The proposals for national policy statements on energy - Energy and Climate Change Contents


Further supplementary memorandum submitted by Blackwater Against New Nuclear Group

ADDITIONAL EVIDENCE AS REQUESTED FOLLOWING PRESENTATION OF EVIDENCE TO SELECT COMMITTEE, 27 JANUARY 2010 BY CHAIRMAN ALAN WHITEHEAD

  This additional submission takes the form of a list of criticisms of the contents of the Draft NPS reports and associated documents which illustrate the quality of these and provide additional support for the demand that this exercise is flawed and should not be approved.

  The list includes only those criticisms which have been particularly notable. There are others.

DRAFT OVERARCHING NPS FOR ENERGY EN-1

  1.1.2  result in adverse impacts outweighing the benefits.

  No suggestion given on how this is evaluated.

  1.3.5  generation of electricity from renewable sources other than wind, biomass or waste is not within the scope of this NPS.

  This excludes some of the options such as tidal, or wave power which the UK is well placed to benefit from.

  2.1.8  applicants should demonstrate to the IPC that they have considered and planned for the impacts of climate change on their proposal.

  How can they do this for nuclear at vulnerable sites like Bradwell when they only have 100 year climate projections and the sites will be occupied for over 160 years?

  2.1.14  We need sufficient capacity to meet demand at all times.

  The document makes only passing reference to planning to reduce energy demand.

  3.1  within the context of the overall strategic framework set by Government, in principle, new nuclear power should be free to contribute as much as possible towards meeting the need for 25 GW of new non-renewable capacity. The Government expects that under this approach a significant proportion of the 25 GW will in practice be filled by nuclear power.

  Nuclear contribution is thus left to decisions of the market place, not government planning. Alternatives must be planned if 25GW deemed essential.

  The IPC does not need to consider the relative advantages of one technology over another given the Government's view that companies should be permitted to determine the individual projects to bring forward within the strategic framework set by the Government, taking account of the clear benefits of a diverse energy mix.

  This further shows the weakness of government planning and also states the importance of diversity, yet having already limited it in 1.3.5 above.

  3.3.10  Over these longer time horizons demand is likely to rise, particularly as a result of increased demand.

  This does not make sense.

  3.4.3  Wave and tidal—the UK has significant potential for wave and tidal energy, but many of the technologies for making use of the wave resource and tidal currents are still at the prototype or demonstration stage, although proven technology exists for tidal range generation. Para 1.3.5 explains how this NPS relates to wave and tidal generation.

  See 1.3.5 above, where there is no mention of wave and tidal power.

  3.8.7  The figures in this section show that approximately 40 GW of energy will flow into the midlands and southeast in 2020 from elsewhere in the country. The NPS makes no attempt to deal with this imbalance of supply with demand. The transmission losses incurred, and the omission of combined heat and power due to remote power station locations, will add to energy inefficiency rather than improving it. This adds to the national energy need unnecessarily.

  4.1.1  (iv)  The IPC should take into account adverse impacts—environmental, social and economic—including those identified in this NPS and the relevant technology-specific NPS, as well as local impacts identified in the application or otherwise. The IPC should ensure it takes account of any longer-term adverse impacts that have been identified and any cumulative adverse impacts.

  4.1.1  (v)  If the IPC is satisfied that the adverse impacts identified (including any cumulative adverse impacts) outweigh the benefits of the proposed development (taking into account measures to avoid, reduce or compensate for those adverse impacts) consent should be refused.

  These statements are not reflected in nuclear NPS-6 where IROPI is regularly mentioned together with the comment that all nuclear sites are needed even if significant adverse impacts cannot be mitigated.

  4.2.1  All proposals for projects that are subject to the European Environmental Impact Assessment Directive must be accompanied by an Environmental Statement (ES) describing the aspects of the environment likely to be significantly affected by the project. The Directive specifically refers to effects on human beings, fauna and flora, soil, water, air, climate, the landscape, material assets and cultural heritage, and the interaction between them. The Directive requires a description of the likely significant effects of the proposed project on the environment, covering the direct effects and any indirect, secondary, cumulative, short, medium and long-term, permanent and temporary, positive and negative effects at all stages of the project, and also of the measures envisaged for avoiding or mitigating significant adverse effects21. When considering a proposal, the IPC should satisfy itself that likely significant effects have been adequately assessed, and should request further information where necessary.

