3 Procurement reform
Background to the Gray review
70. In December 2008, the then Defence Secretary,
Rt Hon John Hutton MP, commissioned Bernard Gray to assess what
steps the MoD was taking to reform its procurement process and
to suggest further recommendations for how that process could
be improved. Gray's report was published on 15 October 2009 and
concluded that:
The Department's commitment to improvement in acquisition
is genuine and progress in some areas has been significant. Nonetheless,
the Ministry of Defence has a substantially overheated equipment
programme, with too many types of equipment being ordered for
too large a range of tasks at too high a specification. This programme
is unaffordable on any likely projection of future budgets.[169]
Bernard Gray told us that he believed that the problems
had existed over a long period of time. He explained that over
the past 40 or so years, Defence Reviews had been used to bring
the programme back under control and that the problems which had
developed since the 1998 Strategic Defence Reviews were "just
the most recent example of a systemic problem".[170]
Industry witnesses to our inquiry welcomed the Gray report, saying
that "it rightly identifies the imbalance that exists between
the programme and the budgets and the need to address that issue".[171]
71. We commend the Government
for commissioning, and then publishing, the Gray report. In doing
so the Government was being refreshingly open. We hope that the
MoD will follow this approach on other occasions.
DE&S response to the Gray
report
72. The Secretary of State announced the publication
of the Gray report on 15 October 2009, and at the same time listed
a number of actions which the MoD intended to take in response
to the report. The MoD published its acquisition reform strategy,
The Defence Strategy for Acquisition Reform, on 3 February
2010.[172] We discuss
those actions and the reform strategy in paragraph 113. In the
following paragraphs, we review some of the evidence which we
heard from DE&S witnesses, with regard to their reactions
to the report.
73. The Gray report noted that it had "worked
to establish a basis of agreed facts with the Department"
in a number of areas relating to the equipment programme and the
levels of time slips and cost overruns.[173]
It provided the following assessment of the extent to which the
equipment programme was now 'overheated':
From a possible universe of around 150 programmes
for which significant data exist, a floating sample of just over
40 where the data are the most complete have been the focus of
attention to try to establish patterns.
The overall picture may be familiar, but it does
not look pretty. On average, these programmes cost 40% more than
they were originally expected to, and are delivered 80% later
than first estimates predicted. In sum, this could be expected
to add up to a cost overrun of approximately £35 billion,
and an average overrun of nearly 5 years.[174]
74. Some DE&S witnesses did not accept the
quantitative data in the Gray report. CDM said that "there
is not a lot of evidence" for the figures,[175]
Guy Lester said that DE&S disagreed with some of the assumptions
behind the figures[176]
and Dr Andrew Tyler said that Gray's figures were based on generalisations
from a very small sample of projects.[177]
However, DE&S witnesses broadly supported Gray's qualitative
analysis. CDM told us that he accepted the equipment programme
was overheated.[178]
Guy Lester said that "we totally accept the analysis in Bernard
Gray's report, which is that all sorts of things of things
are dependent on having a more balanced programme than we have
at the moment".[179]
Dr Andrew Tyler agreed, saying that "qualitatively I think
we would agree with the vast majority of Bernard Gray's conclusions;
once or twice I have described them as 'glimpses of the bleeding
obvious'".[180]
The Minister for Defence Equipment and Support appeared to be
less convinced. He told us that "Some of his judgements I
found persuasive, some of his judgements I found less persuasive;
some of his recommendations I thought attractive, some of his
recommendations I thought less attractive".[181]
75. Bernard Gray described to us the process
which his review team had used to collect and analyse MoD data,
to discuss draft conclusions with MoD staff and to agree subsequent
presentation of the data in the report. He said that:
As far as we are concerned, any questions we were
asked, any issues that were raised, were answered in that process,
which was substantially complete by early July and, to our knowledge,
the people who are in charge of numbers inside of Abbey Wood and
in MoD Main Building are in agreement with us about our numbers.[182]
Bernard Gray said that there did not appear to be
a "wholly singular view" within the MoD as to whether
the equipment programme was unaffordable:
There are a substantial number of people, and I believe
that includes the Secretary of State and Lord Drayson, for example,
who accept the analysis in this report and are intending to do
something about it. There are other people, some of whom came
and talked to you, who appear, as far as I can tell, to think
that there is not a problem, so I do not think there is a single
view inside the Ministry of Defence.[183]
Lord Drayson told us that CDM, and the whole ministerial
team were all agreed with regard to the importance of implementing
Gray's recommendations "with full vigour" and that there
was "clear ministerial focus around the reform process".[184]
76. The Gray team attempted
to establish a basis of agreed facts with the MoD, but, despite
the fact that MoD staff provided the data to the review team and
were given the opportunity to review early drafts of the report,
some key senior individuals in DE&S told us that they did
not accept the data presented in the report. Whilst we welcome
the willingness of DE&S openly to consider the qualitative
recommendations of the Gray report, we are concerned that the
lack of agreement within MoD on the extent of the problem forms
a poor basis on which to build effective reform. We return to
the issue of implementation of Gray's recommendations in paragraph
113.
77. The Gray report included a summary of around
50 specific recommendations and related these to three main areas
of concern:
- balancing the equipment programme
and keeping it in balance;
- providing better leadership and separating and
clarifying roles and accountabilities between the MoD Centre and
DE&S; and
- injecting key skills and tools into DE&S,
possibly through a partnership with a private sector programme
management organisation.[185]
We consider each of these issues in turn in the following
paragraphs.
