3 TECHNOLOGY SPECIFIC ISSUES
43. The five draft NPSs that sit under the overarching
energy NPS, EN-1, contain additional information on specific types
of energy infrastructure, which provides further direction to
the IPC on the factors it will need to take into account when
considering planning applications. They are meant to be read in
conjunction with EN-1, which contains guidance on generic impacts
and assessment principles that apply across various types of energy
infrastructure. We heard a range of views on different aspects
of EN-2 to 6. Though not exhaustive, this Chapter examines the
main specific issues raised during our inquiry.
Carbon capture and storage
44. The Government's policy on carbon capture and
storage (CCS) is set out in EN-1 with further guidance in EN-2,
the Draft National Policy Statement for Fossil Fuel Electricity
Generating Infrastructure. We took evidence on two specific
issues relating to CCS. First, the criteria for demonstrating
carbon capture readiness (CCR); and second, the need for guidance
on future carbon dioxide transportation networks.
CARBON CAPTURE READINESS
45. The draft NPS requires that all combustion-powered
generating plants over 300 MW that are subject to the EU's Large
Combustion Plant Directive (LCPD) will need to demonstrate 'carbon
capture readiness' (CCR). This includes coal, oil, gas and biomass-fired
plant. The draft NPS states that, among other criteria, the IPC
will have to assess the technical and economic feasibility of
retrofitting the developer's chosen CCS technology at some point
in the future. If the IPC is not satisfied that it will be technically
and economically feasible to retrofit CCS, the Commission should
reject the application.[74]
The requirements reflect the Department's recently published guidance
on CCR, which is meant to implement one aspect of the EU Directive
on the Geological Storage of Carbon Dioxide.[75]
46. Some witnesses expressed concern at the need
to demonstrate CCR.[76]
Scottish and Southern Energy, for example, argued that given CCS
is still at the pre-demonstration phase it would not be possible
to conduct a meaningful technical and economic CCR assessment,
and that the effect of the requirements would be equivalent to
a "moratorium" on all fossil fuel-based generating capacity
other than the four plants to be developed under the Government's
CCS demonstration programme.[77]
Scottish Power agreed, noting that the requirement to show economic
feasibility was "an over-implementation of the directive
and [...] should be struck out".[78]
The UK Business Council for Sustainable Energy argued for a phased
approach, stating: "Until you can prove that it can work
at commercial scale, then the industry is just not in a position
to comply".[79]
Elsewhere, RWE Npower told us: "The Government's intended
light touch approach, in that developers should demonstrate no
barriers exist to an eventual CCS retrofit, must be retained and
requirements must reflect the early stage of CCS technology development".[80]
On the other hand, the Institute for Environmental Management
and Assessment (IMEA) pointed out that: "there is no certainty
that CCS will prove to be technically and financially feasible
at the scale required to mitigate emissions on the scale of fossil
fuel generating stations" and that a failure to deliver "would
lead to significant problems in achieving the UK's long-term legally
binding carbon reduction commitments".[81]
47. In evidence, the Department noted that the requirement
to demonstrate CCR had already been in place for a year and that
it did not seem to have deterred applications from coming forward
under the old planning regime.[82]
Officials told us the criteria were more about ensuring that applications
were not submitted where it was clear it would never be feasible
to retrofit CCS.[83]
This was the view of the Environment Agency whose responsibility
under the guidance is to assess technical feasibility.[84]
The IPC also told us: "it is not for us to consider the economic
viability of the individual project; that is a matter for the
promoter".[85]
48. We recommend the Department looks again at
its criteria for assessing carbon capture readiness (CCR) as set
out in the draft NPS to examine whether they reflect sufficiently
the EU Directive on the Geological Storage of Carbon Dioxide.
