The future of Britain's electricity networks - Energy and Climate Change Contents


Memorandum submitted by the Renewable Energy Association (REA)

  1.  The REA is the largest renewable industry body in the UK, with almost 570 corporate members. These companies are active across the range of renewable electricity generating technologies and the association also covers renewable heat and transport fuel interests. The REA's grid expert is involved in several industry/government/regulator working groups, including the review of security of supply standards, the transmission access review, the transmission arrangements for distributed generation,[103] the distribution charging methodology forum and the renewables advisory group grid group.

2.  In this response we would like to make the following general points:

    — There needs to be a swift move towards an enduring "connect and manage" approach to connecting power generation to the networks, if we are to stand any chance of meeting our renewables targets.

    — We welcome the recent moves to divorce strategic development of the transmission network (and providing the finance for this development) from the financial commitment of specific generation projects.

    — The enduring arrangements for charging for use of the networks must continue to be based on the logical premise of net movements across boundaries between different networks (not gross charges).

  3.  Over the past few years, thousands of megawatts of renewable capacity which had been seeking connection to the network, had not been able to get access. The grid operator had been following an "invest and connect" approach—and would only connect a new project if there was sufficient capacity to accommodate the maximum output of the prospective generator without there being a restriction on the output of existing generation. The effect of this has been to delay the connection of zero or low carbon generation and the loss of the carbon savings this new plant would have delivered.

  4.  These frustrated projects had been held in a waiting list and, depending on their position in this list, could have expected to wait over 10 years for connection.

  5.  The Renewable Energy Association has been advocating an alternative approach—termed "connect and manage". This involves connecting all capacity that wishes to connect, and where necessary constraining the total generation delivered to the network to the level which it can accommodate on a day to day basis. This means the connection of renewable generation does not have to wait until enough infrastructure has been built to allow the unconstrained operation of all connected plant.

  6.  The Transmission Access Review (TAR), which started in the summer of 2007, has been addressing this problem. One of the conclusions of the TAR report[104] was that any project should be able to obtain a firm connection date within a time frame reasonably consistent with the development time of the project. Implementation of this TAR conclusion will primarily be via changes to the Connection and Use of System Code (the CUSC)—the rules by which all parties connected to the grid must adhere.

  7.  Three broad groups of CUSC amendments were proposed in the spring of 2008:

    — "connect and manage";

    — the auctioning of transmission access capacity; and

    — some short-term measures that basically help to make better utilisation of the existing network.

  8.  The process of working up the detail of and evaluating these approaches has been taking place in various industry working groups and the proposals are now with Ofgem for consideration and to decide which combination of them are implemented. In our view it is important that some form of connect and manage proposal is chosen so that renewable generation is not prevented from connecting purely to allow higher carbon generation to continue operating without constraint.

THE SEPARATION OF STRATEGIC TRANSMISSION INVESTMENT FROM SPECIFIC GENERATION PROJECT COMMITMENTS

  9.  Until now transmission investment has been reactive ie the transmission companies do not begin to undertake reinforcement work until individual generating companies have guaranteed the cost of those connections. This has caused problems as generating companies are not generally able to provide those guarantees until they are reasonably confident that their projects will proceed, for example after they have got planning consent. The time taken from the granting of planning consent to construction is often much shorter than the time it would take to consent and build the associated transmission reinforcement, thus delaying the delivery of new "clean" electricity. The system is also made harder by many transmission reinforcements being driven by a large number of relatively small projects rather than a small number of larger ones.

10.  Fortunately the general geographical location of a significant portion of the new renewable generation is known, even if it is not yet known which combination of the individual projects will succeed. This enables strategic transmission investments to be planned in advance, potentially alleviating some of the delay to delivering the necessary transmission. Ofgem is working up arrangements to finance transmission owner expenditure on such investment and methods of giving the transmission owners incentive to "get it right".

  11.  The Renewable Energy Association supports these moves and points out that if and enduring connect and manage regime is adopted, and transmission companies pay (in part) for the consequences of not having the right transmission infrastructure in place, this automatically provides an incentive for transmission companies to anticipate the necessary transmission investments accurately.

DISTRIBUTION-CONNECTED GENERATION—THREATS AND OPPORTUNITIES

  12.  One of the greatest uncertainties for our networks between now and 2050 is how much of the new generation will connect at distribution network voltages, rather than to the main transmission system. Because of this the planning and regulation of distribution networks must be able to respond to a wide range of generation penetration levels.

