Memorandum submitted by Billingborough and Horbling against TurbineS (NPS 79)

 

Synopsis

 

Our detailed comments on the Draft National Policy Statement for Renewable Energy Infrastructure (EN3) are given below using the same layout as the document itself.

 

To be helpful however we first summarise some of our key arguments as to what is wrong with the statement and how it can be improved. This synopsis does not cover all the points we are making and should not be taken to represent the whole of our representation. All our synopsis comments relate to on-shore wind power:

 

1. It is necessary to know who determines whether an application is 50MW or over. Wind farm operators clearly see the IPC route as more favourable than a local authority route to consent and there is evidence that they are therefore saying that their proposals are 50MW. Given that EN3 (wrongly) encourages flexibility, developers can go down the IPC route and then later change to a smaller scheme making a mockery of the Act. How will the IPC be required to check out the power generation capacity.? Surely it cannot just take the power company's word ?

 

2. 'Good design' is a hollow principle when it comes to wind turbines. Wind turbines will always be designed to achieve the greatest efficiency in power generation at the lowest cost (often at the sacrifice of noise considerations ) and considering their ever increasing size and industrial nature their visual design will play no part and it is cynical of EN 3 to suggest that it will

 

3. Electricity grid connections must be required to be detailed in the main application as their impacts on communities , especially when overground , can be as great as the turbines themselves.

 

4. The final minor roads and tracks giving access to windfarms should be required to have any 'improvements' removed after the windfarm construction phase. Over zealous highways authorities should not be allowed to insist on concrete kerbs/radii, metalled or concrete roads or hard drainage as all of these can add up to threatening urbanisation of the countryside and can even be used as a pretext for further development. We believe that the industrialization and urbanization of our fast disappearing English countryside is just as affected, in an insidious way, by the access works to windfarms as by the turbines themselves. Indeed if the windfarms truly are temporary as the author would have us believe then these impacts threaten to last longer than they do.

 

5. We have great concern about EN3 setting up the perception that somehow windfarms are temporary and for this reason their impacts are less serious. 25 years is after all a generation. If for example there are adverse effects upon an historic landscape it should not be an offsetting argument (as advocated) to say that they do not matter because they will only be for 25 years. That is ridiculous! If the historic landscape is important then it is important for every generation and one cannot be missed out! It is simply wrong to steer the IPC in the direction of lessening the importance of adverse effects upon landscape, visual amenity and historic assets on the grounds of temporariness, when the life is expected to be at least 25 years. This does not happen in the whole Town and Country Planning System with any other form of development. Temporary should only be a label for a development with a life of less than 3 years.. It is outrageous to suggest that somehow any indirect effects on historic environment features such as effects on setting will not be permanent and therefore should not count as much in weighing up the decision. Does this mean that if one wants to experience the beauty of a Cistercian Abbey in its setting one might have to come back in 30 years time ( if still alive)? Does this mean that the IPC should allow windfarms all around Stonehenge? What about the thousands of other less well known historic settings that this country is known for?

 

6. We object to the way that flexibility for applications is advocated. There is no logical reason why windfarm applications should have greater flexibility than any other planning application - indeed because the impacts are potentially much wider, if anything they should have less flexibility. For example the mechanism for driving the rotors can vary greatly in its noise generation and this is not just to do with its MW capacity. In order to decide whether to support or object to a local application the local community and other consultees need to know precise details of the development. If the developer is able to say in debate or at the hearing that 'this is just an example and the final product could be different' it will be impossible for objectors (and the IPC/ local planning authority) to pin him down and there will be no sensible debate. There is no less reason for a wind farm developer to not know the layout of his windfarm than for a housing developer not to know the layout of his housing estate.

 

7. In its attempt to support a flexible approach EN3 advocates that the 'maximum' scheme that could be built should be appraised. (This also encourages the applicant to go down the IPC route when he may intend to build a smaller development - see point 1) But what does maximum mean and this is not such a clever solution as it sounds because a smaller and cheaper turbine, which the applicant would be allowed to switch to, could well be noisier. The scheme should be the actual scheme.

