4 THE NPSS AS PLANNING DOCUMENTS
79. The primary role of the energy NPS series is
to set out Government policy so as to provide a clear basis for
the decisions on planning applications for major infrastructure
developments taken by the IPC. However, they may also be material
considerations in decision-making on applications that fall under
the Town and Country Planning Act regime. Accordingly, this Chapter
considers whether the draft NPSs are fit for purpose as planning
documents. First, we contrast the site-specific nature of EN-6
with the non-spatial approach taken in EN-2 to 5. We then examine
the relationship between the energy NPSs and the rest of the town
and country planning system, including the treatment of infrastructure
that is associated with energy proposals.
The draft nuclear NPS
80. EN-6 identifies 10 sites as suitable for potential
nuclear development. These are at Bradwell in Essex; Braystones,
Kirksanton and Sellafield in Cumbria; Hartlepool in Cleveland;
Heysham in Lancashire; Hinkley Point in Somerset; Oldbury in Gloucestershire;
Sizewell in Suffolk; and Wylfa in Anglesey. With the exception
of Braystones and Kirksanton, all of the sites are adjacent to
existing nuclear power stations that are either still in operation
or have closed and are being decommissioned.
81. In evidence, one area of concern in relation
to the proposed sites was the Government's assertion that all
them will be needed. EN-6 states that: "the Government believes
that only a limited number of sites are potentially suitable for
the deployment of new nuclear power stations by the end of 2025.
The Government has therefore concluded that it is necessary to
include all 10 sites in this NPS to ensure that sufficient sites
are available for development [...]".[157]
The Planning and Environment Bar Association (PEBA) told us the
effect of identifying a site in the NPS as potentially suitable
would be to set a strong presumption in favour of consent that
would be hard for the IPC to resist.[158]
The Law Society agreed, stating: "The government says that
it has put forward only 10 sites and it needs every single one
[...] to ask [the IPC] to say it believes it has found a really
important adverse effect and one of the 10 cannot go ahead is
a major decision for that body".[159]
We note that the Government's assertion in the nuclear NPS that
all 10 sites are needed could also be taken to mean there is an
expectation that some will not get planning permission from the
IPC. The Commission emphasised its process would not be a rubber-stamping
exercise.[160] It told
us: "The public position of the IPC is that clearly the NPS
is a very significant document but it does not mean to say that
Commissioners would ultimately agree all 10 sites. If it is the
view of the panel [...] that the adverse impact locally of a particular
individual nuclear power station was so great that it overruled
the national benefits of that energy then that panel would have
the right to turn down that application".[161]
82. EN-6 also states that:
The Government [...] has concluded that it cannot
rule out the potential for adverse effects on the integrity of
designated European sites adjacent to or at a distance
from each site listed in
this NPS. In line with the requirements set out in [...] the Habitats
Directive the Government [...] concluded that there were no alternatives
that would better respect the integrity of European sites and
deliver the objectives of this plan. Accordingly the Government
has presented a case for Imperative Reasons of Overriding Public
Interest (IROPI) which sets out the rationale for why the plan
should proceed [...].[162]
A number of witnesses questioned the assertion of
IROPI. The Nuclear Consultation Group told us: "every effort
is expended to get the IPC to basically allow those sites because
of overriding national interest [...]".[163]
The Sustainable Development Commission believed this may need
to be tested in the courts, noting: "That is quite a dangerous
statement to make [...] and a robust case to meet that statement
is not made in the NPS at the moment".[164]
There was also concern over the status of the declaration of IROPI
in Annex A to EN-6. Natural England told us: "[...] it is
not clear from the drafting whether the intention is for that
test to apply to the NPS as a whole or to individual sites [...]
as it is drafted now it meets the criteria for the overall NPS
but that test will need to be applied to individual site decisions".[165]
83. We understand the necessity for making the
nuclear NPS site-specific as to do otherwise would be less than
open in a situation where there are so few alternatives. We are
concerned, however, that the inclusion of 10 sites coupled with
the statements that all are needed and the Government can find
no alternatives that would better respect the integrity of designated
European sites may place undue pressure on the IPC to permit developments
on those sites. We are reassured by the IPC's statement that if
local impacts did outweigh national benefits on these sites then
it would refuse the application. However, we feel that the independence
of the IPC could be more clearly expressed in the NPS in terms
of its ability to refuse consent for any of the 10 nuclear sites.
