The future of Britain's electricity networks - Energy and Climate Change Contents


Examination of Witnesses (Question Numbers 144-159)

MR GORDON EDGE, MR TIM RUSSELL AND MR JASON ORMISTON

29 APRIL 2009

  Q144  Chairman: Good morning and welcome to the Energy and Climate Change Select Committee. We very much appreciate you coming today to talk about Britain's electricity networks and we are very interested to hear your views from the renewables side, which, of course, is going to be a very important part of networks in the future. I wonder, for the record, if you would just like to introduce yourselves and say which organisation you are from?

  Mr Ormiston: My name is Jason Ormiston. I am the Chief Executive of Scottish Renewables, which is also known as Scottish Renewables Forum, or SRF. We will hear those being interchanged within the next few months, I think.

  Mr Edge: My name is Gordon Edge. I am Director of Economics and Markets at BWEA, also known as British Wind Energy Association.

  Mr Russell: I am Tim Russell and I am here today representing the Renewable Energy Association. I advise them on network matters.

  Q145  Chairman: Thank you very much. I will start off. There is a huge interest, discussion and hopefully investment in networks going on at the present time. There are a lot of strategy groups. The Electricity Networks Strategy Group, for example, stated that reinforcements to the transmission system can be delivered in time to meet the 2020 renewables target. That is an ambitious target. There is an awful lot of investment in the pipeline, which is not yet built and connected. Do you think that the investment programme so far and the regulatory framework are suitable in terms of giving that delivery within that kind of timescale to renewables?

  Mr Ormiston: It is probably the major question about whether or not we will deliver for 2020. You use the word "can", which is crucial, of course. We can deliver that investment by 2020. I think the regulatory infrastructure is being developed to be able to deliver that. The ENSG's transmission study was very useful and is the kind of visionary document that we require to deliver the 2020 target. I think it needs to be regularly reviewed, however, because the demand to connect, the amount of capacity that will likely want to connect by 2020 may be greater than that identified in the current ENSG report. Those are the longer term drivers which I think are useful. Shorter and medium term, the regulatory background has to be fit for purpose. Our experience to date over the last ten years trying to deliver our 2010 target has not been good.

  Q146  Chairman: Could you give us an example of why it has not been good?

  Mr Ormiston: A very good example is in Scotland, where we have a significant amount of renewables capacity that wants to connect to the transmission network and the distribution networks but that network is not there. It is a planning issue. In other words, you would not necessarily blame those who wish to invest in the transmission network or, indeed, the regulator for that, but it is arguable that the planning for that investment was not pressing enough long enough ago, and so we are left in a situation with something like nine gigawatts of potential renewables capacity waiting for a connection beyond 2012, beyond even 2018, which is a major problem if you want to meet your 2020 targets. This is now being addressed in the Transmission Access Review, but it remains to be seen whether the Transmission Access Review will deliver the goods or the regulatory infrastructure required. We are going to have a discussion hopefully later about "connect and manage", and we are supporters of that approach, but there is an awful lot to play for in the debates around the Transmission Access Review and the various CUSC amendments and other initiatives and modifications that have been brought forward through that.

  Q147  Chairman: You said the regulatory framework was developing. Does that suggest it is not there yet?

  Mr Ormiston: No, it is not there yet. The Transmission Access Review has to play out, and there are also an awful lot of modifications and proposals for reform outwith the Transmission Access Review. You take a view whether that is useful or not, but, nevertheless, that continuing debate dominates much of the discussion within the industry about what is probably the principal issue for the renewable electricity sector in the UK.

  Mr Russell: I think it is quite important very early on that everybody acknowledges the elephant in the room, and the big risk with all of this is that currently the planning system does not adapt to be able to give more timely decisions, whichever way they go, and everything else that you may or may not wish to ask us about this morning all really arises because of the inordinate length of time it often takes to get planning for networks but also, of course, generation projects of all types.

  Q148  Chairman: Can I perhaps pick this up, Mr Russell. Some of the timescales are really quite remarkable, shall we say. Indeed, if we have got time, you may want to address some of these issues of planning. Do you want to say something, Mr Edge?

  Mr Edge: Yes, please. I think we need to acknowledge that there has been some considerable progress here. The ENSG process and report are actually quite significant advances in taking us on the way. Our view is that there is a current delivery gap between this visionary plan, which is really good, it is excellent and it is on the table and we are really pleased that Ofgem is bringing forward new initiatives for investment ahead of user commitment—again, that is a major advance—but there just does not seem to be someone with whom the buck stops and who is the back-stop, who makes sure that all the different things that need to happen happen in the right time, in the right place, and that leadership element is what we think is missing.

