The future of Britain's electricity networks - Energy and Climate Change Contents


Memorandum submitted by Scottish and Southern Energy

  Scottish and Southern Energy (SSE) is one of the largest energy companies in the UK. We are involved in the generation, transmission, distribution and supply of electricity; energy trading; the storage, distribution and supply of gas; electrical and utility contracting; and telecoms.

SSE owns the high voltage electricity transmission system in the north of Scotland, and owns and operates low voltage electricity distribution networks in the south of England and north of Scotland.

SUMMARY OF EVIDENCE

    — Government can support the electricity industry through clear policy objectives, and stability and certainty in those policies and the associated support mechanisms. — Regulatory stability is a pre-requisite for investment in the electricity networks. The outcomes of Ofgem's regulatory reviews need to be clear and certain to promote investor confidence.

    — Investment in the transmission system is required and this will need to take place before generation users known. Regulated funding of the transmission businesses must allow for anticipatory investment based on credible generation scenarios.

    — Planning remains an issue—Government needs to ensure that the Planning Act, the National Planning Framework and Marine Bill result in a co-ordinated system that can make fair decisions in under a year.

    — Grid access also remains an issue—Government should support industry reform that provides certainty over the date of access ("connect and manage") and the cost of access (postal charging). Ofgem's preferred approach of long term auctions of network capacity coupled with expensive charges for users in remote locations is inconsistent with the delivery of renewables and security of supply objectives.

1.   What networks do we need to meet the EU 2020 target, and longer-term security of energy supply and climate change goals?

  The GB electricity networks have an enviable record of providing security of supply.

Since privatisation, over £25 billion has been invested in the networks. The overall reliability of the GB transmission system during 2007-08 was 99.9995%. Interruptions on the distribution networks have decreased by nearly 20% since 2000. Pan-European benchmarking studies demonstrate that GB has amongst the lowest levels of network interruptions in Europe[106].

  The challenge in the coming decade is to maintain this level of system security while accommodating the new generation mix necessary to meet GB's energy policy and climate change goals:

    — on the transmission system, to ensure timely and efficient network investment to meet the needs of new generation and facilitate further integration with the wider European energy market; and

    — on the distribution networks, adapting to an increasing volume of local, distributed generation and changing demand patterns.

  Meeting this challenge will mean not just network investment, but also technical, engineering and commercial innovation.

  Government can support the industry through clear policy objectives, and stability and certainty in those policies and the associated support mechanisms.

TRANSMISSION SYSTEM

Existing transmission system

  The owners of the GB transmission system are Scottish Hydro Electric Transmission Limited (SHETL) in the north of Scotland, Scottish Power Transmission (SPT) in central and southern Scotland, and National Grid Electricity Transmission (NGET) in England and Wales. National Grid also performs the role of GB System Operator (GBSO) which includes administering access to the whole GB transmission system, directing the operation of the system, and setting and collecting transmission charges from users to cover the costs of all three transmission network owners. The activities and revenue requirements of SHETL, SPT and National Grid are regulated through the GB transmission licence.

In addition to the existing onshore transmission licensees, it is proposed that new offshore transmission licences will be granted following a competitive tender process. These offshore transmission licensees will own the transmission assets that will connect the onshore network to offshore windfarms, and will recover a regulated revenue allowance from the GBSO.



  Existing and planned transmission circuits connecting GB with Ireland or mainland Europe are subject to separate interconnector licensing arrangements. These investments receive no regulated funding allowances through the GBSO. Instead funding is derived from entrepreneurial investment or regulated funding allowances from other national regulators.

Future transmission system

  The challenge for the owners of the GB transmission system in the coming decade is to ensure timely and efficient network investment to meet the needs of new generation and facilitate further integration with the wider European energy market.

Currently, over 80 gigawatts of new generation have applied for connection to the GB transmission system, including over 15 gigawatts of renewable generation. This generation has been `queued', with connection offers contingent on future network reinforcements. Around half of this generation has been offered a connection date after 2015.

  In June 2008, as part of the Renewable Energy Strategy consultation, the Government asked the three transmission licensees to conduct transmission system investment studies to identify the likely generation scenarios and associated transmission investment costs to deliver the EU 2020 target. This work was co-ordinated by the Electricity Networks Strategy Group (ENSG), which is jointly chaired by Ofgem and DECC, and reported in March 2009.[107]

  The ENSG report identifies transmission investments associated with the connection of the large volume of onshore and offshore wind generation required to meet the 2020 renewables target, and to facilitate the connection of other proposed new generation such as new nuclear. The total cost of the proposed reinforcements is £4.7 billion[108] and the resulting network would be able to accommodate a further 45 gigawatts of generation. The study also concludes that, provided the identified reinforcements are taken forward in a timely manner and the planning consent process facilitates network development, the reinforcements can be delivered to the required timescales.