  The Appraisal of Sustainability for Bradwell does not follow these directives. Is it realistic to expect a developer to be more rigorous than DECC and the NPS?

  4.2.2  While not required by the EIA Directive, the IPC will find it helpful if the applicant also sets out information on the likely significant social and economic effects of the development, and shows how any likely significant negative effects would be avoided or mitigated. This information could include matters such as employment, equality, community cohesion and well-being.

  Comment as above.

  4.4.3  Given the level of need for energy infrastructure as set out in this NPS, the IPC should have regard to the possibility that all suitable sites may be needed.

  Straightjacket for IPC?

  4.6.5  Under guidelines issued by BIS (then DTI) in 2006, any application to develop a thermal generating station under Section 36 of the Electricity Act 1989 must either include CHP or contain evidence that the possibilities for CHP have been fully explored.

  This section of the report states the importance of combined heat and power but this importance is not reflected in the choice of sites for nuclear.

  4.8.6  Applicants should use the latest set of UK Climate Projections to ensure they have identified appropriate measures to adapt to the risks to the proposed infrastructure.

  These projections extend for 100 years, whereas sites will need to be secure for 160 or more years.

  4.8.10  The IPC should satisfy itself that there are not critical features of the design of new energy infrastructure which may be seriously affected by more radical changes to the climate beyond that projected in the latest set of UK climate projections, taking account of the latest credible scientific evidence on, for example, sea level rise.

  Inadequate planning, as above.

  4.8.12  Adaptation measures can be required to be implemented at the time of construction where necessary and appropriate to do so.

  Adaptation measures must be required would be more acceptable.

  4.10.3  The IPC should work on the assumption that the relevant pollution control regime will be properly applied and enforced. It should act to complement but not seek to duplicate it.

  This appears to be contradicted by:

  4.10.8  The IPC should not refuse consent unless it has good reason to believe that any relevant necessary operational pollution control permits or licences or other consents will not subsequently be granted.

  Evaluation of pollution controls compliance must carried out to do this.

  4.18.9, 10, 11, 12, 13  These relate to the importance of protecting designated conservation sites but then states that these designations should not be used to refuse development consent. Yet Dungeness has been classified as unsuitable for these reasons. Consultation on draft National Policy Statements for Energy Infrastructure, Dungeness Summary P 71.

  4.18.17  Other species and habitats have been identified as being of principal importance for the conservation of biodiversity in England and Wales and thereby requiring conservation action. The IPC should ensure that these species and habitats are protected from the adverse effects of development, where appropriate, by using conditions or planning obligations. The IPC should refuse consent where harm to the habitats or species and their habitats would result, unless the benefits (including need) of the development outweigh that harm.

  More direction here.

DRAFT NUCLEAR POWER NPS EN-6

  2.3.1  Nuclear power is low-carbon, economic, dependable, safe, and capable of increasing diversity of energy supply and reducing our dependence on any one technology or country for our energy or fuel supplies. Excluding nuclear power as an option for generating electricity would make it harder and more expensive to meet our emission targets. It could also jeopardise the security of the UK's energy supply.

  The claims here are contestable.

  3.6.2  The potential for delivering CHP from a nuclear power station is constrained by the need to minimise the radiological consequences to the public in the unlikely event of

a serious nuclear accident. Consistent with the SSA demographic criterion applied to

the siting of new nuclear power stations sites are likely to be located away from major

population centres, which may limit the viability of CHP schemes.

  This is in conflict with the desire for CHP and illustrates the government's confusing demographic criteria.

  3.8.18  Based on domestic and international experience the Government is satisfied that interim storage facilities are and will be safe and effective, and will remain so for as long as is necessary, for example through building of new stores and periodic refurbishment of stores if needed, until geological disposal is available for use. In the event that geological disposal facilities are not available to accept radioactive waste in accordance with the indicative timetable set out above, the Government is satisfied that interim storage will provide an extendable, safe and secure means of containing waste for as long as it takes to site and construct a geological disposal facility.

  This states indefinite storage beyond 160 years is possible.

  4.2.9  The Government has also concluded that nominated sites in lower flood zones should not be considered as reasonably available alternatives to those in the higher flood zones. This is because the NPS sets out that all the sites listed in this NPS are needed in order for the Government to meet its objectives on climate change and for the UK to become a low carbon economy.

  All sites needed, again.