The IPC's interpretation of the criteria will be crucial in determining
the success of applications before it. We therefore also recommend
the Government provides further clarification in the NPS on how
it expects the IPC to assess applicants against the CCR requirements,
having regard to the risks this might pose for the Government's
carbon reduction targets. Clarity is also required about the necessity
for the IPC to assess the economic feasibility of CCR, given the
Commission's assertion to us that it is primarily a matter for
the developer. This appears to contradict the draft NPS and the
Government should settle the matter conclusively. We also recommend
that the Government looks again at the wording of the NPS in relation
to gas CCS, as concerns have been raised that the need to demonstrate
economic feasibility could prevent its development.
CARBON DIOXIDE NETWORKS
49. A further CCR requirement is that applicants
must demonstrate the technical feasibility of transporting the
captured carbon dioxide to the proposed storage area.[86]
The Government has also said that at present only storage projects
offshore are to be considered.[87]
Apart from these references, though, there is relatively little
discussion of the future development of carbon dioxide networks
in either EN-1 or EN-2. For example, there is no reference to
carbon dioxide transportation in section 2.2 of EN-2, which considers
the factors influencing site selection by developers.
50. In evidence to the Committee several witnesses
highlighted the lack of attention given to carbon dioxide networks.[88]
For example, the Energy Networks Association told us: "carbon
dioxide pipelines are not included in the NPSs, and these are
[...] vital to carry carbon dioxide from power stations to a secure
underground storage place".[89]
Prof Dieter Helm emphasised the fact that the market would not
be able to deliver a carbon dioxide network in an efficient and
integrated way, which therefore made the role of the NPSs particularly
important in providing a strategic overview.[90]
Elsewhere, the Environment Agency said "it was an omission
that should be rectified".[91]
Some argued that "a separate NPS should be developed that
addresses the carbon transport infrastructure and carbon storage
infrastructure, to allow effective planning of these strategic
resources, and for the right market signals to be sent for power
plant siting decisions".[92]
In response, the Department accepted this broad criticism, noting
it did not think that at present there was sufficient guidance
in the draft NPSs, for example, on the consenting of the pipelines.[93]
51. The development of a future carbon dioxide
network will be integral to the future deployment of carbon capture
and storage. It is at present a glaring omission from the draft
energy NPSs, which we recommend the Department rectifies.
Biofuels and energy from waste
52. The Draft National Policy Statement for Renewable
Energy Infrastructure, EN-3, sets out the specific assessment
criteria for biomass and energy from waste. In evidence, some
witnesses raised concern at the current treatment of the fuel
source for both these technologies. For biomass, EN-3 stipulates:
"the IPC does not need to consider the source or sustainability
of the proposed biomass fuel to be used within the proposed plant".[94]
It states this is because operators of biomass plants already
have an obligation to report annually on the sustainability of
their fuel sources, including the volume, type of biomass used,
country of origin and previous land use. However, under the UK
Low Carbon Transition Plan the Government expects a large
increase in the level of biomass generation, and the Environment
Agency told us the majority of the fuel source for this would
be from North and South America or Indonesia.[95]
The Agency said it did not believe the provisions were in place
to ensure that, for example, imported wood-chip for biomass plant
use would be sourced from Forestry Stewardship Council-certified
wood. The Agency described the current requirements as "weak"
and "essentially [...] voluntary".[96]
The Royal Institution of Chartered Surveyors (RICS) shared this
concern, stating the origin of the fuel source for biomass should
be a factor the IPC considered.[97]
53. In response, the Renewable Energy Association
countered that the emissions arising from the ocean transport
of biomass did not significantly increase the carbon footprint
of the technology when comparing against coal.[98]
It is worth noting, though, that transportation is just one aspect
of the sustainability of an imported fuel source. As the Minister
noted, the general principles on this should be "first of
all, that it delivers carbon dioxide savings, second, that it
uses land responsibly, third, that it does not undermine global
food supplies or inflate prices, and overall [...] that it is
sustainable".[99]
Officials also told us that although EN-3 currently reflected
Government policy on biomass fuel sources, the Department was