  The ENSG study work was undertaken on a GB-wide basis; for Scotland, three scenario levels of renewable generation were examined: 6.6 gigawatts, 8 gigawatts and 11.4 gigawatts (all in addition to the existing 1.4 gigawatts of hydro). The figures overleaf summarise the transmission investment options in Scotland and the north of England to accommodate 8 gigawatts of renewables in Scotland (on the left), and further investments to accommodate 11.4 gigawatts of renewables in Scotland (on the right). SSE supports the general conclusions of the ENSG report, and the specific proposals for the Scottish network.

  The ENSG study did not specifically examine the transmission investment options for offshore wind or interconnection. Looking to the next decade, it is likely that an offshore grid will evolve as offshore generation technologies develop and there is further harmonisation within the European energy market. Investment in the GB transmission system needs to be mindful of greater pan-European integration.

Stage 1 and 2 transmission reinforcements to facilitate Scottish contribution to renewables targets


DISTRIBUTION NETWORKS

  The challenge for distribution network operators (DNOs) in the coming decade is adapting to an increasing volume of local, distributed generation and changing demand patterns.

There has been a surge in interest in distributed generation in recent years. For example, in 2008, SSE received 123 applications from small generators[109] to connect to the distribution network in the north of Scotland. Demand patterns are slowly changing as the volume of distributed generation increases, but also as consumers respond to energy awareness initiatives. Going forward, the development of new technologies, such as smart meters or electric vehicles, will contribute to other, potentially significant, changes in demand patterns.

  As a consequence, the size and shape of distribution networks are changing, as is the job of the DNO, but this is happening incrementally and, hence, adapting to these changes will be through evolution, not revolution. We do not advocate a rebuilding of the distribution networks, but rather we believe that innovation and new network technologies are the tools of the future DNO.

  Going forward, the historic model of passive distribution networks built of copper and steel will be replaced by a new model of active distribution networks that incorporate more demand management solutions such as energy storage. For DNOs to explore and implement alternatives to conventional network solutions, the regulatory framework must be sufficiently flexible to accommodate DNOs undertaking unconventional, and possibly unforeseen, activities.

  The regulated funding of DNOs already recognises the role of innovation through the innovation funding incentive (IFI) and the registered power zone (RPZ) mechanism. These initiatives, which have been in place since April 2005, are designed to promote research and development activities. The next step, building on the success of the IFI and RPZ mechanism, is inclusion of innovation as a core business activity of the future DNO, rather than as an optional add-on.

  The DNOs have a strong record in delivering reliable, cost-effective networks and are well placed to deliver our future network requirements. We support the strong drive within the current distribution price control review (DPCR5) to establish further measures to encourage DNOs to take a more innovative and active approach to the management and development of their networks. An important outcome of the DPCR5 should be recognition that innovation is a core business function of DNOs.

2.   What are the key components of a legislative and regulatory framework that meets the needs of Britain's future electricity networks?

  The Government's Renewable Energy Strategy consultation, published in June 2008, identified two grid-related constraints to increasing the UK's proportion of renewable energy:

    — improving delivery through planning; and

    — obtaining a timely grid connection.

  Tackling these barriers remains critical to successfully achieving the transition to a secure, low carbon energy economy.

INFRASTRUCTURE CONSENTS AND THE PLANNING PROCESS

  Historically, the planning systems for major transmission infrastructure projects have not delivered. In particular, the timeline for consenting necessary new transmission network has proved lengthy. It took six years to approve an essential upgrade to the North Yorkshire power line, and the proposed Beauly-Denny power line has been in the planning system since 2005. The shortcomings of the planning systems need to be addressed if the UK is to meet the EU 2020 target and longer-term security of supply and climate change goals.

SSE welcomes the development of new planning systems through the Planning Act in England and Wales and the National Planning Framework in Scotland. This provides a necessary and timely opportunity to ensure that essential energy infrastructure is delivered in an efficient and timely manner, by streamlined and co-ordinated systems that can make fair decisions in under a year.

