The future of Britain's electricity networks - Energy and Climate Change Contents


Memorandum submitted by Professor Goran Strbac, Imperial College London

EXECUTIVE SUMMARY

  In common with most industrialised countries, UK electricity networks were significantly expanded after World War II to support the economic growth of the country, utilising the developments in large scale generation technology of that time. This system now faces challenges of unprecedented proportions. By 2020, according to the Government Renewable Energy Strategy (RES), it is expected that 40% of the UK electricity demand will be met by renewable generation (an order of magnitude increase from the present levels). In the context of the targets proposed by the UK Climate Change Committee (greenhouse gas emission reductions of at least 80% in 2050) it is expected that the electricity sector would be almost entirely decarbonised by 2030, with potentially significantly increased levels of electricity production and demand driven by the incorporation of heat and transport sectors into the electricity system. Delivering these targets cost effectively will require not only an appropriate investment in electricity infrastructure, but also fundamental changes in the philosophy of network operation and development enabled by the application of information, communication and control infrastructure to enhance the utilisation of the existing networks. This requires urgent development of a new technical, commercial and regulatory frameworks associated with the operation and development transmission and distribution networks to support the new network operation paradigm in order to facilitate timely and efficient connection of new forms of generation. In this context, this contribution deals with the following four topics:

(i)   Transmission network operation and design standards (GB Security and Quality of Supply Standards)

  Given the pressing need to provide additional transmission capacity to accommodate renewable generation, our major concern is that the outdated GB SQSS (philosophy developed in 1948 and unchanged since) presents a potential barrier for the application of a range of advanced technically effective and economically efficient non-network solutions that can release latent network capacity of the existing network. Rules that are used to determine the amount of capacity that should be released to network users may be inefficient and limited to the application of asset heavy network solutions to network problems. If updated within a true cost-benefit framework, this would result in a reduction of costs of network constraints and facilitate faster and cheaper connection for renewable generation. We are concerned that the significance of the development of new standards for future transmission network operation and development has not been fully recognised by Ofgem and Government.

(ii)   Network regulatory framework

  Similarly, present network regulatory approach heavily incentivises investment over operational alternatives, which is a significant barrier to the application of innovative technically effective and economically efficient solutions that can enhance the utilisation of the existing network. Network designers and operators are incentivised to consider asset heavy solutions and are not rewarded adequately for releasing network through potentially more efficient non-asset solutions. If the present regulatory approach is urgently updated to incentivise network operators to maximise the benefit of the network to network users, this will facilitate faster and more efficient connection of renewable generation.

(iii)   Network access regime

  Present commercial access arrangements associated with access to transmission network are inefficient due to the absence of locational cost signal associated with the use of transmission network in the short term (the reason for Transmission Access Review started in 2007). The present access arrangements have contributed to the large increase in the cost of network constraints that have recently been a subject of very serious concerns by industry, government and the regulator (costs of constraints increased by a factor of three in the last three years). It is important to recognise that this significant increase in network constraint costs was not driven by changes in generation background or reductions in available network physical capacity, but primarily by the design of the present transmission access regime. If an efficient location specific allocation of constraint costs is introduced, this would result in a reduction of constraint costs and facilitate faster and more efficient connection of new renewable generation. We fully support efforts of Ofgem and National Grid that suggest that cost of short term network operation should be allocated on a location specific basis, following the principles of cost reflectivity and economic efficiency. However, there are a number of remaining concerns we have with the future access regime: demand is excluded from participation in short term access, which is inefficient, discriminatory and contradicts the development of Smart Grids; the spread in imbalance prices is above efficient levels which artificially increases network constraint costs and inflates the need for transmission investment and we are concerned that this issue has not been considered by the regulator; Network charging mechanism is not fully cost reflective, and as such may be a contributor to increasing cost of constraints and if unchanged, could lead to inefficient network investment; Our work demonstrated that wind generation tends to drive less transmission network capacity than conventional plant but network charges do not reflect this, and hence discriminate against wind; There is a serious case of undue discrimination in the network regulation between on- and offshore generation: onshore wind is entitled to receive compensation due to unavailability of the onshore transmission network but offshore wind is not.