The Department should also clarify whether its opinion on Imperative
Reasons of Overriding Public Interest (IROPI) refers to the nuclear
NPS as a whole or to the selection of individual sites.
The non-nuclear NPSs
84. Whether the suite of non-nuclear NPSs should
be more locationally specific was an issue raised by witnesses
from across different sectors. For example, WWF said "It
is clear that the NPSs are not spatial plans or policies [...]
They do not include any vision or sense of place, no indication
of where national infrastructure should be or can be suitably
located (apart from nuclear), no aspirational policies to achieve
decarbonisation of the energy sector whilst protecting the environment,
and they fail to adequately address two essential elements of
spatial planning(a) the management of the competing uses
for space; and (b) the making of places that are valued and have
identity".[166]
Accordingly, in this section we examine the issues of whether
the non-nuclear NPSs should be more locationally specific, and
if they should be linked to some form of national spatial framework.
AREAS OF SEARCH AND CORRIDORS
85. Two potential ways in which witnesses suggested
the non-nuclear NPSs could be more locationally specific was through
some form of "areas of search" approach for particular
types of energy generation, or defined "corridors" for
electricity transmission. The Campaign to Protect Rural England
(CPRE) told us: "there need to be more criteria to guide
the decision-makers in ensuring that development is located in
the most appropriate locations that are beneficial for economic,
social and environmental reasons and away from areas that are
seen and are judged to be likely to be most damaging".[167]
The Sustainable Development Commission echoed this view, stating:
"there are certain areas where it would be inappropriate
to put onshore wind [...] It would just give people a clearer
idea of what the national Government policy was, and it would
also help developers".[168]
This latter point was reinforced by the RSPB which told us that,
"[...] having a greater spatial expression in the plan gives
developers a degree of certainty about what is going to be appropriate
and [...] would be very helpful".[169]
The Local Government Association said too: "the NPSs could
give more of a strategic steer [...] about the kinds of places
where it would be appropriate to bring forward proposals for energy
infrastructure [...]".[170]
86. One specific example given by the SBGI's Gas
Storage Operators Group (GSOG) was that EN-4 on gas supply infrastructure
could recognise the geological constraints affecting the location
of underground gas storage: "There are two forms of underground
gas storage which are in use in the UK [...] Both types of storage
require very specific geological conditions and the locations
available for development of storage are very limited".[171]
More generally, it is worth noting that the Welsh Assembly Government
has already adopted an approach of identifying 'Strategic Search
Areas' for major wind farm proposals and that the Crown Estate
has recently announced the areas for the third round of licences
for offshore wind farm development.[172]
On this point, we were told by the UK Business Council for Sustainable
Energy that: "We suggest that the spatial nature of the Crown
Estate's leasing process could also helpfully have been included
in the renewables NPS and referenced in the overarching NPS".[173]
Elsewhere, the Environment Agency told us about work led by DCLG
and DECC that is looking at capacity assessments for each English
region to deliver a variety of renewable and low-carbon forms
of energy.[174]
87. The energy generation industry, however, did
not believe the identification of broad areas of search would
create benefits. For example, the British Wind Energy Association
said: "[...] this would be a significant departure from existing
government policy on energy. It would result in a significant
increase in costs all around [...] and particularly to the industry
in having to reassess all its current projects in the planning
system".[175]
RWE Npower supported this view, stating: "the resource intensity
and time involved in undertaking that exercise, both in central
and local government [...] will only serve to delay the NPSs and
have a knock-on effect in terms of bringing new projects forward".[176]
The Renewable Energy Association also noted that: "[...]
however you word a spatial policy to say that this is the preferred
area or an area of search, it does immediately [...] demote all
other areas to a lesser status. There are many examples of projects
which have been promoted in areas which might not have been immediately
obvious [...]".[177]
88. A related issue is whether, for example, EN-5
on electricity networks could identify the main transmission 'corridors'
that will require future construction or reinforcement. Some witnesses
pointed to the fact that corridors had already been identified
in the work of the Electricity Networks Strategy Group in their
2009 report, A Vision for 2020, which identifies where
grid upgrades are most likely to be required in the next decade.
