MoD Winter Supplementary Estimate 2009-10 - Defence Committee Contents


Memorandum from the Ministry of Defence

WINTER SUPPLEMENTARY ESTIMATES 2009-10

1. INTRODUCTION

  1.1 This Memorandum covers the Winter Supplementary Estimate for the Ministry of Defence (MoD) and should be read in conjunction with the Department's Winter Supplementary Estimate (2009-10). The Introduction to the Estimate lists the changes being made since the 2009-10 Main Estimate. This is shown by Request for Resources (RfR), and the section number shown in brackets after the detail for each change is a reference to the line(s) that are affected by the change in Part II of the Estimate.

  1.2 There is a separate Estimates Memorandum for the Armed Forces Retired Pay and Pensions Vote.

2. SUMMARY OF RESOURCES SOUGHT IN THE ESTIMATE

  2.1 The Introduction to the Estimate shows a net increase in Voted DEL (Resource and Capital) of £143.792 million from £39,237.543 million at Main Estimates to £39,381.335 million for Winter Supplementary Estimates. The main elements to this are:

    (a) The Treasury fiscal CDEL fine abatement of £17 million; and the Fiscal CDEL relief for lower Northern Ireland receipts of £15 million.

    (b) An additional £20 million Resource DEL (funded from our 2008-09 End Year Flexibility stock) to reflect the Government decision to negate the impact of the planned MoD training costs 2009-10 budget reduction for the Territorial Army (RfR1).

    (c) To reflect the estimated net resource (near cash and indirect cost) impact of the third trigger point of the International Financial Reporting Standards (IFRS) for leases (IAS 17) relating to Annington Homes of £222 million; for provisions (IAS 37) of £5 million; for employee benefits (IAS19) of £35 million; and for the estimated net capital resource impact (near cash) for leases relating to Annington Homes (IAS 17) being a reduction of £3 million.

    (d) To reflect the latest additional estimated Annually Managed Expenditure forecast of the impact of FRS26 (Financial Instruments) on the forward Purchase Contract for foreign exchange Derivative impairments of £650 million.

    (e) To transfer £100 million Capital Resource to Direct Resource within RfR1 relating to Single Use Military Equipment (SUME) flexibility with no overall impact on DEL;

  2.2 The Voted Resource and Capital changes are summarised in the following tables:

Table 1

CHANGES IN NET RESOURCE AND CAPITAL EXPENDITURE
Resource Expenditure £ millions
Provision of Defence Capability (RfR1) 1,025.500
Operations and Peace Keeping (RfR2) 000.001
Total Net Request for Resources 1,025.501

Capital Expenditure£ millions
Net Provision of Defence Capability (RfR1)   -71.000
Operations and Peace Keeping (RfR2)000.000
Total Net Request for Capital-71.000
Total Change in Capital and Resource 954.501


  2.3 The total change in the Estimate is £954.501 million, which generates an additional net cash requirement of £38.501 million. The cash requirement is analysed in the following table, and the reconciliation between the changes in the Estimate and the net cash requirement is shown in Part II of the Estimate, Resource to Cash Reconciliation.

Table 2

CHANGE IN VOTED CASH REQUIREMENT
£ millions
Near Cash (Voted) in Resource DEL 41.521
Near Cash (Voted) AME35.000
Near Cash Non Budget32.980
Near Cash in Capital DEL-71.000
Net Cash Requirement38.501


  2.4 In addition to the changes outlined in paragraphs 2.1 above, the changes to the Winter Supplementary Estimate comprise:

    (a) Net PES transfers out to other Government Departments of £13.229 million, including transfers out to the Foreign and Commonwealth Office (FCO) of £6.500 million under RfR1 and £6.729 million to the Department for International Development (DfID) under RfR2. Further details are provided at paragraphs 4 and 5.

    (b) To increase Non Budget Grants in Aid (Non Voted) for the Council of Reserve Forces and Cadets Association of £31.7 million; £0.180 million for the National Army Museum; and £1.1 million for the Royal Hospital, Chelsea; by reducing Resource DEL current costs and increasing Non Budget Grants in Aid with no overall impact on resource.

    (c) Re-alignment of Resource and Capital Sub Head provisions to reflect changes in budgetary responsibility, with no overall impact on DEL.