Balancing the equipment programme
78. We discussed the issue of the funding gap
in Chapter 3 and referred there to the conclusion in the Gray
report that the equipment programme was significantly out of balance
with funding projections. In this section, we review Gray's analysis
as to why the programme became out of balance, and his recommendations
for reform. Bernard Gray told us that he used the phrase 'out
of balance' to mean that "the proposed equipment acquisition
by the MoD is substantially in excess of any likely projected
future funding", meaning that either there was substantial
under-funding or excessive demand.[186]
REGULAR STRATEGIC DEFENCE REVIEWS
79. The Gray report suggested that a key reason
why the equipment programme had become out of balance was because
the full cost implications had not been fully spelled out at the
time of the 1998 Strategic Defence Review. At that time, the partial
cost estimates for some significant components had "pointed
to significant, and unaffordable, bulges in equipment spending
beyond the formal 10-year planning horizons of the MoD",
but the view had been taken by all concerned "that some kind
of 'bow wave' had existed within the equipment programme for a
long time, and that its effects had always in the end been smoothed
out". It concluded that "with the benefit of hindsight
it now seems clear that the very existence of this bow wave is
itself a significant contributor to the problems that have plagued
defence procurement over a long period" and that:
In reality the bow wave allows the MoD to maintain
a position that a whole variety of defence capabilities are in
the process of being procured. This feels reassuring to the country
about the size and scope of Britain's Armed Forces, but behind
this comforting thought is the cold fact that the budget does
not exist, and has arguably not existed since the end of the Second
World War, to support this level of ambition.
The policies of successive governments, and a lack
of political will to present to the electorate the unpleasant
reality of the position, has been a significant force behind this
double-think.[187]
The Gray report commented that "there is worrying
evidence that the problems are not just an endemic burden, but
that they are an accelerating problem" and that "the
problems of prior years are compounding with the problems of current
years to produce an increasing rate of delay and cost increase".
It also suggested that it was not possible to be precise about
the time at which problems would "start to compound at a
catastrophic rate", but that "it does not feel very
far away".[188]
80. The Gray report stated that "Some military
planners have argued that efforts to update their detailed plans
have been hampered by the lack of a new strategic framework in
which to set their ideas" and that "In corporate life,
no enterprise should persist with a 12 year old strategy without
at least re-evaluating it fully on a regular basis". It recommended
that "a Strategic Defence Review process be conducted on
a regular 4 or at the most 5-year basis" and that this "should
be enshrined in legislation to ensure that incoming governments
did not try too easily to slip out of any difficult examinations
of these issues".[189]
The Secretary of State has accepted this recommendation.[190]
81. Industry witnesses welcomed the proposal
to conduct regular SDRs, but also expressed concern that the scope
of the SDR would have an overly narrow focus, pointing out the
importance of maintaining an up-to-date Defence Industrial Strategy
to enable industry to make the necessary long term commitments
to technology, skills and resources to provide the required defence
equipment. Ian Godden, Secretary to the Defence Industries Council
and Chairman of ADS Group Ltd, said that "there is a fear
that
the next Strategic Defence Review and Defence Industrial
Strategy will simply focus on procurement reform and not deal
with the other very important strategic matters about capability,
operational sovereignty and the need for an industrial base, and
that this becomes the focal point and wrongly so."[191]
Ian King agreed, saying that "We are concerned that the Green
Paper will be done in the absence of looking at what the industry
provides as part of the Defence Review".[192]
Industry witnesses also expressed concern about the impact of
the inevitable period of uncertainty on small and medium sized
enterprises (SMEs) in the defence industry. Dr Sandy Wilson pointed
out that:
Very few SMEs are sitting with fat order books with
several years of sales that allow them to weather any reduction
in order output by a principal customer such as MoD. Therefore,
the SDR really ought to be conducted on a timescale which does
not have a terribly deleterious effect on their business. One
fears that when we get into the purdah that is always associated
with an SDR there will be some fallout, especially in the SME
community, and it will cascade down through the primes, the mid-tier
and finally hit hardest those who are least able to cope.[193]
82. The Gray report concluded
that the MoD's budget is insufficient to deliver its planned procurement
programme, and that there is an accelerating issue of the problems
of prior years compounding to produce an increasing rate of delay
and cost increase. Witnesses from the MoD and from industry accepted
this analysis and the need for urgent action to rebalance the
equipment programme.
83. We welcome the commitment
from MoD ministers to establish regular Strategic Defence Reviews
in order to maintain an up-to-date strategic context for the equipment
programme. There is a risk that more frequent SDRs could undermine
the longer term planning of the equipment programme and the MoD
must establish ways to manage this inevitable tension. We note
the concerns of industry representatives that the next SDR and
the next version of the Defence Industrial Strategy will be focused
too narrowly on procurement reform, and urge the MoD to ensure
that wider capability and industrial issues are also addressed,
so as to ensure that industry can make the necessary long term
commitments to technology, skills and resources. We would welcome
more information on the extent to which the industry partnering
proposals set out in Chapter 6 of the Defence Acquisition Strategy
have already been developed, and the anticipated scope of their
contribution to achieving greater value for money in defence.
We also request an explanation as to how the partnership arrangements
will be reconciled with the commitment given in the Green Paper
for greater transparency. Our successor Committee may wish to
return to this issue and to consider the implications of such
industry partnerships for the future role of Parliamentary scrutiny.