  In England and Wales, the independent Infrastructure Planning Commission will require the full support of the Government in its work, to ensure that it has both the resources and expertise to properly discharge its responsibilities in a timely manner.

  The importance of National Policy Statements (NPSs) cannot be overemphasised. The NPSs are intended to set out the national direction of our energy requirements and, hence, avoid piecemeal, lengthy, case-by-case assessment of strategic infrastructure developments. To achieve this, the NPSs must be clear and have sufficient depth to form the basis for authoritative decisions to be made. The NPS and the approach applied to the planning and decision making processes need to recognise the national need for strategic investment in transmission, both onshore and offshore.

  The same imperatives apply in respect of the Scottish National Planning Framework. The Scottish Government's National Planning Framework 2 (NPF2) identifies and prioritises a range of onshore and offshore strategic network reinforcements in Scotland. These are essential to realising Scotland's renewable energy potential and meeting the Scottish Government's energy policy goals. The NPF2 also recognises the future potential of developing subsea routes to harness renewable energy.

  A co-ordinated approach to planning is needed across the governing administrations and also, critically, where infrastructure has a marine dimension. The interdependence between the provisions of the Planning Act and the Marine Bill needs to be clarified. Integration of the strategic planning system established by the Marine Bill and the relevant NPS is essential to achieving a coherent strategic development of onshore and offshore electricity transmission.

  SSE has some particular concerns surrounding the proposals within the Marine Bill as it currently stands. These concerns centre around the role and remit of the Marine Management Organisation; the order of preparation of, and supremacy in guiding decisions of, the NPSs, Marine Policy Statement, Marine Conservation Zones and marine plans; the lack of timescales in reaching consenting decisions prescribed within the Bill; and the absence throughout the Bill of the need to consider socio-economic factors when designating the use of marine areas. These will all need to be resolved over the coming months in order to create a regime that can be trusted by industry and other stakeholders alike.

NETWORK INVESTMENT TO FACILITATE GENERATION CONNECTIONS

The regulation of network investment

  The ownership and operation of the high voltage electricity transmission system and low voltage electricity distribution networks in GB are permitted under licence, and the terms of that licence restrict the revenue of the licensed network businesses. This revenue restriction term assumes a pre-determined programme of network investment. The revenue restriction term is re-visited every five years by Ofgem at a price control review.

In 2009-10, the transmission companies will recover around £1.5 billion and the DNOs will recover around £4 billion. These costs contribute respectively around 4% and 17% to householders' electricity bills.

SSE supports the principle of price-control regulation for electricity networks as practiced by Ofgem under the current `RPI-X' framework. This approach has successfully reduced costs, improved customer service and provided a stable investment climate. Furthermore, this approach has been, to date, sufficiently flexible to accommodate demands on the networks. We do not believe that a fundamental change to the GB approach to price-control regulation is required, but rather we believe that the current approach can continue to evolve to address new challenges.

Investment in the distribution networks

  The revenue restriction term of the DNOs is currently under review by Ofgem, and will be reset from April 2010. As we describe above, SSE believes that the DNOs can adapt to the challenges of increasing distributed generation through evolution, not revolution. Consequently, the focus of the current price control review (DPCR5) has to be to provide a stable platform for investment, adaptation and growth. An important element must be to ensure there is sufficient flexibility for DNOs to explore and implement alternatives to conventional network solutions and, hence, recognise innovation as a core business activity. This means rewarding DNOs for innovative behaviour in developing and managing their networks, while maintaining a high level of customer service.

Investment in the transmission system

Significant investment in the GB electricity transmission system is required if climate change and wider energy policy objectives are to be met. The ENSG report identifies the necessary developments to the transmission system in the coming decade. The total cost of the proposed reinforcements is £4.7 billion and the resulting network would be able to accommodate a further 45 gigawatts of generation. The impact on householders' bills would be less than £5 per year.

The current revenue restriction terms of the transmission licensees do not allow for investment of this scale (both in cost and time). Ofgem and the licensees have recognised this, and initiated work on funding further pre-construction studies and developing a regulatory funding mechanism for the necessary transmission investment. This work is due to be completed during winter 2009.

  One focus in the development of this funding mechanism is avoiding unused, stranded assets. Historically, regulatory sanction for investment in networks has only been granted when there is clear, demonstrable need from users (either generation or demand). However, the lead time for new network infrastructure can be up to 10 years while the lead time for new generation developments is, dependent on technology, typically less than four years. If transmission infrastructure is to be available when new generation developments need it, then the network investment must be initiated before the generation developments; hence, there is a risk of assets being built and, in the short term, not being fully used.

