The future of Britain's electricity networks - Energy and Climate Change Contents


Memorandum submitted by Areva

  1. What should the Government's vision be for Britain's electricity networks, if it is to meet the EU 2020 renewables target, and longer-term security of energy supply and climate change goals?

1.1 A development vision should include the addition of transmission and distribution capacity. Clearly this cannot be achieved solely by an increase in the number of lines; options include:

    — Upgrades of lines (higher voltage, higher currents)

    — Optimized monitoring and control

    — Novel technologies (eg DC transmission)

  1.2 For this reason it is important to have a vision, which enables the identification of the best option to meet the challenge of distributing and balancing more renewable power. Transmission and distribution expansions are not in contradiction with efficiency improvements: any improvement in efficiency or the influence of embedded generation is extremely unlikely to alleviate the need for added electricity transmission capacity due to the increasing share of electricity in the consumption mix (the more electric society).

  1.3 A larger share of renewables in the generation mix will require increased electricity network flexibility. Since system flexibility is not the clear duty of a single actor, a guidance vision is required here as well. The vision could integrate the following elements:

    — Use of dynamic component rating: this represents a more flexible use of existing assets, just expanding their operation range from a very conservative to a physically justifiable level.

    — Power flow control: a way for the system to adapt to a wider range of operational situations (due to the fluctuations induced by renewables). This can be achieved by using DC transmission and/or flexible AC transmission systems.

    — Investigate architecture changes, especially at sub-transmission level: systems have been laid out under a set of assumptions which included low levels of decentralised generation. Since these assumptions no longer hold, system architectures need to be reviewed.

  1.4 Conflict situations between regulation and flexible system operation will need to be addressed.

  1.5 Added interconnection to continental Europe and Scandinavia is crucial in order to achieve a degree of "mutualisation" of renewable generation which permits to overcome the difficulties associated with the stochastic in-feeds by renewable generators.

  2.   How do we ensure the regulatory framework is flexible enough to cope with uncertainty over the future generation mix?

  2.1 Bring up to date the historical regulatory constraints concerning:

    — Spinning reserve

    — Plug-and-Play micro-generation

    — Benefits for participating in demand side management

  2.2 Reduce the impact of uncertainty and intermittence on the transmission system security (caused by renewable energy connection), install system reserve capabilities, such as energy storage.

  2.3 Rigid rules must be urgently reviewed relating to the needs of consumers and the advent of new technology.

  2.4 Implement real-time and dynamic electricity pricing to maximise the customer benefits.

  3.   What are the technical, commercial and regulatory barriers that need to be overcome to ensure sufficient network capacity is in place to connect a large increase in onshore renewables, particularly wind power, as well as new nuclear build in the future? For example issues may include the use of locational pricing, or the availability of skills.

  3.1 On the technical side, a major issue is standardisation and inter-compatibility of equipment as well as harmonization of practises. In the current R&D landscape, it is blatant that parallel activities too often result in uncoordinated developments. Standards need to be actively encouraged. International collaboration and co-ordination in the Transmission & Distribution area is therefore a key requirement.

  3.2 Significantly increase the connection capacity at suitable sites to allow connection of new-build nuclear and/or renewables. One technology solution to achieve this could be the conversion of AC lines to DC—to facilitate an increase in power transmitted down an existing corridor of up to 300%, using the same towers and foundations.

  3.3 On the regulatory side, solutions to avoid placing the burden of connection to the network (and ensuring adequate capacity) on individual generators should be investigated. Since a large number of novel generators will need system developments, the objective is to achieve a regional network expansion planning.

  3.4 A commercial challenge might result from the difference between the current short and uncertain planning horizon and the difficulty to mobilise resources and skills needed for the integration of renewables. A better long term view of the entire sector would certainly help.

  4.   What are the issues the Government and regulator must address to establish a cost-effective offshore transmission regime?

  4.1 Define who owns the responsibility for the offshore to onshore transmission connection.

  4.2 Define an environment where a cost-effective offshore network around the coast of the UK (not just a single point-to-point connection from offshore to onshore) can be built with clearly defined responsibilities between the offshore generation owner, the offshore network owner/operator and the land based transmission grid owner/operator.

  4.3 R&D support associated with technical development and requirement of establishing an offshore transmission system, including offshore transmission technologies and risk management of security and reliability of the transmission system connecting with large renewables.

  5.   What are the benefits and risks associated with greater interconnection with other countries, and the proposed "supergrid"?

  5.1 Benefits:

  Provide system stability and security, reduce the required spinning/system reserve, and reduce the overall investment cost for these items.