TEN YEAR ROLLING BUDGET
84. The Gray report recommended that "the
MoD's budgeting should be moved from the current short-term cycles
to a ten-year rolling budget". It stated that:
The deal across government should be that the MoD's
programme should be brought into a genuine and transparent long-term
balance, reported to Parliament and externally audited, and in
return the MoD should be funded on a long-term basis that allows
it to manage effectively.[194]
The Secretary of State did not commit to the proposal
of a ten-year rolling budget for the MoD, but announced that the
equipment programme would be planned to a longer time frame "with
a ten year indicative planning horizon for equipment spending
with Treasury".[195]
Bernard Gray acknowledged that there were constraints on what
government could commit to,[196]
but described the ten year indicative planning horizon as "a
sort of promise with one's fingers crossed"[197]
and said that he would have preferred to go further.[198]
Lord Drayson agreed, saying that "Certainly it is not the
same as a legally binding commitment, but I think it is important
progress". Sir Bill Jeffrey suggested that it would not be
realistic to expect Treasury to make a more absolute commitment
but that the provisional agreement on a ten year indicative planning
horizon was nevertheless "a real step forward".[199]
Lord Drayson explained the benefits of creating a ten year framework:
it is about giving the Ministry of Defence
the ability to take decisions in terms of the flexibility of spending
between projects such that they can cope with the reality of the
nature of defencethe enemy changes its tactics, technology
changes, inflation may changebut at the same time having
the confidence that it can do that within an overall planning
envelope for the equipment plan as a whole, which is acceptable.
That is not the way it is done at the moment, it is done by Treasury
approval on specific projects
[200]
Lord Drayson said that an agreement had been reached
in principle with the Treasury, and that more details would be
published with the strategy for acquisition reform.[201]
85. Industry witnesses supported the proposal
to have a longer term budget framework. Ian Godden said that industry's
view was that a longer term planning commitment was "long
overdue". However he pointed out that if, the budget commitment
was to be set at a time of depressed economic conditions, "you
get into an argument about whether the cyclical nature of the
economy and the needs of the nation have been cemented in at the
wrong time". He explained that:
We would assume a ten-year plan is then refreshed
quite regularly as most ten-year plans can never survive the ten
years. The idea of an SDR every five years and a DIS as a follow-through
to that is a sensible thing to do with a ten-year programme where
you can make decisions about bringing things in and out of it
and have to adjust, as all corporations do, to changing circumstances."[202]
Sir Brian Burridge, Vice President Strategic Marketing,
Finmeccanica UK Ltd agreed, explaining that "There needs
to be a much clearer view of what proportion of national wealth
is a government willing to commit to defence and security."[203]
86. We accept that there are
wider constraints which limit the Government's ability to make
a firm ten year commitment with regard to the MoD's budget. We
consider, however, that the fact that other Government departments
would demand the same treatment would be not be a reason for the
Government to resist it. The scale and nature of MoD contracts
is quantitatively and qualitatively different from other Government
procurement. It is clear that greater financial stability could
help to control and reduce the hundreds of millions of pounds
of unproductive costs which are incurred annually to keep the
equipment programme spend within each year's budget. We welcome
the proposal to introduce a ten year planning time-frame for equipment
expenditure but we doubt that the proposed ten year planning horizon
will provide sufficient certainty to stabilise the equipment programme.
We recommend that our successor Committee returns to this issue
when further details about HM Treasury's agreement with the MoD
are made available.
SCRUTINY AND TRANSPARENCY OF THE
EQUIPMENT PLAN
87. The Gray report recommended that the costings
in the equipment programme and the veracity of the estimates be
subject to independent audit by a major accounting firm; and the
audit report published. The MoD advised us that the NAO had agreed
in principle to conduct such audits, starting with the SDR, and
that it was now developing a proposed approach.[204]
88. Lord Drayson described the proposed increased
transparency about the equipment programme as "a critical
component of a reform package", saying that:
Clearly, it has to be done within the constraints
of national security and, in some cases, relating to commercial
confidentiality, but the more that we can have transparency about
the acquisition process, the more effective I believe it will
be.
The MoD's acquisition reform progress report listed
one of its eight commitments as "Establish a ten-year planning
horizon and increase transparency", and recorded the status
of this task as "On Track. Ministers, HMT and Cabinet Office
have agreed that MoD will annually share its assessment of affordability
with the HCDC". However, it listed no activities to provide
wider public scrutiny, nor any other measures to increase transparency.[205]
89. The MoD told us that it
had asked the NAO to audit its assessment of affordability of
the equipment programme. We welcome this and seek an assurance
from the MoD that the NAO will be given access to all of the relevant
technical and commercial data necessary to do this job properly.
DE&S has accepted that its cost estimating has been poor and
such independent scrutiny will be necessary to provide evidence
that the new iteration of the equipment programme resulting from
the SDR is closely matched to available resources.
90. Whilst we also welcome the
commitment by the MoD that it will annually share its assessment
of affordability with us, we note that this falls well short of
the Gray report's recommendation that the annual audited assessment
should be made public. Transparency is not a practice which has
traditionally been embraced by the MoD. Although the MoD has identified
increased transparency as one of the commitments in its strategy
for acquisition reform, it has provided no details of any concrete
steps or milestones for realising that ambition. We ask the MoD
to provide us with a description of the specific measures it plans
to take in order to ensure greater transparency. We also ask the
MoD for an undertaking that it will provide our successor Committee
with accurate and complete responses to its requests for information.
