The proposals for national policy statements on energy - Energy and Climate Change Contents


Examination of Witnesses (Questions 380 - 386)

WEDNESDAY 20 JANUARY 2010 (afternoon)

MR KEITH PARKER, MR SIMON JAMES, MR RICHARD WAITE AND MR BRUCE MCKIRDY

  Q380  Charles Hendry: To go back to some of the evidence we had from the NGOs over the last week or so, they were talking in terms of the lack of consultation and therefore the constant lack of potential public buy-in, commitment to some of these projects, I want to tie that in specifically to the repository issue. I had the opportunity a couple of years ago to go to Sweden and look at the model repository which had been built at Östhammar, which seems to me to be an extremely effective way of engaging the community. Ten thousand people a year get taken down it, have an idea of how it would work and seem to be generally comforted having seen the approach. Is that an approach which you would look to take in this country as well, of having a model repository first?

  Mr Waite: We have considered whether or not we should have a separate block characterisation facility or whether we should actually have the actual construction itself able to be used for that kind of public engagement and we decided the latter was probably a better course of action, so as the facility finally finds a site and we start constructing it, open access to the public, public engagement, building stakeholder confidence by doing so, as indeed you quite rightly say the Swedes have done very successfully. We believe you can integrate that type of activity into the actual facility itself rather than having a stand alone test facility, if you like, or a practice facility. We do not actually believe we need that test facility or practice facility to prove the acceptance of the site, we can actually do that while we are constructing the actual site, so we would combine both of those things together would be our current view.

  Q381  Charles Hendry: Also in terms of public confidence, the whole of the decommissioning programme, which is slightly removed from the NPS, but a lot of this debate we have had has been about public confidence and carrying the public with us, where there is a nuclear power station which has stopped functioning and a new one is now planned to be built how important is it for people to see decommissioning work being carried out on the redundant plant in order to give them the confidence that there is a complete lifecycle approach being taken and that eventually the land will be turned back into useable land?

  Mr Waite: I think the good progress on decommissioning is essentially in those communities, particularly when they see the potential job impacts, and so on, and there are obviously synergies between jobs that may not be required in an operating station that may be a an NDA station decommissioning facility where those people could be re-skilled, retrained, recycled into the new build environment, so on a local socioeconomic basis it makes sense to join the two together. That can only happen if we have made good progress on decommissioning, of course.

  Q382  John Robertson: Moving on to the appraisal of sustainability, do you find the actual appraisal itself in relation to the nuclear NPS satisfactory?

  Mr Parker: Yes.

  Mr James: Yes, we do. We have noted some of the comments that have been made in earlier evidence sessions along the lines that when considering alternatives they have only considered alternative forms of NPS, and it is certainly true that, for example, it goes into whether or not that is the level to which you should take into account the spatial planning element, i.e. the site specific nature, and looking at those. But it also looks at the alternatives of energy choices as well and of, for example, not having nuclear in the mix. That is actually considered in there, so it is certainly not true to say that other energy alternatives have not been looked at. As part of that process and to comply with the Strategic Environmental Assessment directive you are required to look at all realistic and deliverable alternatives, and certainly our view is that that has been done. There is an inexhaustible supply of alternatives you could possibly think of and there are plenty of those that are not going to be considered to be realistic or deliverable, so we think the realistic alternatives have been looked at and therefore it does meet the requirement. It has also looked at some of the socioeconomic benefits as well, so we think it is actually a very thorough assessment.

  Q383  John Robertson: Yet the NGOs argued about the AoS that it did not comply with the requirements of the Strategic Environment Assessment?

  Mr James: Our view is that we think it does. It is required to look at all realistic and deliverable alternatives and we believe it has done that.

  Q384  John Robertson: So how would you respond to the NGOs then?

  Mr Parker: Well, we disagree with them on that.

  Mr James: They are factually wrong when they say that the energy alternatives have not been looked at in the assessment. You can plainly see them within the assessment. They are right in that part of the alternatives that have been looked at are about alternative forms of NPSs but that is not to say, just because it has done that, that that is the only thing it has done. It has looked at energy alternatives also, so we think they are factually wrong on that.

  Q385  John Robertson: The NGOs felt that the conclusions were of very poor quality. Is that fair?

  Mr James: It depends on their definition of "poor quality". I mean, they disagreed with the outcome.

  Q386  John Robertson: Should they have been deeper, should there have been more in it, or is it just done with the bare minimum of assessment? That was the reason why they said it died not comply with the SEA.

  Mr Parker: I think in general terms the assessment and amount of discussion and consultation on nuclear generally since the new build proposals really emerged in around 2006 it has been really extremely extensive involving national and local stakeholders. The Government has done a tremendous amount of work in ensuring that these discussions have taken place and that they are confident that the public has been taken along and I think the appraisal of sustainability has been as thorough as other elements of the overall process in looking at nuclear and having got to the stage where we are now in a position to designate a nuclear NPS.

  Chairman: Bruce, Richard, Keith and Simon, thank you very much. I am sorry our proceedings have been interrupted but we are very grateful and, Richard, you are going to drop us a note. Thank you.





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 23 March 2010