 

8. A tolerance of up to 50 metres in the 'micrositing' of turbines is unacceptable and could have unexamined effects on noise, archaeology or the historic environment. This does not happen with any other development requiring consent - what is different?

 

9. EN3 proposes giving special consideration to impacts affecting sites of 'national designation' including listed buildings but it talks about where application sites are 'in' these sites. To prevent applicants drawing their application boundaries around such designations as listed buildings or monuments the consideration needs to apply to sites which contain or are close to nationally recognised designations. It should be borne in mind that other planning legislation and advice (PPGs) refers to the importance of 'the setting' of listed buildings and ancient monuments as well as the structures themselves. This important concept should also be incorporated here. The aim to weigh up any harmful impacts with environmental, social and economic benefits is admirable and is what decision making on development is all about. EN3 should make it clear that this approach should apply to all application sites and not just those within or close to national designations.

 

10. It is illogical to suggest that windfarms will bear greater scrutiny in greenbelts - greenbelts were introduced to stop urban sprawl and to achieve the separation of cities. There are no greenbelts where there are no cities but this does not mean to say that the countryside is any less precious - it belongs to all the citizens of this increasingly crowded country. The circumstance of greenbelts , when it comes to windfarms are therefore not 'very special' relative to anywhere else.

 

11. All other things being equal there is no reason why a sequential approach should not be applied to windfarms meaning there is no reason why priority should not be given to siting turbines on previously developed land. If this approach is specifically banned then it will simply mean that windfarm operators will always go for the cheapest solution which means constructing on greenfield land.

 

12. Considerations regarding birds is not just a question of the risk of collision with turbine blades. It is also a question of not interrupting large open spaces important for the winter grazing of such species as golden plover and lapwing which require uninterrupted space to land flocks of 1000 or more birds.

 

13. Potential adverse impacts which are missing from EN3 include:

 

· Effects of large concrete foundations on aquifers used for drinking water (eg the South kesteven fen margin in Lincolnshire)

· Effects of large concrete foundations on drainage and on carbon release in their manufacture

· Effects upon radar at airports and airfields (these have been used by local planning authorities and the MOD as reasons to refuse applications )

· Effects in areas heavily used by light aviation

· Effects on broadcasting and mobile phone signals

 

14. There should be a requirement for the land on which windfarms stand to be reinstated when they become disused for a given period of time ( say a year) and not just when the consent period runs out . This is to prevent the possibility of windturbines, towers and infrastructure standing disused for many years when their operation might cease because of changes in the economics and sources of power supply

 

15. Concerning the effects of noise, keeping turbines at a safe distance from homes is a key requirement. EN3 should set a minimum distance between turbines and any residential accommodation. This would then save a great deal of work and argument by the IPC, the power companies and by communities who otherwise might be in opposition and make the whole business of approving windfarms easier, which seems to be the Government's objective. This distance should be 2km. This is the distance recommended by La Societee de Medicins in France and it has been the distance for the search criteria for windfarm sites issued in planning advice by the Scottish Government. If there are one or two isolated homes within the 2 kilometre radius of a turbine then there should be a compulsory purchase power in order to move and compensate that home (at present there is no such power and some home owners who have been much closer than 2km have been forced to leave their homes - such as the Davis family in Deeping, Lincolnshire.

 

16. The reliance on the standard known as ETSU-R-97 for the testing of noise effects from windfarms is unreliable because it dates from 1996 when there were very few and much smaller wind turbines in the UK. Much more is now known internationally about the noise effects from windfarms and their repercussions for human health including vibro acoustic disease. This 14 year old standard must be urgently reviewed in the light of empirical evidence including that of families who have been forced to leave their homes. However this complication and arguments over the complex business of measuring noise noise could be completely removed if a minimum distance of 2km between turbines and human habitation was adopted.