INCREMENTAL DEVELOPMENT
91. The Gray report suggested that one of the
benefits of a balanced equipment programme would be to facilitate
the use of "sensible processes such as 'spiral development'
and 'technology insertion' which were heavily discouraged by the
current overheated programme". It proposed that:
Development risk (and hence cost overrun/delay) could
be reduced by introducing equipment into service, with space allocated
within it to introduce more sophisticated technologies later,
and to learn from using the equipment rather than trying to guess
at all ends before the first of type is ever fielded. But bitter
experience shows that any restraint shown in this way will be
punished by the loss of uncommitted budget to some other more
immediate requirement at a later date. 'Bid High Spec, Bid Full
Spec', seems to be the encouraged behaviour, however much technical
risk that this imposes.[206]
92. Industry witnesses agreed that benefits could
result from an incremental development approach. Dr Sandy Wilson
said that:
we could do a lot more to deliver earlier an initial
capability which could then be onward developed through a spiral
development process. This has a tremendous advantage of eliminating,
or at least reducing, vast swathes of risk that go in the greater
the complexity of your target. This leads to faster acquisition,
probably better value for money and automatically even improves
exportability of the product at the end of the day."[207]
Sir Brian Burridge described the example of Typhoon
which had come into service with very basic operational capacity
and then been upgraded.[208]
Witnesses said that it would not necessarily be appropriate for
all platforms or across all technologies; saying "there could
be could be no 80% solution for body armour for example",
but that there were other areas such as armoured vehicles and
communication systems which were appropriate.[209]
Sir Brian Burridge explained that "the ability to do spiral
development does depend on the nation's ability to maintain the
skill base in its engineering industry.
just doing support
availability contracts on a support basis does not necessarily
preserve the highly skilled aspects of systems engineering, of
design engineering and of development engineering. These are very
important aspects in being able to do spiral development."[210]
93. The Gray report proposes
that development risk, and hence time and cost overruns, could
be reduced by introducing equipment into service with an initial
operating capability which could then be upgraded. Industry witnesses
agreed that acquisition could be faster, provide better value
for money and greater export potential if this approach were to
be taken, provided that steps were taken to ensure that the engineering
industry skill base was maintained. We recommend that the MoD
provide us with an evaluation of the scope for using an incremental
approach, setting out the steps it will take to overcome the obstacles
to this approach which were outlined in the Gray report.
Clarifying roles and accountabilities
94. The second group of recommendations in the
Gray report related to ways of improving MoD leadership and decision-making
processes in order to ensure that the equipment programme stayed
in balance. With regard to the planning of defence capability,
the Gray report identified a number of underlying factors driving
the unaffordability of the equipment procurement and support programmes
and other problems with the current planning and financial control
processes. It stated that, whilst cutting back programmes might
bring the equipment programme back into balance, there were "serious
and deep-rooted behavioural and organisational issues that will
drive again towards unaffordability". In oral evidence, Bernard
Gray described the MoD's decision-making processes for keeping
the equipment programme under control as "dysfunctional",[211]
and said that:
the behaviour of putting things in the programme
and slowing everything down is endemic and it is expensive and
they do not, systematically at least, understand how much that
actually costs them.[212]
95. The Gray report made a number of recommendations
to improve leadership, decision-making and accountability, one
of which was the formation of an Executive Committee of the Defence
Board. The Executive Committee would be chaired by the Permanent
Secretary and would be accountable for an affordable Equipment
Programme. Bernard Gray explained that:
the attempt to make the Permanent Secretary
legally responsible to Parliament for a balanced programme
is an effort on our part to force him to say no to people who
want things in the Department that the Department cannot afford
[213]
With regard to improving the performance of equipment
and support delivery, the Gray report recommended that the original
Smart Acquisition principle of a clear distinction existing between
customer and project deliverer should be reasserted, and that
a real customer-supplier relationship should be created between
the capability sponsor (MoD centre) and project delivery (DE&S).[214]
It also recommended that aspects of the approval process be revised
to improve decision-making[215]
and that further cost reductions within in-service support be
pursued and the aspirations of through life capability management
(TLCM) be reappraised.[216]
96. Industry witnesses agreed that there was
room for improvement in the MoD's decision making processes. Ian
Godden told us that "decision-making between Armed Forces
and procurement, or customer, for industry is very often too lengthy,
is quite often unclear or unstrategic, and therefore gets reversed
or can have a period of uncertainty created around it, and that
aspect of the decision-making and the clarity of decision-making
and direction is something that we believe does need to be tackled."[217]
Sir Brian Burridge described a tendency for "tribal rivalry"
among the individual Services which led to a lack of strategic
thinking, a tendency to generate complexity in decision-making
and a failure to recognise time was cost; and he pointed out that
"these behaviours which either leave decisions tenuous or
unmade have a cost to them".[218]
The MoD advised us that it had already implemented Gray's recommendation
to create a Defence Board Executive Committee, and that the first
meeting had taken place in November 2009. It also stated that
other proposals were being developed to improve project initiation
and control and to "sharpen" relationships.[219]
97. One of the three key areas
of weakness identified by the Gray report was the lack of clarity
and leadership from those in charge of the MoD, which resulted
in poor decision making processes and an inability properly to
keep the equipment programme under control. The Gray report concluded
that, even if the equipment programme were to be brought back
into balance by the next SDR, poor leadership and decision-making
processes would soon cause old problems to return and the programme
again to become unbalanced. We note that the Defence Acquisition
Strategy includes a number of specific actions to improve leadership
and decision-making and the MoD should provide us with a progress
report on these activities.
