The future of Britain's electricity networks - Energy and Climate Change Contents


Memorandum submitted by Scottish Renewables

  Scottish Renewables is Scotland's leading green energy trade body. We represent over 240 organisations involved in renewable energy in Scotland and include many environmental NGOs in our wider associate membership.

Scottish Renewables believes that the harnessing of renewable energy sources in a sustainable manner provides a unique opportunity to not only tackle climate change but to provide economic benefits to Scotland. Regulatory and public policy on energy and reducing carbon emissions is vital if we are to send the right signals to industry and wider society that significant changes are required to establish a low carbon economy.

EXECUTIVE SUMMARY

  1.  Strong and long term signals to investors is absolutely crucial if a fit for purpose electricity network is to deliver a decarbonised and reliable electricity supply.

2.  Scotland's role in delivering the UK's targets for renewable electricity by 2020 is significant and particular attention should be placed on delivering this potential.

  3.  Access to electricity networks remains the number one barrier to delivering renewable electricity objectives and action on planning and the regulatory regime needs to be addressed urgently.

  4.  Demand side management of electricity generation requires innovation such as better responses to "peak demand", better and more extensive storage, and a shift from transmission to local distribution networks.

  5.  "Connect and manage" is the best way to manage temporary shortfalls in transmission supply and connect generation that is socially and environmentally beneficial.

  6.  The scale of transmission charging in the north and islands of Scotland undermines investment in all new generation, conventional and renewable, and therefore hampers our efforts to make a telling contribution to climate change and deliver affordable supplies of electricity.

  7.  Allow small generators to contract with Distribution Network Operators (DNO) rather than the transmission operator and allow the DNO to manage the "interface" between distribution and transmission.

INTRODUCTION

  8.  Scottish Renewables, the leading green energy trade body in Scotland, appreciates the opportunity to provide written evidence on the fundamentally important issue of electricity networks in Scotland[111] and the wider Great Britain market.

9.  It is fundamentally important because investment in any new infrastructure generally enables economic development. In the case of the investment in transmission networks, especially in Scotland, it also allows, through the deployment of renewable electricity projects, an effective response to climate change and energy insecurity.

  10.  The Committee poses a number of questions in launching this timely inquiry, the first of which is the most important and relates to the Government's vision for electricity networks. In answering that question I hope to be able to also provide evidence in relation to the subsequent questions that the Committee poses.

BEYOND 2020

  11.  In responding to the "vision" question it is necessary to have a picture of how energy will be both used and generated in the UK over time so that electricity, heat and transport are decarbonised. I am confident that this will form an important part of your inquiry.

12.  This will be subject to some debate and uncertainty but a strong and long term signal to the investors is absolutely crucial if a fit for purpose electricity network is to deliver a decarbonised and reliable electricity supply.

  13.  The recently published UK Committee on Climate Change's first annual report describes a UK electricity supply that is all but emission free and supplying energy for heat and transport as well as for its more traditional uses.

  14.  If this is the case then long term investment and innovation will be required if that electricity supply is to be both affordable and reliable.

  15.  Scottish Renewables believes the management of demand will be crucial. Presently demand is typified by severe peak and troughs over very short periods and this is likely to continue until there is investment in innovation in demand side management.

  16.  On the supply side this is currently more actively managed and, in terms of reliability, currently successfully so.

  17.  As the generation mix in Great Britain changes to accommodate more and more renewable electricity technologies and capacity there should be greater management of the demand side. This demand side management involves thinking about how to most effectively respond to peaks and troughs in demand. Responding to "peaks" might involve powering down non-critical devices and using back-up technologies such as storage or zero emission coal and "troughs" using any "surplus" generation to feed into extensive storage capability to provide a flexible response in peak periods.

  18.  The balance may also shift from transmission to distribution. Whilst there is still a requirement for investment and innovation in distributed networks there ought not to be significant barriers to "local" networks feeding "local" supply to "local" customers. "Local" could range from larger distributed generation using hydro, wind or combined heat & power to the domestic where households control their own generation and demand.

  19.  However, it should also be pointed out that I am not trying to articulate a vision of a world with no transmission networks—these are still likely to be required—but rather where distributed generation and networks play a more prominent role in our everyday lives.

DELIVERING 2020

  20.  That is a long term vision probably taking us beyond 2020. A recent report by the Electricity Networks Strategy Group (ENSG), Our Electricity Transmission Network: A Vision for 2020 has been recently published. This should be essential reading for the Committee.