13.  Distribution is 132kv and below in England and Wales, but in Scotland the 132kv network is classed as part of the transmission system. With the exception of all but the largest projects, most renewable generators are "embedded" within the distribution network, rather than connected to the transmission network. In simple terms, these generators are nearer the point of end use of electricity (both in terms of distance and voltage level). Consequently they have historically avoided various charges associated with transmitting power over the transmission system—and enjoyed what are known as "embedded benefits".

  14.  The justification for these embedded benefits is simple. Irrespective of any commercial arrangements to sell the power from an embedded generator, power does not physically flow on to the transmission system but is absorbed by the local demand. It is therefore not imposing any flow-related costs on the transmission system. We have concerns that these "embedded benefits" are under threat, for reasons explained below.

  15.  Ofgem and NGC have been concerned for some time about the ability of generation connected to distribution systems to avoid transmission charges. This issue was discussed at length by a special working group set up to look at the issue (and some less important matters relating to distribution connected generation). It was known as the Transmission Access for Distributed Generation (TADG). The TADG held its first meeting in July 2006.

  16.  National Grid proposed a move to gross charging (ie charging embedded generators and the associated demand the full transmission network use of system charges—thus doing away with the main component of embedded benefits). National Grid's belief was that even if it connects to the distribution network, a generator will have an impact on the transmission network; therefore it should pay transmission use of system charges. We think this is illogical, and it is the net flow onto or off the transmission system that determines National Grid's costs and therefore what it needs to recover by way of charges. Charging on this net basis is cost reflective and in general retains the status quo. Charging for gross generation and gross demand would be like the transmission system operator trying to charge for all the gross generation and gross demand in continental Europe, rather than just the net flow that comes across the interconnector with France.

  17.  The TADG concluded in a state of complete polarisation of views between National Grid and industry on this issue. It remains unresolved. Ofgem has imposed a license condition on NGC requiring it to establish an enduring solution for charging distribution connected generators for using the transmission system by the end of March 2011. We are concerned that the long established benefit of locating close to demand and not paying transmission charges for power that does not flow onto the transmission system will be undermined.

  18.  Another threat that those distribution-connected generators that existed before April 2005 have is the imposition of Distribution Use of System Charges. Generators connecting before that date paid what are known as "deep" connection charges. This means that they had to pay 100% of the cost of any work done to connect them anywhere on the distribution network, including a capitalised sum to reflect the ongoing operation and maintenance cost of new bits of network that they so funded. There were no ongoing charges.

  19.  Ofgem is now considering going back on this deal and making those generators pay DUoS charges from April 2010. The REA strongly opposes this move. It is both unfair and is likely to result in reduced output from some projects, through them becoming uneconomic and having to cease generation. Project developers would have based their financial profiles on the pre-2005 rules and would obviously not have taken into account unexpected, additional use of system charges.

  20.  On the upside for generators considering connecting to a distribution network—there has been progress towards the point where well-located generators may eventually be able to receive a credit for the benefit they provide to the network. This benefit is the avoidance of reinforcement. This should help to avoid the pressure to build unnecessary private networks, where a suitable distribution system already exists.

What should the Government's vision be for Britain's electricity networks, if it is to meet the EU 2020 renewables target, and longer-term security of energy supply and climate change goals?

  21.  The vision should be a transmission network which is more strategically planned, designed to maximise the amount of renewable and low carbon generation. This is particularly significant for the building of new offshore networks; and a distribution network which is actively managed to balance power flows, similar to the way the transmission network is operated. At present the rules governing whether new plant can connect to a distribution system and how this plant interacts with the network are described as "fit and forget". The active approach allows more generation to be connected to less infrastructure, and operated more effectively with lower distribution losses.

22.  As we stated earlier there is a high degree of uncertainty about the proportion of the new generation that will be connected to distribution systems so their planning and financing arrangements must remain flexible.

How do we ensure the regulatory framework is flexible enough to cope with uncertainty over the future generation mix?

  23.  Some of the ideas that Ofgem is suggesting for incentivising transmission owners to anticipate where generators will connect are heading in the right direction.

What are the technical, commercial and regulatory barriers that need to be overcome to ensure sufficient network capacity is in place to connect a large increase in onshore renewables, particularly wind power, as well as new nuclear build in the future? For example issues may include the use of locational pricing, or the availability of skills.

24.  The correct commercial arrangements must be put in place. In very simplistic terms the following principles should be followed:

    — Pricing should be cost-reflective.

    — Demand and generation should be treated the same (ie as inverses of each other).

