which may not have, on the
face of it, the technical expertise, and which may not have entirely
the commercial wherewithal. For this to happen, most governing
bodies of sport recognise that a handholding process is probably
likely to be more in evidence as we go forward, if we are to maintain
that interest.
Q96 Alan Keen: On the way to the
Grand Prix Athletics at Crystal Palace the previous year, I was
astonished to see the Herne Hill cycle track. I was there at the
1948 Olympic Games, watching the cycling eventsall of them.
Is somebody looking at the history of the 1948 Games and incorporating
that into this?
Lord Coe: Yes, there is. I should
know the answer to this. I met an organisation the other day that
is trying to chronicle this. There is the official report from
the 1948 Games anyway that the IOC has. I have a copy of it at
home; probably alongside the medals, wherever they are. This is
an interesting point, because in the course of the next three
years we also want to be able to celebrate some of the achievements
in 1948 that were there, and many of those competitors are living
today.
Alan Keen: Thank you very much.
Q97 Paul Farrelly: Alan started with
some questions on the broadcast and media centre and also the
Village, and before we move off I wanted to ask a couple of questions
on that. With respect to the broadcast and press centre, who is
leading the legacy negotiations and up until when?
Mr Higgins: The legacy negotiations
on the press centre are clearly being lead now by the Legacy Company,
the Olympic Park Legacy Company, and prior to that the LDA. We
do not control the freehold of that land there; we are just building
it. Up until 2008, towards the end of 2008, the ODA was negotiating.
We were then out to tender and we were hoping to bring in a private
investor, but it proved not to be value for money at that stage,
at that particular time, with the way banking sector was and the
risk concerns that private investors had, but I am sure that in
a year or two's time it will be an appropriate time to get back
out and seek to find another private investor.
Q98 Paul Farrelly: These pictures
are very helpful of progress. So that we are not unfair, it would
be quite useful to have a parallel brochure in terms of final
design and what they all will look like. At the moment I clearly
cannot see the finish of the broadcast and press centre, but it
looks to me like a very big double-decker shed.
Mr Higgins: That is it. I cannot
describe it better myself.
Q99 Paul Farrelly: I may be being
unfair to the finishing off. Hackney borough's original ambitions
were to have, shall we say, a Shoreditch East. I cannot see that
this is going to be attractive to many media or arty types, to
come and work in a village feel.
Mr Higgins: There are three items.
There is the big car park, which makes it a very attractive area
to invest in, because you do not get approvals for large car parks
next to motorways within a mile of Canary Wharf nowadays. The
media centre itself is a traditional office building. It is a
column-free space. It will be well serviced with lifts and fire
rated. It will be a conventional office building and already there
are media companies, one in particular, which are thinking of
taking space in there. It is years away, of course, but there
are organisations that have expressed interest.
Q100 Paul Farrelly: ITV have been
mentioned.
Mr Higgins: It is early days.
As to the broadcast centre, you are right, it is a large tin shed,
insulated. The roof structure is built to be part of building
regulations, so it is built so it can remain there, but the structure
on the outside is designed so it can be split into three different
blocks. You can hang a different façade on it, so if you
want to put more windows in it is designed so that you have enough
flexibility in the structure to allow either officer storage or
warehouse or other industrial usages, as may come.
Q101 Paul Farrelly: If the demand
was there, it could be the next distribution centre of Amazon
Books or Screwfix.
Mr Higgins: I suppose it could
be all of those things.
Q102 Paul Farrelly: It could be any
of them.
Mr Higgins: That is right.
Q103 Paul Farrelly: It could be a
world away from what was envisaged.
Mr Higgins: In the end, you have
to work with the market. The market will determine what usages
are. The big thing that will deliver it is that it is flexible
structurally; it is very well located in terms of transport; and
it does not have any debt attached to it, so it is really up for
working in the market and with potential tenants.
Q104 Paul Farrelly: We have a picture
of the Olympic Village, which looks like a set of high-rise blocks.