Some witnesses were surprised that this approach had not been
carried forward into the draft NPS. Scottish and Southern Energy
told us: "If you look at the example of the Scottish National
Planning Framework, they have adopted within that a representation
of the areas where the lines may need to be developed [...] There
are only limited spatial areas where those can and will be sensibly
developed, and that is sensible then to specify in the NPS".[178]
However, National Grid were sceptical of this approach, noting:
"the number of permutations for the start and finish points
and the number of permutations in between all of those start and
finish points" meant it would be difficult to make this approach
work within the NPS.[179]
89. Several witnesses suggested that the more locationally
specific an NPS was, the easier it would be to engage the public
in the planning process. It is worth noting that we received a
large volume of submissions on nuclear power in comparison to
other issues. For example, the Sustainable Development Commission
told us: "[...] without having any spatial element, it is
very hard to engage people in this whole process and that is one
of the critical weaknesses [...] in the National Policy Statements".[180]
We examine this issue more closely in the next Chapter.
90. Whilst we accept EN-1 to 5 should not be as
specific on the location of energy infrastructure developments
as the nuclear NPS, we believe there are ways in which the non-nuclear
NPSs could take greater account of spatial issues. Possible examples
include: those areas of the transmission network requiring reinforcement
to meet the UK's renewable energy targets; the Welsh Assembly
Government's strategic search areas; the DCLG/DECC work on regional
capacities for renewable generation; and areas with suitable geology
for gas storage. Such an approach would not constrain the choice
of sites for developers but would provide valuable guidance and
an incentive to bring applications forward in the most appropriate
locations. Nor would it constrain the decision-making of the IPC,
which should treat all applications on their merits. It could
also facilitate greater public engagement in the NPS process.
A NATIONAL SPATIAL STRATEGY
91. Some witnesses raised the issue of having some
form of overarching statement of national spatial priorities to
which all the NPSs on energy, transport, waste and water could
relate.[181] For example,
the Sustainable Development Commission told us it had consistently
supported the idea of a national spatial strategy.[182]
Elsewhere, the Institution of Civil Engineers noted the lack of
a spatial link between the draft energy NPSs and the draft ports
NPS.[183] One benefit
of such an expression of spatial impacts and priorities could
be that it would provide a means of linking together all the NPSs.
For energy developments it could facilitate the location of new
infrastructure nearer to sources of demand. In considering this
issue, it is worth noting the recommendation of the then Transport,
Local Government and the Regions Select Committee in its Report
on the 2001 Planning Green Paper which argued that policy statements
should relate to the national spatial strategy, and that Wales
already has a Spatial Plan and Scotland a National Planning Framework.[184]
92. We believe the Government has not fully explored
the potential for some form of English national spatial strategy.
Such a document could provide the means of drawing together the
many spatial aspects and implications of not only the energy NPSs,
but all the NPSs. It could also provide the means of relating
policies in the NPSs more clearly to the range of existing national
spatial policies and environmental designations. However, we do
not believe such a strategy should be a pre-requisite of designation
of the energy NPSs.
The relationship between the
energy NPSs and the overall planning system
93. The Planning Act 2008 states that the
IPC will make decisions on development consent for the following
types of nationally significant energy infrastructure:
- Onshore electricity generation
stations with a capacity of over 50 MW;
- Offshore electricity generation stations with
a capacity of over 100 MW;
- Certain underground facilities for the storage
of gas in natural porous strata by a gas transporter;
- Certain cross-country pipelines of the kind previously
covered in the Pipelines Act 1962 and certain gas transporter
pipelines; and
- Overhead electricity lines of 132 kV and above.
