The future of Britain's electricity networks - Energy and Climate Change Contents


Memorandum submitted by Scottish Power

  ScottishPower is a major owner and user of electricity networks in Great Britain. We own the high voltage transmission network in the South and Central Belt of Scotland, working with National Grid who act as the GB System Operator. We also own and operate the electricity distribution network in the same area, together with that in the Merseyside and North Wales (Manweb) area. As a network user, ScottishPower has some 6,000 MW of power generation, being mainly coal fired units in Scotland and gas fired units in England, and sells electricity to over 3 million customers.

SUMMARY

  We welcome this inquiry, which is timely as the GB network is beginning to be re-configured toward a low carbon future in which renewables, nuclear and carbon capture and storage are expected to be the key technologies for power generation. The main points we would like to make are as follows:

    (a) In practice, the decarbonisation of our electricity will mean a considerable increase in the use of wind generation in the North of Britain, especially Scotland. There will also be the need to accommodate significant new inflows of nuclear power, likely in our judgement to come from existing nuclear sites both in the South of England but also in Wales and the North.

    (b) Against this background, the essential task is to get on with ensuring that the new generation plants, whose location is essentially fixed by the resource or other constraints, can be connected without undue grid constraint problems. This can only be achieved by pressing ahead with the significant grid upgrades that have been identified in the Energy Network Strategy Group (ENSG) final report. Ofgem has granted the funding to allow for the design of the key high priority upgrades and it will be important that the construction funding is made available in a timely manner.

    (c) We have been concerned that Ofgem have allowed themselves to be distracted by creating elaborate schemes of locational price signals and incentives around the necessary grid enhancements. These will not change the underlying realities of what needs to be done, but could increase costs and delay delivery by deterring and distracting investors. Instead, we would urge Ofgem to utilise the mechanism in the existing transmission price control to fund the necessary investments.

    (d) More generally, it is important that price controls for the ongoing operation and refurbishment of the networks reflect the challenges to investment posed by current credit conditions. We see the markets applying significantly higher premia to both equity and debt; in order to attract capital which the markets (or holding companies) could allocate elsewhere, network companies will need to show rates of return which are competitive with other similar opportunities elsewhere. Recent price control innovations in Britain have increased the risk borne by network companies, which could cause investors to question whether they can be sure that efficiently incurred expenditure will be remunerated.

    (e) The availability of suitably skilled individuals needed to deliver the required investment represents a significant risk.

    (f) Smart metering and smart grid can play a helpful role in mitigating some of the variability in wind generation and in more efficiently handling micro generation, and we support their continued development. However, significant back-up will be necessary for wind (where calm conditions can last several days) and we consider that large scale low carbon sources such as wind farms, CCS and nuclear will inevitably be the mainstays of the future network.

THE COMMITTEE'S QUESTIONS

1.   What Should the Government's vision be for Britain's electricity networks, if it is to meet the EU 2020 renewables target, and longer-term security of energy supply and climate change goals?

  1.1  The UK faces a significant challenge in delivering its share of the EU Renewables Energy target. Critical to success is Government support and recognition of the need for significant investment in network infrastructure and the creation of a more efficient and supportive planning framework. Enhancements to the networks will also be needed to support the new nuclear build that is likely to play a key role in decarbonising the electricity sector while maintaining security of supply.

1.2  There is a need for significant investment in the network infrastructure to manage the increased contribution from renewable energy, and to manage the associated peak capacity and operational and system stability issues. Innovative approaches to optimising use of present network assets as well as network expansion require serious consideration.

1.3  Delivery of the 2020 renewable energy target and the longer term goals will require swift action to ensure that; the supporting infrastructure is in place; planning decisions are made in a timely manner; and that key issues such as technology supply chain constraints are addressed. In addition to planning and infrastructure, including identifying Offshore Transmission Owners, coordinating connection between offshore and onshore infrastructure followed by construction.

  1.4  We fully support the recommendations in the Energy Network Strategy Group (ENSG) final report. This sets out a programme of priority transmission investments to resolve the constraints in the GB network and it is essential that it is implemented promptly. We welcome Ofgem's proposals to fund the necessary design work for the key priority projects and look forward to the early go-ahead for the actual construction.

2.   How do we ensure the regulatory framework is flexible enough to cope with uncertainty over the future generation mix?