  4.6.1  The AoS identified that the potentially suitable sites share the following landscape issues: the sites are generally in less populated areas that may have value for visual amenity and as landscape resources; they are coastal/estuarine sites; and that the scale of the facilities means that the scope for visual mitigation is quite limited. In addition, because of the timescales involved, there is some uncertainty over future land uses once sites are decommissioned.

  This is not the case at Bradwell due to the proximity of the north coast of the estuary, less than 2 miles, and the importance of employment in holidays, tourism and sailing in the estuary. The value of visual amenity is important to these industries.

  4.6.3  Visually-intrusive cooling towers can increase a nuclear power station's visual impacts on the landscape. However, with the exception of Oldbury, cooling towers are not the preferred option proposed by the nominators for cooling.

  This is untrue, Iberdrola, currently the most likely site developer, in their letter of interest in Bradwell, sent to DECC March 23rd 2009, clearly stated their wish to construct up to three reactors including cooling towers as required for reactors 2 and 3.

  4.7.1  The AoS identified that there are likely to be positive effects of local economic

significance, although these are less significant at the regional scale except where there are clusters of potentially suitable sites for new nuclear power stations, particularly in the south-west and north-west of England.

  The AoS omits mention of negative economic effects which are likely to occur.

  4.8.7  Given the potential for positive employment opportunities as a result of the development of new nuclear power stations the IPC should give significant weight to the effect of employment on human health and well being.

  More of the same.

  4.13.1  The objective of Government's policy on demographics and the siting of nuclear power stations is to limit the radiological consequences to the public in the unlikely event of a serious nuclear accident. This policy is a measure of prudence over and above the stringent regulatory requirements imposed on nuclear operators to prevent such accidents.

  This prudence does not extend to credible emergency plans for the 15,000 on West Mersea who are regularly cut off by tides. If the stringent regulatory requirements are indeed sufficient then the power stations can be placed closer to where they are needed.

  5.6.5-10  Covers demographics at Bradwell and the need for any emergency planning to be covered at the time of an application. This implies that effective plans are possible even over 160 or more years. In the case of West Mersea this seems unlikely. Who would pay for this? The site operator? What if major expenditure is required after decommissioning but during the indefinite interim waste storage period?

  5.6.28  The Environment Agency has advised that it is potentially reasonable to conclude that a nuclear power station within the nominated site could potentially be protected against flood risks throughout its lifetime133, including the potential effects of climate change, storm surge and tsunami, taking into account possible countermeasures. The Environment Agency have noted in making this assessment that it is likely that any new development at Bradwell would be built on higher or raised ground so reducing the need for protection.

  This statement is extremely weak and could be considered unreasonable due to the compounded number of potentials. It is not helped by the reliance on 100 year projections

to deal with a 160+ year problem.

  5.6.31  This site passes this criterion. This is because, based on, in particular, the advice of the Environment Agency and the findings of the Appraisal of Sustainability, it is reasonable to conclude that a nuclear power station within the nominated site could potentially be protected against flood risks throughout its lifetime, including the potential effect of climate change, storm surge and tsunami. This takes into account the potential identified by the Environment Agency to protect the site and to mitigate risks although, as with all sites, the potential effects of any mitigation on the surrounding area will have to be carefully considered as part of a flood risk assessment should any application be forthcoming.

  The environment agency carries the can for this woolly statement which has now been hardened up to look better.

  5.6.56-62  Cover the potential impacts on the sites of international importance covering almost all of the Blackwater Estuary and around the Dengie Peninsula. These areas immediately border the proposed site and extend within it.

  57.  The Appraisal of Sustainability findings on sites of international importance are taken from the Habitats Regulations Assessment137. Taking into account the strategic nature of the plan and the information available, the Habitats Regulations Assessment at this strategic level cannot rule out potential adverse effects on Dengie SPA/Ramsar site, Blackwater Estuary Ramsar Site, Colne Estuary SPA/Ramsar site and the Essex Estuaries SAC, through impacts on water resources and quality, air quality, habitat and species loss and fragmentation/coastal squeeze and disturbance. The designation identified fall immediately adjacent or slightly within the site boundary and the Habitats Regulations Assessment finds that there is a risk that development activities encroach into these designated areas, for example the potential for a marine landing facility, cooling water infrastructure and upgraded coastal protection measures could all have adverse impacts.