How are you managingbecause this has changed over timesthe
architects and the design process and the teams that are involved?
Mr Higgins: The original master
plan, which was approved in 2004, was modified over the last three
or four years to better integrate it into the local community
groups and to create more public squares and more open space.
We have done that, and that amendment was approved 18 months ago.
Then each individual block has its separate independent architect,
who is an international or leading UK architect, as well as international
landscape designers. That allows for the quality. The most crucial
thing, having put a lot of time and effort into the design and
buildings and public space, is maintenance of this area now. It
is really very important that we set aside the money and put the
agreements in place to ensure it is done.
Q105 Paul Farrelly: How many architects
are involved at the moment?
Mr Higgins: At least 12.
Q106 Paul Farrelly: Who is the lead?
Mr Higgins: There are lots of
different architects. Patel Taylor did the one you are looking
at there.
Q107 Paul Farrelly: Could we have
a note on how that has changed and who is involved at the moment?
Mr Higgins: Yes, of course.
Q108 Paul Farrelly: Finally, what
is the total anticipated outturn cost to the Village?
Mr Higgins: £1.1 billion.
Q109 Paul Farrelly: How much of that
was involved in your original baseline?
Mr Higgins: If you go back to
the original bid documents that were lodged in 2005, they say
the Village would cost around £1.1 billion.
Q110 Paul Farrelly: Is that in your
baseline figures?
Mr Higgins: No, because originallyand
you can go back a long, long waythe Village was going to
be privately financed.
Q111 Paul Farrelly: Exactly, so the
Village was not in the baseline figures at all.
Mr Higgins: That is right. The
Village was never in the original bid, it was going to be privately
financed. In the baseline project the infrastructure was there,
which is the bridges and the roads and the utilities, but the
vertical build of the Village was going to be privately financed.
Q112 Paul Farrelly: I am trying to
get to a cost. In the figures I have, I have Village contingency
released so far of £587 million. That is the funding for
the village so far.
Mr Higgins: Yes.
Q113 Paul Farrelly: Of the £1.1
billion, where is the extra £513 million?
Mr Armitt: We were always going
to fund the infrastructure; for example, the railway has been
covered over and put into tunnel. All those costs were in our
original infrastructure within the Olympic Park, but allocated
to the Village because it was part of the Village, but it was
never going to be funded by the private sector. The private sector
was going to fund the vertical build, and it is therefore the
£600 million or so of that which we had to find from contingency
and savings.
Q114 Paul Farrelly: Of the contingency
that has been released at the moment, the £587 million, that
takes it to the final conclusion.
Mr Armitt: Yes.
Mr Higgins: And you need to then
allow for the sale of the social housing, which is the £268
million figure, as it brings in receipt, and that helps finance
the
Q115 Paul Farrelly: Is that including
the £324 million?
Mr Higgins: Perhaps we should
send you a summary.
Q116 Paul Farrelly: Perhaps you could
break it down, so we do not get the wrong end of the stick and
people do not shift in their seats and get bored.
Mr Higgins: We will send you a
summary.
Q117 Mr Ainsworth: Alan Keen was
asking you about your happiness quota just now. I do not want
to reduce it in any way, but I think we have to mention Greenwich
Park and the equestrian events and the controversy over the venue
there. It was reported in the Evening Standard on 9 December
that the cost of staging those events in Greenwich Park with temporary
facilities has increased from £12 million to an estimated
£42 million. Is that correct?
Lord Coe: (a) that is not correct,
and (b) you will understand, given the commercial sensitivity
of purchasing and overlaying all the other things, that those
are not figures we would want to state at the moment. But that
is inaccurate.
Q118 Mr Ainsworth: Are you quite
sure there is not an alternative venue that you could be using
for this?