 

17. It is stated that 'The IPC should use ETSU-R-97 to satisfy itself that the noise from the operation of the wind turbines is within acceptable levels' but will the IPC really carry out its own independent tests? Experience has shown that it is very easy for applicants to contrive the results of noise tests. This is particularly the case because the practice has developed of using laboratory/workshop readings for noise from particular turbines and this does not simulate the actual field conditions neither does it simulate the cumulative effect of several turbines combined with wind noise. The actual arrangement of the turbines on site can significantly affect noise generation. It is vital that the noise tests are taken from the same operational turbines that the applicant proposes to construct. If a new machine is envisaged then it should not be accepted until field tested in real operational conditions.

 

18. As advocated IPC should condition consents in respect of the maximum noise levels of machines. But control is much more effective and easier before a consent is given. How is the IPC going to monitor noise levels after developments have been constructed? Is it really going to close down turbines that are too noisy? This amounts to shutting the stable door after the horse has bolted.

 

19. Requiring wind turbines to be a minimum distance of 2km from any human habitation would obviate the need for any complex testing and control of shadow flicker

 

 

 

1. The Purpose of Energy National Policy Statements

 

 

Introduction

 

1.1.1

 

The Government's transition to a low-carbon economy sounds like fait accompli in terms of policy. It needs to be recognised that whereas many of the measures to effect a low carbon economy are desirable anyway, they are not all (for example covering the whole of England's countrytside with wind farms) and it should be recognised that many people still question the evidence for man-made global warming and the effects of carbon dioxide and that consequently the Government's policy may be wrong and may have to be changed. It can be dangerous to back the measures to carry out a policy without constantly re-examining the policy itself, especially when there are many vested interests in the policy, both financial and political. In this way the low carbon economy is like the Emperor's New Clothes.

 

Role of the NPS in the Planning System

 

1.2.1 and 1.4.1

 

It is evident that the new Infrastructure Planning Commission (IPC) is being required to have primary regard to the NPSs and EN3 and therefore if the NPSs in general (and EN3 in particular) are too heavily bent towards Government Policy without allowing a fair consideration of wider social ,economic and environmental considerations then the IPC will not be a truly independent body but simply a puppet of the Government ( a dangerous step towards totalitarianism). The document must be equitable both in allowing the weighing up of the costs and benefits of planning decisions and in allowing both sides of the argument on a proposed development to be heard in a balanced way. This has been an important attribute of the British Town and Country Planning System since 1947. The law may well have been changed but this does not throw out the principles of equity.

 

Infrastructure covered by this NPS

 

1.7

 

The Act itself makes it clear that any renewable energy project for onshore wind of over 50MW is covered . By implication any project under this limit will go down the route of a normal planning application to a local authority in which case the NPSs will not be the primary determinant of the result? But who decides the size of the project in MW? This is not as simple as it seems especially as the draft EN3 itself and the IPC ( see letter to me attached) are both advocating flexibility and it is clearly evident at present that windfarm developers will want to push all applications down the IPC route because they will expect a more favourable result. Is it just sufficient to say that the power generation is over 50MW? If impacts are to be considered for a maximum size rather than an actual size then applicants will tend to exaggerate the possible sizes of their developments just to get consent (and then be free to switch to something smaller). That would make a mockery of the system and of Parliament.

 

2. Assessment and Technology- Specific Information

 

2.1.1

 

This seems to be saying that the need for any application coming before the IPC cannot be questioned. This seems to be saying that both man-made global warming is proven beyond doubt and that wind turbines (or any other specific technology forming an application) are the best means of provision of renewable energy. One or both of these statements may well not be true and it is not equitable for the Government to try to close down any debate on these matters. History shows that planning inspectors and judges have found it inequitable to adopt a position that one important aspect of a decision (ie need) cannot be debated. All planning decisions are about weighing up benefits with costs and by costs we mean social, economic and environmental costs. If the benefits cannot be examined then how can they be weighed up with the costs? The author's stance is approaching totalitarian.

 

2.2.1

 

Even the least articulate applicant will have no difficulty in stating how his or her application 'fits' with the NPS. That will be what is called a 'no-brainer'!