negotiating at a European level with the aim of agreeing a set
of standards, which they hoped could be incorporated into the
designated NPS.[100]
54. On energy from waste, Friends of the Earth argued
that this technology should not be included in EN-3 because a
large proportion of its fuel source was non-renewable. Instead,
it should be part of the fossil fuel NPS.[101]
A further concern from the NGO was that greater development of
energy from waste would result in direct competition with recycling
and re-use as alternative waste options. In support of this argument,
the organisation noted that while total waste arisings had now
either stabilised or begun to fall, recycling rates were still
increasing.[102] This
could therefore create a problem over time as energy from waste
plants would wish to have long-term contracts with local authorities
for their fuel source. In response, the Renewable Energy Association
told us the fuel feedstock for energy from waste would be of too
low a quality to be available for recycling.[103]
Nevertheless, the Environment Agency told us the NPS should "identify
[...] that waste is not diverted from re-use or recycling where
those are feasible options".[104]
In evidence, the Minister agreed that energy recovery was near
the bottom of the Government's hierarchy of preferred approaches
to dealing with waste.[105]
EN-3 does draw the IPC's attention to the waste hierarchy, and
requires: "the proposed waste combustion plant is of an appropriate
type and scale so as not to prejudice the achievement of local,
regional or national waste management targets".[106]
However, the Department acknowledged that it may need to re-consider
the issue to ensure it had said what it intended in the draft
NPS.[107]
55. The current draft NPS on renewables, EN-3,
reflects the Government's current policy on the fuel sources for
biomass and energy from waste power plant. However, we are concerned
that the IPC is directed not to consider the sustainability of
biomass fuel. Although to do this would require a change of policy,
we believe the existing draft guidance would mean the IPC would
not be able to examine fully all adverse environmental, social
and economic impacts as it is required to do in paragraph 4.1.1
of EN-1. We therefore recommend the Department revises EN-3 to
require all biomass power station applicants to make a full assessment
of the sustainability of their fuel sources. We also recommend
that the Department re-assesses whether its current guidance on
energy from waste ensures that only waste that cannot otherwise
be economically recycled or reused is sourced as feedstock for
energy from waste production.
Other
renewables
56. EN-3 provides guidance for the IPC's consideration
of biomass and waste combustion projects, as well as onshore and
offshore wind. It does not include other renewables such as wave,
tidal, and solar power because no onshore projects over 50 MW
or offshore projects over 100 MW are expected in the near future
that do not use any of the technologies already dealt with in
EN-3. This could change later in 2010 if the Government decides
to pursue one of the proposed Severn tidal projects. The British
Wind Energy Association (BWEA) told us it was happy with the exclusion
of wave and tidal power from the current draft renewables NPS,
although it believed a section dealing with these technologies
would need to be added at an appropriate time.[108]
In contrast, the Renewable Energy Association felt wave and tidal
power had been "dealt with poorly" in EN-3, and argued
the current guidance was not sufficient.[109]
Any wave and tidal projects under 100 MW will be consented by
the Marine Management Organisation (MMO). The BWEA also emphasised
the need for consistency between the approaches taken by the MMO
and the IPC for different sized projects, in the same way that
this will be important for the two onshore consenting regimes,
which we discuss later in this Report.[110]
57. We agree that at this stage there is no urgency
to include technologies such as wave and tidal in the renewables
NPS. Nevertheless, EN-3 should set out the Government's intentions
for how these technologies will be dealt with in future versions
of the NPS. We note too that a decision over whether to pursue
one of the proposed Severn tidal projects will require a substantial
revision of EN-3, if not a new NPS in its own right.
Combined heat and power
58. EN-1 states that: "In developing proposals
for new thermal generating stations, developers should consider
the opportunities for combined heat and power (CHP) from the very
earliest point and it should be adopted as a locational criterion".[111]
The IPC is also told to give "substantial additional positive
weight" to applications that incorporate CHP.[112]
Applicants not proposing to use CHP will be expected to show:
why it is not economically feasible or practical; potential future
demand sources for the heat load; and demonstrate provisions within
the proposed scheme for exploiting any such demand should it arise.