Lord Coe: Let me go back to the
beginning here. The recognition that we wanted to put the equestrian
events in as close to the Olympic Park as possible was an important
one. I speak from some experience here. When we started bidding
and I became Chair of that bid, pretty much most of the senior
riders in this country came to me and said, "Look, do not
do what we have always been lumbered with in the past, which is
venues that have been a long way from the Games where we felt
little or no part of those Games." In fact Beijing was a
good example, but for quarantine reasons: the equestrian events
were in Hong Kong. For legacy reasons, a way of encouraging a
group of people into a sport which is particularly unfamiliar
to them was, for us, a very important part of that process. Greenwich
Park will be a stunning backdrop. It has been signed off by the
domestic federation, the international federation, the television
values are extraordinary, and we have worked very, very closely
with all the community groups within Greenwich.
Q119 Mr Ainsworth: What is the legacy
for Greenwich Park? What do they get out of it in terms of long-term
benefit?
Lord Coe: First of all, it is
encouraging Londoners who are probably not that familiar with
equestrian sport, to get involved. Second, there is a large attraction
because Greenwich is an extraordinary place to visit anyway. But
let us be very clear about legacy in equestrian sport. I have
often heard the argument: Why do not take it to Badminton or Burghley
or Bramham or wherever? There is no legacy in three-day eventing.
All these other venues are often working farms. Badminton House
is a good example. His Grace the Duke of Beaufort in his munificence
might open the park, but I am not sure that he would want a 23,000
seat permanent arena adjoining the West Wing. We have to be very
clear that when we are talking about legacy this is not a bricks
and mortar legacy. There are proposals, there are plans within
the London Borough of Greenwich, to look at leaving a legacy for
Londoners in a riding facility. There is a scheme called Hoof
which is currently underway to encourage more Londoners into that,
but this is not a straightforward legacy story; this is a much
softer legacy story and in our view Greenwich serves as many of
those finely balanced judgments as we have had to make.
Q120 Mr Ainsworth: Your planning
application, which is a huge documentand I have to confess
I have not read it in the detail which no doubt it deserves
Lord Coe: You surprise me!
Q121 Mr Ainsworth: does admit
that there will be some damage caused to what is a World Heritage
Site.
Lord Coe: Let us be very clear
about that. The cross-country section of the three-day event was
held on a golf course in Hong Kong and people were playing golf
back on that course four days afterwards. We have consulted widely
with Natural England, with English Heritage, with the Royal Parks.
We have modified our plans in some cases to take into account
the concerns of local people: there are no residential road closures;
the deer park itself will be closed for only one day (that is
the cross-country course); we have maintained the opening of the
playground. We have worked extraordinarily closely with all stakeholders.
We have a big communications programme going on in Greenwich.
It started over a year ago and we are now into the planning applications.
This is absolutely the way that it should be proceeding.
Q122 Mr Ainsworth: Are you concerned
that the Metropolitan Commons Act 1861 is going to interfere with
your ability to use Blackheath?
Lord Coe: I am not going to pretend
to you that I am an instant expert on 19th century legislation,
but I am advised that this has been misinterpreted. The planning
application for Greenwich Park is quite rightly driven by Greenwich
Council. The consent for the use of Circus Field rests with the
secretary of state, but these two issues should not be conflated.
Q123 Mr Ainsworth: You will not be
asking Parliament to revisit the 1861 Act.
Lord Coe: I think it is very unlikely.
Q124 Mr Ainsworth: Good.
Lord Coe: Certainly not before
recess, anyway.
Q125 Paul Farrelly: In a parallel
inquiry we had occasion to visit the Bill of Rights recently.
We thought we were experts on that, but it turned out not.
Lord Coe: I do not wish to intrude
on private grief, but I think it is unlikely we will be taking
you down that road.
Q126 Paul Farrelly: I love Greenwich
Park and this is the only reason for asking this question. It
is the London Borough of Greenwich that is the planning authority.
Lord Coe: Yes.
Q127 Paul Farrelly: When do you anticipate
it going into committee?