3. DETAILED EXPLANATION OF CHANGES

  3.1 Part I of the Estimate summarises the changes described above and provides detail about the costs included in each RfR.

  3.2 Part II of the Estimate shows the changes proposed in the Estimate, by Top Level Budget Holder (TLB). This shows the present net position (the position at Main Estimates), the changes in the position, and the new net provision (Winter Supplementary Estimates). Again this is set out by Request for Resources. The transfers and other changes outlined in the Introduction to the Estimate are analysed in this section of the Memorandum.

  3.3 The table overleaf shows how the Winter Supplementary Estimate is compiled, identifying changes since the 2009-10 Main Estimates.

Table 3

SHOWING CHANGES TO VOTED RESOURCES AND CAPITAL AT 2009-10 WINTER SUPPLEMENTARY ESTIMATES

Direct
RDEL

Indirect
RDEL

Total
RDEL

Resource
AME
Non
Budget
near cash

Total Net
Resources
Net
Capital
DEL

Capital
AME
Capital
Non
Budget
Total
Net
Capital
£m (rounded)1 234 567 8910
RfR1 Provision at Main Estimates 23,887.111,632.535,519.6 173.3139.935,832.9 7,555.156.82.1 7,614.0
Switch from CDEL to RDEL100.0 0100.00 0100.0-100.0 00 -100.0
Additional CDEL provision for Northern Ireland loss of receipts 000 00015.0 0015.0
EYF drawdown for TA budget relief20.0 020.00 020.0
CDEL Fine Abatement00 000 017.000 17.0
IFRS accounting changes-39.0 261.0222.0690.0 0912.0-3.0 00-3.0
Transfers In0.50 0.500 0.5000 0
Transfers Out-7.00 -7.000 -7.0000 0
Reallocation of NDPBs-23.2 0-23.20 23.200 000
Additional Grants to NDPBs-9.8 0-9.80 9.8000 00
RfR1 at Winter Supplementary Estimates 23,928.611,893.5 35,822.1863.3 172.936,858.4 1400 14.0
RfR2 Provision at Main Estimates2,449.3 422.72,872.01726.6 345.82,872.01,564.6 001,564.6
Transfers Out-6.70 -6.700 -6.7000 0
Adjustment to ensure RfR is not reduced 6.706.7 006.70 000
RfR2 at Winter Supplementary Estimates 2,449.3422.7 2,872.01,726.6 345.82,872.0 1,564.60 01,564.6
RfR3 Provision at Main Estimates0 001,023.7 01,023.7
RfR3 at Winter Supplementary Estimates 000 1,023.70 1,023.7
Winter Supplementary Estimates Total* 26,377.912,316.2 38,694.11,887.0 172.940,754.1 9,048.756.8 2.19,107.6

4. RFR1 PROVISION OF DEFENCE CAPABILITY—EXPLANATION OF CHANGES

Transfers In/Out:

  4.1  The Estimate includes one transfer in from Other Government Departments and three transfers out, which are detailed in Table 4.

Table 4

SHOWING TRANSFERS BETWEEN MoD AND OTHER GOVERNMENT DEPARTMENTS
Transfers OutRfR £mPurpose
Department for International Development 1(0.500)Contribution to the Stabilisation Unit.
Foreign and Commonwealth Office1 (6.500)Afghanistan Delivery Group.
Department for International Development 2(6.729)Contribution to the Conflict Pool.
Transfers In
Department for Transport1 0.500Contribution to the Royal Flight funding arrangements.
Total Net Transfers Out (13.229)


End Year Flexibility (EYF):

  4.2  With Treasury approval the Department has been able to draw down £20 million of its near cash Resource EYF at WSE. This EYF access was allowed so that the MoD could reverse its planned reduction for the Reserve Force training budget in the current financial year. The Department's current EYF position is set out in the table below.

Table 5

END YEAR FLEXIBILITY STOCK


End Year Flexibility
Direct Resource
DEL £m
Indirect Resource
DEL £m
Capital
DEL £m
EYF Stock B/Forward from 2008-0960 00
EYF Stock Drawn Down at 2009-10 WSE(20) 00
Balance40 00


Fiscal CDEL 2009-10 Fine abatement:

  4.2 £17 million of fiscal CDEL has been reinstated to the MoD 2009-10 capital budget because the final 2008-09 audited outturn overspend was lower than the original forecasted over spend, on which the fine of £81 million imposed at Main Estimates was based.