THROUGH LIFE CAPABILITY MANAGEMENT
(TLCM)
98. TLCM seeks to harmonise and maximise defence
output by ensuring that all areas of defence activity that have
an impact on one another are considered together. It aims to ensure
that capability delivery is viewed at a more strategic level rather
than just the delivery of individual new equipment projects or
individual in-service capabilities. The Gray report noted that:
A large number of factors exist from relatively early
in a project's lifecycle that later lead to delay and increased
costs. This includes the failure of the Department to consider
whole life costs on a regular basis
These effectively hide
true costs and store up problems for later in a projects life
[220]
However, the report described TLCM as "fearsomely
complex" and "fraught with potential pitfalls in practice".
The key problems it identified were a lack of financial data and
financial management skills available to members of Programme
Boards; the tendency for TLCM to blur lines of accountability
(made worse by rapid rotation of staff through posts); and an
environment within the MoD which did not support the concept of
increasing short-term spending to gain economies in the longer-term.
It recommended that "TLCM should be considerably simplified,
and financial modelling tools should be imported along with the
staff capable of using them to allow the system to make choices."
The NAO Major Projects Report 2009 made a similar assessment.[221]
99. Industry witnesses supported the use of TLCM
and were of the view that its aims were achievable, but that DE&S
was aiming too high too soon, for example by trying to trade across
lines of development.[222]
CDM told us that creating DE&S as an entity had made TLCM
easier to deliver, but that "It is not easy; it needs working
at.
but the prize is well worth seizing for Through Life
Capability Management and I do not agree that it is as complex
as Bernard Gray suggests."[223]
Vice Admiral Lambert said that "I think that Bernard Gray
highlighted a real risk that we can, or could, over complicate
these issues
in response to Bernard Gray, I would say that
we are aware of the risks and we are trying to manage them".[224]
The Minister for Defence Equipment and Support agreed.[225]
100. The Gray report recommended
that the MoD's aspirations for Through Life Capability Management
(TLCM) be reappraised. Witnesses from industry and the MoD were
unanimous that TLCM was the right way to proceed, in order to
support the making of sound decisions. However, evidence from
the Gray review and from industry indicates that the MoD's TLCM
approach is incomplete and over-ambitious. We note that both the
Gray report and the NAO identified a lack of financial tools and
data as significant factors affecting the implementation of TLCM.
We ask the MoD to provide a report setting out the progress it
has made in addressing these issues, and in particular the progress
made on the specific activities described in the relevant section
of the Defence Acquisition Strategy.
Injecting key skills and tools
into DE&S
101. The third group of recommendations in the
Gray report related to the need to improve skills within DE&S,
and ways in which the necessary skills improvements might be achieved
via some form of private sector partnership. The report concluded
that DE&S "needs significantly greater skills and tools
in a number of areas if it is to be able to deliver effectively
on a better-balanced programme". It specifically identified
a need for a greater level of resources and skills in programme
and project management, finance, cost estimating, engineering
and contracting, and for better project management and management
information systems.[226]
It added that the skills shortages were "exacerbated by the
current rotation system for military personnel and civil servants,
which has created a situation where mobility is prized/required
and tenure is short".[227]
The Gray report identified a lack of continuity of staff in positions
of responsibility as a "key concern" and commented that
this contributed to a lack of accountability for project performance
over the long-term; an increased reporting/briefing burden; a
loss of context and knowledge; and a loss of working relationships.
It compared the tenure in post for 30 team leaders of large projects
being managed by DE&S with that in 2003 and concluded that
the tenure of project leaders had decreased significantly over
the past five years.[228]
STAFF SKILLS
102. CDM told us that he accepted that there
was a shortfall of relevant skills in DE&S.[229]
He accepted that cost estimation needed to be improved and cost
estimation tools used more widely across the Department, saying
that the equipment programme was overheated partly because of
inadequate cost estimation and partly because "our aspirations
are always much greater than the money we have available".[230]
He explained that DE&S was seeking to improve its skills in
four main areas: cost assurance (including cost forecasting, cost
engineering and cost certification); technical assurance; financial
skills; and complex programme management.[231]
However, he added that "as far as project management is concerned,
DE&S is the best in government, and I am not too sure we are
not the best across industry as well".[232]
He said that "I have in my organisation 700 people with project
management qualifications, external civilian project management
qualifications. That is a pretty good record."[233]
103. Bernard Gray told us that he had discovered
that half of the management accounting jobs in the Finance Department
of DE&S were not filled by qualified accountants, and that
the explanation of the Finance Director had been that he was unable
to pay sufficient salary to attract qualified accountants into
those jobs.[234] Sir
Bill Jeffrey said that it was always going to be hard to compete
with the outside world, but that "the trend in recent years
had certainly been towards the professionalisation of the finance
function right across the MoD."[235]
104. Industry witnesses told us that they believed
there was a shortfall in skills within DE&S, and that this
was part of a wider skills problem. Ian Godden said that:
There is a shortage
of skill-base in programme
management, systems engineering and equivalent, and you can see
that across many industries in the West
it is not just
a UK problem. Overall there is a shortage of high skill in that
area, but the skill level within DE&S and equivalent is lower
than you would expect and is lower than necessary."[236]
He added that:
As I survey the four sectors I am involved incivil
aviation, defence, civil aerospace and security
the demands
on that type of skill are increasing over time, and with the civil
nuclear coming into that equation quite dramatically, there is
a real risk of a further skill drain out of the traditional defence
sector, particularly because
[people] are beginning to
fear that the security, space and civil nuclear are much better
future careers for them because it has got growth, it has got
expectations of more money, it has got more research etc and there
is therefore a belief that defence has got this risk of being
stuck in a box and not going anywhere."[237]
Dr Sandy Wilson agreed, saying that:
It is not just an MoD versus defence industry issue.