Lord Coe: The process started
two weeks ago or three weeks ago.
Mr Deighton: Yes. I think it will
go into committee in March next year.
Lord Coe: Yes, probably at the
end of the first quarter.
Q128 Paul Farrelly: Planning committees
can be fairly unpredictable in my experience. Do you think it
is a formality?
Lord Coe: No. We have 117 planning
applications and I do not think we would consider any of them
to be a formality, but of course it does have the advantage of
the complete support of the local authority in helping us put
this through.
Q129 Paul Farrelly: If planning members
for whatever reasonbecause sometimes they can behave perverselydecided
not to follow that advice and recommendation, what contingency
plans do you have if it does not run smoothly?
Lord Coe: We certainly do not
take anything for granted. Having sat on your side of the table
for a few years, I know that planning is at best an uncertain
process. That is something we would visit as and when, but we
do not envisage any long-term difficulty.
Q130 Paul Farrelly: If you were to
ask for it to be called in, there might be a role for a secretary
of state in the future.
Lord Coe: That is, by implication,
the planning process, yes.
Q131 Chairman: Whilst we are on venues,
you would expect me to mention Woolwich. As far as you are concerned,
is that matter now settled absolutely?
Lord Coe: Yes.
Q132 Chairman: There is no obstacle
to the use of Woolwich for the shooting?
Lord Coe: Nosubject, of
course, to local planning.
Q133 Chairman: Have the shooting
community signed up to that?
Lord Coe: The international federation
thinks it is an extraordinary site.
Q134 Chairman: British Shooting have
not yet reached that conclusion.
Lord Coe: I wish not to intrude
on private grief here: British Shooting is a fractured organisation.
But we are driving ahead with a venue that has been signed off
and will serve its purpose.
Q135 Chairman: There are no safety
problems.
Lord Coe: No. It meets all the
requirements.
Q136 Chairman: Having examined all
the alternatives, you have now completed that process.
Lord Coe: Yes.
Q137 Chairman: No further work will
be done.
Lord Coe: Noand with great
clarity.
Q138 Chairman: To return briefly
to the Olympic route network, what do you think of the Mayor of
London's concern that as many officials as possible should use
public transport?
Lord Coe: The reality of it is
that where public transport is the best option, in the past we
have seen officials, whether they are members of the Olympic family
or even occasionally IOC members, opting for that. It is very
important that we do not depart from one place too quickly. The
delivery of Olympic and Paralympic Games is a very complex process.
The ability to move 10,500 competitors, 4,500 paralympians, 20,000-odd
people involved (what we call the Olympic family: their coaches,
their officials, their drug testers) around a city Games in a
way that allows the Games to operate with no reputational damage
to that city going forwardand not all cities have escaped
that in the pastis for me acute. That is why the Olympic
route network, which I tend to view as a route network to allow
people to work on the Games, is absolutely essential.
Q139 Chairman: Would you accept that
once Londoners discover that major thoroughfares are reserved
for Olympic traffic, it may dent the enthusiasm for the Games
that Londoners currently have.
Lord Coe: Only on the assumption
that that is not done with a proper consultation and communication
process of letting people know exactly what we are doing, when
we are doing it and why we are doing it. I think most Londoners
will understand that they live in one of the most global cities
in the world. It is staging an Olympic Games and that is an important
part of making sure we come out of this with a great Games, no
reputational damage and having been great hosts.
Q140 Chairman: When will you start
trials of the network?