Fiscal CDEL Relief: Northern Ireland Receipts

  4.3 The Winter Supplementary Estimate also includes Fiscal CDEL relief to compensate for a lower forecast of Northern Ireland capital receipts than originally planned, of £15 million.

OTHER CHANGES

Financial Instruments (FRS 26)

  4.5 The first stage of the IFRS implementation related to discounting of long-term debtors/liabilities and the movement on financial derivatives on forward purchase contracts under FRS 26 was implemented in our Estimates last year. The latest forecast indicates a non cash impairment impact of £650 million, which we have requested in our Winter Supplementary bid. Most of this relates to the change in the value of the pound sterling against the US dollar. The volatility of exchange rates may further impact on our 2009-10 final outturn.

Implementation of Stage 3 of the International Financial Reporting Standards

  4.6 The Department has implemented the third trigger point of the IFRS requirements at Winter Supplementary Estimates. These are technical accounting changes relating to the disclosure of finance leases and balance sheet liabilities. The impact on resource is set out in table 6 below.

Table 6

SUMMARY OF IFRS CHANGES AT 2009-10 WSE
Budgetary AreaNet Resource
Impact £m
Financial
Instrument
Explanation
Resource DEL222 IAS 17Annington Homes to be recognised as a finance lease.
AME    5IAS 37 Depreciation and cost of capital charges for capitalised nuclear decommissioning costs provisions of MoD assets.
AME  35IAS 19 Employee benefits resulting from the movement on the liability in respect of untaken leave, earned bonuses, and unpaid overtime.
CDEL  (3)IAS 17 Deferred income on the forecasted disposal of surplus Annington Homes.
Total259


Neutral Sub Head Budget Transfers:

  4.7 The changes under these sub-headings reflect alterations to TLB allocations of Resource and Capital funding to bring the allocations into line with responsibility transfers between TLBs, and other funding adjustments to align TLB provision with current forecasts. The capital transfers between sub heads are principally for further transfers of budgetary provision from "customer" budgets to Defence Estates, which is responsible for most estate expenditure. There are related IRDEL cost re-allocations associated with the Capital budget re-allocations.

Grants in Aid

  4.8 There are three Grants in Aid increases recognised in the Winter Supplementary Estimates. The Grant in Aid of £1.100 million to the Royal Hospital Chelsea (to cover higher Utilities, superannuation costs and maintenance of the infirmary and care of the pensioners in the Margaret Thatcher infirmary); £31.700 million for the Council of Reserve Forces and Cadet Association (a transfer of £23.222 million from Defence Estates to pay for grants which was too late to be made in Main Estimates, £4.815 million for increased works programme costs, and £3.034 million increase to cover staff costs, utilities, IT and other costs; and £0.629 million for vehicles) ; and £0.180 million for the National Army Museum (£0.095 million for replacement boilers, £0.030 million for removal of asbestos, and £0.055 million for staff costs). The Grants in Aid have been allocated within the existing provision of the TLBs' current DEL.

5. REQUEST FOR RESOURCES 2: OPERATIONS AND PEACE KEEPING

  5.1 The latest forecast for operations in Iraq and Afghanistan is summarised in Table 7 below, with a more detailed analysis shown in Table 8. Although we are not requesting any additional funds at WSE the overall forecast of costs in Iraq and Afghanistan has changed. These are set out in table 8.

  5.1.1 The transfer to DfID and the re-allocation of the Stabilisation Aid Fund require Parliament to make a token vote of £1,000 in resource.

Table 7

SUMMARY COST OF OPERATIONS AND PEACE KEEPING FORECAST AT 2009-10 WSE


Operation
Direct
Resource
DEL £m
Indirect
Resource
DEL £m

Capital
DEL £m
Total WSE
forecast
2009-10 £m
Total ME
request
2009-10
Iraq25676 56388877
Afghanistan1,914295 1,5453,7543,495
Total2,170371 1,6014,1424,372

5.2  Afghanistan (Operation Herrick)

  5.2.1 When the Main Estimate was drawn up in January of this year, the forecast was based on the best information available at the time. Forecasts supported a force level across the entire 2009-10 financial year of 8,300. In the light of announcements by the Prime Minister in April that force levels would increase to 9,000 to support national elections, and enable the deployment of the counter improvised explosive device task force, there have been increases in elements of personnel costs, additional sustainment costs, the corresponding additional equipment, essential Urgent Operational Requirements and associated costs of providing counter improvised explosive device capability and expertise.