    — Charging principles should be based on net and not gross flows—see discussion above about loss of embedded benefits.

  25.  As the question implies there are other significant barriers; it remains to be seen how effective the new planning regime (for larger infrastructure projects) will be. It seems highly likely that lack of electrical engineers will hamper the deployment of the large increase required in renewable electricity generation. This shortage has been felt by the distribution network operators for some time, and is anticipated to get worse.

  26.  A commercial/regulatory barrier projects regularly face is difficulty in obtaining wayleaves or easements across land (ie rights for cables to cross land). There is a standard compensation arrangement, agreed between the Country Landowners Association, the National Farmers Union and network operators [1]. The amounts of money offered under this agreement per pylon or per metre of cable laid are low, regularly leading to landowners holding out for far higher amounts. This can seriously delay projects and add hugely to costs.

  27.  DNOs have the ability to step in and compulsorily purchase land, but are reluctant to use it to the point of it being almost unheard of. DNO's will retire from wayleave negotiations when a "customer connection" is being carried out if the agreed rates are declined, despite adopting the finished connection on energisation of the project. The end result is that project developers are regularly left having to negotiate wayleaves with landowners, who can be assisted in their negotiations by companies that specialise in assisting landowners get the highest rates.

  28.  This process should be reviewed. The ideal outcome would be more realistic payments to landowners, such that having a wayleave is not an unattractive proposition, coupled with more rigorous approach to the DNO enforcing the standard agreement.

What are the benefits and risks associated with greater interconnection with other countries, and the proposed "supergrid"?

  29.  Our view is that increased interconnection is beneficial. The ability to share reserve over as large an area as possible will have an increasing value as the amount of wind and other weather dependent generation increases.

What challenges will higher levels of embedded and distributed generation create for Britain's electricity networks?

30.  The main effect of this will be on the distribution networks. Depending on where within the distribution networks the embedded generation locates the net effect could be either to increase or decrease the amount of investment needed in distribution networks. This is why we (in agreement with Ofgem) believe that cost reflective distribution network charging is so important.

What are the estimated costs of upgrading our electricity networks, and how will these be met?

31.  We refer the committee to the report by the Electricity Networks Strategy Group, entitled Our Electricity Transmission Network: A Vision For 2020[105] published in March 2009.

How can the regulatory framework ensure adequate network investment in light of the current credit crunch and recession?

32.  The issue of the cost of capital in the current financial climate is primarily one for Ofgem and the network companies to resolve. Companies with an allowed regulated income should though in principle remain good credit risks.

How can the regulatory framework encourage network operators to innovate, and what is the potential of smart grid technologies?

33.  Innovation policies need to include systems technologies beyond the generator itself. In particular there is substantial scope for actions to support active network and load management technology:

    — Adoption of smart technology whenever new meters are fitted; and a timetable for smart metering nationwide.

    — Investment in know-how and funding to deploy intelligent networks to permit timely and economic delivery of renewable power.

    — Review of potential approaches for load management control to be applied at the level of consumer units or individual appliances.

    — Review the potential for electric vehicle battery charging as a balancing facility.

  34.  Flexible demand can be used in conjunction with variable energy resources to balance demand with available output and to manage certain transmission and distribution network constraints, as an alternative to installing more hardware. This strategy avoids constructing power stations that are only needed for a short time every year to meet peak demands and can result in significant carbon savings.

  35.  The use of demand flexibility does not have to be centrally managed. It could evolve through the autonomous actions of individuals (or appliances) if they could respond to short term price and availability signals. This could be achieved through smart metering or in the case of appliances, response to frequency fluctuations.

  36.  The key incentive to make these things happen is to ensure that there is no systematic advantage given to a network company from investing in its own hardware rather than contracting for others to provide services that can avoid the need for this investment.

What can the UK learn from the experience of other countries' management of their electricity networks?

  37.  In some other European Member States renewable generation gets priority connection. In other words its connection can not be delayed by the need to invest in network infrastructure (other than the local connection).

38.  Providing the key recommendation of the Transmission Access Review (ie that all plant should obtain firm access in timescales reasonably consistent with its own development) is implemented, we do not believe that specific priority for renewable generation is needed. If renewable generation is delayed in achieving access in the future then, of course, priority would be needed.

April 2009







103   Which has now finished. Back

104   Published 27 June 2008. http://www.berr.gov.uk/files/file46774.pdf Back

105   http://www.ensg.gov.uk/assets/1696-01-ensg_vision2020.pdf Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 23 February 2010