Memorandum submitted by the Campaign to
Protect Rural England
INTRODUCTION AND
SUMMARY
1. The Campaign to Protect Rural England
(CPRE) welcomes the opportunity to submit evidence to the Select
Committee's inquiry on the future of Britain's electricity networks.
The development of the nation's electricity network has been a
key interest of CPRE since our formation in 1926. We played a
central role in calling for the environmental obligations that
were placed on the Central Electricity Generating Board, and subsequently
National Grid. We were closely involved in discussions of the
routing of transmission lines created under the most recent major
development of the network, in the 1950s and 1960s. Alongside
this we are the leading voluntary organisation engaged in both
shaping and engaging with the spatial planning system at all levels.
Our network of local branches in every county and our regional
groups participate in the planning process on a daily basis.
2. The Committee's Inquiry comes about at a time
where major investment in new electricity generating capacity
is being proposed, both from conventional and renewable sources.
One consequence of this is likely to be major development of the
electricity transmission network, on a scale not seen since the
1960s. The recent report of the Electricity Networks Strategy
Group (ENSG) confirms this, calling for £4.7 billion of investment
in the period to 2020. In response, CPRE has recently issued,
in alliance with the Campaign for the Protection of Rural Wales
(CPRW), Campaign for National Parks (CNP), and the National Association
for Areas of Outstanding Natural Beauty (NAAONB), A Countryside
Friendly Smart Grid, a manifesto for the future development of
the transmission network in England and Wales. A copy of the full
manifesto is included with this submission.
3. CPRE supports moves towards a "smart
grid" making use of technological innovation to manage electricity
consumption, in order to reduce the need for new generating capacity.
Crucially, development of a "smart grid" should integrate
the need for a national network, which we acknowledge will remain
for the foreseeable future, with minimising or avoiding damaging
visual impacts in our most valued areas of rural landscape. In
our view, minimising the impact of the grid can be achieved in
part through sensitive spatial planning. But we also believe that
this will have to be harnessed to measures encouraging greater
use of local and decentralised energy networks, as well as energy
efficiency, to reduce dependence on national transmission networks
in the longer (20-30 year) term.
4. In preparing our evidence we have sought
to address the following issues posed in the Call for Evidence:
the Government's vision for electricity networks; issues surrounding
the regulatory framework; and technological innovation.
5. The structure of our evidence is as follows:
the role that the spatial planning process,
and in particular the proposed National Policy Statement (NPS)
on electricity transmission, will play in guiding the future development
of the networks;
the need for the future development of
the network to minimise visual intrusion into the countryside,
in particular designated landscapes; and
the role of technological innovation
in helping to minimise visual intrusion and allowing the network
to better absorb electricity generated from renewable sources.
THE ROLE
OF PLANNING
6. The Planning Act 2008 institutes a new
planning process for electricity transmission (and potentially
also high voltage distribution) networks, through which future
expansion of capacity will have to be considered. CPRE believes
that some of the reforms contained in the Act are sensible, in
particular the proposed new National Policy Statements to guide
development and the creation of single development consent order
for individual projects. We have grave concerns, however, about
the nature and extent of the powers of the new Infrastructure
Planning Commission (IPC) to make decisions on electricity transmission
and other projects.
7. Although Ministers have argued that the IPC
will function as an independent body, its remit appears to be
specifically about promoting and approving major infrastructure
projects in line with national policy. The experience of developing
the electricity transmission network in the UK and elsewhere has
shown that it is not simply a matter of facilitating development.
It is a highly political process of reconciling the economic arguments
for centralised electricity generation and transmission with avoiding
or mitigating the significant visual impact that the transmission
network has on town and country. Although some may consider the
planning process to be a "barrier" to progress, to CPRE
it is a vital means of ensuring that the future development of
the transmission network takes full account of the public interest.
8. The NPS on electricity transmission,
to be prepared by the Secretary of State for Energy and Climate
Change, is expected to be issued in draft in June 2009. The Committee
will have scope to play a key role in the development of the NPS,
through the parliamentary procedure for NPSs set out in the Planning
Act.
9. The NPS should seek to ensure that the
future development of the network happens in a manner consistent
with the wider public interest and the achievement of sustainable
development. As our manifesto makes clear, we accept in principle
the need for major investment in the electricity transmission
network. There will be a need for clear spatial planning, taking
into account that certain areas are not suitable for new overhead
transmission lines, and that good design to minimise visual intrusion
should be paramount. Some of the most obvious methods of lessening
environmental impact, such as the use of undergrounding and undersea
cables, appear more expensive in the short term but can deliver
significant long term savings, in terms of a reduced need for
planning inquiries, time savings, and maintaining environmental
quality.