  Q149  Chairman: Who do you think should give that leadership?

  Mr Edge: We cannot see anyone else but government being the one that holds the ring here.

  Q150  Chairman: Not the regulator?

  Mr Edge: Government is the one that is setting the targets; I think it has to be the one that actually actively propels us forward.

  Q151  Chairman: So it is the Government, basically?

  Mr Edge: Basically, yes.

  Q152  Sir Robert Smith: You touched on investment ahead of need. How much difference will it make if you go down that route?

  Mr Edge: I think it will make quite a significant difference if the incentives are right. There are many slips between cup and lip in terms of putting that system in place. What I have a problem with is, incentives are all very well, but people do not have to take the incentive, there is no compulsion for them to actually take it up. It is an enticement, but it does not necessarily ensure that it happens.

  Q153  Sir Robert Smith: So you may be being a bit more fundamental and so using the market.

  Mr Edge: I think the market is good, but there needs to be a back-stop to make sure that, if it is not coming forward, buttons can be pushed to make sure things do happen, and there needs to be that back-stop power because we do not have much time.

  Q154  Sir Robert Smith: How do you respond to the concern that, if you do it ahead of need, you could end up with investment in all sorts of a nice shiny bits of network that are not actually going to be needed but make money for the network provider?

  Mr Ormiston: I think that is a bit of a red herring, to be honest. I think we already have a situation where there are parts of the networks that are under utilised, and that is managed perfectly well and acceptably by Ofgem, National Grid and other organisations. Are there likely to be bits of the network in the future that are likely to be under utilised as such? I think the answer to that is probably, yes, but that may have happened in any case. I think the key is in planning and things like the ENSG report and our understanding of where development is likely to take place, not just the renewables but in other generation as well, and what type of response is required in terms of delivering the networks. If we are clever about it and we are sensible about it, we will get that right. You will find that where there is spare capacity, there is an encouragement to develop projects in any case, and that can be an incentive as well.

  Mr Edge: I think the only risk is that it may be under utilised for a bit longer than we thought it might be. The other side of this is that we do not build the capacity; we do not get anywhere near our targets.

  Mr Russell: Can I just correct an unfortunate use of words. Nobody actually in this context, when they say "investing ahead of need", means that. The investment is needed now, but if it is genuinely not needed, it should not be done. What people actually mean by "investment ahead of need" is investment ahead of individual generation projects being able to give specific and substantial financial commitment. So we are not investing ahead of need; nobody is talking about that. What is actually meant is investing ahead of specific financial commitment. Now, with a large number of (for the transmission system) often not very large projects, you know there are, for example, going to be several gigawatts of new generation in Scotland, as an example. You do not, however, know which of the many individual projects are going to be successful. Therefore, those individual projects cannot themselves incur liabilities of many millions of pounds to give financial security to the investment, which is why this sort of requiring specific projects to give financial commitment does not work any more, but there is a high degree of certainty that the reinforcements are needed, which is why the investment is needed now. The other thing that is very important to say in this context is that most transmission, the expensive part of building it, when you actually order the kit and buy the wires and string them up on overhead lines or bury them in the ground, the timescales for that are not dissimilar to the timescales for constructing most types of power stations. The one exception would be nuclear, I guess, but we are talking two to three years. What has got to be done ahead of that is doing the preliminary engineering work and starting the planning process and getting planning consent. That expenditure is not hundreds of millions or billions of pounds. The really expensive stuff really only starts at the same time as the power stations that precipitate it are being built. So there is no expenditure ahead of need. What people are talking about is expenditure ahead of individual plants being able to put their hands in their pocket.

  Q155  Charles Hendry: Can I broaden it slightly to financing support. We have seen companies like Shell pulling out of the London Array; we have seen Centrica putting some of their offshore schemes on hold. The issue has been raised that the ROCs were not generous enough, and the Chancellor changed that support system in the Budget last week. This goes really beyond the investigation we have got in front of us, but as we have you here it would be very helpful to know whether you feel that they have now gone far enough to encourage those offshore projects to come back into the system?

  Mr Edge: I believe so. We have been very pleased with the announcements in the Budget. We think that should be sufficient to keep the projects that are currently in the market going and, indeed, to make orders as they should. So in that sense we think it is probably about right.

  Mr Ormiston: Now that we have accepted the principle of differentiated support for different renewable technologies, known as banding, you have to do an objective test of the cost of developing different technologies and respond accordingly. Clearly, developing offshore wind is perhaps a bit more expensive than we anticipated a while ago and the response by the Chancellor last week was helpful.

  Q156  Chairman: I wonder if we could just turn to the issue of accessing the transmission network. The traditional pattern has been to invest in "connect", and there has been a proposal that we should move towards "connect and manage". Des, do you want to start off with this?