59. We heard evidence from the Institution of Civil
Engineers (ICE) and the Environment Agency (EA) that argued strongly
for the NPS to give greater direction to the IPC to favour planning
applications that proposed CHP.[113]
The EA told us: "We see an absence of any strong statement
on the priority of energy policy being about energy efficiency
and using energy well".[114]
The ICE went so far as to suggest the Commission should not consent
new infrastructure unless it made use of the waste heat produced.[115]
Both organisations acknowledged that to do so would introduce
a spatial element in guiding developers' decisions on where to
locate plant because they would need to find a suitable demand
load.
60. We accept that, in the absence of a targeted
policy to encourage combined heat and power, it is difficult for
the NPSs to indicate a greater preference for CHP than that which
is already present in the current draft. If in the future, the
Government decides to introduce a more spatial approach to the
non-site specific NPSs, we recommend it considers whether it could
use this to promote further deployment of CHP where it is cost-effective
to do so.
New nuclear build
61. The Draft National Policy Statement on Nuclear
Power Generation, EN-6, is arguably the most controversial
part of the proposed NPS framework and the area on which the Committee
received most evidence. As noted in Chapter 1, we have not examined
in depth each of the sites proposed for potential nuclear development.
However, several issues emerged, which we believe merited particular
comment. In this section we consider the treatment of radioactive
waste management in the draft nuclear NPS, and the relationship
between the IPC regime and the other regulatory processes that
will take place alongside future planning applications. We also
examine the Department's decision to exclude Dungeness from the
draft NPS.
RADIOACTIVE WASTE
62. EN-6 states that: "Having considered this
issue, the Government is satisfied that effective arrangements
will exist to manage and dispose of the waste that will be produced
from new nuclear power stations. As a result the IPC need not
consider the question".[116]
It bases this conclusion on the consideration of three factors.
First, it believes that deep geological disposal will be technically
feasible. Four years ago, the Committee on Radioactive Waste Management
(CoRWM) reported that: "within the present state of knowledge,
geological disposal is the best available approach for the long-term
management of all the material categorised as waste".[117]
EN-6 also quotes a finding by the British Geological Survey that
up to 30% of the UK has suitable geology for such a facility.
Although the Government already requires a solution to the UK's
existing radioactive waste legacy, it believes the waste arising
from a new generation of nuclear power stations will not present
significant new issues in terms of its disposability. This approach
has also been adopted in Finland and Sweden, which are already
developing geological disposal facilities that are expected to
begin operation by 2020.
63. A second factor is that the Government believes
a suitable site can be found to host the facility. In 2008 it
published a White Paper on Managing Radioactive Waste Safely,
which set out the framework for site selection. The process is
based on the principle of voluntarism and partnership between
the project and the local community as recommended by CoRWM. Because
of this, there is no fixed timetable for delivery. EN-6 notes
the Nuclear Decommissioning Authority's (NDA) assessment that
a facility could begin operation around 2040, although it might
not start to receive high-level waste until 2075.[118]
The third factor underlying the Government's conclusion on waste
is that "geological disposal will be preceded by safe and
secure interim storage".[119]
The NDA told us new nuclear power stations would have a higher
rate of fuel burn-up that would give rise to waste that was hotter
and more radioactive. This would require on-site storage until
it had cooled sufficiently to be moved to a long-term disposal
facility.[120] EN-6
states that interim storage on-site may be required for up to
160 years from the commencement of the power station's operation,
although the NDA told us this was a conservative estimate and
that the actual time required may be some years less.[121]
Overall, the Minister told us: "I am confident we have the
right policies for dealing with waste, both in terms of interim
storage and eventual disposal in a geological disposal facility".[122]
64. The NDA strongly supported the Government's assertion
that effective arrangements will exist to manage future radioactive
waste.[123] The Nuclear
Industry Association also said: "We are confident that the
arrangements are now in place for a satisfactory resolution to
the waste issue".[124]
Yet in evidence a large number of organisations and individuals
questioned both the Government's conclusion and its underpinning
evidence.[125] For
example, Prof Blowers, who was previously a member of CoRWM, told
us he believed the Government had misrepresented the Committee's
conclusions on the feasibility of deep geological storage, stating:
"in fact it is unknowable whether effective arrangements
will be in place".[126]
He said there had not yet been sufficient research to conclude
definitively that geological disposal would work. Others raised
concerns over the cost of a facility, which is as yet unknown.