  5.2.2 The costs of Operations are driven significantly by the tempo of operations, which particularly affect equipment support costs, attrition, fuel and ammunition consumption. Exchange rates, fuel prices and costs incurred with contractors can all also vary during the financial year. We have, however, involved HM Treasury in formulating the estimates to reassure them of the rigour applied, and to inform forecasts of wider government spending. We do expect some corresponding cost changes throughout the year, as burden sharing and partnering requirements are clarified. Therefore, we may have to increase our request for resources at Spring Supplementary Estimates. We will inform the Committee of any significant changes.

  5.2.3 As announced by the Prime Minister on 14 October 2009, an additional 500 troops will be made available to support the Operation in Afghanistan—but they will only be deployed when certain conditions are met. The figure detailed above does not include the forecast expenditure to meet this requirement—we will supply further details to the Committee as appropriate.

5.3  Iraq (Operation Telic)

  5.3.1 Operational costs in Iraq reflect the planned withdrawal of UK forces over the first few months of this financial year, including drawdown costs. As advised in the Government response to the HCDC report on 2009-10 Main Estimates, forecasts of expenditure are lower than envisaged when the Main Estimates were published, due to the accelerated drawdown process. Since then, we have now completed the orderly withdrawal of UK troops from the Contingency Operating Base (COB), Basra in line with the UK security agreement deadline of 31 July 2009. We have successfully extracted and re-mediated all personnel and equipment; and all UK occupied or managed facilities have been passed over to US forces, or handed back to Iraqi or Kuwaiti authorities.

  5.3.2 In line with the recent ratification by the Presidential Council, we expect a continued presence of UK forces and assets to be stationed in the region, primarily providing naval and air support—for which, at the moment, we forecast there to be continuing costs. We will supply further details to the Committee if this estimate changes significantly prior to the Spring Supplementary Estimates.

  5.4 The current detailed cost estimate for operations in Iraq and Afghanistan for the 2009-10 Winter Supplementary Estimates is shown in Table 8.

Table 8

THE ESTIMATED COST OF OPERATIONS IN AFGHANISTAN AND IRAQ AT WSE 2009-10

Cost Type
Iraq ME £m Iraq WSE
Forecast £m
Afghanistan ME
£m
Afghanistan WSE Forecast £m
Direct Resource DEL
Civilian Personnel9 61624
Military Personnel37 39148171
Stock/Other Consumption189 28480492
Infrastructure Costs69 68216276
Equipment Support Costs231 89485535
Other Costs and Services93 52423445
Income Foregone/Generated (-)1 -26-12-29
Total Direct Resource DEL629 2561,756 1,914
Indirect Resource DEL165 76258295
Total Resource DEL794 3322,014 2,209
Capital DEL
Capital Additions83 561,4811,545
Total Capital DEL83 561,481 1,545
Total Estimated Costs877 3883,495 3,754

5.5  Balkans (Operation Oculus)

  Earlier this year, the Supreme Allied Commander Europe decided that the specific capability provided by the UK to NATO force in Kosovo, was no longer required. The UK force, has therefore drawdown to a small number of remaining personnel. As such, costs associated with the drawdown, and all MoD-led discretionary tasks in the Balkans, have now been subsumed into, and will be charged against the Wider Europe Programme of the Conflict Pool. As a result, the ability of Operation Oculus to draw on the Reserve ceases.

5.6  Conflict Pool

  At the time the Main Estimates were prepared, overall responsibility for administration of the Stabilisation Aid Fund (SAF) was being re-negotiated between Government Departments. The final agreement, as outlined by the Foreign Secretary in a Written Ministerial Statement[1] on 25 March 2009, is that the new combined Conflict Pool subsumes all activity under the Conflict Prevention Pool and Stabilisation Aid Fund. Since then, it has been confirmed that the overall responsibility for the Conflict Pool rests with DFID and as such, the funding rests on that baseline. The transfer from MoD to DFID at WSE reflects this change.