 

Good Design

 

2.4.1 and 2.4.2

 

'Good design' is a hollow principle when it comes to wind turbines. Wind turbines will always be designed to achieve the greatest efficiency in power generation at the lowest cost (often at the sacrifice of noise considerations ) and considering their ever increasing size and industrial nature their visual design will play no part and it is cynical of EN 3 to suggest that it will. This is virtually acknowledged in para 2.7.3.!

 

2.7 Onshore Wind

 

2.7.1

 

Just because windfarms are' the most established large scale sources of renewable energy in the UK' does not mean that they are the best, nor that they should continue to be the main source. The reason why they are the most established is entirely a result of the Government's financial regime which favours power companies building them - they are not naturally economic and they represent old technology, not new. In Gordon Brown's tele-conferencing input to the post Copenhagen de-briefing conference at the Queen Elizabeth Conference centre he talked about 'low-carbon investment ' being 'one of Britain's main industries with half a million jobs' . But we have missed the boat with wind turbines having closed our last manufacturing plant and we should be concentrating on new technologies in wave and tidal power which also have the advantage of not intruding on residents everyday lives. These options should be financially incentivised much more, not wind turbines.

 

 

Predicted Wind Speed

 

2.7.7

 

It is agreed that wind speed increases with height above ground level , which is the reason why turbines are becoming taller. Wind speed does not vary hugely across the country however and is less likely to be the reason for a particular siting of a windfarm than the perceived sparsity and inarticulateness of the local population. Indeed the latter is probably the key factor in power companies siting their projects but is not mentioned in EN-3.

 

Electricity Grid connections

 

2.7.12 should also say that the grid connection , especially where overground by using pylons, can have considerable adverse impacts on the amenity of residents and on landscapes. All applicants should be required to set out detailed proposals for these connections at the time of the main application for the wind farm. Because of the possible adverse impacts it is not acceptable for electricity grid connections to form subsequent applications once the development is approved.

 

Access Tracks

 

2.7.15

 

Access tracks should be required to be largely removed and the land re-instated once construction has taken place. This is to protect the countryside because creating urban type roads with metalled surfaces and concrete kerbs is one of the most sinister effects of onshore windfarms in terms of erosion of countryside character. Ironically it is often likely to be an over zealous local highways department which wrongly insists on these urban type standards

 

Project Lifetimes

 

2.7.16

 

EN3 should positively state that consents should be conditioned so that upon decommissioning wind turbines should have their concrete foundations removed to at least one metre's depth.

 

2.7.17 and 2.7.18

 

It is not just a question of requiring decommissioning after a set life of say 25 years. Technology may change fast and the turbines may stop being used after a much shorter period. There should therefore be conditions that require any turbines that have not been generating electricity for a specified period ( eg one year) to be decommissioned and removed. This is to prevent the countryside from being littered in future with dead turbines or their towers just because the act of finally removing them and reinstating the ground is too costly for their owners. 2.7.18 has not been thought through sufficiently.

 

2.7.19

 

We object strongly to the first sentence of this paragraph, if not the whole of it.

 

We have great concern about EN3 setting up the perception that somehow windfarms are temporary and for this reason their impacts are less serious. 25 years is after all a generation. If for example there are adverse effects upon an historic landscape it should not be an offsetting argument to say that they are lessened because they will only be for 25 years. It the historic landscape is important then it is important for every generation and one cannot be missed out!

Britain's world leading role in Town and Country Planning since the innovative Act of 1947 has many time considered the definition of a 'temporary ' planning permission. This has always varied between one and three years and has never been considered for as long as 25 years. In the planning of housing the life of a house has often been considered as 30 years, yet houses are never regarded as temporary! To say that wind turbines are temporary when they should have a life of 25 years and when in any case they are likely to be replaced with new machines is not a credible argument in their support.

 

It is simply wrong to steer the IPC in the direction of lessening the importance of adverse effects upon landscape, visual amenity and historic assets on the grounds of temporariness, when the life is expected to be at least 25 years. This does not happen in the whole Town and Country Planning System with any other form of development. Temporary should only be a label for a development with a life of less than 3 years.