  58.  In the wider context, the Habitats Regulations Assessment also concludes that adverse effects cannot be ruled out on the Mid-Essex SPA/Ramsar as a whole (for water quality impacts and impacts on birds) and the Abberton Reservoir SPA/RAMSAR (for impacts on birds only). Government notes the scope for avoidance and mitigation identified in the Habitats Regulations Assessment for sites of international importance, and the need for more detailed studies should an application for development consent come forward.

  61.  Given that the Habitats Regulations Assessment has not been able to rule out adverse impacts on sites of European nature conservation importance, the Government has carefully considered whether it is appropriate to include this site in the NPS.

  62.  Annex A of this NPS sets out that the Government has concluded that there is an Imperative Reason of Overriding Public Interest that favours the inclusion of this site in the Nuclear NPS despite the inability to rule out adverse effects on European sites at this stage.

  The IPC is directed to ignore all the listed site impacts. So it now passes. What is the point of designated sites? Dungeness?

  5.6.85  The nomination described different cooling technologies and stated a preference for

direct cooling from the Estuary. Some responses during the opportunity for public comment were received about whether cooling towers would be necessary at the site. The nominator of the site has noted that the "direct cooling option will require long cooling water culverts to reach deep water to obtain the coolest water and to permit dispersion of the thermal plume to avoid any significant impact on designated ecological sites" but has indicated that direct cooling is the preferred option for the site if it can be achieved. The Environment Agency has advised that there is access to suitable sources of cooling at the site.

  No mention of additional reactors with cooling towers as per Iberdrola application.

  5.6.86  There were public concerns about whether local ecology around the site, including the

local oyster beds, could be adversely affected by the intake and outfall of cooling water from the site and whether this could impact on the local fishing industry.

  5.6.87  The Appraisal of Sustainability for Bradwell has identified potential effects on water quality and fish/shellfish populations in nearby coastal waters due to the abstraction and release of sea water for cooling. Indirect effects on nationally and internationally designated habitats, including from the thermal impact of cooling water discharges have also been identified. The Appraisal of Sustainability considers this of potential wider significance because of indirect effects on national and European designated sites.

  5.6.88  The Environment Agency has advised that there is an important spawning site for herring on Eagle Bank. The Blackwater Estuary provides a major nursery ground for herring, sprat, bass, and a range of flatfish species. Migratory trout, smelt, eel and twaite shad are all present.

  Some of the risks to the estuary are included here but the AoS is biased towards mitigation of effects in the restricted waters of the estuary, which will be impossible given the huge volumes of water passing through a new system.

  5.6.109  Part 4 of this NPS (Human health and wellbeing) sets out that the risk of an accident resulting in exposure to radiation for workers, the public and the environment is very small because of the UK's strict regulatory regime. Part 4 should be referred to for further guidance.

  This is not convincing in the light of a recent prosecution:

BRADWELL OPERATOR GUILTY OF 14-YEAR RADIOACTIVE LEAK

    — Buzz up!

    — Digg it

    — Terry Macalister

    — guardian.co.uk, Friday 6 February 2009 20.38 GMT

    — Article history

  The nuclear power industry suffered an embarrassing blow today when the operator of the Bradwell-on-Sea plant was found guilty of allowing a radioactive leak to continue for 14 years.

  Magnox Electric Ltd, the operator of the site, denied some of the allegations but was found guilty of breaking the Radioactive Substances Act 1993 over the way it dealt with waste on the premises.

  The Environment Agency, which brought the company to court, said the case demonstrated how the operator had failed to carry out inspections on a holding tank between 1990 and 2004. The company pleaded guilty to two separate offences for failing to maintain the tank.

  "Our prosecution sends a clear message to the nuclear industry that we require the highest standards of operation at all such sites and will take firm action, even if the environment beyond a site's boundaries is not affected," said Phil Heaton, team leader of the agency's nuclear regulation group.

  Peter Fenn, hearing the case at Chelmsford crown court, said he would pass sentence on Magnox Electric on 17 February. Mark Harris, prosecuting on behalf of the Environment Agency, said radioactive liquid had leaked into the ground because the tank had been poorly designed and badly maintained.

  The most senior figure in nuclear safety had been forced to defend the regulation of the Essex nuclear power station in an interview the Guardian published on Monday. Mike Weightman, chief inspector at the Nuclear Installations Inspectorate, said it was not possible to "inspect or check every feature of a complex plant" but he insisted that as soon as the leak was discovered the safety body did all it could to ensure that the cause of the problem was identified and dealt with.

  This resulted in a fine of £250,000 plus £150,000 costs.