6. RFR3 WAR PENSION BENEFIT (WPB)

  6.1 There are no changes to the RfR3 War Pension Benefit at Winter Supplementary Estimates.

7. THE DEPARTMENTAL EXPENDITURE LIMIT (DEL)

  7.1  Table 9 shows the DEL from 2006-07 to 2009-10 for all RfRs. The Total DEL is calculated by adding Resource DEL, Capital DEL and deducting depreciation, which forms part of Resource DEL. Depreciation is excluded from Total DEL; including this as well as Capital DEL would be double counting. The figures are for Voted and Non-voted DEL; the Non voted DEL figure for WSE 2009-10 is £214.776 million net of depreciation, and this is shown in more detail in the Notes to the Winter Supplementary Estimate.

Table 9

CHANGES TO MOD DEPARTMENTAL EXPENDITURE LIMITS (VOTED AND NON VOTED)
2006-07
SSE £m
2007-08
SSE £m
2008-09
SSE £m
2009-10
ME £m
2009-10
WSE £m
Resource DEL34,104 36,94038,07138,582 38,911
Capital DEL7,4488,120 8,3139,1219,050
Depreciation-7,401-8,218 -8,247-8,284-8,365
Total DEL34,151 36,84238,137 39,41939,596

8. ADMINISTRATION COSTS LIMIT

  8.1 There are no changes to the Administration Costs Limit.

9. PROVISIONS AND CONTINGENT LIABILITIES

  9.1 No changes have been made at WSE.

10. MACHINERY OF GOVERNMENT CHANGES

  10.1 There are no Machinery of Government Changes.

11. THE DEPARTMENT'S PUBLIC SERVICE AGREEMENTS AND STRATEGIC OBJECTIVES

  11.1 As set out in the 2007 Pre-Budget Report and Comprehensive Spending Review (Cm 7227), the Ministry of Defence will contribute over the CSR 07 period to the delivery of the cross-Governmental Public Service Agreements to reduce the impact of global and regional conflict and to reduce the risk to the UK and its interests overseas from international terrorism. These are underpinned by the three Departmental Strategic Objectives (DSO) to achieve success in the military tasks we undertake at home and abroad; be ready to respond to the tasks that might arise; and build for the future. The Department formally reports performance against its targets to Parliament in the Autumn and in its Annual Report.

12. NET ADDITIONAL CASH REQUIREMENT

  12.1  The Net Cash impact for the Winter Supplementary Estimate is an increased net cash requirement of £38.501 million. This is broken down in Table 2.

13.  VOTES A

  13.1 The Ministry of Defence Votes A Winter Supplementary Estimate 2009-10 will be laid before the House on 24 November 2009 as HC7. We will be seeking an increase in the number of Royal Marines Men and Women, Royal Fleet Reserve Naval officers, and ratings and Royal Fleet Reserve officers and marines.

  13.2 The current maximum number of officers, men and women to be maintained for Naval Service category was established at 42,100 and within this total the Royal Marines were 8,450 for Financial Year 2009-10. The Reserve Naval and Marine Forces total was 15,092 for Financial Year 2009-10. The ceiling was calculated from historical trend data and best estimates for future plans. However, since the start of the year, the numbers in this category have steadily increased due to higher than expected untrained personnel increases, and subsequent increases in trained strength following completion of training.

  13.3 We have therefore requested an increase of 400 for Royal Marine Men and Women bringing the total for Royal Marines to 8,850 and the overall total for the Naval Service to 42,500. This represents an increase of 0.19% compared to the established Regular Tri-Service Votes A maxima of 212,030.

  13.4 For 2009-10 the maximum in this category was established at 15,092 for the Reserve Naval and Marines Forces. This was calculated from historical trend data and best estimates. As part of the review of the quality of the data held in JPA it has been determined that some of the records were incorrect. This exercise has lead to an increase in Marine Officers and Marines, and naval men and women; and a reduction in the number of naval officers. However, based on calculations of strength increases, a prudent maximum would be 17,652 (for all categories), an increase of 2,560 (3,775 -1,215) based on the Votes A 2009-10 estimate.