The Sustainable Development Commission noted, for example, that
the complexity of dealing with high-level radioactive waste could
prove so expensive that it undermined the commercial viability
of new nuclear build.[127]
The Government has already set out that the developers of new
nuclear power stations will have to pay the full cost of dealing
with the waste they produce.[128]
65. Witnesses also questioned whether the Government
had made sufficient progress in identifying a site. The NDA told
us it was at the first stage of the process set out in the 2008
White Paper. To date three communities have expressed an interest
in hosting the facilityCopeland Borough Council, Allerdale
Borough Council and Cumbria County Council.[129]
The British Geological Survey would now look at the areas proposed
to determine their suitability. The NDA also said it was not possible
to define the timeline for delivery because this would depend
on the local community.[130]
However, the Sustainable Development Commission told us it did
not believe there had been much tangible progress since 2008,
stating: "we do not think that just having the documentation
in a White Paper [...] really cuts the mustard".[131]
Prof Blowers argued there was no guarantee that a community would
be willing to host a facility, despite the current expressions
of interest.[132] Greenpeace
noted too that even if communities did come forward, their geology
may prove unsuitable.[133]
Both the SDC and the Environment Agency believed that as a minimum
the Government should establish a timetable with milestones for
the various stages required for the delivery of a geological disposal
facility.[134]
66. Witnesses also criticised the treatment of interim
storage in EN-6. As noted already, high-level radioactive waste
could remain on-site for up to 160 years from the commencement
of a power station's operation. Nuclear Waste Advisory Associates
argued that the draft nuclear NPS provided little information
on how spent fuel would be stored and managed at the reactor sites,
and whether a spent fuel packaging plant would need to be built
on-site at some point in the future.[135]
This concern was also shared by Prof Blowers, who contrasted the
Government's voluntary approach for a geological disposal facility
with that for nuclear new build sites, noting that the latter
would still be hosting high-level waste for many generations.
He highlighted CoRWM's original recommendation that voluntarism
should "be applied to new central or major regional stores
at new locations if they are to inspire public confidence".[136]
However, he told us: "communities hosting spent fuel stores
will be given no opportunity to consider whether they wish to
volunteer to host a long-term radioactive waste facility".[137]
67. One issue underlying the concern over the length
of time for interim storage was the potential risk of flooding
due to rising sea levels. The Nuclear Consultation Group noted
it was almost impossible to predict what the impact of climate
change would be across the period when nuclear sites would be
active, and that the draft nuclear NPS did not consider adequately
the risks over the likely lifetime of a project.[138]
In evidence, however, the Minister said he did not believe that
the length of time nuclear sites would have to provide interim
storage of high-level waste should be a relevant consideration
for the IPC.[139] Greenpeace
told us: "It is almost as if somebody outside Hinkley Point
could have a discussion in front of the IPC about whether they
wanted the gates painted blue, green, or yellow, or the reactor
dome pink, but these major issues around nuclear spent fuel [...]