(iv)   Smart Grids: Opportunities for UK

  The decarbonisation of electricity and energy systems beyond 2020 with the present operating paradigm would require a very significant capital investment in primary generation and network assets while simultaneously degrading the utilisation of these assets. An alternative solution, involving innovations in ICT technology and active network management, would be potentially cheaper, faster to implement and more commercially adaptable than simply building more primary assets. The core issue facing the network in the future is not only to make our grids larger, but much more importantly to make them more intelligent. Development of a Smart Grid technology strategy is of considerable relevance to the UK, given its weak interconnections with other systems and the need to balance demand and supply largely within the GB Island. These challenges could be turned into an important commercial opportunity for the UK to gain early experiences and lead the worldwide system integration of advanced future grid technologies at the international level.

  The importance of the above issues is in our view very significant. This present GB SQSS, the present regulatory regime and the present network access arrangements formed the basis for the transmission network reinforcements recently presented by Energy Network Strategy Group (ENSG), needed to accommodate renewable generation to meet 2020 target.[116] This involves a single, business as usual, asset heavy solution, constrained by the present regulatory incentive approach and inefficiencies in network access arrangements. Although it is clear that some significant network reinforcements will be needed, complementary and alternative solutions based on more sophisticated network management techniques (such as dynamic line rating, wider application of advanced special protection schemes, coordinated control, application of advanced maintenance techniques, application of advanced decision making tools etc) and application of non-network solutions particularly demand and generation solutions that can substitute for network reinforcements, were not considered. Furthermore, in this exercise the justification for network investment was based on observed inefficient constraints costs.

  Network assets have a lifetime of 50+ years and if the questions of network operation and design standard, network regulation and access regime are not addressed with some urgency, a major opportunity for the development of 21st century GB transmission network may be significantly slowed down and we may be locked into potentially costly investment strategy driven by outdated network design standards and inappropriate regulatory and commercial frameworks. The incumbent UK network regulation framework and network operation and design standards favour the release of new network capacity through network asset reinforcements and this is incompatible with the concept of Smart Grid. Under the Smart Grid vision, non-network solutions, particularly demand side participation are expected to play a vital role in enhancing transmission and distribution network utilisation and hence facilitating an efficient delivery of low carbon future; this future will not be realised if the current network technical, regulatory and commercial approaches are not urgently changed.

  A key opportunity to facilitate efficient operation and development of smarter transmission network in support of the UK low carbon energy policy is presented by the Fundamental Review of GB Supply Quality and Security Standards, Ofgem's Review of RPI-X, Transmission Access Review and Smart Grid initiative.

1.  FRAMEWORK FOR FUTURE NETWORK OPERATION AND DESIGN STANDARDS

  1.1 In the context of the RES, wind energy is the principal commercially available and scalable renewable energy technology, and is expected to deliver the majority of the required growth in renewable energy, continuing to be the dominant renewable technology out to 2020. Recent ENSG Report showed that the cost of on-shore transmission network reinforcements needed to accommodate on and off-shore wind generation will be very significant. This work however was based on the outdated approach to network planning and network control, cost of transmission network constraints based on inefficient network access arrangements within the regulatory regime that is known to incentivise assets heavy network solutions to delivery of additional network capacity. Within 2020 and beyond, a complementary approach that involves a departure from the current practice should be urgently considered, as it could deliver significant increases in network assets utilisations and hence a significant reduction in cost relative to this baseline and facilitate faster connection of renewable, without unduly compromising on network security.