In fact as we progress into the reinvigoration of nuclear energy
in this country, we are going to find a whole gamut of technologists
being required across a much wider industrial landscape than we
currently have in defence, and they are the same skillssystems
engineering, complex contracting
, programme management.
As other industries come up in importance that is going
to be a greater problem, and it speaks to us having to have a
skills strategy that feeds all of those industries over the next
ten to 20 years."[238]
105. Ian King agreed that there was a salary
differential between industry and MoD but denied that MoD trained
staff would necessarily move to better paid jobs in industry.
[239] Sir Brian
Burridge suggested that acquisition reform over the years had
changed the skills needs within the MoD away from contract writing
skills towards a more commercial approach. He said that "the
challenge for the MoD is to get the commercial experience; the
challenge for industry is to understand the user better".[240]
Ian King pointed to the need for a long term commitment to training,
saying that "You
have to put in training schemes,
you need a skills strategy and there has to be a commitment to
meet these training schemes, because there is not a surfeit of
these types of people with these skills sets
. It is a really
long-term commitment."[241]
He also said that this long-term commitment would need to underpinned
by "a proper SDR which then determines the Defence Industrial
Strategy and that allows us to invest, because it takes a long
time to train these people."[242]
He told us that there were already joint training schemes available
both to the MoD and to industry.[243]
Sir Brian Burridge added that:
Following the creation of the Defence Academy and
real focus on acquisition skills, I think it has moved a long
way since the days when it was the Royal Military College of Science
focusing purely on weapon technology. I think there is some very
good management training available. No doubt it is proving difficult
for the MoD to release people. We release people and it is difficult
for us as well but you have to make that investment.[244]
106. The skills required by project and programme
managers in the defence industry are particularly specific which
means that they are not interchangeable with those in other industries.
In a review of education in defence systems engineering, the Defence
Engineering Group (1991-2004) at University College London have
commented that:
the delivery of an education in defence systems
engineering presents a difficult challenge. Defence systems engineers
must have not only a sound knowledge of a broad range of engineering,
analytical, management and military topics relevant to their equipment
projects, but also an overarching understanding of how these topics
and their multiple interactions affect the acquisition process.[245]
STAFF ROTATION
107. CDM did not accept that there was too much
staff rotation. He told us that he did not perceive a problem
with regard to the movement of staff,[246]
he did not believe it had increased,[247]
and that he did not recognise the figures on staff rotation quoted
in the Gray report.[248]
He explained that "The reason the military are there is to
bring current operational experience, and it is less important
that they stay there forever. Civil servants are the continuity,
they actually produce that deep continuity and the understanding
of business."[249]
He said that some staff had been moved away from the project teams
they were originally on to work on UORs[250]
and Dr Tyler suggested that there appeared to be more changes
than had occurred in reality because of changes in job titles
and project team boundaries which had resulted from recent organisational
restructuring.[251]
Sir Bill Jeffrey told us that he had seen some analysis that the
staffing arrangements were steadier than Gray had suggested, but
added that "we probably need more continuity that we have
even now".[252]
Lord Drayson described some of the ways in which he planned to
reduce staff rotation:
I feel this is an issue which we need to look at
very carefully indeed. I have asked the chiefs of the Services
to take very seriously the idea that they should be flexible in
their career planning within the Services to ensure that those
people posted into defence procurement, particularly into major
IPTs [integrated project teams], are posted with sufficient flexibility
that they can make sure that they are able to effectively carry
out that role.[253]
STAFF NUMBERS
108. As part of the PACE (Performance, Agility,
Confidence and Efficiency) programme launched by DE&S in March
2008 to transform DE&S into a more effective organisation,
DE&S staff numbers have been reducing from around 27,000 in
2007-08 to a target of 20,000 by 2012. In our Defence Equipment
2009 Report, we expressed some concern that DE&S was pushing
ahead with this streamlining programme, given that procurement
performance had declined in 2007-08.[254]
CDM confirmed to us that reductions in staff numbers were still
planned, saying that "I believe that DE&S can come down
to a figure of 20,000we are at about 22,000 now; but
we must spend money on re-skilling and up-skilling if we are to
get down to those sorts of numbers."[255]
He explained that one of the consequences of the programme was
that some of the work previously done by DE&S was being outsourced
to industry.[256]
PRIVATE SECTOR INVOLVEMENT
109. The Gray report suggested that the best
way to provide the necessary injection of skills and tools into
DE&S would be "through a partnership with a private sector
programme management organisation, of the type operating in civil
engineering and other complex engineering fields". It stated
that "The suggested route to achieve this is through a Government-owned,
Contractor-operated (Go-Co) entity", but that "At the
very minimum it [DE&S] should become a Trading Fund".[257]
Bernard Gray told us that the review team had considered five
principle types of business model: next-steps agency, trading
fund, outright privatisation, Go-Co, and leaving DE&S as it
is.[258] He said that
the team's central assumption had been that the Go-Co would be
the best operating model, but that further work was necessary
in order fully to understand the implications.[259]
With regard to the trading fund option he said that:
A trading fund would have the advantage of ensuring
that there was clarity between the requirements community and
the head office on the one hand and DE&S, as deliverer of
the programme, on the other.