 

Flexibility in the Project Details

 

2.7.20

 

The fact that 'many different makes and models of on-shore wind turbines are available' does not require the flexible and lax attitude to these developments promulgated in the following four paragraphs (2.7.21 to 2.7.24). This seems to be just an excuse for giving the power companies a licence to do what they want and for making generic and vague applications which presumably the author thinks will be able to be made quicker . There are many makes and types of home available in the provision of housing but ,if anything ,matters there are going the other way, requiring more and more detail with any planning application as this country becomes more and more crowded. How much more important is the detail and fixing the detail in these industrial scale developments which have the ability to affect many people's daily lives.

 

2.7.21

 

This paragraph shows great naiveity. There is no logical reason why windfarm applications should have greater flexibility than any other planning application - indeed because the impacts are potentially much wider, if anything they should have less flexibility. For example the mechanism for driving the rotors can vary greatly in its noise generation and this is not just to do with its MW capacity. In order to decide whether to support or object to a local application the local community and other consultees need to know precise details of the development. If the developer is able to say in debate or at the hearing that 'this is just an example and the final product could be different' it will be impossible for objectors (and the IPC/ local planning authority) to pin him down. Also in response to an objection the developer can say that he will alter the design ( at some vague point in the future) whereas in practice there is very little that a developer can do to alter the design of a windfarm.

 

Why should the wind farm operators not know which turbine they will use? They should be forced to, otherwise it cannot be tested properly - for noise and other effects. The aim of this paragraph seems to be to give operators a charter for applying for one thing and building another. For example what will happen if these paragraphs stand is that the application could be for a relatively quiet turbine, only to be replaced by a much noisier ( and cheaper) one once the work is tendered following consent. This is like applying to extend a listed building in natural stone and then building it in concrete blocks.

 

Are these paragraphs (2.7.20 to 2.7.24) written so that the windfarm operators can keep their costs down rather rhan the best development (if any) achieved?

 

2.7.22

 

The author must have been hoodwinked here by the power companies. There is no less reason for a wind farm developer to not know the layout of his windfarm than for a housing developer not to know the layout of his housing estate. The answer is that precise permissions should be given for precise developments and if circumstances change thereafter then variations can be sought. We are not trying to speed windfarms through the planning process at any cost. The forestry example is extremely weak.

 

2.7.23

 

This paragraph should be removed ( as should the whole section on flexibility) as it merely encourages applicants to invent reasons why their applications are vague and endorses a lazy or even arrogant approach

 

2.7.24

 

The author evidently thought that assessing the 'maximum case' was a clever way around any criticism of a flexible approach. This clearly has not been thought through . We strongly object to the notion that if something bigger is evaluated as being acceptable then something smaller must be as well. This is flawed logic. For when it comes to maximum do we mean maximum generating capacity of turbines, height of turbines , noise of turbines , numbers of turbines, area of windfarm etc etc.? As written it would be perfectly possible for a windfarm operator to apply for a windfarm of say 18 3MW turbines and then once approved to replace it with 18 much noisier and cheaper 2.3MW machines. This would make a mockery of the crucial noise section of the Environmental Assessment as the wrong machines would have been tested. Please believe us that noise emissions vary considerably between machines and not necessarily in proportion to their generating capacity. Moreover it is no good saying that if changes need to be made later these can be run past the IPC ( or LPA) because once granted permission it will be very difficult to refuse such changes, especially if the flexibility provision in EN3 is allowed to stand (note that in several places the draft EN3 states that on technical matters the windfarm operator knows best anyway).

 

Stating that the maximum adverse effects should be considered rather than the accurately assessed effects of a specific development gives the windfarm operator an unfair advantage in the debate with consultees and the examination of the proposal by the IPC. This is because when challenged he can constantly revert to saying ' well the effects could be this but actually we very much intend that they won't so they should be less' . Such a stance then becomes almost impossible to argue against as the applicant can just keep moving the goalposts. The Environmental Impact Assessment, required by law, is meant to be a serious scientific assessment but it can only be so if the development is precisely defined - the flexibility argued in this section will make a mockery of any EIA and the developer himself will be able to decry it by saying that it is only appraising a theoretical scheme and not the one he is actually likely to build.

