The future of Britain's electricity networks - Energy and Climate Change Contents


Memorandum submitted by Scottish Natural Heritage

  1.  Scottish Natural Heritage (SNH) is a non-departmental public body funded by Scottish Government and responsible through Ministers to the Scottish Parliament. Our purposes are to promote the care and improvement, responsible enjoyment, greater understanding and appreciation, and sustainable use of the natural heritage, now and for future generations. The natural heritage embraces landscape, habitats and wildlife, and the capacity that these have to contribute to people's well-being. SNH is an adviser to Government and to planning authorities on natural heritage matters, including on the impacts of electricity infrastructure, and a statutory consultee on environmental impact assessments and strategic environmental assessments.

2.  Electricity networks have a very significant impact on Scotland's natural heritage, particularly through the visual and landscape effects of the many overhead pylon lines constructed to serve Scotland's communities, and to harvest "power from the glens" in the mid-20th century programme of hydropower development. In localised areas in or adjacent to protected sites, bird impacts can be a concern, but these have normally been resolved by careful routing and mitigation (e.g. bird deflectors).

  3.  The requirements to enhance the grid in Scotland have increased because of the scope for wind power and will increase again in future to enable the potential to be realised for wave and tidal power, for which much of the UK resource is in north and west Scotland, and offshore wind.

Q1.   What should the Government's vision be for Britain's electricity networks, if it is to meet the EU 2020 renewables target, and longer-term security of energy supply and climate change goals?

  4.  By 2050, if the Climate Change (Scotland) Bill is passed, Scotland like the rest of the UK will have a target of reducing greenhouse gas emissions by 80%. Given the substantial residual emissions from land use change which it will not be possible to eliminate, and the likely continued dependence on fossil fuels for some modes of transport, this would require electricity generation to be virtually carbon-free by 2050. This will require a change in approach so as to ensure that the electricity grid is capable of collecting all forms of renewable energy both on and offshore, and facilitates the development of small-scale and distributed generation. Given the long-term nature of energy infrastructure, it is important that this aim is reflected in all decisions on new infrastructure and substantial refurbishments from now on.

5.  To do so, grid networks should:

    — enable electricity to be collected from those areas rich in renewable energy resources and where there is environmental capacity (e.g. parts of upland Scotland for onshore wind, tidal streams in north Scotland, wave power in north and west Scotland, offshore wind).

    — minimise any problems arising from the intermittency of renewables, and the need for backup conventional generation.

    — enable distributed and small-scale generation to become a reality, allowing small scale renewable generators and distributed plant including CHP to be developed locally, so as to meet local demand, reduce the need for strategic interconnection, and helping to foster a new public awareness of the relationship between energy use and the requirement for energy infrastructure.

    — deploy best environmental practice, placing a much higher priority on undergrounding of electricity networks or the use of undersea cables so as to reduce visual and landscape impacts, albeit with recognition of potential impacts on habitats and the need to secure an appropriate cost balance.

Q2.   How do we ensure the regulatory framework is flexible enough to cope with uncertainty over the future generation mix?

  6.  At present the regulatory framework is demand-led, that is the electricity network is developed by transmission companies in response to demand expressed by proposals for new generation. This process is inadequate in the face of current needs for a strategic change to equip the UK in meeting climate change targets. While demand-led regulation may operate at a lower level, there is a need for Government to develop a high-level strategy for the development of the electricity network, as a key infrastructure requirement. That strategy should be developed taking account of:

    — associated potential environmental impacts—e.g. by undertaking a strategic environmental assessment. The impacts considered should include the visual, landscape and biodiversity impacts associated with overhead power lines and buried cables, as well as the climatic benefits of enabling the UK's climate change targets to be met;

    — the available renewables resource in different parts of the UK and surrounding waters, and their ability to accommodate such development within their environmental capacity;

    — the uncertain timescales over the development of technologies such as wave power or carbon capture and storage. The strategy might identify a number of options, deployment of which would depend on such technological progress. It should take account of the risks and uncertainties for generating technologies throughout their life-cycle; and

    — the need for network infrastructure to be resilient to the impacts of changing climate and associated weather events, weather patterns and coastal and river flood risk.

  In this connection we are aware of the recent report by the Electricity Networks Strategy Group "Our Electricity Network: a Vision for 2020" which is a welcome forward look at requirements to 2020. However we note that it is purely a technical appraisal in terms of expected transmission requirements; it does not include any environmental considerations.