  This would appear an intractable, "chicken and egg" problem. However, we believe that the current regulatory funding framework is sufficiently robust to allow for a solution.

  One of the benefits of the GB regulatory model is being able to consider the economics of a network investment over the whole-life of the asset. The life of network assets is, typically, in excess of 20 years. Cost-benefit analysis can demonstrate that assets do not need to be fully utilised for all of their life to be economic. Such analysis should also include the "hidden" costs and benefits of network reinforcement such as operational impact, environmental impact, electrical losses and security of supply.

  The onus should be on the transmission licensees to demonstrate, through whole-life economic appraisal, that a proposed network investment is efficient for credible generation and demand scenarios. This means that the licensees should identify future generation users, and undertake analysis that quantifies and costs the potential benefits and risks of transmission investment. This analysis can be subject to open consultation and, where the balance is found in favour of investment, funding allowed through the revenue restriction term of the transmission licence. There is an opportunity to implement this approach through the new regulatory funding mechanism scheduled to be introduced in winter 2009.

  This approach would retain the many benefits of price-control regulation while addressing the delay that has arisen as a result of network investments only being initiated once new generation developments have been identified. It is consistent with the cross-industry analytical approach developed through the work of the ENSG and could be extended for offshore generation connections and future interconnectors. The transmission licensees have a strong record in delivering a reliable, cost-effective and secure system and are well placed to deliver the future network requirements identified in the ENSG report.

Grid access and charging

  New generation developers seeking connection to the GB transmission system today are likely to receive an offer to connect in 10 years time. Many developers of distributed generation, including small generators, are also receiving an offer to connect in 10 years time. Such an offer places the generation developer at the bottom of a long queue of prospective generators seeking connection to the electricity networks.

Grid connection offers provide no certainty to new generation developers over the date of connection, the upfront cost of connection or the ongoing cost of exporting power. Connection offers are contingent on the progress of network investments and the action of other developers that are further up the queue because access to the transmission system is allocated on a "first come, first served" basis. This means that projects with planning consent can be stuck in the GB queue behind projects that are less well developed. In the north of Scotland, SSE is aware of over 350 megawatts of renewable generation developments with planning consent but no access to the grid.

  The current approach to grid access and charging does not provide a stable climate for investment in necessary new generation, be it renewable, thermal or nuclear. Given this, it is not surprising that potential investors (particularly in emerging renewable technologies) are opting to locate elsewhere in the global energy market.

  Stability and certainty in the grid access and charging arrangements are essential to achieving the EU 2020 target, and long term security of supply and climate change goals. This means providing new generation developers with certainty over when they will gain access to the grid, certainty over the cost of access and certainty that the cost will remain stable over the lifetime of their development.

  SSE supports the `connect and manage' approach to access to the GB transmission system. This means providing generators with a firm date for grid access that is consistent with the development time of their project (typically, four years). To avoid speculative applications (that comprise a significant proportion of the current grid queue), new generation developers would be required to make a significant, but proportionate, financial commitment before receiving their firm connection offer.

  In relation to the charges for use of the electricity networks, we support the European model of `postal' charging where a GB-wide charge is levied for each unit of energy that is exported onto the network. Recognising the potential upfront investment cost associated with new generation developers in remote locations, developers should be required to contribute to the cost of new infrastructure that is necessary to connect them to the network.

  This change would be a welcome shift away from the peculiar current charging model, which leads to transmission charges in Scotland being high, volatile and unpredictable. Currently generators in the south of GB receive a payment from the GBSO while generators in the north face a large charge. For example, at present, it costs £22 per kilowatt in transmission charges to have generation located in the north of Scotland, and negative £8 per kilowatt south of London. This means an 800MW plant in North Scotland will pay £17.6 million a year, while in Southampton a developer would receive £6.4 million a year. With renewable generation located in remote areas, this concept is clearly outdated.

March 2009






106   See, for example, Council of European Energy Regulators: 4th Benchmarking Report of Quality of Electricity Supply 2008. Back

107   Our Electricity Transmission Network: A Vision for 2020. A report by the Electricity Networks Strategy Group, March 2009. Back

108   Note, this does not include the cost of connecting offshore wind which a recent report for the Crown Estate has estimated at around £10 billion. Back

109   Small generators are those of less than 10 megawatts. 10 megawatts is equivalent to four to eight commercial wind turbines. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 23 February 2010