  Part of a solution to "onshore" congestion

  5.2 Risks

  May experience more network disturbances caused by other countries

  Dependence on security of the interconnectors

  Need for more coordination of network operations between countries (which may be difficult to implement).

  5.3 Challenges:

  Achieving acceptable cost levels

  Technical feasibility of off-shore terminals, multi-terminal operation

  Exposure to "imported" high energy prices

  6.   What challenges will higher levels of embedded and distributed generation create for Britain's electricity networks?

  Lower observability/controllability

  Higher stress on the Distribution network

  More dynamic network operation

  Architectural challenges: fault-levels, distribution of power flows, etc.

  6.1 Definitions

  Embedded generation is the term used for any electricity generating plant that is connected to the regional electricity distribution networks. These networks are owned and operated by the Distribution Network Operators (DNOs). The DNOs are the distribution arms of the former Public Electricity Suppliers (PESs) and came into existence when the distribution and supply licences were separated by the Utility Act (2000). At present, most power generating plant in the UK is connected to the high-voltage transmission system, which, in England and Wales, is owned and operated by the National Grid Company.

  6.2 UK distribution network capacity

  While the distribution networks do have some capacity for adding new embedded generation plant, the constraints are significant: the usual scenario, as a result, is that the locations where generation can be added do not coincide with the optimum location for the proposed plant. This is particularly true for renewable energy technologies, which, in most cases, must be located where the renewable resource exists or is optimal.

  During the period to 2010, current government targets for renewable energy and CHP, if achieved or approached, will result in more than 20-25GW of total capacity being added to the distribution networks. Given the current configuration of the networks, this level of additional capacity cannot be accommodated without significant change.

  6.3 Observations on Embedded Generation: Fault Contribution

  The addition of embedded generation will lead to an increase in fault contribution within the point of connection of the generation. This reduces the margin in hand of the equipment already operating on the network busbars, disconnectors and switchgear. In locations where equipment is already operating at or close to it fault rating and new installation of embedded generation can necessitate or accelerate the need for plant replacement to ensure switchgear rating remain above the aggregate of fault levels from the network and embedded generation. With the relatively short planning times from concept to installation of new embedded generation schemes imposes difficult network planning decisions for the DNO's.

  The use of fault current limiters between the DNO network and the oncoming embedded generation provides a fault buffer to ensure that any fault infeed into the network from embedded generation is limited. This can assist in areas where network fault levels are running close to the switchgear ratings and would enable embedded generation to be installed without the need or switchgear replacement.

  Any current limiters would need to have a response time consistent with the operating time of protection scheme and that of the circuit breaker.

  In the UK the DNO's are seeing an increase in the dc time constant component of short circuit currents, this is due in part to the solid mesh network, lower transformer losses and standardised method of calculation. Normally within the DNO network the ac component of the short circuit current is steady state sinusoidal however for circuit breakers close to sources of generation the ac component is a decaying to steady state sinusoidal due the sub transient and transient components of the generator reactance, which when superimposed upon by the high time constant of the dc component can lead to delayed current zero duty for the circuit breaker. With more embedded generation it is possible that this will lead to a higher population of circuit breakers close to these new generation sources with delayed current zero duty.

  6.4 Observations on Embedded Generation: Plant Availability

  For correct operation the switchgear availability and availability of the embedded generation plant should be coordinated. To maximise the maintenance regime of network switchgear plant and embedded generation plant will need to be reviewed to ensure that they are being maintained in accordance with the manufacturers' instructions. For example number of switchgear operations when connected to embedded generation might increase dependant upon the time cycle the embedded generation is connected to the network. A change from traditional time based maintenance to condition based maintenance could be considered as a means of minimising the number of outages required due to carrying out intrusive time based maintenance work. Condition monitoring procedures provides the users with indications when maintenance is required based on the condition of key switchgear components. This is especially of benefit for un-manned substations.

  6.4 Back up Connections

  Dependant upon the location of the embedded generation its importance to the support of the network decisions needs to be taken. Duplicate connections onto existing network may be required. This could have an impact on the decision of the connection layout and suitability of existing switchgear.

  6.5 Synchronisation of Embedded Generation onto the Network

  Switching generation onto a network will involve synchronising procedures. If this is carried out via the network circuit breakers, they will need to be verified by the manufacturers whether the switchgear is suitable and rated for out of phase duty. This could present a problem where old switchgear is to be used for the connection, leading to a decision to replace with new switchgear.

  6.6 Spares and Manufacturing Support

  Increased amount of embedded generation onto the network would need some careful consideration into spares and emergency work procedures in order to minimise the unavailability of embedded generation in the event of switchgear failure.