  Q157  Dr Turner: Yes, I will be slightly more keen and start at the tail of last year's questions. Everything that is being planned with grid restructuring at the moment and with reinforcement relates to the needs which are already identified—the queue of onshore wind, et cetera, and several gigawatts—and does not seem me to relate to what could be facing us in, say, five years' time, when the picture could look very different, when we start to see gigawatt scale exploitation of marine resources which will not necessarily even match the grid distribution that is already envisaged. Do you think that our grid vision for the future is going to be adequate to take maximum account of our renewable resources?

  Mr Edge: I think the issue there is more of a 2030 issue than a 2020 one. We, obviously, champion the wave and tidal industries, alongside wind, but we do not see it producing much more than the gigawatt scale in the 2020 timescale. You need to be planning into the 2030 level, and that is why we are very keen that there be a vision for beyond 2020 out to 2030, because, particularly with the grid, you talk about long lifetime assets: you need to be planning long lifetime visions. So we need government to be bringing forward its view for the post 2020 era, but what I would also say is that those wave and tidal marine resources are very complementary to wind in a lot of ways. You maximise the use of the network through having that diversity of resources. Indeed, tomorrow we will be publishing a report on precisely this issue, the way that the complementarity of wind and marine resources can actually benefit the system overall, which we are very happy to share with the committee.

  Q158  Dr Turner: I would be grateful for a copy of that, certainly. Coming back to the short-term, do you feel that the short-term measures arising from the Transmission Access Review are going to have a significant impact on the current queue of renewable generators waiting to connect?

  Mr Ormiston: You use the word "significant". In Scotland there are nine gigawatts of projects that have a contract to connect on a firm basis, and they stretch from tomorrow right through to beyond 2018. Some of those projects have consent; they have a connection offer going beyond 2014. In response to the Transmission Access Review and the desire for interim "connect and manage", National Grid was asked to actively pursue advancement of projects that can advance, that can connect through the queue more quickly, and in doing that have identified projects that are consented or are close to a decision and they have identified 450 megawatts in the north of Scotland to advance to the queue. I think that is very helpful, and I think they should be congratulated on that effort. They have now identified a further 450 megawatts. That perhaps will make it a little bit longer, but they think they can also advance those through the queue in Scotland as well, and, again, I think they should be given credit for that. If you consider a 50 per cent attrition rate in planning for that nine gigawatts that has not had a consent yet, you are looking at four and a half gigawatts. So 900 of that—you are talking about a fifth—has been advanced through the queue, and I think that is very helpful. I would not know whether to call that significant or not, but it is certainly a very helpful amount and will have a big impact actually on meeting renewables targets. What was disappointing from my perspective was recent debate around the cost of advancing that capacity through the queue and Ofgem's apparent u-turn on its commitment to put short-term measures through the Transmission Access Review and calling into question the efficacy of moving that 450 megawatts that have been identified by National Grid through the queue more quickly. It actually caused a huge amount of consternation in Scotland, because we thought Ofgem was at least behind the Transmission Access Review, but it appeared to step back a bit and have second thoughts. Fortunately, they realised they could not actually continue with that position and have supported the advancement of the 450 megawatts, and more megawatts, in Scotland. Just to sum that up, I think everyone now is back on course. I think that queue advancement work by the National Grid is to be applauded.

  Mr Russell: I think the technical position is we are waiting for Ofgem's final decision in terms of its policy on derogations that will facilitate the interim "connect and manage" that I think they have promised by the end of April, which is tomorrow. So as long as it goes ahead, yes, it should make a difference in the short term.

  Mr Edge: There is a general issue with Ofgem's attitude to the constraint costs that arise from "connect and manage", which obviously all three of us here very strongly support. Their view is it is all very well, but look at the bill. There was a CUSC amendment to Cap 48 that some of our members brought forward, and we commissioned some analysis of the impact assessment that Ofgem did around that. Ofgem was assessing a net cost of £917 million for this proposal, and our analysis said 23. So Ofgem takes a very high view of what those constraint costs are going to be, which we do not think is actually the reality.

  Q159  Chairman: Why do you not think that?

  Mr Edge: They take a very pessimistic view of how much constraint will be needed and how much needs to be paid. We can provide you with that analysis to show you what it was. It was a rather strange attitude to the cost of the Renewables Obligation.

  Mr Ormiston: Ofgem had some previous history as well on this 450 megawatts. Initially they were responding to a concern that advancing 450 megawatts would cost £100 million extra in constraints. Subsequent research and a reappraisal of the situation brought that down to 40 million, which is a much more acceptable position.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 23 February 2010