Q3.   What are the technical, commercial and regulatory barriers that need to be overcome to ensure sufficient network capacity is in place to connect a large increase in onshore renewables, particularly wind power, as well as new nuclear build in the future? For example issues may include the use of locational pricing, or the availability of skills.

  7.  In Scotland, there has been widespread development of onshore wind power and there are many new proposals in the planning pipeline. While there are some grid capacity limitations in south Scotland, it seems likely that these can be addressed through grid reinforcement or new grid sections without major contention. For north Scotland and the northern islands, however, there is a need for major new network capacity between the demand centres of central Scotland and distant areas of prime wind resource including Morayshire, East Highland, Caithness and Shetland.

8.  We point to four ways in which regulation might be improved.

(i)  Setting environmental standards

  9.  SNH was an objector at the Public Local Inquiry for the Beauly-Denny strategic grid enhancement. While we supported the overall need for a grid enhancement in principle, and stressed that support at inquiry, we were not satisfied that the transmission companies had undertaken a sufficiently thorough exploration of alternative options, including the option of undergrounding, in two sensitive sections—one of which was where the proposed line would cross the Cairngorms National Park. That exploration only took place through the public inquiry as a result of the interventions by SNH, the relevant planning authorities and many other parties.

10.  Some see this as an example of a "regulatory barrier" which has delayed an important proposal by a period of years. Our view is that it is indicative of a lack of Government encouragement as to the need to pursue best environmental options in developing electricity infrastructure. Currently there is a "vicious circle" in which Ofgem interprets its requirement to regulate to protect the interest of consumers as meaning that network developments should be identified at lowest cost; while the grid companies argue that if they design developments other than at lowest cost, they will not be approved by Ofgem. Ofgem accepts that a higher cost option may be necessary if it is deemed to be a requirement by the planning system. This approach sets up the planning system as a "regulatory barrier" and in our view is likely to lead to continued contention over major grid proposals in the future.

  11.  We strongly recommend that Government articulates some clear guidelines on the expected environmental standards of electricity network development and associated energy infrastructure. These guidelines should include acceptance that higher cost options including undergrounding of high voltage cables or the use of undersea cables are required in some locations in order to avoid potential adverse impacts on landscapes and local communities. Underground and undersea cables are by no means a panacea—they have many associated environmental impacts of their own—but should play an important role in enabling a UK electricity network to develop without an overall increase in wirescape impacts.

(ii)  Use of underground and undersea cables

  12.  The use of high-voltage underground cables for strategic grid lines has to date been limited in the UK, but there is considerable experience elsewhere in Europe. The use of solid dielectric cables has now generally replaced the use of oil-filled cable technology, even at the highest voltages, thus avoiding the potential oil pollution problems associated with the latter. There is a need to promote greater confidence in the use of underground cable technology, by ensuring free flow of information on any problems in installation and use.

(iii)  Consents process for underground high-voltage cables

  13.  There is an anomaly in the consents system, in which overhead power lines of voltage 20kV or more require ministerial consent under Section 37 of the Electricity Act, while underground power lines, at whatever voltage, do not. Nor do they require planning consent, as they are deemed permitted development (in Scotland, under the General Permitted Development Order). We currently have the situation in Scotland in which a strategic high voltage electricity link is being proposed between Beauly and the Western Isles, deploying an underground DC cable across nearly 50 miles of the Scottish Highlands, without a need for planning or Electricity Act consent. Installation of an underground cable is no minor work—it involves disruption of ground on a scale similar to that required for a pipeline installation, and there are cable joints and cable heating effects to be considered.

14.  Consent is however required, from SNH, where such a cable affects any site of special scientific interest. SNH may therefore in the position of exercising a consent over small parts of a major linear engineering project, in principle without the need to consider the project and its benefits within the context of the development plan. We suggest that this is an anomaly which should be put right—for example through inclusion of underground cables above a certain threshold capacity or voltage within the scope of Section 37 of the Electricity Act, and possibly by qualifying the scope of permitted development status within planning legislation. This would enable Scottish Ministers or the planning authority to take a view of the project as a whole, including any impact it may have on SSSIs, seeking advice as required from SNH. While this might be seen as an additional regulatory requirement, rather than overcoming a regulatory barrier, in the long term it will be in the interest of transmission companies that major transmission routes carry the consent of the local authority. There is no need for such a new regulatory requirement to impinge on the present ability for low voltage local cables to be undergrounded as a form of permitted development.

(iv)  Rules for grid connection

  15.  In some parts of Scotland renewable generation proposals have been delayed because of a lack of grid connection capacity. We welcome the flexibility applied by Ofgem in some "Renewable Energy Zones" whereby new renewable generation can be developed on the basis that at times it may be constrained off. This seems an appropriate approach, particularly for outlying or island areas, where there is a reasonable expectation that grid connection capacity will be enhanced in the future.