  With the different numbers of generation companies owning and operating the embedded generation sites throughout the UK, it might be conceivable for these companies and the DNO's to share a common spares holding comprising both consumable and strategic spares. This could be some form of a "spares club". Manufacturers could be part or even run this shared club, their input being supplying the spares, providing technical support as well as site activity support.

  6.7 Summary

  The key to an optimised high level of embedded generation into the network is for the end users, network owners and equipment manufacturers to pool their expertise and review all aspects of embedded generation in terms of the operation, network and switchgear equipment.

  7.   What are the estimated costs of upgrading our electricity networks, and how will these be met?

  No comments available

  8.   How can the regulatory framework ensure adequate network investment in light of the current credit crunch and recession?

  8.1 Change of policy to enable the unbundling of network ownerships to allow new players to own and/or operate new electricity network infrastructures.

  8.2 Mitigate risks by providing tax benefits to the new players, for first few years of the investment.

  8.3 Match duration of legislation to duration of return of capital for asset investment.

  8.4 Technology specific incentives based on technological maturity.

  8.5 Increase transparency to enable informed investments

  9.   How can the regulatory framework encourage network operators to innovate, and what is the potential of smart grid technologies?

  9.1 Reduce penalties and/or increase incentives to encourage new/novel technologies to be embraced and implemented.

  9.2 From incentives to "obligation" to devote money to R&D

  9.3 SmartGrid technologies enable:

    — Efficiently operated (and reliable) networks

    — Differentiated Power Quality at connection point

    — Faster response to network disturbances

    — Self diagnostic, self healing & self re-dispatch capabilities, therefore reduced interruptions and minutes lost

    — Integration of (potentially) millions of small scale generators

    — Bulk power and small scale sustainability to coexist

    — Demand and supply balance solutions

    — Customers to be part of the electrical power supply system:

    — Both producer and consumer of electricity = "prosumer"

    — Real-time price information (smart meters)

    — Automated and embedded systems (DR/DSM)

    — Adequate investment and reward incentives

    — Mature markets and regulation

  10.   Is there sufficient investment in R&D and innovation for transmission and distribution technologies?

  10.1  The magnitude of R&D investments into T&D, especially from public funds should be reviewed:

    — In comparison to generation technologies, R&D investments into the "upstream network" have been lagging.

    — Size and duration of individual projects need careful attention. Innovation in T&D is comparatively slow and complex. Use of R&D money can be improved by allocating R&D money to larger projects. This requires:

    — The encouragement of alliances and larger consortia (with special attention to the inclusion of industrial partners)

    — Special encouragement of long term and durable R&D efforts, more emphasis on long term exploitation of results

    — Dissemination of R&D results should also be included as an integral part of the overall investments. This increases the leverage with respect to the money invested.

  10.2 Beyond investments into R&D, a regulatory framework for R&D is required. This includes three aspects:

    — DNOs and TSOs should be allowed, and rewarded, to use revenues for R&D. The reward seems at the moment too low, such that DSOs appear not to use the full extent of the IFI scheme. In this situation, the regulator could take these funds and redistribute them to those who are able to use them, including relevant industrial companies.

    — Innovation also impacts upon regulation. Experience has demonstrated that some R&D project ideas have never been proposed because they were in contradiction with current regulation. To permit the investigation of innovative schemes, solutions and technologies, the possibility to grant exceptions to the regulatory framework should be included in the R&D support schemes.

    — A closely related issue is "loss of revenue" incurred in demonstration based innovation and research projects. These appear to be a barrier in some cases. Allowing Generators, TSOs and DNOs to compensate their losses to a larger extent would increase the R&D activity.

  10.3 Technical consortia involving all parties, end users, network operators and manufacturers should be formed to explore and share the respective technologies of each. In this way new innovative technologies can evolve towards optimising the technical solutions of embedded generation schemes.

  10.4 The benefit of this would be for each party to be familiar with the whole picture rather than with their own scope of responsibility, this should aid the generation of innovative ideas and in doing so speed up the R&D solution to market time.

  11.   What can the UK learn from the experience of other countries' management of their electricity networks?

  11.1 Early adopters of electronic meters: Italy

  11.2 High proportions of renewables: Denmark, Germany, Portugal

  11.3 EDF (France) is committed to enhance its efficiency and responsiveness under the cases of major disturbances, and to improve the overall performance of the network. Several plans have been then implemented:

    — Climatic area plan so as to reduce the sensitivity of the grid to the climatic risks (ice, storm, flood, heat wave)

    — Fast mobilizing plan for emergency

    — Daily load shedding exercises

    — Restoration of the power supply of critical sites in 12 hours

    — Restoration of the supply in less than five days to 90% of the consumers under the exceptional circumstances of a major climatic disaster (ref. wind storm of 1999)

March 2009



 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 23 February 2010