would be outside of its remit".[140]
68. In 2006, the then Trade and Industry Committee
was told by the chief executives of E.ON UK and EDF Energy that
achieving a long-term solution to the UK's existing radioactive
waste legacy was vital, not only from the perspective of helping
gain public acceptance of new build, but also to reassure potential
investors and operators in the sector.[141]
In evidence to this Committee those companies supported the Government's
position in EN-6, stating there were "no apparent technical
show-stoppers" to delivering deep geological storage, and
highlighting their existing experience of managing on-site interim
storage.[142] EDF Energy
also said that there had been sufficient progress towards developing
a long-term facility to give them confidence to move ahead with
the company's plans, although it would want to ensure the Government
was still making progress at the time it submitted a planning
application for a new nuclear power station.[143]
69. Finally, we received conflicting evidence on
the question of whether the planning application for a geological
disposal facility would be dealt with by the IPC or by the Local
Planning Authority for the community that would be hosting the
depository. The Nuclear Decommissioning Authority told us it believed
the decision would be made by local communities as this would
be in line with the voluntarism approach used to identify the
site.[144] However,
the Minister said he was minded for the consenting process to
be the IPC's responsibility. He told us, though: "we have
not made a firm decision, and, frankly, we are not really anywhere
near having to make a decision".[145]
70. Planning consent from the IPC for new nuclear
power stations will entail the storage of high-level radioactive
waste on-site for up to 160 years. From the perspective of the
community affected, it is a misnomer to describe this as interim
storage as it will be several lifetimes between the commencement
of a power station's operation and the eventual removal of waste
from that site. A key objective of the new NPS framework is to
focus discussion on planning applications on site-specific issues.
As such, we believe on-site storage cannot be ruled out from the
IPC's deliberations and that the nuclear NPS should contain significantly
more detail on what interim storage will entail for local communities
and for the integrity of any site chosen.
71. We do not dissent from the process adopted
by the Government for identifying a site for the eventual storage
of radioactive waste deep underground. However, we received conflicting
evidence over whether this process would yield a suitable site
and if the proposed approach of geological disposal was technically
feasible. We are not convinced that the progress to date supports
the Government's robust assertion that suitable arrangements will
be in place to manage the UK's waste legacy. However, we note
too that the Government has no choice but to find a solution,
regardless of a decision on nuclear new build. Furthermore, we
agree that the waste arising from new nuclear power stations will
not pose a significant additional challenge in terms of finding
a permanent storage solution. Therefore, as this is an issue of
national policy, the political and ethical elements of which have
been debated widely over the past five years, we agree that this
should not be a consideration for the IPC with regard to individual
applications.
72. Nevertheless, we believe the Government must
continue to demonstrate progress in delivering a geological disposal
facility for radioactive waste. Accordingly, we recommend the
Department now sets out key milestones in EN-6 and reports progress
against these to Parliament on an annual basis. This should include
establishing which body will be responsible for consenting the
site.
PARALLEL REGULATORY PROCESSES
73. EN-6 states that: "the IPC should make its
decisions in relation to a development consent application on
the basis that: the relevant licensing and permitting regimes
will be properly applied and enforced; it does not need to consider
matters that are within the remit of the nuclear regulators; and
that it should not delay a decision on whether to grant consent
until completion of the licensing or permitting process".[146]
For example, alongside the consultation on the draft NPSs, DECC
has also been consulting on the Regulatory Justification of new
nuclear power stations, which is required under EU law.[147]
Elsewhere, the Environment Agency and Health and Safety Executive
are conducting a generic design assessment of the two reactor
types proposed for use in the UK. Greenpeace, however, expressed
concern that the IPC might begin to consider a planning application
for a new nuclear power station while these and other processes
had not yet completed.[148]
74. We believe it is not the role of the IPC to
concern itself with the regulatory processes relating to new nuclear
build that may be conducted in parallel to its own decision-making
on planning consents, and which might otherwise lead to confusion
and a duplication of efforts. However, the Commission should at
least have cognisance of the wider regulatory framework as it
is likely that it will receive submissions on issues outside of
its remit when considering applications. We would therefore expect
regular and open communication between the IPC, the Environment
Agency, the Health and Safety Executive and other relevant bodies
on these matters.
DUNGENESS
75. The sites proposed as suitable for nuclear development
in EN-6 represent the outcome of a strategic siting assessment
(SSA), which took place in 2009. Out of the 11 sites nominated
by developers, one failed the assessmentDungeness. This
was on the basis that it would be unlikely to be possible to mitigate
the adverse effects on a Natura 2000 (N2K) site, which overlaps
with the footprint of the proposed site.[149]
N2K sites are designated because of their importance to habitats
and species of importance to European conservation.
