Defence Equipment 2010 - Defence Committee Contents


Examination of Witnesses (Question Numbers 180-199)

GENERAL SIR KEVIN O'DONOGHUE, DR ANDREW TYLER AND MR GUY LESTER

1 DECEMBER 2009

  Q180  Chairman: Once you have decided how many to buy, how quickly can they be brought into service?

  General Sir Kevin O'Donoghue: I think pretty quickly. We are pulling off, as you know, up to 150 out of a total build of some 3,000. It is not like a UK-specific programme with all that design and development. That is going on at the moment. I do not think it will be that difficult. They will come off quickly.

  Q181  Chairman: I have said this before, and it is perhaps a bit mean, but we all know what "up to 150" means—it means fewer than 150, particularly nowadays with the pressure that there is on defence budgets. Do you have any sort of rough ballpark figure? If you were putting this "up to" figure into ministerial speeches now, what would be it be?

  Mr Lester: It would be up to 150, I think. One thing I can say is there has been some speculation that we have cut the number of JSF we are planning on buying, but we have not, so up to 150 is still right. There has not been a cut which is somehow buried within that figure.

  Q182  Chairman: But you know what you are planning on buying, do you?

  General Sir Kevin O'Donoghue: Up to 150.

  Q183  Chairman: You know what you are planning on buying. You said, "There is some speculation that we have cut the number of JSFs we are planning on buying."

  Mr Lester: What I am saying is that there are a lot of variables in how many airframes to do with how we train and what the capability of the aircraft turns out to be once we start trialling them, but what we have not said is this is a capability that we are going to cut the numbers against.

  Q184  Mr Jenkins: The interesting date about 2015 when we start ordering, do we have to put a total order in at that date or can we take them in tranches?

  General Sir Kevin O'Donoghue: We will take them in tranches.

  Q185  Mr Jenkins: You can order 30, 30, 30, over a period.

  General Sir Kevin O'Donoghue: Yes.

  Q186  Mr Jenkins: So the last order might be 2025, for instance.

  General Sir Kevin O'Donoghue: It could be. Of course, what is a huge advantage with Joint Strike Fighter is that when we bought Harrier we had to buy what we call the "attrition buy" as well—we bought a certain number of aircraft which included an attrition buy—but with Joint Strike Fighter, because it is such a big programme, we do not need to buy those until we need them. So, absolutely, it will go on for quite some time.

  Q187  Mr Jenkins: When we start ordering them, of course, there will be some trials, sea trials, for these things to land. We will not want large numbers; we will want a small number.

  General Sir Kevin O'Donoghue: We have ordered three. We have three on order, which are the OT&E aircraft (operational test and evaluation aircraft). They have been ordered. They will come in at 2012.

  Dr Tyler: They are being delivered into the test programme in the next a couple of years, yes.

  General Sir Kevin O'Donoghue: They will be flown by Royal Air Force pilots as part of the operational test and evaluation programme.

  Q188  Mr Jenkins: These three cannot land on the carrier because the carrier will not be there until 2015?

  Dr Tyler: They are going into a test programme in the US.

  General Sir Kevin O'Donoghue: They will join with the US Marine Corps with their STOVL aircraft as part of the test and evaluation programme.

  Q189  Mr Jenkins: We will be sending these pilots over to the US to get their training.

  Dr Tyler: During the test programme we will have our test pilots over there operating within an integrated test programme alongside the United States.

  Q190  Mr Jenkins: When do we intend to put the simulators in place in this category for the pilots?

  Dr Tyler: I do not know. I would have to come back to you on that.

  General Sir Kevin O'Donoghue: It will be sequenced so that we have the operational test and evaluation flight training programme, test programme. We will get the simulators in.

  Q191  Mr Jenkins: We have thought of ordering the simulators, unlike the Apache where we did not order the simulators for a couple of years, did we?

  General Sir Kevin O'Donoghue: Indeed.

  Q192  Chairman: I have no idea who is in charge of that.

  Dr Tyler: We do.

