The future of Britain's electricity networks - Energy and Climate Change Contents


Memorandum submitted by The Crown Estate

SUMMARY

    — The Crown Estate is committed to working with Government, National Grid, developers and all stakeholders to help ensure that the aspirations of the UK for offshore renewable energy are met. — There is excellent potential within UK waters for wind and marine renewable energy deployment with an industry keen to exploit this potential. — One of the most significant barriers facing this generation is access to the onshore transmission network. It is essential that a significant level of reinforcement is carried out if these natural energy resources are to be exploited to their full potential.

    — The offshore transmission regime should not be looked at in isolation from the onshore system. The most cost effective solutions can be found through considering the best overall solution to optimise the building and operation of the onshore and offshore network.

    — Significant investment in Britain's electricity network is required if the Government's targets for renewable generation are to be met.

    — The offshore transmission regime must be allowed to consider the provision for more than one offshore energy installation at one time. The Crown Estate advocates a strategic approach to the planning and design of the offshore grid.

1.0  THE CROWN ESTATE

  The diverse portfolio of The Crown Estate comprises marine, rural and urban properties across the whole of the United Kingdom valued in total at over £7 billion (2006-07 figures). Under the 1961 Crown Estate Act, The Crown Estate is charged with maintaining and enhancing both the value of the property and the revenue from it consistent with the requirements of good management. We are a commercial organisation guided by our core values of commercialism, integrity and stewardship.

The Crown Estate's entire revenue surplus is paid directly to HM Treasury for the benefit of all UK taxpayers; in 2006-07 this amounted to £200.1 million.

1.1 THE MARINE ESTATE

  Our Marine Estate comprises virtually the entire UK seabed out to the 12 nautical mile territorial limit, in addition to the sovereign rights to explore and make use of the natural resources of the UK continental shelf, with the exception of oil, coal and gas. We own approximately 55% of the foreshore and around half the beds of estuaries and tidal rivers in the United Kingdom. A wide variety of businesses and organisations conduct economic and conservation activities across our Marine Estate, with an estimated total value of some £46 billion providing almost 890,000 jobs. Over 20% of our coastal estate is leased out to conservation bodies.

The Crown Estate manages its marine assets on a commercial basis, guided by the principles of sustainable development and social responsibility. We take a consistent approach to the management of our activities around the UK, whilst retaining flexibility to take local factors into account whenever necessary.

  The Crown Estate can bring to bear an unparalleled level of knowledge and expertise on issues relating to management of the foreshore, the territorial seabed and continental shelf. This knowledge includes marine resource management (e.g. marine aggregate extraction, marine renewable energy installations, seabed infrastructure, aquaculture and new activities such as gas storage and carbon capture and storage) and its interplay with other marine activities such as defence, energy, navigation and marine safety. We have a strong understanding of the needs of a broad range of sea users, as commercial partners, customers and stakeholders.

2.0 INTRODUCTION

  This response to the Committee's call for evidence is informed by The Crown Estate's extensive experience of managing activities within the marine environment and, within its core remit, of balancing economic activity with stewardship of natural resources for future generations to use and enjoy.

We are aware that the first inquiry by the Energy and Climate Change Committee into "The Future of Britain's Electricity Networks" will examine how Britain's networks will need to adapt in response to future changes in the generation mix, and the role of the Government and Ofgem in facilitating this, and the potential for a supergrid. This response does not specifically address the questions raised but we believe it is a useful contextual document that will help inform the Committee on this important issue.

  In June 2008, The Crown Estate announced the third leasing round for offshore wind energy. This is intended to deliver up to 25 GW of new offshore wind generation by 2020. In addition during 2008, a leasing application process for offshore wind in Scottish Territorial Waters was also held with 6.4GW of exclusivity agreements being granted in January 2009 pending the outcome the Scottish Government's SEA. Finally, The Crown Estate are currently holding a tender for marine renewable energy installations in Pentland Firth. It is anticipated that up to 700MW of marine renewable energy will be achieved by 2020, but there is the potential for considerably more to be delivered from the Pentland Firth and also from other areas around the UK coast.

2.1 ONSHORE GRID REINFORCEMENT

  There is an excellent resource within UK waters for wind and marine renewable energy deployment with an industry keen to exploit this potential. However, one of the most significant barriers facing this generation is access to the onshore transmission network. It is essential for a significant level of reinforcement to be carried out if these natural energy resources are to be exploited to their full potential. In December 2008, The Crown Estate published a study showing an indicative scenario for deployment of offshore wind generation under Round 3. This study identified onshore and offshore network requirements and fed into the excellent work that was carried out under the auspices of DECC by the Energy Networks Strategy Group (ENSG). The Crown Estate encourage the Committee to recommend further work by groups such as ENSG where the total network requirements can be considered in a coordinated and strategic manner. This will present opportunities to identify cost savings which will benefit the consumer.

2.2 ACCESS TO THE GRID

  It is essential that improved access to the National Grid system is implemented within a reasonably tight timeframe for offshore wind, wave and tidal developers. Failure to deliver improved access will inevitably result in developers taking their technology to other locations, possibly abroad. The Crown Estate has been instrumental in seeking to improve grid access for all offshore renewable energies and will, in conjunction with others, continue to seek early resolution to this problem. Developing offshore transmission links will allow energy projects, including those in remote areas, to improve access to the wider UK and European markets.

2.3 INVESTMENT AND STRATEGIC PLANNING

  Significant investment in Britain's electricity network is required if the Government's targets for renewable generation are to be met. In December 2008, The Crown Estate published a connection study in support of Round 3. This work considered a scenario for connecting 25GW of offshore wind. The study identified that approximately £10 billion of network reinforcements would be needed. Of this, approximately 7% related to onshore works.

In order that the most efficient and economic solution for network investment is delivered, it is essential that a strategic plan is developed and implemented. The Crown Estate commend the work undertaken by the Electricity Networks Strategy Group (ENSG), established under the auspices of DECC, in identifying necessary reinforcements for the onshore transmission network.

  The offshore transmission regime should not be looked at in isolation from the onshore system. The most cost effective solutions can be found through considering the best overall solution to optimise the building and operation of the onshore and offshore network. In doing so, innovation and integration with the use of High Voltage Direct Current (HVDC) technology can be accounted for. Additionally, in order for the delivery of offshore renewables to be made in the required timescales it is essential that a long term view of network requirements are taken and that relevant onshore planning and consenting is carried out expeditiously.

  The offshore transmission regime must be allowed to consider the provision for more than one offshore energy installation at one time. The Crown Estate advocates a strategic approach to the planning and design of the offshore grid. This should be reflected in a coordinated approach to the licensing of potential offshore transmission assets.

3.0 CLOSURE

  We would be very willing to provide the Committee with further information on any of the points we have raised above. All of this response may be put into the public domain and there is no part of it that should be treated as confidential.

March 2009


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 23 February 2010