Q4.   What are the issues the Government and regulator must address to establish a cost-effective transmission regime?

  16.  We identify three issues:

    — Regulators should have as a key objective the need to secure carbon reductions compatible with the targets in the UK Climate Change Act and Climate Change (Scotland) Bill. Therefore, decisions should be taken which are consistent with the overall emission factor for UK electricity supply reducing over time, in accord with the needs of the climate change programme, and with a goal for 2050 of having a virtually carbon-free electricity system.

    — Offshore renewables development offers a clear opportunity for Government to adopt a strategic approach to the provision of grid connections, with a view to minimising the number of offshore cables laid, the number of grid landfalls and the need for associated grid infrastructure at the coast, and the overall disruption to the seabed. Such an approach should also help to reduce duplicative costs. Where a grid connection is developed as a component of a specific generation development (rather than part of the nationally-operated grid), the regulatory system needs the ability to oblige an operator to make spare capacity available, under reasonable network access rules, to other generators.

    — Through Ofgem, Government has established a high level of electricity network reliability through the application of national grid standards including the requirement that the grid system has a high level of redundancy built in, such that failure of any one component will not disrupt electricity supply. SNH is not able to comment on the need for or desirability of maintaining these grid standards across all parts of the UK. However we suggest that Government needs to keep under review whether these standards remain appropriate and cost-effective, in circumstances where there is a wider range of generation sources than hitherto, and, in due course, where the level of distributed and embedded generation may be sufficient to provide electricity to meet those electricity needs deemed essential.

Q5.   What are the benefits and risks associated with greater interconnection with other countries, and the proposed "supergrid"?

  17.  Interconnection with other countries would enable the UK to minimise the level of little-used conventional power generation capacity which may otherwise have to be installed simply to cover for intermittency in renewable generation.

Q6.   What challenges will higher levels of embedded and distributed generation create for Britain's electricity networks?

  18.  Embedded and distributed generation may in early years be less reliable than current major plant. However once developed in number they will provide a level of local supply which should reduce the risks associated with strategic grid failure and reduce the need for conventional plant to cover for the intermittency of large-scale renewable generators. The challenge for electricity networks is to provide the flexibility needed to accommodate any intermittency in local production, and to enable connection to the grid at a cost which is not a disincentive to the development of embedded and distributed generation.

Q7.   What are the estimated costs of upgrading our electricity networks, and how will these be met?

  19.  No comment.

Q8.   How can the regulatory framework ensure adequate network investment in light of the current credit crunch and recession?

  20.  As explained above (Q3) we believe there should be a strong element of Government vision in the development of a strategic grid network. Government could place an obligation on grid companies to develop plans and to secure approval for the development of networks which match up to that Government vision. That would not of itself ensure network investment, but it would ensure that when that network investment funding becomes available, it can be translated with immediate effect into implementation of agreed plans, rather than triggering the start of a lengthy planning process. There would be a need to approve early expenditure on the development of such plans.

Q9.   How can the regulatory framework encourage network operators to innovate, and what is the potential of smart grid technologies?

  21.  One of the main and commonest arguments made against renewable technologies is that they are intermittent, and therefore require back-up by fossil fuel power stations which may remain unused for large periods of time. Smart grid technology should be seen as an important tool in accommodating intermittency, for example by activating local or distributed generators, or by limiting non-crucial demand, at times when there is a shortfall in supply, and by directing electricity to storage systems (heat or electricity) at times of surplus. The development of storage systems may require new incentives.

22.  In the future, when it may be expected there will be very substantial dependence on renewable generation, it seems likely that the concept of "electricity demand" will have to become more clearly structured into, for example "essential demand", "desirable demand" and "optional demand" so as to facilitate active demand management by grid operators. Structuring demand in this way would enable peak load periods to be spread, using smart grid technology in combination with differing tariffs for different types of demand. Reduced peak loads would translate into a reduced overall requirement for energy infrastructure.

Q10.   Is there sufficient investment in R&D and innovation for transmission and distribution technologies?

  23.  No comment.

Q11.   What can the UK learn from the experience of other countries' management of their electricity networks?

  24.  Our impression is that there is considerable experience of installation and operation of high voltage underground cables elsewhere in the world. It would be helpful to ensure that such experience is collated in an open, transparent way so that there is a widely shared understanding of best practice and the construction and operational costs of such installations.

March 2009




 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 23 February 2010