10. The most recent major line upgrade project
in England, in North Yorkshire, took nearly ½ years from
application to final grant of permission. Significant amounts
of this time involved the developer in considering ways to lessen
the impact of the line on the landscape, not fully addressed in
the initial proposal.[14]
Ministers often refer to this case in arguing the need to avoid
a lengthy planning process. In our view, however, the main lesson
to be drawn from the North Yorkshire case is the need for a clear
initial policy framework that sets robust standards of environmental
protection and clear expectations upon developers.
THE NEED
TO MINIMISE
VISUAL INTRUSION
FROM THE
TRANSMISSION NETWORK
11. We fear that the Committee's questions,
as set out in the Call for Evidence, miss an important issue with
the future development of the network. We agree that development
should take place in a manner that addresses renewable energy
targets, security of supply and climate change goals. It is no
less important, however, that a future vision for the electricity
network should fully incorporate other environmental goals, such
as minimising damage to the beauty and tranquillity of our finest
countryside.
12. To address this issue, CPRE believes that
the remit of Ofgem should be widened to consider the most sustainable
methods of developing the network to address both climate change
and landscape impacts. It should look at possible new power stations
and transmission connections in the round. The new NPS process
will necessitate a spatial, strategic approach to network development
to ensure that designated and other valued landscapes are avoided
by new overhead transmission lines where possible. This implies
that Ofgem will need to become more flexible in allowing forward
investment than under its current remit. This would, in turn,
allow National Grid and the distribution network operators to
promote demand management on their networks through energy storage
and other techniques, and environmentally sensitive network development.
13. A 2003 report by the UK Centre for Economic
and Environmental Development found clear evidence that the public
find the landscape impacts of overhead lines unacceptable.[15]
Alongside this, CPRE has carried out extensive research on the
issue of rural tranquillity. A key stage of this research, conducted
by Northumbria and Newcastle Universities, was to discover what
rural tranquillity meant to people. "Seeing a natural landscape"
was the top response as to what tranquillity was, and "seeing
overhead power lines" was among the top 10 responses as to
what detracted from a sense of tranquillity. We can supply further
details, including maps, to the Committee on request.
14. According to a 2004 MORI poll, tranquillity
is the main reason why 49% of us visit the countryside. Government
data suggests in turn that through rural tourism, tranquillity
directly supports 186,200 jobs and 12,250 small businesses, and
contributes £6.76 billion a year to our economy. There is
convincing evidence of the importance of the natural environment
in helping people to recover from stress. A 1998 review of over
100 studies showed that the primary reasons for visiting natural
environments included escape from the stress of urban areas and
the experience of tranquillity and solitude.[16]
Research published by the Campaign for National Parks in 2006
indicated that 69% of businesses in the National Parks in the
Yorkshire and Humber Region believe high environmental quality
has a positive impact on their business performance.[17]
15. Further recognition of these points,
albeit in an urban context, has been shown in the major work that
has been recently completed to underground high voltage overhead
lines and remove 52 pylons (including both transmission and smaller
distribution pylons) in and around the site of the London 2012
Olympic Games. At the beginning of the project, Lord Coe and David
Higgins, both leading figures in the delivery of the 2012 Games,
respectively stated that "the undergrounding of power lines
will provide an uncluttered landscape against which the Games
can be staged" and "placing the power lines underground
is a vital part of our long term regeneration of East London".[18]
This has led to a growing public interest in the possibilities
for undergrounding transmission lines in other locations.
16. We recognise that undergrounding the
highest voltage lines can carry significant short term expense
(for example, £250 million in the case of the London Olympic
project), and can also give rise to issues of disruption to subsoil,
archaeological and landscape features. Nonetheless, we believe
it crucial that National Grid and the distribution companies take
their responsibilities seriously. Bill Bryson showed a particular
concern for this issue in his maiden speech as CPRE's President
in July 2007:
"In 1986, at the time the electricity
companies were being privatized, the Economist magazine calculated
that if all the electricity generating companies were required
to devote one half of one percent of their turnover to burying
overhead cables, we would be able to bury 1000 miles of them every
year. There are 8,000 miles of high-voltage power lines in this
country, so they would all be buried now.