94. The energy NPSs will not only form the basis
for decision-making by the IPC, but are also meant to form a key
part of the wider policy context for decisions on energy proposals
that fall below these thresholds. Although this is not spelt out
clearly in the draft NPSs, these decision-makers will include:
local planning authorities; the new Marine Management Organisation;
the Planning Inspectorate, when dealing with any appeals; and
the Secretary of State for Communities and Local Government if
dealing with 'called-in' planning applications or 'recovered'
appeals. One example of the importance of the NPSs within the
overall planning system concerns renewable energy. The British
Wind Energy Association told us around 70% of onshore projects
in England and Wales will go through the town and country planning
regime rather than being dealt with by the IPC.[185]
It is, therefore, vital that the energy NPSs are fit for purpose
in fulfilling their wider role. In the next few sections we consider
a number of aspects relating to the relationship between the energy
NPSs and the rest of the planning system.
NPSS AND THE TOWN AND COUNTRY PLANNING
REGIME
95. A key issue raised in evidence was whether the
draft energy NPSs provided adequate guidance for those authorities
and bodies that are required to take decisions on energy infrastructure
that falls below the thresholds set out in the Planning Act
2008. The draft overarching energy NPS states that: "In
England and Wales this NPS may [...] be a material consideration
in decision-making on applications that fall under the Town and
Country Planning Act 1990 (as amended). Where relevant, decision-makers
of such applications in England should apply the policy and guidance
in this NPS as far as practicable".[186]
In November 2009, the Chief Planner at the Department for Communities
and Local Government (DCLG) wrote to Local Planning Authorities
(LPAs) in England, stating: "NPSs may specifically set out
policies which will need to be taken into account by decision-makers
other than the IPC [...] LPAs and other decision-makers should
therefore take account of those policies when determining applications
for consent for below-threshold infrastructure applications made
under the town and country planning regime".[187]
This letter appeared to strengthen the extent to which the NPSs
are meant to guide LPAs' decision-making on applications that
fall to them.
96. Our evidence raised concerns that the role of
the energy NPSs in providing guidance for other parts of the planning
system has not been clearly established. For example, the Energy
Networks Association told us: "We need to make sure that
the difference between what happens on DECC consents, the Town
and Country Planning Act and the IPC is absolutely seamless, and
that there is not one going off in one direction and another going
off in another direction".[188]
The UK Business Council for Sustainable Energy highlighted the
potential risk of perverse incentives if developers favoured one
system of decision-making over another. It said: "The reason
you need consistency both in terms of the process and the efficiency
of the two regimes is that you do not want to skew the market
so that developers bring forward very many more large projects
and no smaller scale projects".[189]
NPSS AND REGIONAL AND LOCAL PLANS
97. A second and related aspect is the relationship
between NPSs and regional and local plans. The DCLG Chief Planner's
letter stated that: "Regional planning bodies and local planning
authorities must [...] have regard to NPSs when preparing their
plans at regional and local level".[190]
The Town and Country Planning Association expressed concern at
this statement, noting that the development of the NPSs by different
government departments outside of DCLG created a risk that there
would not be proper integration between the policy content of
the Statements and regional local planning frameworks.[191]
RWE Npower told us, however: "our expectation is that the
development plans will in time be aligned with the NPSs [...]
Clearly there is that opportunity for conflict. At the end of
the day, a dispute is resolved ultimately through the law [...]".[192]
98. It is worth noting that the 2007 Planning White
Paper, which introduced the new system, envisaged a symbiotic
relationship between different levels of policy. It stated that:
"Where national policy statements are more locationally specific,
they would need to set out clearly how national interests and
local impacts had been considered and balanced in setting the
policy. This would include taking into account relevant national
planning policy and the development plan for the locations being
considered".[193]
NPSS AND OTHER NATIONAL PLANNING
POLICY
99. There are two aspects to integrating planning
policy at a national levelthe relationship between the
energy NPSs and other NPSs and that between the NPSs and existing
guidance used by Local Planning Authorities, such as Planning
Policy Statements (PPSs). On the first of these, the Royal Institute
of Chartered Surveyors (RICS) expressed concern that consideration
of the draft energy NPSs would be in isolation to other NPSs on
issues such as roads, rail and airports, despite the fact that
much of the energy infrastructure in the draft NPS would be reliant
on locating near to good road or rail links. RICS felt this made
it difficult to have a joined-up approach to strategic planning
in the UK.[194] We
note too that the Transport Committee, following its consideration
of the draft ports NPS, has recommended delaying designation until
the Department for Transport has produced the national networks
NPS.[195]
100. We also received evidence suggesting a lack
of clarity on the relationship between the policy statements contained
in EN-1 to 6 and those in existing Government planning guidance.