  The leak was only discovered due to the diligence of a decommissioning worker.

CONCLUSION ON THE NOMINATED SITE AT BRADWELL

  5.6.121  Given that the site meets the SSA criteria, and having considered the evidence from, inter alia, the public, regulators, the Appraisal of Sustainability and Habitats Regulations Reports, the Government has concluded that the site is potentially suitable.

  5.6.122  This assessment has outlined that there are a number of areas which will require further consideration by the applicant, the IPC and/or the regulators should an application for development consent come forward, including amongst other things flood risk, seismic risk, the impact on biodiversity and the potential impacts of cooling technology. However, the Government has concluded that none of these factors is sufficient to prevent the site from being considered as potentially suitable as part of the SSA.

  No mention of negative economic impacts.

COMMENTS FROM THE APPRAISAL OF SUSTAINABILITY FOR BRADWELL

COPY OF SUMMARY OF KEY FINDINGS

  A number of the strategic effects identified for Bradwell will be similar across all the nominated sites, including positive effects for employment and well being. However a number of potential strategic effects have been identified that are of particular note for the nominated site at Bradwell. These are discussed below:

  There are potential negative effects on three national and internationally protected nature conservation sites, including the Essex Estuaries and Blackwater Estuary; effects on water quality and fish/shellfish populations in nearby coastal waters due to the abstraction and release of sea water for cooling.

  Part of the site is in flood zone 3 and therefore at a higher risk from coastal flooding.

  There are both hard and soft flood defences already in place, but these may require upgrading over the lifetime of a new power station. This could have potential effects on erosion and visual appearance of the coastline. These effects are significant, but mitigation opportunities are likely to be available following further study.

  A new nuclear power station would be set in the context of the existing nuclear power station at Bradwell, but the surrounding area is predominantly undeveloped and there is limited potential for mitigation of the adverse impact on the local landscape. There are no significant adverse effects anticipated on nationally designated landscapes.

  Potential setting effects upon nearby scheduled monuments and listed buildings, and the West Mersea Conservation Area, could also be of regional or national importance, depending on distance and sight lines. The impact on the setting of Othona Roman fort and St. Peter's Chapel would be of exceptional significance.

  However, mitigation could be applied by siting the proposed facility close to the existing power stations on the western side of the nominated site. Detailed assessment will be required at the project level Environmental Impact Assessment stage.

  There remains some uncertainty relating to the significance of some effects and the most appropriate mitigation. It is expected that the mitigation measures will be refined iteratively as part of the development of the proposals for the nominated site, and will be assessed further in the project level Environmental Impact Assessment.

    1.19 To provide a standardised approach to the appraisal of the nominated sites, the assumptions about generic design characteristics have been summarised into a base-case. The base-case was used to guide the assessment for each site, except in cases where a nominator has provided further detail at variance to the base-case. For example, if a nominator is proposing cooling towers instead of abstracting water for cooling, this has been considered in the assessment.

  This is not true, Iberdrola have stated they expect to need cooling towers when they construct reactors 2 and 3.

    2.3 Bradwell lies some 40km to the east of Chelmsford and 4km from the town of West Mersea across the Blackwater River and Estuary. It is 2km from the village of Bradwell-on-Sea, with the hamlet of Bradwell Waterside adjacent to the west. Other nearby settlements on the Dengie peninsula includes Tillingham, Southminster and Burnham-on-Crouch to the south and Ramsay Island to the west. Tollesbury village lies 4km across the estuary to the north west, and the town of Maldon lies some 15km to the west up the estuary. The site lies to the east and south of Bradwell "A" power station, and comprises open agricultural land (largely arable), the former Bradwell Bay airfield, an existing electricity sub-station, a farmstead (Weymarks Farm), other agricultural buildings and areas of foreshore.

  This section omits mention of Colchester 15km, Brightlingsea 10 km, Clacton-on-Sea 17km, Southend-on-Sea 27km.

  Chelmsford is only 30 km away, not 40.

    2.4 The nomination is for a nuclear power station development incorporating:

        At least one nuclear reactor

  The nomination includes three reactors.

    4.65 The site is located next to the Blackwater Estuary. There are three identified Shellfish Waters in close proximity, located in channels that feed into the estuary: Strood Channel, Tollesbury Channel and Salcott Channel. A large area of the Blackwater Estuary itself, adjacent to the site, is marked as designated Shellfish Waters on a 1999 schedule but it is not shown on the 2007 maps. There are Bathing Waters at West Mersea, 3km to the north of the site. The quality of these Bathing Waters has not been classified.