  2.1  We do not consider that uncertainty is a major problem at this stage. The ENSG recommendations identify the key and immediate transmission upgrades that are required and which will enable a significant proportion of the required renewables to be connected. Additional upgrades identified by ENSG can be progressed as the renewables fleet builds up. Similarly, we believe that the feasible sites for new nuclear development are well known and that integration of the necessary grid upgrades into the process should not be difficult.

2.2  A supportive regulatory regime, aligned to Government's ambition in meeting EU targets and security of supply objectives, is paramount. Network operators have a central role to play in the delivery of energy policy objectives. However, it must be recognised that the regulatory body also bears a responsibility in delivering energy policy and it is not sufficient to simply place all responsibility for delivery with industry. Ofgem need to become an important facilitator in the process by developing a balanced, supportive and forward-looking regulatory framework.

  2.3  A key requirement of any regulatory framework is to ensure that the confidence of the financial market is retained, particularly during the current economic climate. Increasing network investment will require the provision of significant amounts of finance from the investment market and should current circumstances persist, this will mean higher financing costs and more restrictive debt covenants. Prospective investors must therefore be re-assured that all efficient expenditure by network owners is recoverable and that the rewards available to them are commensurate with the risks they are faced with in transforming their networks.

3.   What are the technical, commercial and regulatory barriers that need to be overcome to ensure sufficient network capacity is in place to connect a large increase in onshore renewables, particularly wind power, as well as nuclear build in the future? For example issues may include the use of locational pricing or the availability of skills.

  3.1  The ENSG final report highlighted that the UK will need to incorporate the use of technologies that have yet to be employed in the UK energy network that include HVDC and Series Compensation. Coupled with the expected volume of renewable generation, these could present a number of technical challenges for the operation of the network.

3.2  Under capacity of the supply chain places a significant risk to timely delivery of sufficient network capacity. A consequence of the volume of activity being undertaken in the replacement and assembly of new network assets is the ability of suppliers to deliver to short timescales. Currently forecast lead times for delivery of equipment is prohibitive in completing projects on a timely basis. In addition, the UK is now heavily reliant on sourcing equipment from oversees suppliers leaving it exposed to global markets and volatility when placing procurement contracts.

  3.3  To deliver the combined DNO investment plans in respect of DPCR5, will require approximately 9000 new posts in engineering and crafts across the industry. The unavailability of suitably skilled individuals needed to deliver the required investment represents a major risk. The industry faces a dilemma as many of the people with the necessary skills are approaching the end of their careers. This combined with the average lead-time to fully train suitable replacements in the order of 5 years, represents a significant barrier. The industry needs to be able to attract new people that have the necessary skills, education and training.

  3.4  Planning remains a significant barrier to the development of the necessary infrastructure required to accommodate new forms of generation. In order to meet the 2020 target, investment in infrastructure must take place ahead of construction of new generation. Historically, the timeline for constructing new transmission network has taken longer than for that of the new generation.

  3.4  The key to connection of a large volume of renewable and nuclear generation is the provision of infrastructure within timescales aligned with the development programmes of those generators. Short-term measures such as the rationing of capacity through an auction process or the introduction of locational charging will deter potential developers from investing in areas rich in renewable resource but lacking in transmission infrastructure. Developers require certainty over connection dates and predictability and stability of transmission costs before funding can be secured in an increasingly difficult economic climate.

  3.5  Moreover, developing these measures, which will inevitably lead to winners and losers, will inevitably distract all parties as they seek to protect their commercial interests. But, as the location of the wind resource is known, and (in our judgement) so are the locations of new nuclear power stations, these measures will not actually help get the necessary infrastructure built or lead to more efficient location of generation. Instead, Ofgem should focus on efficiently funding the delivery of the ENSG recommendations and the necessary upgrades for nuclear development.

4.   What are the issues the Government and regulator must address to establish a cost-effective offshore transmission regime?

  4.1  The successful development of offshore wind and fulfilling the potential of wave and tidal stream generation as well as the associated network infrastructure is essential if the UK is to meet its EU 2020 targets.

4.2  The proposed offshore licensing regime gives rise to individual licences for connecting offshore wind farms to the onshore grid. This will promote a `radial connection' approach and raises questions as to whether such an arrangement is sustainable or whether instead (or in addition) an offshore interconnected transmission system might be desirable from both a technical and economic perspective to fully realise the potential offshore resource. It should also be noted that significant investment in the onshore network would also be required. It will be necessary to consider an integrated approach towards the planning and design of both the onshore and offshore system.