Mr Armitt: We have recently published
the latest iteration of the network for consultation. That consultation
over the next few months will then, next year, be publishing another
version of that. Clearly, in the year before the Games we will
be going through a significant process of telling people what
is going to be operating during the Games, how it is going to
be operating, the impact potentially at peak hours of Olympic
traffic and Olympic spectators combining with people going to
work, so that people can have a clear understanding of what is
going to be happening. It is quite difficult to create the particular
circumstances of the evening of the Opening Ceremony, for example,
and try to dress rehearse that prior to the Games, but London
is constantly having major events and we have seen time and time
again London's ability to cope with these major events. A couple
of years ago, for example, we had the first stage of the Tour
de France; we have marathons every year here; we have events regularly
such as Trooping of the Colour, which take place in the centre
of London and therefore potentially must create more difficulties
than simply moving people across London to go to particular events
at Stratford, Wembley, Earls Court or wherever it might be. The
key to this is that it is being thoroughly planned. It is being
planned across all the different organisations involved, from
TfL to Network Rail and other train operators, with the Metropolitan
Police and British Transport Police. There will be a dedicated
control centre at which all these organisations will be involved,
with a team of people overseeing the whole thing and able to make
minute-to-minute, hour-to-hour alterations in conjunction with
information which is coming through from LOCOG about timing of
events and so on. There is a lot of work going into this. We have
had an across-the-board committee chaired by Chris Garnett, who
used to be the head of GNER, making sure that everybody is understanding
the issues that their particular contribution to this has to deal
with, so that at the end of the day you have a very well planned
approach ready to go and in July 2012.
Q141 Paul Farrelly: I have an add-on
or supplementary in relation to this public relations challenge.
Clearly there is an ongoing disagreement between Transport for
London and the US Embassy about payment of the congestion charge.
How are you approaching your preparations for the payment of non
payment of the congestion charge?
Mr Armitt: The congestion charge
is the responsibility of the Mayor, not us, but I have never heard
anybody suggest that the congestion charge is going to be a particular
impediment or otherwise to the Games. I would expect it to operate
in the way that it normally does.
Lord Coe: Marathon runners will
be exempt!
Q142 Paul Farrelly: You know the
point I am making, that there is nothing more certain to press
lights than an ambassador or an official using, say, a non designated
car, which might or might not be exempt from the congestion charge,
refusing to pay his £8 whereas Londoners have to pay it.
Mr Armitt: Yes.
Paul Farrelly: We will leave it here.
Q143 Mr Ainsworth: I would like to
touch on the question of security and the arrangements that you
have in place now. Who is responsible for those arrangements and
what plans do you have going forward to the opening of the Games
and the Games themselvesand of course post-Games too, I
guess.
Mr Higgins: Day-to-day site control
is under the responsibility of the ODA. That being said, we have
had people from the Metropolitan Police embedded in our organisation
for the last four years, including people from the Ministry of
Defence. There is close co-ordination on that. The site has recently
gone to biometric testing for all of our workforce. We have put
5,000 or 6,000 people through that recently. We continue to escalate
the security of the site. We have finished the Olympic fence around
the Olympic Park. We take accountability for securing the Olympic
Park and Village up to the Games time, and then, post-Games, to
hand over to the Legacy Company. During Games time, clearly it
becomes the responsibility of the Home Office, Met Police and
LOCOG.
Q144 Mr Ainsworth: Is the site secure?
Mr Higgins: Yes.
Mr Armitt: Yes.
Q145 Mr Ainsworth: And it is patrolled.
Mr Higgins: Four hundred people
on rosters 24 hours a day secure the site internally and externally.
We have police based in the site itself as well.
Q146 Mr Ainsworth: How are your relations
with the Metropolitan Police?
Mr Higgins: Excellent. We have
had Met Police based in the middle of our main operation centre
in the Park for three years now.
Q147 Mr Ainsworth: You are happy
that everything that needs to be done is being done and will be
done.
Mr Higgins: Yes, we have had Borders
and Immigration embedded in our organisation for three years,
so they have been there helping to secure people coming into the
site as well.
Q148 Mr Ainsworth: I will move on
to the Cultural Olympiad. £16 million worth of Lottery money
has gone into this. Is there much to show for that yet? Is it
being measured and monitored in any way? We had a note from the
National Audit Office saying that there was not really any system
in place to monitor the effectiveness of how that money was being
spent.