  1.2  Such an approach, based on a cost benefit framework rather than on the present deterministic standards that exclude potentially technically effective and cost efficient operational solutions from being considered, would require:

    (i) a shift in the source of the system control and flexibility from physical assets to more sophisticated system management, through wider deployment and application of appropriate control, information and communication technologies, and

    (ii) a re-allocation of the duties and opportunities for the provision of system control services to include demand side, wind generation technologies that use power electronics interfaces and modern network technologies, in addition to network primary assets.

  1.3  Although there are a number of drivers for the Fundamental Review of the GB SQSS the key concerns are that the present network standards:

    — are potentially inefficient and do not deliver value for money to network users, ie that the network standards unduly restrict user's access to the system and hence prevent optimal utilisation of the existing network infrastructure; and

    — impose barrier for innovation in network operation and potentially prevent implementation of technically effective and economically efficient solutions that enhance the utilisation of the existing assets (ie present standard is based on prescribed levels of asset redundancy and is clearly an obstacle for the application of Smart Grid technologies).

  1.4  The overarching concern is that the historical approach to network planning and operation is inherently inefficient and will adversely impact the development of the UK low carbon future, both in terms of timing and costs. The work carried out by SEDG and others (at the international level), points out that the present standards are inadequate and that the philosophy of the network standards should change from deterministic to a cost-benefit approach. This change is necessary if the above concerns are to be comprehensively addressed. There is a clear trend of adopting cost-benefit framework as the basis for network operation and investment (for example in Victoria in Australia, New Zealand, Chile).

  1.5  Establishing an optimal level of network capacity that should be made available by network operators in real time must appropriately balance (i) the value that users attribute to the level of network capacity released, through being able to access efficient generation resources, against (ii) cost of this access, primarily driven by various forms of generation reserves, losses and expected costs of interruptions (primarily caused by forced outages of generation and network facilities) that is associated with the released network capacity.

  1.6  However, it is important to emphasise that network operators should be appropriately incentivised to provide additional network capacity through not only building transmission circuits (asset based redundancy), but through non-network solutions involving demand and generation and more sophisticated network management, whichever is more efficient. The present deterministic GB SQSS framework fundamentally prevents non-network solutions to be adopted, even if these are technically effective and economically efficient.

  1.7  Cost-benefit based framework for network operation and investment includes all key ingredients required for the development of future network operation (and development) standards to support efficient delivery of a low carbon electricity system. Only cost-benefit based standards can be used for determining the network capacity that should be released to network users in real time that will maximise the value of network access to all network users. Only cost-benefit framework can provide the basis for risks of supply interruptions to be understood, quantified and managed through optimising the amount the network capacity that is released to network users.

  1.8  Such a cost-benefit approach to network operation would be fully consistent with the core objective of Smart Grid concept, an integrated electricity and information and communication system infrastructure that is intended to enhance the utilisation of existing and future primary electricity assets. The cost-benefit based network standard will assist both operational and design engineers in delivering these objectives.

  1.9  In this context, the ENSG 2020 transmission reinforcement programme may need to be updated in the light of future cost-benefit framework. A system based around advanced information, communication and control technologies, as well as incorporating demand-side management into the system control structure, provides a way to maximise the utilisation of future networks, preventing unnecessary and expensive overinvestment. This is the essence of the concept of Smart Grids, which however cannot be developed before the outdated network operation and design standards are updated.

  1.10  It is hence critical that the Fundamental Review of GB SQSS delivers urgently a new technical framework for future network operation, as this will speed up connection of renewable generation, result in a reduction in network constraint costs and reduce the need for network reinforcements, hence contributing significantly to timely and efficient delivery of Government policy. It is concerning that the significance of this important Review has not been fully recognised by Ofgem and Government.

2.  INADEQUACIES OF THE PRESENT NETWORK REGULATION FRAMEWORK

  2.1  The existing regulation heavily incentivises investment over operational alternatives hence preventing the implementation of technically effective and economically efficient non-network solutions as an alternative to the conventional network asset based solutions. This directly contradicts Smart Grid concept that involves a shift to more sophisticated system management through opening opportunities for demand side, generation and advanced real time network control techniques. These are options that contribute to the release of additional network capacity and control services, and function as an economic alternative to reinforcement of network infrastructure.