Instead they seem to be a part of nearly every
rural scene, nearly always running along hilltops and ridgelines
where they ruin views in both directions. Other countries make
electricity companies paint their pylons dark green or otherwise
lose them against the background. I don't understand why National
Grid, the company responsible for erecting pylons, is allowed
such freedom. We don't put motorways on the tops of hills. We
don't run natural gas pipelines overhead. Why should power lines
be permitted to go wherever it suits the distributing company
to put them?'
WHERE IS
VISUAL INTRUSION
A PROBLEM?
17. The relationship of the new NPS to existing
Planning Policy Statements produced by Communities and Local Government
(CLG) will be crucial. We draw the Committee's attention in particular
to statements made by two Ministers (Baroness Andrews and Jim
Fitzpatrick MP, respectively) which undertook that all NPSs would
reflect existing Government policies protecting designated areas
of landscape, such as AONBs, National Parks and Green Belts, from
major or inappropriate development.[19]
It is important that these undertakings are fully respected.
18. National Grid uses guidelines on the routing
and siting of transmission infrastructure (the Holford and Horlock
Rules, respectively). Despite these, overhead transmission lines
directly intrude into designated landscapes at a number of locations
(and indirectly at many more), for example in and around Trawsfynydd
in Snowdonia National Park and at two points in the Cotswold Area
of Outstanding Natural Beauty, north of both Bath and Cirencester
respectively.
19. CPRE, CPRW, CNP and NAAONB are particularly
concerned that the existing situation could be worsened by transmission
reinforcement plans being considered by National Grid, many of
which are referred to in the March 2009 ENSG report. Much of this
proposed expansion appears to us to be driven by a desire to accommodate
an increased amount of new nuclear generation on existing nuclear
sites, alongside clusters of offshore wind farms in most of the
coastal regions of England and Wales. Based on the initial indications
provided, the strategy for accommodating new offshore wind farmsthrough
underground connections to existing substations on the transmission
networkappears broadly sensible and consistent with our
vision for minimising visual damage.
20. Our analysis indicates, however, that
plans could lead to new overhead lines or larger pylons in Snowdonia
National Park as well as in four Areas of Outstanding Natural
BeautyAnglesey, the Kent Downs, the Lincolnshire Wolds,
and the Mendip Hills. It is significant that in all these areas
(except possibly the Lincolnshire Wolds), the driver for new development
may well be the possibility of new or expanded nuclear capacity
in the vicinity.
21. CPRE is also concerned to protect the
open, undeveloped character of the Green Belt around our largest
towns and cities and to improve its value for people to live near
them. Overhead transmission lines already damage the appearance
of the Green Belt around London and other major cities. Possible
new lines in Derbyshire, Essex, Kent, and Somerset, and larger
pylons in London and South Yorkshire, could have a further damaging
impact on the Green Belt in those areas.
22. If expansion of the transmission network
along the lines suggested by the ENSG is unavoidable, then CPRE
would call for the NPS to set clear guidelines relating to better
design of any new overhead lines, and the avoidance or undergrounding
of lines in designated landscapes. We explore the issue of design
in more detail below in our comparison with other countries.
THE ROLE
OF INNOVATION
23. CPRE is pleased that a political consensus
is emerging on the need for a "smart grid" that focuses
on the encouragement of renewable energy, and better management
of supply and demand for electricity in order to increase energy
efficiency. We note with interest that the ENSG report advocates
the use of both undersea High Voltage Direct Current (HVDC) cables
from Scotland to England and "series compensation" (essentially
the increasing of transmission capacity on existing lines) in
Cumbria. It appears that the application of such innovations in
the network are the direct result of planning constraints forcing
National Grid to make the best use of both existing assets and
to apply technologies causing less visual intrusion.
24. To encourage continued innovation, we believe
that the new NPS could usefully set a policy lead for Ofgem in
future distribution and transmission Pricing Control Reviews.
Future reviews should promote the statutory environmental responsibilities
for the Distribution Network Operators through a rolling programme
of undergrounding or minimising visual intrusion from the existing
networks.
25. Smart grid technologies can move us
towards a more robust mix with less dependence on centralised
energy in the long run. We acknowledge, however, that the need
for national transmission and overhead distribution networks is
likely to remain for the foreseeable future. One way in which
this need may be reduced would be through the development of commercially
viable means of energy storage, particularly from renewable sources.