The BWEA believed central Government departments had not yet decided
the relationship the NPSs would have to PPSs. The Association
told us: "it makes no sense to have two policies that have
the same weight when one is saying something slightly different
potentially in emphasis to the other, and they both claim to deal
with renewable energy".[196]
For example, the Campaign for National Parks pointed out that
the guidance on development within nationally designated landscapes
in para 4.24.7 of EN-1 is at odds with current Government policy
for assessing major development proposals within National Parks,
as set out in Planning Policy Statement 7. Whereas EN-1 attempts
to define exceptional circumstances as those where development
can be demonstrated to be in the public interest, PPS7 states
that both exceptional circumstances and public interest must be
demonstrated, as the two are not always necessarily equivalent.[197]
Overall, the Sustainable Development Commission summed up the
situation thus: "At the moment, it is very unclear how these
things all fit together [...] what Government needs to do is very
clearly set out that relationship".[198]
101. We are concerned that the current status
of the NPSs within the wider planning system is, at best, ambiguous.
Whilst the NPSs' role in relation to the IPC is embodied in statute,
their important role in relation to Local Planning Authorities
(LPAs) and other bodies has not been addressed with sufficient
thoroughness. For example, it is not clear what weight LPAs should
give to NPSs in their decision-making. Nor is it clear what happens
in cases of conflict between an NPS and other Government statements
of planning policy. This ambiguity risks creating perverse incentives
for developers within the planning regime.
102. We note the Chief Planner has attempted to
provide some clarity on the role of the NPSs within the planning
system. However, this intervention has raised more questions than
it has answers. We recommend the DCLG should first consult on,
and then issue, definitive guidance on the role that all NPSs
will play in the preparation of plans at the regional and local
levels and in informing and guiding decision-makers other than
the IPC in considering applications for relevant infrastructure
projects. This guidance should clarify whether there is a hierarchy
of planning documents, for example in relation to NPSs and Planning
Policy Statements, and how decision-makers are to deal with conflicts
between different policy statements when they arise. We do not
believe the Government should designate the energy NPSs until
this guidance is in place.
Associated infrastructure
103. The Planning Act 2008 allows the IPC
to deal with development that is associated with a main
proposal in a single application.[199]
Associated infrastructure includes a variety of developments,
such as: fuel depots; measures to prevent coastal erosion; substations;
distribution lines; security measures; and waste heat plant and
pipe work. DCLG has published guidance stating: "Associated
development should not be an aim in itself but should be subordinate
to and necessary for the development and effective operation [...]
of the NSIP that is the subject of the application". Furthermore
"The IPC can only consider associated development in conjunction
with the main application and has no power to consider a separate
application unless this is an NSIP in its own right".[200]
An applicant can still apply for permission for associated development
through the town and country planning regime.