76. Several witnesses voiced concern at the exclusion
of Dungeness from EN-6. The Nuclear Industry Association (NIA)
argued that a new power station would not pose substantially different
impacts to those already created by the existing two power stations
at the site. The NIA also noted that most of the sites included
in EN-6 posed potential adverse effects on adjacent N2K sites,
stating: "it is not clear why the Dungeness site alone should
be excluded on this criterion".[150]
EDF Energy and Scottish Power also questioned the ruling-out of
the site. Both believed the list of sites available for the IPC
to consider should not be constrained at this stage, with Scottish
Power noting that: "the issues around the sites of special
interest can be adequately addressed".[151]
The site's exclusion has also disappointed representatives of
the local community. Both Shepway District Council and Hastings
Borough Council provided extensive arguments as to why it would
be wrong, at this stage, to reject any new nuclear build at Dungeness:
"[
] there are good reasons to believe that any environmental
impacts at Dungeness can be mitigated and managed successfully.
The Infrastructure Planning Commission (IPC) could take any site-specific
decision on the suitability of Dungeness for nuclear build, based
on a full project-level application for development consent [
]
Dungeness should be reinstated as a nuclear build site within
the finalised nuclear NPS for approval by the Secretary of State".[152]
77. Natural England, whose evidence influenced significantly
DECC's decision not to pursue Dungeness, told us that for all
the other sites there was some potential either to mitigate or
compensate for the likely environmental impacts. The organisation
said, however: "Dungeness is a very special place and is
the result of 5,000 years' worth of interaction between the sea
and land and it is simply not possible to recreate it anywhere
else".[153] The
proposed site, along with the existing power stations, are on
the largest example of a shingle beach in Europe.[154]
The SSA had also highlighted concern regarding flood risk, although
this on its own was not felt to be sufficient to rule out the
site. Acknowledging that the decision was controversial, the Department
defended its position, citing the unique nature of the shingle
beach, and the fact that given the potential availability of 10
more preferable sites, there was not an Imperative Reason of Overriding
Public Interest (IROPI) for developing there.[155]
The Minister told us: "I certainly do not have a closed mind
to this issue, but equally the advice I received [...] would suggest
that development in Dungeness would be very, very difficult indeed".[156]
78. We note the reasons for the Government's exclusion
of Dungeness from the draft nuclear NPS and the arguments against
this decision put by the industry and the local community. We
recommend the Department maintains an open mind throughout the
current consultation, that it considers carefully the evidence
submitted to the Committee by Shepway District Council and any
other evidence submitted during the consultation and, if necessary,
reconsiders its position.
74 EN-1, para 4.7.3 Back
75
Department of Energy and Climate Change, Carbon capture readiness-A
guidance note for Section 36 Electricity Act 1989 consent applications,
November 2009 Back
76
Q 450 (RWE Npower); also DECC consultation responses 0042 (Mersea
Island Society), 0063 (John McGough) and 0247 (Ian McFarlane) Back
77
Q 500 (Scottish and Southern Energy) Back
78
Q 501 (Scottish Power) Back
79
Q 504 (UK Business Council for Sustainable Energy) Back
80
Ev 491 (RWE Npower) Back
81
Ev 378 (Institute of Environmental Management and Assessment) Back
82
Q 812 (Department of Energy and Climate Change) Back
83
Ibid. Back