  This acknowledges that there is a holiday and tourism area only 3km away, but no mention of impacts on this are documented.

    5.5 The construction of a nuclear power station at Bradwell is likely to have localised adverse effects on air quality in the short term (five to six years), including dust and emissions from construction vehicles, Heavy Goods Vehicles (HGVs) and traffic movements generated by the estimated construction workforce. This has the potential to affect residential properties in the surrounding area and villages.

  If three reactors are constructed this disruption could continue for 15 to 25 years.

    5.9 There is a very low risk of an accidental release of radioactive emissions from the Bradwell site, which could have a significant strategic effect on air quality. The HSE/NII and the EA will consider this matter during their risk assessments, which will be carried out as part of the consenting process to ensure that risks to public health and safety through accidental release of emissions are within acceptable limits. Whilst the risk is very low, the potential for a large number of people to be adversely affected means that, at this stage of assessment, the potential for strategic adverse sustainability effects has been identified.

  The meaning of this is unclear, large numbers of people could be adversely affected.

  Should this mean the site is not suitable?

    5.15 Water intake from the coastal waters for cooling purposes could lead to the incidental mortality of fish and other aquatic species. Fish, larvae and eggs can be sucked into condenser units and be subjected to heat before being returned to the sea. This could lead to loss of fish or invertebrate food sources and could have an adverse effect on the important bird assemblages for which the SPA/Ramsar sites are designated. The design and siting of the intake system should be carefully considered so as to avoid/minimise depletion of such food sources.

  This directive to avoid/minimise is not possible, for reasons previously presented at HoP. The demand for much larger volumes of cooling cannot be sustained by the estuary without major damage to ecology, fish and oysters.

    5.25 Whilst there is likely to be significant positive effects for employment and local communities, the magnitude of these effects is reduced at a regional and national scale. An exception to this is likely to be the Isle of Mersea, which although relatively close to Bradwell, is located on the north coast of the estuary and has no direct transport links to the site. On a strategic regional level, impacts are considered to be positive.

  West Mersea is very close to Bradwell. Similar problems apply to Tollesbury, Brightlingsea, Colchester, Clacton.

    5.30 It is commonly perceived that proximity to a nuclear facility such as a power station would have an adverse effect on property values. However, the evidence for this is inconclusive and contradictory. A study of effects in America found that property values were actually increased in the vicinity of nuclear facilities, although the authors caution that this finding is subject to several caveats including being based on a small sample and may be unrepresentative. It is suggested that in relatively poor areas, or where the local economy is depressed, the income generated by employment at a new nuclear facility may have a positive effect on local property values. For the present appraisal, any effect on property values is not considered to be strategically significant because it is limited to the local area.

  These comments may apply to areas near Bradwell on the south side of the estuary, but the north side of the estuary is currently a relatively affluent area.

    5.31 Strategic Effects on Communities: Population, Employment and Viability: Positive effects of local economic significance are likely to occur, although these are less significant at the regional scale. A potential negative effect of regional significance is the project leading to a shortage of local construction labour available to other industries. Bias again.

    5.56 It is possible that the presence of a nuclear power plant may lead to increased stress levels in certain individuals, due to potential perception of risk associated with living or working near a power station. However, there is little literature available on this potential impact which suggests that it has not been a significant problem in the past. In any event, in the case of the nominated site, people living and working nearby have had a long time to get used to there being an adjacent nuclear plant so this is unlikely to be a problem at this location.

  This claim is totally at odds with surveys currently being conducted around the estuary and cannot be regarded as evidence based information. It is unjustified speculation.

    5.58 Strategic Effects on Human Health and Well-Being: The rigorous system of regulation of routine discharges from the proposed nuclear power station at Bradwell should ensure that there are no unacceptable risks to the health of the local population when the plant is operating normally. There is also a very small risk of adverse health impacts arising from an accidental release of radiation but the multiple safety features within modern nuclear plants makes such an event exceedingly unlikely. Overall, the likely enhancement in employment, community wealth, housing stock and other associated neighbourhood infrastructure should improve community well-being and health generally.

  Most of this section is again speculative and not evidence based. The last part could not be further from the truth for most of the area.

  The first part claiming how safe it is should justify placing closer to areas of energy need.