Mr Deighton: The £16 million
of Olympic Lottery distributed money that has gone into the Cultural
Olympiad was only awarded a few months ago. That money is being
applied to the ten major projects which form part of the overall
Cultural Olympiad. The whole process for determining the quality
and the impact of those is something that we will be working on
over the next 12 months. We have put in place since being awarded
that money a Cultural Olympiad Board. We asked Tony Hall, the
Chief Executive of the Royal Opera House, to join our LOCOG board
and to set up the Cultural Olympiad Board, which comprises a number
of luminaries from across the creative sector, to make sure that
we absolutely have a set of projects which really do hit our aspirations
for the impact the Cultural Olympiad can have. If you look at
what has happened already, of the ten projects, three have already
launched and are in really good shape. One was Artists Taking
the Lead. That was in March 2009, with just over £5 million
worth of investment. It was not from the OLD but from the Arts
Councils around the United Kingdom. We have a Major Commission
which has now been chosen in each of the nations and regions.
There are some wonderful, wonderful ideas that are now being brought
to life, which will be finished in the main in 2012. We have had
a marvellous series of exhibitions in the museum and libraries
sector called Stories of the World. It is in 50-odd museums around
the country and is already up and running. Earlier on this year,
I think in October, we launched a projected called Unlimited,
which is the biggest disability arts commission this country has
ever seen. Those three are already underway and we have some brilliant
things coming. The Royal Shakespeare Company is working on a Shakespeare
Festival. That is one of the primary beneficiaries of the OLD
money. We have had a carnival proposition, which again will be
worked into more detail. The next one to launch will be a music
festival, together with the BBC, which will probably be called
something like Sounds. If you think that each of the strands of
the creative sector has been represented in these major projects,
that is where the money is going, and we have had the governance
around it that will ensure that it is effectively controlled and
the impact of it meets those aspirations.
Q149 Mr Ainsworth: There is fairly
low awareness at the moment of this programme, it seems to us.
There was some research done recently which showed that only 4%
of people were aware of any Cultural Olympiad activity in the
area in which they lived.
Mr Deighton: First, it is relatively
early. Second, think of the Cultural Olympiad as leading up in
a crescendo to 2012 when we have the torch relay which sets the
country alight, with the opening ceremony and everything going
on and these events coming to life. I would also say we are not
particularly trying to brand the activity as the Cultural Olympiad.
We are trying to use the inspiration of the Games to get people
to be involved in activities in their community who would otherwise
not be involved: things to do with welcoming the world, things
to do with getting young people involved, things that are inspired
by the Games. For example, we have something like between 250
and 300 Inspired By projects around the country, many of which
are culturally driven. We have London 2012 Open Weekend held on
the countdown to the Olympic Games, four years to go and three
years to go. Four years to go was something like 650 projects,
and three years to go we had nearly 800. That is all sponsored
by BP, and, again, right around the country. People would not
necessarily think of the term `Cultural Olympiad' but they would
think, "I just went to a great event/participated in a great
event which was inspired by the Games coming here."
Q150 Mr Ainsworth: The whole thing
then builds and we have the Opening Ceremony. Who is in charge
of the creative side of that?
Mr Deighton: That is our organisation.
Q151 Mr Ainsworth: You cannot manage
a creative event by a committee really.
Mr Deighton: No.
Q152 Mr Ainsworth: It takes inspired
and experienced people.
Mr Deighton: Absolutely. After
we came back from Beijing, our creative team spent the best part
of a year meeting with a great variety of cultural brains around
the country to discuss what our Opening Ceremony should be about,
what the themes should be, a very open creative process. We are
now privately talking to the small number of individuals who have
been identified as the potential creative controlling mind for
the Opening Ceremony, and we would expect to finalise that appointment
next year.
Q153 Mr Ainsworth: A single appoint.
A head honcho to run the thing.