21.  It outlines the necessary investments in transmission to deliver 2020 renewables targets. The level of investment required is significant and, if the target is to be met, largely in place before 2020.

  22.  The report describes the investment needed to deliver renewables potential and offshore wind potential in the north of England and Scotland and sends a strong signal to Transmission Operators (TO) what and where they are likely to invest. It is important therefore that work on these upgrades and reinforcements should start as quickly as possible. That is why industry has welcomed the proactive approach taken through the ENSG and the permissions given by Ofgem to TOs to start preliminary work on design and planning so that delays to connection are minimised.

  23.  Whilst we hope that there will be access to the transmission network available to those that need it and when they want it this is unlikely to be the case. That means there needs to be a regime in place that manages this imbalance in supply and demand.

  24.  The Transmission Access Review (TAR) has sought to resolve this issue in a way that promotes the connection of new renewables generators whilst protecting the rights of existing generators.

  25.  This has proved a difficult process that has placed a significant burden on the whole electricity sector. The debate has centred on how access rights can be managed and the costs attributed.

  26.  The debate has brought the transmission management model of "connect and manage" to the fore. Connect and manage is a way to provide controlled access to generators whilst managing any costs in providing that access. In practical terms it might mean providing access to all renewables generators and in times when there is congestion on the networks managing the costs so that they are minimised and not a significant burden on the consumer.

  27.  Whilst the Committee is deliberating, TAR will start to play out. Connect and manage is not the only option on the table but it is we believe the best way to manage temporary shortfalls in transmission supply and connect generation that is socially and environmentally beneficial.

  28.  What ENSG and TAR should tell us is that our long and medium term visions can be bold, inspirational and responsive to all our needs but ultimately if the rules and regulations that govern electricity networks are not fit for purpose we will ultimately be disappointed.

SCOTLAND

  29.  To deliver 2020 renewable electricity targets Scotland will be required to lift current installed capacity of 3GW of renewables to more than 11GW. This 11GW will be around a quarter to a third of UK requirements and demonstrates the importance of Scottish renewables generation to meeting the 2020 objective.

30.  What is exercising the Scottish renewables industry now is a combination of severe short term challenges and long term uncertainty. In Scotland these principally relate to issues of access to the transmission network and the cost of using it. We believe the Committee should pay considerable attention to Scotland because the problems being played out here will be visited upon the rest of the Great Britain market in the coming years.

  31.  In Scotland more than nine gigawatts (GW) of potential renewables capacity is contracted to connect to the grid, with more than half having to wait until after 2014 and many beyond 2018. This is caused by an undersupply of transmission capacity in Scotland and northern England. Some of this blockage will be removed by the consent and build of the Beauly to Denny transmission upgrade[112] and the completion of reinforcements to the Cheviot Boundary. The former, importantly, will also release further reinforcements in Scotland allowing more than 5GW of installed capacity to connect.

  32.  If you apply a planning attrition rate of 50% to the 9GW mentioned above then these reinforcements will be sufficient to provide necessary firm access. However, Beauly-Denny has been a source of significant frustration to the renewables industry in Scotland. It was first conceived in 2001 and was formally submitted into planning in 2004. A public inquiry was subsequently triggered and it was only last month when Scottish Ministers received the Reporter's opinion. If it is consented this month it will be completed by 2012 and projects can connect. From conception to completion it will have taken 11 years—which seems pretty standard for deployment of new transmission networks across the UK. This must improve if 2020 and subsequent objectives are to be achieved.

  33.  Recently National Grid introduced a scheme of active "queue management" to ease the Scottish congestion and has identified 450 megawatts (MW) of capacity that can connect earlier than currently contracted. In part this is in response to the Transmission Access Review, a joint initiative of the UK Government and Ofgem to connect renewables projects in a timeframe consistent with their project timeline.

  34.  Scottish Renewables welcomed the National Grid initiative but recently Ofgem has threatened to block it because of concerns about high levels of constraint costs predicted for the GB network. We are frankly incredulous at this turn of events especially where Ofgem appear to be u-turning on a commitment it made last year to support the kind of measures identified by National Grid to connect renewables more quickly.

  35.  The subsequent debate has seen Ofgem accept that the cost of congestion is not going to be as high as first thought and a consensus that higher than usual annual costs will be temporary whilst the Cheviot Boundary reinforcements are completed.