104. The associated infrastructure provision was
widely welcomed in the evidence we received. The UK Business Council
for Sustainable Energy told us: "One of the key benefits
of the new regime is the opportunity for developers to bundle
up all the different associated developments in one application
[...]".[201] Equally,
National Grid said: "the flexibility built in to enable us
to bring an integrated application or to bring applications that
will be considered in different timescales is very important".[202]
105. We also received evidence of a degree of concern
about the possibility of delay in gaining consent for associated
development that was not included in a main 'bundled' application.[203]
National Grid, for example, told us: "We must [...] make
sure that we do not build a process where we consent the main
plant items through IPC and then we are frustrated by having got
[...] permission for the power station, the line, the sub-station,
but we cannot get the equipment to the sub-station site because
we cannot get access roads".[204]
Elsewhere, the Royal Institute of Chartered Surveyors (RICS) said:
"If a developer is looking at proposals for a particular
large power plant development [...] it will want to know that
that proposal is going to be able to go into operationnot
just receive consent for the proposal on site, but also that the
remaining infrastructure which is necessary will be provided".[205]
106. We support the flexibility within the overarching
NPS for applicants to decide whether to include associated development
within an application to the IPC for consent for the main NSIP
development or to apply for consent for it via other routes. However,
we are concerned that there are potential risks of delay where
associated infrastructure falls under a different planning regime.
This opportunity for delay strengthens the case we have already
made for a clearer statement of the relationship between an NPS
and the rest of the planning system.
157 EN-6, para 2.5.3-4 Back
158
Ev 459 (Planning and Environment Bar Association) Back
159
Q 584 (Law Society) Back
160
Q 683 (Infrastructure Planning Commission) Back
161
Q 664 (Infrastructure Planning Commission) Back
162
EN-6, para 1.6.2 Back
163
Q 250 (Nuclear Consultation Group) Back
164
Q 115 (Sustainable Development Commission) Back
165
Q 630 (Natural England) Back
166
Ev 574 (WWF) Back
167
Q 163 (Campaign to Protect Rural England) Back
168
Q 84 (Sustainable Development Commission) Back
169
Q 165 (RSPB) Back
170
Q 707 (Local Government Association) Back
171
Ev 494 (SBGI's Gas Storage Operators Group) Back
172
Welsh Assembly Government, Technical Advice Note 8: Planning for
Renewable Energy, 2005 Back
173
Q 487 (UK Business Council for Sustainable Energy) Back
174
Q 607 (Environment Agency) Back
175
Q 271 (British Wind Energy Association) Back
176
Q 455 (RWE Npower) Back
177
Q 272 (Renewable Energy Association) Back
178
Q 488 (Scottish and Southern Energy) Back
179
Q 311 (National Grid) Back
180
Q 83 (Sustainable Development Commission) Back
181
For example, DECC consultation response 0206 (Swindon Borough
Council) Back
182
Q 85 (Sustainable Development Commission) Back
183
Q 47 (Institution of Civil Engineers) Back
184
House of Commons Transport, Local Government and the Regions Committee,
Thirteenth Report of Session 2001-02, The Planning Green Paper,
July 2002, HC 476 Back
185
Q 281 (British Wind Energy Association) Back
186
EN-1, para 1.2.1 Back
187
Letter from the DCLG Chief Planner to Local Authority Chief Planning
Officers, 9 November 2009 Back
188
Q 303 (Energy Networks Association) Back
189
Q 493 (UK Business Council for Sustainable Energy) Back
190
Letter from the DCLG Chief Planner to Local Authority Chief Planning
Officers, 9 November 2009 Back
191
Q 35 (Town and Country Planning Association) Back
192
Q 460 (RWE Npower) Back
193
HM Government, Planning for a Sustainable Future, Cm 7120,
para 3.19, 2007 Back
194
Ev 475 (Royal Institution of Chartered Surveyors) Back
195
House of Commons Transport Committee, Fifth Report of Session
2009-10, The proposal for a National Policy Statement on Ports,
March 2010, HC 217 Back
196
Q 284 (British Wind Energy Association) Back
197
Ev 238 (Campaign for National Parks) Back
198
Q 91 (Sustainable Development Commission) Back
199
Planning Act 2008, Section 115(1)(b) Back
200
DCLG, Guidance on associated development applications to the IPC,
para 11, September 2009 Back
201
Q 494 (UK Business Council for Sustainable Energy) Back
202
Q 307 (National Grid) Back
203
For example, Q 52 (Institution of Civil Engineers) Back
204
Q 317 (National Grid) Back
205
Q 55 (Royal Institute of Chartered Surveyors) Back
|