  4.3  There needs to be acknowledgment of the importance of a coordinated approach for the development of infrastructure for Round 3 offshore projects, as opposed to the current piecemeal approach promoted through the regulatory framework for Rounds 1 & 2.

  4.4  To achieve the very significant export capacities proposed in Round 3, a strategic view of the overall infrastructure must be established which concludes, that by reacting to individual requests for connections, even when grouped together within a framework of an annual window, this will inevitably lead to an inefficient design and ultimately increase the cost to consumers. We therefore believe that there is now an opportunity to progress the Round 3 offshore transmission networks by identifying a single OFTO for each geographical area.

  4.5  As a consequence consideration of the regulatory regime needs to take place of how it can effectively deal with Round 3 connections and allow infrastructure associated with an entire development zone to be constructed by a single OFTO. Such infrastructure could be strategically developed in an economic and efficient manner with a mechanism allowing for adjustments to the revenue stream that reflect the extent of investment efficiently completed.

  4.6  The final regulatory regime is key to ensuring that potential OFTOs are attracted into the offshore arena and are able to attract the required investment from the financial markets.

5.   What are the benefits and risks associated with greater interconnection with other countries, and the proposed "supergrid"?

  5.1  Any proposal to increase the interconnection between Europe's electricity networks will require national regulators to adopt a consistent approach in performing and executing their duties. Another key consideration will be the harmonisation of the various industry codes and planning standards that governs the development of infrastructure within each country.

5.2  The financial capacity of network operators will be an obstacle for building new network against the backdrop of the current financial crisis. However, this should not detract from the fact that investment in network infrastructure is critical that further emphasises the importance of ensuring that network operators are adequately funded.

  5.3  It is widely recognised that the commercial and regulatory issues surrounding the construction and use of any proposed "supergrid" would be complex, however if EU objectives are to be met, the proposed supergrid could be an important enabler, particularly in relation to security of supply. A valuable first step would be for a cost and benefit analysis to be completed; as well as the cost of the project and the benefits in terms of security of supply, promotion of competition and greater access to energy storage, this could also consider risks such as increased exposure to power outages in other EU member states.

6.   What challenges will higher levels of embedded and distributed generation create for Britain's electricity networks?

  6.1  We are answering this question in terms of multi-megawatt connections such as distribution-connected wind farms. Different issues arise in relation to micro generation, which we will address in question 9 (innovation).

6.2  The current rate of connection for new generation is limited by the complexities of obtaining planning consents and land rights. It is also held back by the structure of incentives faced by the Great Britain Transmission System Operator (GBSO) under the current regulatory regime, whereby the GBSO is incentivised to reduce constraint payments received by generators whose energy production is restricted.

  6.3  Whilst planning remains key, it is a concern that NGET's CAP167 proposals seek to further restrict future generation connecting to the networks of distribution operators that, whilst they do not trigger any local transmission works are seen to be a contributing factor to the rising cost of constraints on the wider transmission network. This proposal, should it be implemented, would severely limit the level distributed generation connecting in Scotland. We acknowledge, however, the lack of support for its implementation from the industry as a whole. The CAP167 amendment currently sits with Ofgem for approval and it is critical to the future of distributed generation in Scotland that Ofgem do not approve the NGET proposal.

  6.4  National Grid recently issued an updated GB Queue Management methodology that now gives embedded generators the ability and right to request advancement to connection, if contingent upon future transmission upgrades. The work carried out to date by the three transmission companies has been encouraging, and has seen the advancement of connection dates of a number of projects.

  6.5  There is however a concern as to how distributed generator schemes will be treated under the enduring Transmission Access Reform (TAR) arrangements. The TAR amendments to the Grid's Connection and Use of System Codes (CUSC) focus on generators who have access rights to the transmission system, and while it is assumed that arrangements for smaller embedded generators will continue to be managed by the Statement of Works process, it may lead to small generators having to apply for explicit rights that will place more onerous obligations upon them as a consequence.

  6.6  It appears that Ofgem would prefer not to see renewable generation connected in Scotland at the present time because of the additional constraint costs that arise due to the connection. While we accept there will inevitably be short-term issues around constraints, these should be resolved by the steady progress of the infrastructure upgrades that are taking place and are planned to take place across the GB grid.