the trading fund would give
some management freedom of action to the trading fund chief executive,
but not as much as a Go-Co would, so it would be a step in the
right direction, in my view, but maybe not far enough.[260]
110. Ian Godden described the Go-Co proposal
as "a mechanism to get an electric shock through the system",
but said that it was industry's view that it would not be a "very
practical" answer.[261]
Ian King explained the issues:
If we are talking about some Go-Co, so you are talking
about this fantastic organisation that has got all these commercial,
these programme management, these financial skills as specialist
to the area, all of which we debated earlier and which are in
short supply, where is this going to come from? What benefit are
we going to have from putting somebody between industry and the
MoD when, if you look at the real things which are showing progress,
the real things which are showing value, these availability contracts,
these partnering structures, if we think of how the munitions
programme is now structured, the terms of business around naval,
that is the way forward rather than putting some artificial interface
in the way.[262]
With regard to the creation of a Trading Fund, Sir
Brian Burridge said that:
It will take a long time to create a trading fund
out of the structure that they have already, and it does provide
the one advantage, necessity even, that a Go-Co does not. Under
a Go-Co structure I was hard pressed to understand how, say, the
Permanent Under Secretary as the Accounting Officer would exercise
his accountability because so much of decision-making would potentially
be outside his purview and I think he would have a very difficult
time justifying a programme, say, in ten years' time that was
run under a Go-Co arrangement.[263]
111. Lord Drayson said that he had rejected the
Go-Co option because he believed it vital that the military were
fully involved in the process of defence acquisition, and that
defence acquisition should not be seen as a semi-detached activity
from defence. He explained that "Therefore, I believe that
what we should do, and what we are doing, is implement the changes
to get the advantages that you would get from a Go-Co structure:
common project management tools, improved skills, a clear project
management charging structure between the people responsible for
the projects and the people who are the customers for the project."[264]
He added that the trading fund option was still "on the table",
but that it would also have "some of those disadvantages
in terms of putting it slightly at arm's length."[265]
112. Over the years we have
highlighted the need for key skills in acquisition and procurement,
and have received reassurances from the MoD that appropriate training
programmes were in place. However, we are unconvinced that DE&S
has a properly effective strategy for the training and education
of its staff, and believe that it has failed to prioritise this
issue. Project leaders in DE&S must have an understanding
of all of the military, technological, industrial and political
issues which impact on their projects. What is required is not
only the provision of appropriate training, but also a longer-term
commitment to career management which is organised to suit efficient
acquisition, not just military needs, and a recognition that key
project staff have to be released from time to time to attend
proper education and training. The MoD should provide an update
on the progress it has made with regard to the actions described
in the Defence Acquisition Strategy to achieve the necessary levels
of staff skills.
The implementation of Gray's
recommendations
113. On 15 October 2009, following the publication
of the Gray report, the Secretary of State and Lord Drayson announced
that they would take the following steps:[266]
- A Green Paper to be published
early in the New Year; a Strategic Defence Review to be undertaken
immediately after the General Election; and the Government to
examine legislative frameworks to require a Strategic Defence
Review to be conducted early in the term of each new Parliament.
- Equipment programme to be brought into balance
with future requirements and likely availability of resources.
- Equipment expenditure to be planned to a longer
time-frame, with a ten year indicative planning horizon for equipment
spending with the Treasury. This planning horizon to be published,
along with an annual assessment of the affordability of the equipment
programme.
- Board-level governance to be strengthened within
the MoD by the formation of a new sub-committee, chaired by the
Permanent Secretary as Accounting Officer.
- Methods of costing projects in the equipment
plan to be improved; better techniques to be applied more consistently;
investment decisions to be based on the most reliable forecasts;
management of risk across the programme to be improved.
- Stronger controls to be introduced with regard
to the entry of new projects and changes to existing projects
in the equipment programme.
- The business relationship between MoD Head Office,
DE&S, and the Service Commands to be 'sharpened' by clarifying
roles and responsibilities and providing greater visibility of
project management costs in DE&S to the Capability Sponsor.
- Improvement of key skills (including cost forecasting
and programme management) in DE&S and MoD Head Office to be
accelerated.