    5.59 The main impacts of the development within the footprint of the proposed facility would be felt at a local to regional scale. Potential setting effects upon nearby scheduled monuments and listed buildings, and the West Mersea Conservation Area, could also be of regional or national importance, depending on distance and sight lines. However, the impact on the setting of Othona Roman fort and St. Peter's Chapel would be of exceptional significance especially if the development occurs on the eastern side of the site. However, mitigation could be applied by siting the proposed facility close to the existing power station on the western side of the site. Detailed assessment, including consultation of the Essex Historic Landscape Characterisation, consideration of Conservation Areas and other heritage assets will be required at the project level EIA stage.

  The location of the development on the site will have to be spread along towards St Peter's Chapel and Othona Fort if three reactors are built.

    5.68 Strategic Effects on Landscape: The AoS has identified potential, adverse indirect effects on the local surrounding landscape and some direct effects on features of the site. There are no significant adverse effects anticipated on nationally designated landscape. However, there are likely to be indirect adverse effects of the development on nearby Special Landscape areas. In visual terms, the new power station would be seen in the context of existing power station facilities, prior to any decommissioning. It is predicted that there will be limited further potential for mitigation of these local visual impacts, given the scale of the development, until after decommissioning. Therefore, overall, impacts are considered to be of minor adverse strategic significance.

  This ignores the probability of damage to tourism and holidays due to the visual intrusion.

    5.76 If cooling water is returned to the sea at elevated temperatures, this could have adverse effects on both sediment transport and water quality in coastal waters. Nearby coastal waters include the Essex Estuaries SAC, the Blackwater Estuary SSSI/SPA/Ramsar site and the Dengie SSSI/SPA/Ramsar sites. A more detailed appraisal is required by the developer at the project EIA level to assess the implications of this thermal discharge. This process will include an assessment of the impacts of any discharges to the aquatic environment, including impacts on specific designated sites under both the Habitats and Shellfish Directives.

  This is grossly understating the impacts known to result from power station cooling water extraction, see press article below.

NUCLEAR PLANTS SUCKING THE SEA LIFE FROM BRITISH WATERS, RESEARCHERS CLAIM

From The Times

14 April 2008

Robin Pagnamenta, Peter Stiff and Lewis Smith

  The nuclear industry in Britain is killing billions of fish every year and taking a devastating toll of stocks, an Oxford University academic suggests.

  The impact can be so severe in the worst-affected regions of the seas around Britain that death rates are equivalent to half the commercial catch for some species.

  Coastal power plants that have cooling systems that extract water from the sea are to blame for the destruction, according to Peter Henderson, an environmental researcher. Figures he has compiled suggest that the damage to fish stocks is much more severe than records have indicated previously. He calculated that had the young fish killed in power stations survived they would have added thousands of tonnes of fish annually to Britain's stocks.

  With a new generation of nuclear power stations likely to be built over the next 20 years the threat posed to fish stocks needed to be addressed urgently, he said. The net impact on fish populations was poorly understood because too few studies had been carried out.

  Dr Henderson is concerned that too little account is taken of the impact on fish stocks of the deaths of many billions of eggs and young caused by coastal power plants, both nuclear and conventional.

  The number, weight and species of fish and crustaceans removed from filters at power plants can be measured accurately, but it is much harder to assess the impact of the deaths of eggs, larvae and small fish.

  "The number of animals killed is colossal," Dr Henderson, an associate lecturer at the University of Oxford and director of the Pisces Conservation environmental consultancy, said. "Very small fish get sucked in in very large numbers."

  The impact on populations is compounded by the loss of prawns and shrimps which, like young fish and eggs, form an important part of the diet of larger animals. At Dungeness nuclear power station at Romney Marsh, Kent, where huge numbers of sprats are known to form shoals, the outfall pipes have been known to become clogged with dead fish. "We are talking as many as 250 million fish in as little as five hours," Dr Henderson said.

  In the southern region of the North Sea it was calculated that the mortality of eggs and young was so high for sole that it had been equal to 46% of commercial fishing. Similarly, herring mortality off parts of the East Coast was 50 per cent of commercial landings.

  Dr Henderson also identified the English Channel as a badly affected region because of the number of nuclear power stations on the coast on both sides of the Channel. Coal-fired stations and other installations such as those in the petrochemical industry present similar problems, but nuclear plants are among the biggest extractors of water.