  6.7  Also, in areas where natural renewable resources are plentiful, for example wind, the distribution system if often sparse. This results in new generation triggering significant infrastructure, and in many cases will involve the construction of overhead lines. A very good example of this exists in Wales where the Welsh Assembly has laid out its TAN 8 proposals. Whilst we believe that the existing distributed generation incentive mechanism (DGIM) provides and effective framework that enables Distribution Network Owners (DNOs) to coordinate with multiple generator parties in providing efficient and timely connections, there remains a case for augmenting the DGIM to deal with very high cost strategic infrastructure projects.

  6.9  With regard to the technical challenges faced by DNOs in accommodating large volumes of distributed generation, as more distributed generation connects, it will initially displace local demand, however it will ultimately result in "export" onto the transmission system. This will have implications both for the transmission system which will need to accept power import at times from the distribution system, and for the distribution system itself which will need to be more "active" to handle the resulting power flows. This is further considered in response to question 9 ("Innovation").

7.   What are the estimated costs of upgrading our electricity networks and how will they be met?

  7.1  We agree with the estimate of £4.7bn cited by the Energy Networks Strategy Group (ENSG), to facilitate necessary GB reinforcement following studies completed by the three transmission owners based upon a range of scenarios taking into account the significant changes anticipated in the generation mix between now and 2020, in particular the large volume of onshore and offshore generation and the connection of new nuclear generation within GB.

7.2  This figure is however a relatively small proportion of the total amount that needs to be invested in the electricity network over the next few years as part of the normal investment cycle. We estimate the total investment required between now and 2020 (including the ENSG work) to be approximately £37 billion. This figure takes account of both transmission and distribution investment. It is based upon the investment levels assumed in the current transmission price controls and in the industry's submissions for the current distribution price control review, and assumes that these levels are maintained through to 2020.

  7.3  We would highlight that the current transmission price control arrangements have been, and continue to be, a successful mechanism for delivering optimal and cost-efficient investment for all forms of grid investment. In out view it is important that the present price control arrangements should continue in order to allow companies to progress existing connection and infrastructure upgrades with relative certainty over the regulatory arrangements. However given the potential scale of future grid investment beyond 2012, and the urgency to deliver this investment timeously, we would agree that there is a need to look at the process for authorising major infrastructure projects and whether this should remove the need for specific advance commitments to be made by users when the strategic requirements are already clear.

8.   How can the regulatory framework ensure adequate network investment in light of current credit crunch and recession?

  8.1  The combined DNO investment plans submitted to Ofgem in respect of Distribution Price Control Review 5, will not only be about maintaining the integrity of the UK Distribution system, but will now represent a significant opportunity to help underpin the UK's economic recovery with the opportunity to create a further 9,000 new posts in engineering and crafts across the industry.

8.2  We would highlight that the current price control arrangements have been and continue to be a successful mechanism for delivering optimal and cost-efficient investment for all forms of grid investment and are of fundamental importance to our energy future.

  8.3  Price controls have an important role in ensuring that electricity network companies are able to continue to attract investment, however successive price reviews have significantly increased the risk borne by network operators. The importance of implementing a workable and balanced set of incentives aligned with energy policy objectives needs to be recognised.

9.   How can the regulatory framework encourage network operators to innovate, and what is the potential of smart grid technologies?

  9.1  Network operators have a critical role in facilitation of a low carbon future. We have already mentioned above the fact that increasing levels of distribution connected generation will require networks to be more "active" in their operation and the possibility that this may require export on to the transmission system. In anticipation of this future, ScottishPower is involved in a range of industry-leading projects. DNOs will need to consider solutions such as voltage control, power flow management, dynamic circuit ratings and potentially energy storage technologies to deliver a better and more efficient electricity transport.

9.2  In this context, it will be important that GB network operators are able to innovate. The regulatory framework must be such that it does not create barriers to development through complex and uncertain economic schemes that are based around subjective reviews. We remain concerned at Ofgem's apparent reluctance to reintroduce the Technical Director's role within its operation. The previous incumbent in the role was a key enabler to the UK DNOs establishing the IFI scheme. This type of engineering leadership will be key in enabling network operators to meet future challenges.