Mr Deighton: It is not inconceivable
that the result might involve aspects of partnership, but we are
certainly talking about a tight creative control not a process
that is run by committee, absolutely. I think everybody shares
your concern that something run by a committee might not produce
the best outcome.
Q154 Mr Ainsworth: I have vivid memories
of the Dome. Anything you can do to keep Peter Mandelson out of
your creative thinking would be good news. Also, like so many
others, I just hope when the night comes it has an amazing wow
factor and is not just a total embarrassment. Are you convinced
that you are going to deliver something good?
Mr Deighton: Yes.
Q155 Mr Ainsworth: On a different
issue I would just like to give you the opportunity to say whatever
you wish to say on the sustainability of the Games, in terms of
impact on the environment and what you are doing to ensure that
you meet those promises which were made at the time of the Bid.
Lord Coe: I will not speak for
John or David here, but this was a very important part of our
bid. It is a very important part of what we have committed to
do. I suppose we can define that by what we are doing, but also
by some of the market-led initiatives that I have always believed
would drive some of these legacy values. For instance, EDF, our
sustainability partnerit is one of four or five, but the
lead sustainability partnerwithin their own activation
have set a target of their client base reducing their own carbon
footprint, their own household emissions, by 15% between now and
2012. I fancy that has more of a chance of getting there than
some other organisations that have been in that same field. In
simple practical terms on the Park, 60% of the material that we
are bringing in now comes by water and by rail. That, in simple
terms, takes 600,000 to 700,000 lorry journeys off London roads.
We have widened rivers, not just for legacy purpose but to enable
that material to be brought up. 90% of the material we are using
on the Park is recycled. We have set very tough standards, both
in waste management control and in our own carbon footprint. We
are independently monitored by the Commission for a Sustainable
London 2012. It is a very important part of our process.
Mr Armitt: The Olympics provided
an opportunity for an exemplar project. Seb has just referred
to the London Sustainability group led by Shaun McCarthy, who,
together with us, established a series of objectives. For example,
20% of the energy used on the Park will come from renewable sources,
so we have a combined cycle power station which is capable of
burning biomass. We have planning consent for our first wind turbine.
We are ensuring that we make maximum use of rainwater; for example,
for flushing urinals. As Seb has said, we have recycled all the
waste materials from the site, and we have done the same with
the contaminated soil. The Village is being designed to what is
called BREEAM level 4,[2]
which is the highest level at the moment to which anybody would
be designing a similar housing community. Our objective all along,
as I say, has been to use it as an exemplar to pull forwards the
expectations of future projects as to what can be achieved in
this area.
Q156 Paul Farrelly: As a rider to
Peter's whole prospect of managing a creative event by a committee,
I recoil at memories of the moments that Liverpool went through
in organising its Capital of Culture events. They had a few prima
donna moments during that. It has to be clearly managed well,
whoever is the creative force behind it.
Mr Deighton: I would certainly
agree.
Lord Coe: We do not dissent from
that.
Alan Keen: In defence of Peter Mandelson
Mr Ainsworth: Why?
Q157 Alan Keen: I was on this Committee
all the way through when it looked at the preparations of the
Millennium celebrations. The job that Peter did was to antagonise
the press right from the beginning, and he did not have to do
anything to antagonise it.
Lord Coe: Would you like us to
stay or...?
Q158 Alan Keen: You have obviously
learned lessons from somewhere, if not from then. There is no
doubt about it, the person who does a fantastic job delivering
the building and everything else should be the last person to
deliver the cultural aspects.
Lord Coe: This is a very particular
skill set. We are very conscious of that.
Mr Armitt: We are happy to pass
the responsibility elsewhere.
Alan Keen: Anybody who is good at building
trenches and putting up structures is not the person best to deliver
the culture. My mind is set at rest by your answer.
Chairman: That is all we have. Thank
you very much.
1 Note by witness: Which will lead to thousands
of business opportunities. Back
2
Note: Building Research Establishment Environmental Assessment
Method (BREEAM). Back
|