  2.2  The present network regulation does not explicitly consider and is unable to deal with the fundamental question of whether the level of network capacity released to network users in an operational time scale is delivering good value for money to users. There are no mechanisms that provide assurances to all parties (network users, network operators and the regulator) that an appropriate balance is being struck between costs and benefits in the decision making process associated with the release of network capacity in real time and the provision of additional infrastructure. Our recent analysis suggests that the present practice in most cases significantly compromises the economic efficiency of system operation. This practice may also be a major barrier for innovation needed to enhance efficiency of network operation and its development.

  2.3  A cost-benefit framework for network operation and planning (discussed in the section above) can explicitly address the question of the (optimal) amount of capacity that should be released to network users in real time (which should be the key question of the review of the network standard too). In this context it is concerning that the significance of this has not been fully recognised by Ofgem.

  2.4  The present regulatory approach, that incentivises the enhancement of network flexibility through network asset redundancy, may potentially undermine National Grid licence obligation to carry out its duties in an economically efficient fashion. There has been a clear trend at the international level of growing use of advances in various technologies that can release latent network capacity through more sophisticated system operation, including application of coordinated special protection schemes, coordinated corrective power flow and voltage control techniques supported by wide area monitoring, protection and control systems, application of advanced maintenance techniques, application of advanced decision making tools etc, including the use of various non-network solutions, particularly demand and generation. All these technologies have the potential to increase utilisation of existing network and substitute for network reinforcements. Although some of these methods are applied by the GB System Operator, the present deterministic standards and the regulatory framework are a barrier for taking full advantage of such techniques given the absence of incentives for network asset and alternative non-network asset based solutions to be compared on equal footing.

  2.5  In response to the challenge of connecting new renewables, the ENSG Report involves an asset reinforcement based solution. This is a business as usual response, constrained by the present regulatory approach. Complementary and alternative solutions based on more sophisticated control techniques that would involve generation and demand participation in substituting network reinforcements, were not considered in this exercise. Only solutions based on asset reinforcements are identified, which is a direct consequence of the limited remit allowed by the present regulatory incentives framework.

  2.6  By heavily incentivising investment over operational alternatives, present network regulation, effectively prevents Smart Grid concepts and technologies from providing an economically efficient alternative to the conventional network asset based solutions. The current regulatory framework needs to change; it is no longer appropriate to restrict solutions to those based only on network assets. Instead it must allow the evaluation of all solutions, both network and non-network, particularly those that involve responsive demand, generation and advanced network management techniques. Otherwise, the development of Smart Grid concepts and technologies will be undermined.

  2.7  Clearly, one of the key challenges that will need to be resolved is associated with the current separation of networks from energy. Technologies such as demand-side participation, where demand is responsive to changes in the supply of energy, are beneficial to a range of different market participants. Hence, the benefits of this technology can be associated with a number of industry sectors operating as individual businesses that may all be willing to reward specific aspects of this activity. Clearly, no individual recipient of the services (for example, generating companies or transmission/distribution network operators) is interested in maximising the overall system benefits achieved by trading off the benefits between individual segments of the industry. In this context, the current regulatory arrangements present a significant barrier to the introduction of these technologies.

  2.8  Revised frameworks for network regulation are essential for facilitating the delivery of a low carbon electricity system based on 21st century smarter, more secure and more cost effective transmission and distribution networks. The hope is that the RPI-X@20 review will provide an environment where innovation is rewarded and incentivised.

  2.9  The overarching concern is that the incumbent UK network regulation framework favours the release of new network capacity through network asset reinforcements and this is incompatible with the concept of Smart Grid. Under the Smart Grid concept, non-network solutions, particularly demand side participation are expected to play a vital role in enhancing transmission and distribution network utilisation and hence facilitating an efficient delivery of low carbon future; this future will not be realised if network regulation remains unchanged.