  General Sir Kevin O'Donoghue: May I interrupt you? On the carrier, one of the reasons we are being slightly hesitant over numbers is that there is a submission going through the MoD at the moment for a re-approval of the carrier costs. Our numbers are not clear at the moment, and they will not be clear until the IAB and Ministers have approved them, and that will be out fairly shortly. I would not want you to think that we are being evasive for the sake of it, but our figures are, as we speak, being refined and a paper submission will go through.

  Q193  Chairman: When do you think that paper will come out?

  Dr Tyler: A small number of weeks.

  General Sir Kevin O'Donoghue: I think it will go to the IAB in December, this month.

  Q194  Chairman: So it will go to Ministers in, what, January?

  General Sir Kevin O'Donoghue: At the latest, I would imagine, yes.

  Q195  Chairman: And it will be made public?

  General Sir Kevin O'Donoghue: Yes, it will feature in the MPR10.

  Q196  Chairman: When is that going to conclude?

  Dr Tyler: The numbers close at the end of this financial year. You will first see it in the Ministry of Defence's accounts and then you will subsequently see it in the MPR.

  Q197  Chairman: Not meaning to use rude words, the Bernard Gray report says that the planning process is broken, badly broken. Would you disagree with that?

  General Sir Kevin O'Donoghue: No, I do not think it is broken. I think there would be better ways of doing the planning process, and I do not think I would disagree, I think we might have to get the budget in balance with the requirement. We have to get our cost estimation much better to give to the programmers so that they have got a clearer idea of what the overall through-life cost will be of some of these programmes.

  Dr Tyler: One of the challenges we will always have with the larger programmes, the more complex programmes, is that the costs of those programmes does genuinely mature through time. For many years there was a lot of uncertainty as well as a lot of risk in the programme, which is always going to challenge the costing. That is not to say we cannot do better, because I definitely think we can. In the case of the carrier, for example, one of the things that we did was we pushed Main Gate as far right as we could but we also said that we would agree the final target cost, the cost against which industry is going to be ultimately incentivised. We would agree that two and a half years after Main Gate, and that will be June of next year where we will strike a final target cost which will be the number, if you like, it will be the noose around the neck of the CVF Alliance in terms of delivery, and for me that seems like a very sensible way, and very consistent with Bernard Gray's report, to get oneself to a point where you really have got a thoroughly good understanding of what it is you are buying and the risks associated with it and you have got rid of a lot of uncertainty, as opposed to the risk, to then being able to confirm and stick to a number. One of the things that we have constantly done to ourselves over the years (and it has been self-inflicted harm in many ways) is trying to commit ourselves to a number long before we really credibly should be able to.

  Mr Lester: One of Bernard Gray's criticisms in relation to the planning process was some of the behaviours it engenders. I think there he was quite shrewd. A lot of the measures we are taking to improve our process are about sorting out behaviours and forcing us to be more honest, I guess, and making it less prone to vested interest is too strong a term, but to make sure that we have robust—

  Q198  Chairman: Perverse incentives would be fair, would it?

  General Sir Kevin O'Donoghue: Yes.

  Mr Lester: Perverse from the wider defence point of view. It probably would be fair, yes.

  Chairman: And that is not vested interests!

  Q199  Mr Jenkin: Can I ask about how planning rounds operate? Is one of the reasons the programme has got overheated because there has been too much wishful thinking about programme costs in order to squeeze them through the Treasury mangle, and the only way to get the Treasury to sign things off is to pretend they are going to be cheaper than they are?

  General Sir Kevin O'Donoghue: No, I do not think that is correct. There is certainly what, you will remember, Peter Spencer used to call the conspiracy of optimism, but I do not think it is to get through the Treasury. It is a genuine lack of understanding about what things will really cost, and that is why—what I was talking about earlier—the cost estimation process that I have down in Abbey Wood, which I hold on behalf of the Department as a whole, has to be able to give independent costings which everybody then accepts and people do not shave bits off because, with a bit of luck, the risk will not materialise. It is accuracy in costing, sticking with that cost, putting in management risk funding because it will certainly materialise as the project unfolds.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 4 March 2010