This has been identified as a particular barrier to allowing supply
from renewable sources, which is often intermittent, to match
peak periods of demand for electricity.[20]
We suggest that the Committee investigates this issue.
LEARNING FROM
OTHER COUNTRIES
26. CPRE has noted that the current debate
around grid expansion in the UK has parallels in other countries.
The most obvious example of this is President Obama's plans for
a smart grid in the USA, where major investment is being directed
to address the storage and transmission of power from renewable
sources.
27. New Zealand has already produced (in March
2008) a National Policy Statement to guide the development of
electricity transmission networks through the planning system.[21]
This is a short four pages statement of high level principles.
It is too early to fully evaluate the effect of the NPS on planning
in New Zealand, but CPRE would have concerns if this was seen
as readily transferable to the context of England.
28. We would suggest to the Committee that
the forthcoming NPS for England will need to be significantly
more detailed than the New Zealand NPS. In particular, we would
want to see a thorough integration of principles around minimising
the environmental impact of network development alongside the
expected consideration of the overall need for development. Although
the expected NPS will be the first of its kind on electricity
transmission in England, there is an extensive history of policy
and practice to which CPRE has significantly contributed, and
would wish to bring to bear in the forthcoming debate around the
English NPS.
29. A more applicable international comparator
in CPRE's view would be Denmark. In Denmark, minimising environmental
impact is recognised as a high level objective of the transmission
network, alongside other operational issues such as robustness,
maintaining security of supply and ensuring well-functioning competition
in the power market. Significantly, Denmark is also planning a
major expansion of offshore wind energy development to meet its
target of at least 30% of energy demand to be met from renewable
sources. In April 2008, Energinet.dk, the country's equivalent
of National Grid, issued a technical study on expansion of the
national transmission network, with prominent consideration given
to increasing the use of underground cables. The study considered
six "principles" for future network development ranging
from complete undergrounding to new overhead lines along traditional
lines and no expansion at all.
30. The report includes cost analyses of
adopting different options. Perhaps unsurprisingly, those involving
major undergrounding are significantly more expensive than those
involving new overhead lines. Nonetheless, Denmark is setting
a clear policy direction of travel towards reducing the impact
of the existing transmission network, and has already undergrounded
up to 18% of its high voltage (above 132 kV) lines. Part of the
policy also involves the use of two less intrusive pylon tower
designs, which can be applied where new lines are constructed.
These are shown in Figure 1 on the next page along with the more
traditional, taller, design in current use.
31. The two new designs in Denmark involve
tower designs of a typical height of 33 metres. This is up to
one third shorter than a typical tower design for a high voltage
line in the UK of around 50 metres. CPRE notes that shorter designs
have already been applied on the transmission network in specific
cases in England, for example in the Cotswolds AONB at Tormarton,
near Bath. We believe that the new designs being developed in
Denmark should be investigated for application to new overhead
line development in England, or in any locations where lines are
being replaced and renewed and where undergrounding is not feasible.
We note that although shorter designs can necessitate more towers
than under a 50m design, there is still clear potential for visual
intrusion to be reduced.
Figure 1 Existing and new tower typesall
intended for two 400 kV systems in Denmark. The top tower is used
in several places in Jutland. The development of the Eagle tower
(middle) has been completed, and can now be used in new projects.
The fibre mast (bottom) is currently being developed and is planned
to be ready for use in five years. Reproduced with permission
from Energinet.dk.

14 See Department for Communities and Local
Government, Planning for a Sustainable Future-White Paper, May
2007, p 31. Back
15
See UK CEED, The Scope for Undergrounding Overhead Electricity
Lines, March 2003. Downloaded from www.ukceed.org/downloads/files/15-undergrounding_summary_with_contents.pdf
on 19 February 2009. Back
16
See CPRE, Saving Tranquil Places, October 2006,
with detailed references on p 13. Back
17
CNP, Prosperity and Protection, 2006. Back
18
London Development Agency, Olympic regeneration powers ahead,
6 April 2006, accessed from www.lda.gov.uk/server.php?show=ConWebDoc.1486
on 25 February 2009. Back
19
Jim Fitzpatrick MP, House Of Commons Public Bill Committee, 29
January 2008; Baroness Andrews, Planning Bill, House Of Lords
3rd Reading, 18 November 2008. Back
20
Ed Crooks, "Obama's smart vision for the electricity grid",
Financial Times 16 January 2009. Back
21
Available from www.mfe.govt.nz/publications/rma/nps-electricity-transmission-mar08/index.html Back
|