3.  INADEQUACIES OF NETWORK ACCESS ARRANGEMENTS

  3.1  The UK market model has historically separated energy and networks. However, it has been demonstrated that an efficient network congestion management (relevant for transmission in the short term and distribution in the medium term) will be a key requirement in a lower carbon future (hence Transmission Access Review). The need for closer integration of networks and energy is fully consistent with Smart Grid concepts where both network and non-network based solutions compete in order to ensure efficient network operation and future investment. The key challenge for the regulatory and commercial framework here is to design efficient network access arrangements (ie efficient access pricing).

  3.2  Increased constraint costs have concerned Ofgem, Government and industry. In response to these concerns, National Grid developed a more cost reflective allocation of network constraint costs which would effectively make generators in Scotland more responsible for constraint costs caused. This approach would incentivise conventional generators in Scotland to reduce their output on windy days, and hence facilitate the sharing of network capacity. We welcome and support this initiative as this would reduce network constraint costs and could also remove the need for some of the transmission network reinforcements.

  3.3  We are also concerned that the present practice and thinking in the area of network access excludes demand. The role of demand in defining short and long access is not considered in any of Ofgem consultation papers. This is not only discriminatory (leading to both inefficient system operation and inefficient network investment), but it may be fundamentally incompatible with the Smart Grid concept as demand is not given the opportunity to compete for the provision of access with transmission based solutions.

  3.4  Furthermore, we are concerned with the basis of Transmission Network Use of System charges. TNUoS charging mechanism is not fully efficient (not cost reflective enough), and as such may be a contributor to increasing cost of constraints and if unchanged, could lead to inefficient network investment. In the existing TNUoS mechanism, the locational charge, the charge paid depending on the location of the generator/demand, is too small. The mechanism is dominated by a non-locational charge that is paid by demand.

  3.5  Our work demonstrated that wind generation tends to drive less transmission network capacity than conventional plant. However, network charges do not reflect this, and hence discriminate against wind. If the TNUoS charge were to reflect the network costs that different generation technologies drive, wind generators in Scotland would pay significantly lower charges than conventional generators. All recent UK work in this area suggests that wind generation drives less transmission investment than conventional generation. We note that the latest consultation document on the TNUoS residual charge states that wind generation drives the same transmission investment as conventional plant. However, no analysis is provided to support this finding.

  3.6  There is a serious case of discrimination in the regulations between on- and offshore generation. In the case that an onshore wind farm connection design complies with the onshore network standard, the wind farm is entitled to receive compensation due to unavailability of the onshore transmission network; however, in case that an offshore wind connection design is compliant to the offshore network design standard, the wind farm is not entitled for compensation when the offshore transmission network is unavailable.

  3.7  We are concerned that the spread of imbalance prices is above efficient levels and this will increase network constraint costs and inflate the need for transmission. A simple measure, such as post settlement trading could mitigate this to some extent and increase the liquidity of trading within the Balancing mechanism. Furthermore, using our network operation and investment models we simulated efficient market operation for the present BETTA system and a market where constraint costs are driven solely by the cost of fuel. In a perfectly competitive market, annual constraint costs under BETTA could be about £240 million higher than the most efficient constraint costs based on fuel costs only (which, for the background considered, would amount to about £10 million per annum). This analysis demonstrates that the design of BETTA may inherently lead to higher constraint costs and hence drive larger and (inefficient) network investment when compared to a traditional vertically integrated utility or the previous pool regime. Most importantly however, under BETTA, prices of short-term access, which will depend on the difference between offers and bids in importing and exporting areas respectively, will be above efficient levels. The sharing of network capacity between conventional and renewable generation will hence be reduced below efficient levels. We are concerned that the question of the ability of BETTA to provide efficient network investment signals has not been fully considered.