84
Q 637 (Environment Agency) Back
85
Q 658 (Infrastructure Planning Commission) Back
86
EN-1, para 4.7.1 Back
87
EN-1, para 4.7.8 Back
88
Q 507 (UK Business Council for Sustainable Energy) Back
89
Q 478 (Energy Networks Association) Back
90
Q 409 (Prof Dieter Helm, University of Oxford) Back
91
Q 635 (Environment Agency) Back
92
Ev 473 (Institution of Chemical Engineers, Institution of Civil
Engineers, Institution of Engineering and Technology, Institution
of Mechanical Engineers, and Royal Academy of Engineering) Back
93
Q 816 (Department of Energy and Climate Change) Back
94
EN-3, para 2.5.10 Back
95
Q 644 (Environment Agency) Back
96
Ibid. Back
97
Q 68 (Royal Institution of Chartered Surveyors) Back
98
Q 295 (Renewable Energy Association) Back
99
Q 807 (Minister for Energy) Back
100
Q 806 (Department of Energy and Climate Change) Back
101
Ev 334 (Friends of the Earth) Back
102
Ibid. Back
103
Q 296 (Renewable Energy Association) Back
104
Ev 300 (Environment Agency) Back
105
Q 805 (Minister for Energy) Back
106
EN-3, para 2.5.59 Back
107
Q 807 (Department of Energy and Climate Change) Back
108
Q 297 (British Wind Energy Association) Back
109
Q 298 (Renewable Energy Association) Back
110
Q 299 (British Wind Energy Association) Back
111
EN-1, para 4.6.6 Back
112
EN-1, para 4.6.7 Back
113
Also DECC consultation responses 0206 (Swindon Borough Council)
and 326 (Richard Bull) Back
114
Q 619 (Environment Agency) Back
115
Q 61 (Institution of Civil Engineers) Back
116
EN-6, para 3.8.20 Back
117
EN-6, para 3.8.7 Back
118
EN-6, para 3.8.11-12 Back
119
EN-6, para 3.8.16 Back
120
Qq 347 and 348 (Nuclear Decommissioning Authority) Back
121
Q 346 (Nuclear Decommissioning Authority) Back
122
Q 795 (Minister for Energy) Back
123
Q 345 (Nuclear Decommissioning Authority) Back
124
Q 361 (Nuclear Industry Association) Back
125
For example, Qq 157 (Sustainable Development Commission), 255
(Friends of the Earth, Greenpeace and WWF), 511 (Pobl Atal Wylfa
B), and 553 (Blackwater Against New Nuclear Group); Ev 396 (Natural
England); DECC consultation responses 0085 (Barbara Fairbairn)
and 0259 (Catherine Goss) Back
126
Q 252 (Nuclear Consultation Group); DECC consultation response
0314 (Hull City Council) Back
127
Q 154 (Sustainable Development Commission) Back
128
Department for Business, Enterprise and Regulatory Reform, A
White Paper on Nuclear Power, January 2008 Back
129
Q 356 (Nuclear Decommissioning Authority) Back
130
Q 346 (Nuclear Decommissioning Authority) Back
131
Q 135 (Sustainable Development Commission) Back
132
Q 254 (Nuclear Consultation Group) Back
133
Q 251 (Greenpeace) Back
134
Q 140 (Sustainable Development Commission); Ev 300 (Environment
Agency) Back
135
Ev 428 (Nuclear Waste Advisory Associates) Back
136
Ev 400 (Nuclear Consultation Group) Back
137
Ibid. Back
138
Q 245 (Nuclear Consultation Group) Back
139
Q 798 (Minister for Energy) Back
140
Q 245 (Greenpeace) Back
141
House of Commons Trade and Industry Committee, Fourth Report of
Session 2005-06, Nuclear new build-Examining the issues, HC 1122,
July 2006 Back
142
Qq 468 and 469 (EDF Energy) Back
143
Q 472 (EDF Energy) Back
144
Q 357 (Nuclear Decommissioning Authority) Back
145
Q 803 (Minister for Energy) Back
146
EN-6, para 3.4.2 Back
147
Department of Energy and Climate Change, The Justification of
practices Involving Ionising Radiation Regulations 2004, November
2009 Back
148
Qq 200 and 238 (Greenpeace) Back
149
EN-6, Annex A, A2 Back
150
Ev 421 (Nuclear Industry Association) Back
151
Qq 437 (EDF Energy), 487 and 490 (Scottish Power) Back
152
Ev 502 (Shepway District Council) Back
153
Q 612 (Natural England) Back
154
British Energy, Proposed Nuclear Development at Dungeness Environmental
Scoping Report, November 2008 Back
155
Q 747 (Minister for Energy); EN-6, Annex A Back
156
Ibid. Back
|