  Water is pumped from the seas in vast quantities, with British nuclear plants extracting at up to 60 cubic metres (2,100 cubic ft) per second. The Gravelines plant on the French north coast pumps at up to 120 cubic metres per second.

  Once the water has been used to cool the reactors it is pumped back into the sea where, having been warmed up, it attracts a variety of marine creatures, many of which get caught up in the intake systems and killed. Fish that are too young or too small to be caught by the 1cm mesh screens—especially pipe fish and eels—travel through them, as do eggs and larvae, and pass into the reactors' cooling pipes. Many die after being heated to 30C (86F), chlorinated and given small doses of radiation.

  The toll of fish stocks can be avoided at new nuclear plants with the introduction of dry-cooling, said Dr Henderson, who called for this method to be adopted, despite the higher costs, if another generation of nuclear power plants is built.

  Callum Roberts, Professor of Marine Conservation at the University of York, said that the report, which had not been subjected to peer review, raised serious questions about the role of nuclear and other power stations in damaging fish stocks. "I think it's interesting that the quantity taken by the power stations is large, especially if you look at the possible cost in the future [of] prematurely killing these fish," he said.

  "It has become more significant over the years because of the decline of inshore stocks and, indeed, of the decline of some species going so far that they are reaching the status of becoming endangered, like the eel. We have to look at this problem."

  The Centre for Environment, Fisheries and Aquaculture Science has been commissioned recently to carry out an environmental survey of the waters near where four new nuclear plants are expected to be proposed. British Energy commissioned the survey to check which fish and other marine animals were found around Sizewell, Dungeness, Hinkley Point and Bradwell. Researchers will attempt to establish the quantity of fish in the four areas, how nuclear plants have affected them in the past and what impact could be expected if new power stations were built there.

  "All of these sites are suitable for new nuclear power stations," said Sue Fletcher, of British Energy, who maintained that the industry would "strongly contest" any suggestion that unsustainable quantities of fish were killed in cooling systems. A spokesman for Magnox, the operator of a coastal nuclear plant at Wylfa on the Isle of Anglesey, said that the group undertook "extensive monitoring activities".

  Emily Lewis-Brown, a marine campaigner for WWF, the wildlife charity, said it was concerned that coastal power stations represented a frequently overlooked, additional burden on British fish populations. "There is evidence to suggest that when power stations stop killing fish, local populations start doing better," she said.

    5.82 Strategic Effects on Water Quality and Resources: The AoS has identified potential, adverse, effects on water quality and coastal processes, including sediment transport. Adverse effects on water resources, including groundwater resources, could occur through increased demand, particularly during construction. Indirect effects on nationally and internationally designated habitats, including from the thermal impact of cooling water discharges have also been identified. This is of potential wider significance because of indirect effects on national and European designated habitat sites.

  The work to assess these significant adverse impacts should be conducted as part of the AoS report. To leave this until later when an application is received implies these effects can be mitigated.

    6.2 The AoS has explored both adverse and beneficial potential effects of building a new nuclear power station at Bradwell. Both beneficial and adverse effects were identified as potentially significant at the local level and it is recommended that these need to be further considered by the developer, regulators and the decision-maker (the IPC), during project level assessments.

  The AoS is very biased towards finding beneficial potential effects and overlooking os minimising adverse effects.

  Table 6.2 is supposed to document the Potential Significant Effects, Adverse and Beneficial, and this table is the basis for findings in the NPS EN-6 for Bradwell.

  Distortions are:

  Biodiversity and Ecosystems Potential Significant Effects

    Adverse Effects

    Discharge of heated water into aquatic habitats could alter ecosystem in Essex Estuaries SAC and Blackwater Estuary SPA/Ramsar sites.

    Abstraction of water for cooling purposes could lead to incidental mortality of fish and aquatic invertebrates, with secondary effects on the interest features (particularly birds of the Blackwater Estuary and Dengie SPA/Ramsar sites).

  These adverse effects are grossly understated, "could lead to incidental mortality", should read "will lead to incidental mortality". The adverse effects of biocide use do not appear.

  Communities: Population, Employment and Viability

    Adverse Effects

    There is no mention under this heading of loss of employment in tourism, holidays, leisure, sailing, fishing, oyster cultivation, loss of property values, difficulty attracting new industries.

    The inclusion of the Bradwell site has been assisted by the bias shown in the AoS, and had the report been more balanced then it is believed the site would have been excluded without the need for further consideration.





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 23 March 2010