4.  RESEARCH, INNOVATION AND BUSINESS OPPORTUNITIES ASSOCIATED WITH FUTURE GRIDS

  4.1  It is widely recognised that there has been little technical innovation in network operation, planning and investment over the last twenty years. In this context, the introductions of the Innovation Funding Initiative (IFI) and Registered Power Zones (RPZ) by Ofgem have been critically important in incentivising distribution and transmission network operators to engage in innovation. We fully support OFGEM in their intention to provide a step change in the investment in RD&D as well as broader and deeper engagement of wider communities and organisations involved in the innovation chain, through the Low Carbon Network Funding.

  4.2  As stated above, the decarbonisation of electricity and energy systems beyond 2020 with the present operating paradigm would require a very significant capital investment in primary generation and network assets while simultaneously degrading the utilisation of these assets. This may lead to inefficient and costly overinvestment, and an alternative solution, involving innovations in ICT technology and active network management, would be potentially cheaper, more successful and more commercially adaptable than simply building more primary assets. We believe that the core issue facing the network in the future is not only to make grids larger, but to make them more intelligent.

  4.3  This approach will require two major departures from the current philosophy. Such an approach would require (i) a radical shift in the source of the system control and flexibility from physical assets to more sophisticated system management through the deployment of appropriate ICT solutions, and (ii) a major re-allocation of the provision of system control services to include demand and networks in addition to generators. Most of the key individual technologies are already available or well under way to demonstration and deployment, as there is considerable research in plant and equipment based technologies and the Energy Technologies Institute is playing a very important role here.

  4.4  Implementation of ICT for monitoring and control of the electricity system (including demand, networks and generation) will lead to the development of a Smart Grid, an integrated energy and information and communication system architecture that is intended to bring together two elements of the power industry: the electrical delivery system and the information system that controls it. Maximising the utilisation of the primary electricity assets and infrastructure, by deploying and utilising smart information and communication technologies and developing effective energy system integration strategies is the core objective of the concept of Smart Grids.

  4.5  This requires the development of more sophisticated network control, operation and investment strategies, for which new tools and methodologies are yet to be developed. The proliferation of energy storage, distributed generation, solid-state equipment (converters, switches and transformers to name a few) and greater demand-side participation are not addressed well in today's analysis and decision making tools and applications from a whole systems approach. To enable power system analysts and planners to evaluate new technologies and recommend effective and efficient applications to power systems requires a rethink of the analysis tools that provide the foundation for a whole systems approach to decision-making.

  4.6  Furthermore, information management, wide-area measurement, disturbance recognition, and visualisation tools will be needed by grid operators to process real-time information, accelerate response times to problems in system voltage and frequency levels, and achieve compliance with reliability and criteria. These are considered to be critical to ensure that appropriate responses to disturbances are created before widespread blackouts can occur. This also includes the development of interface technologies and standards to enable seamless integration of distributed energy and loads with the local distribution system.

  4.7  Although the key ingredients of this technology exist, targeted trials are required to gain more experience within the context of a functioning energy network. Hence, the key unresolved challenge is in the development and demonstration of effective energy system integration, showing that Smart Grid can deliver the functionality and performance needed for real time control of the power system. This is an area that the UK is well positioned to lead. Development of a Smart Grids technology strategy is of considerable relevance to the UK, given its weak interconnections with other systems and the need to balance demand and supply largely within the GB Island. Furthermore, the UK has significant resources and interest in offshore wind power (and other marine technologies) and development of offshore grids and their efficient integration in the GB network will be a significant challenge. These challenges could be turned into an important commercial opportunity for the UK to gain early experiences and lead the worldwide system integration of advanced future grid technologies at the international level.

April 2009







116   Our Electricity Transmission Network: A Vision For 2020, A Report by the Electricity Networks Strategy Group, March 2009; http://www.ensg.gov.uk/assets/1696-01-ensg_vision2020.pdf (this is referred to as ENSG Report in this document). Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 23 February 2010