  9.3  There is a need for a much closer degree of coordination between the Regulator and network operators in future, this will require an active and participating Regulator that signs onto a shared vision of the UK's energy future that network operators can deliver against. This will in all likelihood involve revisiting some decisions previously taken by Ofgem that may seem politically difficult to them at this time.

  9.4  Distribution networks will also facilitate smarter behaviour by consumers and by their appliances. Smart metering will be a key enabler of this and we welcome the Government's decision to proceed with this project; it will be important to take a decision as soon as possible on the market model for the roll-out. Demand side management by consumers will help mitigate some of the variability of wind generation; the scale of this will depend on the speed of adoption and therefore the development of appliance solutions that are attractive to consumers. Plug-in hybrid vehicles look to be a promising option. However, it must be recognised that this will not avoid the need for large scale fossil fuelled back-up, for example to deal with the possibility of calm conditions lasting for a period of several days in the winter.

  9.5  Similar considerations apply to micro generation. This provides slightly different challenges for DNOs than larger scale distribution connected generation, for example as a result of being connected at the low voltage level. Our present judgement is that this sector will remain relatively small because the underlying economics appear to be significantly worse than larger scale renewables. We would note that gas fired micro CHP is a technology that is unlikely to be a viable part of the mix as the 2050 target approaches, as its residual carbon looks too high.

10.   Is there sufficient investment in R&D and innovation for transmission and distribution technologies?

  10.1  The Innovative Funding Incentive (IFI) mechanism introduced as part of the DPCR4 has been a resounding success against which companies such as ScottishPower have levered further funding to develop and implement technologies with mid range Technology Readiness Levels (TRLs).

10.2  It is widely recognised that the facilitation of a low carbon electricity system will require changes on both the supply (high penetration of variable renewable generation resources) and the demand side (energy efficiency and the potential electrification of transport). As the network operator is the common link between these changing inputs/outputs it is recognised that these developments could lead to evolutionary change in both network topology and network operation from the largely passive system of today.

  10.3  There remains uncertainty about the choice and costs of the solutions that will be used to make the network more flexible and controllable, this being related to the availability of solutions and their positioning in the R&D lifecycle. It must be recognised that all DNOs have effectively ramped up R&D from a point of almost zero in 2005 to today's level (leveraged programme in excess of £35 million). It is an accepted fact that network related R&D has longer timescales in comparison to many other sectors.

  10.4  We recognise, through projects in our own IFI portfolio, that many of the concepts and technologies underpinning a change to a more flexible network are still very much at an embryonic stage, with little or no firm commercial offerings in the marketplace. Examples include, Active Network Management (ANM) functions such as dynamic load management, multi-generation constraint management, fault current limitation etc. However, uncertainty around the costs and choices of solutions and the inability to benchmark against other schemes in detail should not, in itself, become a reason for delaying investment in these enabling technologies. In order to avoid such behaviour a `no regrets' approach to specific and targeted expenditure to such projects would be of benefit.

  10.5  It is increasingly apparent that a wider form of cross sector participation is required to facilitate the paradigm shift to a low carbon energy system. We would acknowledge that working as an individual DNO, or even a body of network operators is insufficient to develop a future network in the most economic and "future-proofed" manner.

  10.6  Feedback from recent stakeholder events highlighted the need for active engagement of network operators with suppliers (smart metering), generators (energy mix), planning authorities (geographical issues) and other key stakeholders (eg car manufacturers—relating to "plug-in" hybrid vehicles) in order to fully understand the risks and opportunities presented by changes outside of the current networks arena.

  10.7  It is fundamental that in order to meet these challenges, network operators need to be appropriately resourced.

11.   What can the UK learn from the experience of other countries' management of their electricity networks?

  11.1  We would observe that the UK has a tradition of investing the minimum in infrastructure and utilising assets for as long as possible. While this does indeed save money in the short term, there is a risk that it builds up a bow wave of under-investment that is expensive, both for consumers and utilities. We believe that continental utilities have generally adopted a more regular asset replacement programme that has led to a lower average age of the assets and avoided the replacement build-up that we currently face.

11.2  A number of other countries have also pressed ahead with the introduction of smart metering as a DNO led activity. While the market model is open to debate, it is instructive to learn that some others are ahead of us in this field, and have succeeded through an organised programme.

March 2009




 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 23 February 2010