  36.  However, current and future Scottish generators in the North of Scotland and the Islands face considerable burdens from the cost of using the transmission network. For many generators the cost of these charges account for 25% of turnover (whereas counterparts in the south of England are paid to use transmission networks) and from year to year the charges are unpredictable and highly volatile.

  37.  That is why we, along with the Scottish Government, ScottishPower and Scottish & Southern Energy put forward an alternative charging model.[113] At present the current charging model is supposed to encourage generation to locate close to demand and is expected to be proportionate to the cost of running the transmission network. However, the locational principle is only an academic point for renewables generators because they can only go where there is a resource unlike conventional power. Also it is clear that the cost of the charge is not proportionate to the cost of the impact on the transmission network of new generation.

  38.  That is why Scottish Renewables is clear that the scale of transmission charging in the North and Islands of Scotland undermines investment in all new generation, conventional and renewable, and therefore hampers our efforts to make a telling contribution to climate change and deliver affordable supplies of electricity.

  39.  The model currently used is developed by National Grid and approved on a periodic basis by Ofgem, the regulator. The new model that we have put forward with our partners introduces a "postage stamp" approach to charging that is proportionate, predictable and stable and will do much to promote new generation in the UK. Importantly this approach will not add to the cost of electricity to the consumer.[114]

  40.  It also has the virtue of being inline with current European thinking which concludes that renewable generation in geographically peripheral areas must not be discriminated against in any charging regime. The industry believes that the current regime discriminates against generators in the North and the Islands and that Ofgem and National Grid have a strong case to answer.

THE OFFSHORE REGIME

  41.  Scottish Renewables has concerns that the Offshore Transmission Operator (OFTO) regime designed to deliver relatively modest offshore wind interest in Round 2 will not be capable of delivering the step change in delivery required under Round 3. This is because it does not promote co-ordinated transmission capability and, therefore, there is the significant risk of an over-build of offshore networks.

42.  Scottish Renewables would like to see a review of the current OFTO regime conducted after each milestone is reached in Round 3 delivery.

  43.  If we can get this right the potential for European interconnection is greater. The benefits of interconnection are significant and will allow the UK the opportunity to make the most of its renewable energy potential.

OFGEM REMIT

  44.  Scottish Renewables believes that the Social & Environmental Guidance that has been given to Ofgem by the Secretary of State for Energy and Climate Change may have a positive impact on challenging issues of access and charging. However, if it does not then we believe that Ofgem's remit should be changed by legislation in Westminster so that it gives equal prominence to affordability and action on climate change.

DISTRIBUTED GENERATION

  45.  Often when there is a debate about transmission issues smaller generators that use the distribution networks are often forgotten even though many small generators are being forced to pay both distribution and transmission network charges.

46.  Many small generators will be contracted to use both networks based on their installed capacity because there is a theoretical risk that some of their electricity will reach the transmission network. At present many small generators are paying charges as if they are using both networks 100% of the time even though only a proportion, and often none, of the electricity generated will reach the transmission network. Scottish Renewables promotes the concept of the "gross-net" model whereby small generators pay for the amount of transmission they actually use.

  47.  We also propose, and this has some support across the industry, to allow these small generators to contract with the Distribution Network Operators (DNOs, in Scotland: ScottishPower Distribution; and Scottish Hydro-Electric Power Distribution) rather than the transmission operator and allow the DNO to manage the "interface" between distribution and transmission.

  48.  The DNO "Agency model" would create one point of connection, contact and charging for all small scale generators and would incentivise the DNO to actively manage networks and demand to maximise asset value.

  49.  This would be a positive shift that would enable the connection of more renewable electricity generation and importantly, make it easier for community projects to get off the ground.

  50.  Any discussion about the electricity grid usually boils down to the related issues of access and cost. Scottish Renewables believes that unless both are resolved in the way we outline above the Great Britain market is unlikely to deliver its full renewable electricity potential.

March 2009




http://www.scottishrenewables.com//MultimediaGallery/1f497cc5-a276-4ac2-85bc-a48bd947b1e7.pdf



111   The Committee may find useful a Glossary and Acronym list published by Scottish Renewables in partnership with Senergy Econnect as they consider the issue of electricity networks. It can be found here: Back

112   SSE website link. Back

113   You can view the consultation paper here www.nationalgrid.com/uk/Electricity/Charges/modifications/uscmc/. The consultation code is GB ECM-17. Back

114   It may also be worthwhile noting that the entire cost of building and operating the transmission network across the UK accounts for only 3% of a typical household's electricity bill. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 23 February 2010