114. The Secretary of State and Lord Drayson
rejected Bernard Gray's suggestion of establishing DE&S as
a Government-Owned Contractor-Operator entity. They announced
that they intended to publish a wider, more detailed Strategy
for Acquisition Reform in the New Year. The MoD press release
stated that Mr Gray would work with the MoD on the development
of the strategy, although we later discovered that Mr Gray chose
to leave the MoD at the beginning of December 2009. We asked the
MoD in December 2009 to provide us with a progress report regarding
the development of its acquisition strategy. Its initial response
merely stated that the strategy was progressing and gave no new
information,[267] but
in January 2010 it provided a one-page paper describing a few
specific actions and their current status.[268]
The MoD published its acquisition reform strategy, The Defence
Strategy for Acquisition Reform, on 3 February 2010.[269]
115. Industry witnesses expressed some concern
that the Gray recommendations, whilst welcomed by Ministers, would
not be translated into effective action. Ian Godden told us that
there was a fear in industry that Gray would live as a document
and would not have "the sharp implementation associated with
it", and that "perhaps [the Gray report] misses the
people, leadership and implementation issues in addressing how
this is going to become, not a change programme, but a reform
programme, and that is, I think, the worry."[270]
116. Witnesses from DE&S referred to changes
which were already being implemented within the MoD in response
to Gray.[271] However,
the Minister for Defence Equipment and Support made it clear that
he was not involved with Lord Drayson's acquisition reform work,
so it was unclear to what extent any changes within DE&S were
being coordinated with the development of the strategy for acquisition
reform.[272] The Minister
for Defence Equipment and Support also made it clear that he did
not agree with all of the conclusions of the Gray report.[273]
Lord Drayson said that he was "optimistic" that the
acquisition reform process would be effective,[274]
saying that:
We are, I think, fortunate in that we have clear
ministerial focus around the reform process. This is my job to
make sure it has happened and I am very, very clear, in part because
of my previous experience of having done the MinDES ministerial
role. I know that for this to be successful it has to have the
buy-in of MinDES and CDM.
117. It is quite clear that
some senior individuals in DE&S do not accept the need for
radical reform, and that they are only reluctantly involved in
the reform process. Whilst it might be possible to write a good
reform strategy in isolation, it would clearly not be possible
to implement it without united commitment from the leadership
within DE&S. With the publication of the Gray report, the
MoD has come clean about the extent of its problems with the equipment
programme, but the Department will have to work hard to persuade
people that it will not return to business as usual.
118. The MoD's Defence Strategy
for Acquisition Reform explicitly accepts Gray's broad analysis
of the difficulties faced by the Department with regard to defence
acquisition, and includes a summary of objectives and key actions
which it intends to take to address those difficulties. Some of
the key actions correspond with recommendations we have made in
this Report, although we await the further details which we have
requested on a number of points. We expect the MoD to make a statement
to the House by summer 2010, updating it on progress with acquisition
reform. We hope that the NAO will report on acquisition reform
progress as part of its Major Projects Report 2010,
and we recommend that our successor Committee returns to this
issue later in 2010.
169 The Gray report, p 6 Back
170
Q 638 Back
171
Q 261 Back
172
Ministry of Defence, The Defence Strategy for Acquisition Reform,
Cm 7796, February 2010 Back
173
The Gray report, p 56 Back
174
The Gray report, p 16 Back
175
Q 2 Back
176
Q 72 Back
177
Q 64 Back
178
Q 2 Back
179
Q 76 Back
180
Q 81 Back
181
Q 486 Back
182
Q 609 Back
183
Q 636 Back
184
Q 686 Back
185
The Gray report, pp 7-8 Back
186
Qq 604-605 Back
187
The Gray report, p 23 Back
188
ibid., p 20 Back
189
ibid., pp 22-23 Back
190
HC Deb, 15 October 2009, col 34WS Back
191
Q 341 Back
192
Q 355 Back
193
Q 358 Back
194
The Gray report, p 26 Back
195
Written Ministerial Statement, 15 October 2009, col 35WS Back
196
Q 681 Back
197
Q 680 Back
198
Q 679 Back
199
Q 698 Back
200
Q 701 Back
201
Q 703 Back
202
Q 366 Back
203
Q 370 Back
204
Ev 118 Back
205
ibid. Back
206
The Gray report, p 32 Back
207
Q 267 Back
208
Q 270 Back
209
Q 317 Back
210
Q 331 Back
211
Q 637 Back
212
Q 639 Back
213
Q 638 Back
214
The Gray report, p 160 Back
215
ibid., p 162 Back
216
ibid., p 164 Back
217
Q 263 Back
218
Q 265 Back
219
Ev 119 Back
220
The Gray report, p 159 Back
221
NAO, The Major Projects Report 2009, pp 28-30 Back
222
Qq 272 and 274 Back
223
Q 4 Back
224
Q 488 Back
225
Q 487 Back
226
The Gray report, p 7 Back
227
ibid., p 179 Back
228
ibid., pp 183-184 Back
229
Q 7 Back
230
Q 13 Back
231
Ev 113 Back
232
Q 16 Back
233
Q 499 Back
234
Q 647 Back
235
Q 720 Back
236
Q 280 Back
237
Q 291 Back
238
Q 281 Back
239
Q 288 Back
240
Q 290 Back
241
Q 283 Back
242
Q 295 Back
243
Q 345 Back
244
ibid. Back
245
Conquering Complexity: Lessons for defence systems acquisition,
The Defence Engineering Group, 2005, p 285 Back
246
Q 29 Back
247
Q 24 Back
248
Q 27 Back
249
Q 17 Back
250
Q 56 Back
251
ibid. Back
252
Q 718 Back
253
Q 717 Back
254
HC (2008-09) 107, para 71 Back
255
Q 6 Back
256
Q 496 Back
257
The Gray report, pp 12-13 Back
258
Q 673 Back
259
Q 666 Back
260
Q 673 Back
261
Q 332 Back
262
Q 335 Back
263
Q 343 Back
264
Q 744 Back
265
Q 745 Back
266
HC Deb, 15 October 2009, col 34WS Back
267
Ev 112 Back
268
Ev 118 Back
269
Ministry of Defence, The Defence Strategy for Acquisition Reform,
Cm 7796, February 2010 Back
270
Q 304 Back
271
Q 61 Back
272
Qq 505-506 Back
273
Q 486 Back
274
Q 687 Back
|