  13.5 The changes for the Reserve Naval and Marine Forces are set out in the table below.


Category
Main
Estimate
Officers
Winter
Supplementary
Estimate Officers


Difference

Main Estimate
Men and Women
Winter
Supplementary
Estimate Men and Women


Difference
Royal Fleet Reserve
(naval officers and ratings)
5,2254,000-1,225 3,9907,0003,010
Royal Fleet Reserve
(marine officers and marines)
39040010 1,2352,000765
Total5,615 4,400-1,215 5,2259,0003,775

26 November 2009

Annex 1

A. DEFINITION OF TERMS

1.   Direct Resource Departmental Expenditure Limits (RDEL)

  This is a control aggregate within the resource budget. It excludes the non-cash items such as depreciation, cost of capital and movement in provisions. Direct Resource DEL is also known as "near cash in the resource budget".

2.   Indirect Resource DEL (IRDEL)

  This covers items such as depreciation, cost of capital charges, movement in provisions, and the notional auditors' fees for the National Audit Office (NAO). This is also known as non-cash.

3.   Total Resource DEL

  This is the sum of Direct and Indirect Resource DEL.

4.   Annually Managed Expenditure (AME)

  Annually Managed Expenditure (AME) includes Programmes that are demand-led, such as War Pensions (RfR3) and exceptionally volatile items that cannot be controlled by the Department. AME also includes Programmes that are so large that the Department could not be expected to absorb the effects of volatility within them, such as cash release of nuclear provisions, foreign exchange fluctuations and certain asset value impairments.

5.   Non-Budget:

  Items of expenditure which are included in the Estimate, but are outside of DEL and AME eg Grants in Aid, Royal Hospital Chelsea. This is a Parliamentary control but not a Treasury control.

6.   Total Net Resources

  This is the net of items 1 to 5.

7.   Capital Departmental Expenditure Limit (CDEL)

  This is for new investment, including Capital additions, disposals, and the capital repayment of loans.

8.   Capital AME

  Includes the capital element of the loan repayments for self-financing public corporations, such as QinetiQ.

9.   Total Net Capital

  This is the sum of the above capital items.

10.   Total Near Cash

  This is the total accrued expenditure spend and is the sum of Direct RDEL and Capital DEL.

11.   Request for Resources 1

  Provision of Defence Capability, provides for expenditure primarily to meet the Ministry of Defence's operational support and logistics services costs and the costs of providing the equipment capability required by defence policy.

12.   Request for Resources 2

  Request for Resources 2 provides primarily for the additional costs of peace keeping and operations. These are the net additional costs incurred: the costs that the Department would have incurred regardless of the operation taking place, such as wages and salaries are recorded against RfR1.

13.   Request for Resources 3

  War Pensions and Allowances, etc. provides primarily for the payments of pensions and allowances for disablement or death arising out of war or service in the Armed Forces after 2 September 1939, and associated non-cash items.

B. LIST OF ABBREVIATIONS USED IN THE ESTIMATE
AMEAnnually Managed Expenditure
CSRComprehensive Spending Review
DE and SDefence Equipment and Support
DSODepartmental Strategic Objective
EYFEnd Year Flexibility
FCOForeign and Commonwealth Office
GARGeneral Accounting Rate
HCDCHouse of Commons Defence Committee
MoDMinistry of Defence
NAONational Audit Office
NDPBNon Departmental Public Body
PSAPublic Service Agreement
RfRRequest for Resources
SSESpring Supplementary Estimates
SUMESingle Use Military Equipment
UORUrgent Operational Requirement
WSEWinter Supplementary Estimates


Annex 2

ARMED FORCES RETIRED PAY, PENSIONS, ETC WINTER SUPPLEMENTARY ESTIMATES 2009-10 ESTIMATES MEMORANDUM

REQUEST FOR RESOURCES 1—ARMED FORCES RETIRED PAY, PENSIONS, ETC

1.   Summary of Changes sought in the Winter Supplementary Estimate

  The main reason for the Armed Forces Retired Pay and Pensions Winter Supplementary Estimate is to increase the Appropriations-in-Aid (A-in-A) estimate by £50 million, with a corresponding increase in the current forecast of pension payments.

2. Detailed Explanation of the Change and Allocation

  The increase of £50 million resource is to increase the estimate in relation to the latest forecast of A-in-A.

3. Changes to Cash Requirement Allocation

  There is an increase in the net cash requirement of £1,000 as a result of these changes.







1   Hansard 25 March 2009 Column 18WS. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2009
Prepared 10 December 2009