 

Micrositing

 

2.7.25 and 2.7.26

 

Our comments on paras 2.7.22 to 2.7.24 apply equally here. Why should there be this degree of flexibility in siting the turbines or other infrastructure which is unprecedented in the tried and tested British Town and Country Planning System. If someone applying for a house was to be allowed to move it by 30m to 50m without a new or amended consent all hell would be let loose. What is the difference? Why do windfarms require any greater flexibility than any other development? If there is uncertainty on the part of the operator this uncertainty should be removed at the preparatory stage of the detailed plans and EIA. Encouraging such flexibility is encouraging an attitude where the operator simply sticks something in for approval in order to gain approval and then thinks about what he really wants to construct. 'Unforeseen events' can arise with any development .

 

Para 2.7.26 seems to be backtracking by saying that the IPC may decide that the so-called tolerance or flexibility of the design of the scheme might be restricted. This just muddles the point of this sub section further. 'Tolerence' is the wrong word as in technical use it implies something that cannot be helped (as in manufacturing tolerance) - in this day and age siting can be assessed down to 30cm to 50cm or finer never mind 30m to 50m.

 

This whole sub section should be removed.

 

Repowering

 

2.7.27 and 2.7.28

 

Of course the proposal to re-power is a 'commercial matter for the applicant'. What are we being told here? Who would have thought otherwise? The proposal to construct any development is a commercial matter for the applicant. This is unnecessary and incredibly naïve.

 

2.7.29 and 2.7.30

 

Of course re-powering requires a new application.

 

 

National designations

 

2.7.32

 

This paragraph starts by using the words 'in sites' with various designations. Surely this does not just refer to the boundary of the site which the applicant has drawn for his application? For he could draw his site boundary to deliberately miss such designations such as listed buildings. The start should be changed to 'In sites which contain or are close to nationally recognised designations ..... . Bear in mind that other planning legislation and advice (PPGs) refers to the importance of 'the setting' of listed buildings and ancient monuments as well as the structures themselves. This important concept should also be incorporated here. The last part of this long sentence clearly and correctly mentions weighing up any disbenefits of harm to say listed buildings (should be and their settings) with any 'environmental, social and economic benefits'. This allows an examination of the need for the electricity generation and the amount of it which is right in equity but which seems to have been ruled out at the beginning of EN3. Weighing up costs and benefits is the only way to resolve such dilemmas and nothing can be off the agenda.

 

Green Belts

 

2.7.33

 

This paragraph is interesting and should be applauded for wanting a wide and equitable discussion of the arguments for and against a windfarm. It expresses the same approach as for national designations above. There is no reason why such an approach should not apply everywhere in open countryside because many other areas of the country are protected by local planning policies often embodied in statutory development plans. It is illogical to suggest that windfarms will bear greater scrutiny in greenbelts - greenbelts were introduced to stop urban sprawl and to achieve the separation of cities. There are no greenbelts where there are no cities but this does not mean to say that the countryside is any less precious - it belongs to all the citizens of this increasingly crowded country. The circumstance of greenbelts , when it comes to windfarms are therefore not 'very special' relative to anywhere else.

 

We hope that the government is not suggesting here that the view of windfarms in greenbelts might be abhorrent to city dwellers but that they are quite acceptable in other countryside. The increasing demand for power is predominantly from our increasing population which lives in cities. It is not equitable for the source of this power to be simply pushed out of sight into country areas.

 

Other locational considerations

 

2.7.34

 

This paragraph seeks to give carte blanche to wind farm operators to apply for windfarms wherever they see fit on the pretence that the wind generation circumstances of a particular location are so crucial. If this is the case then the government is having the wool pulled over its eyes by the power companies. Wind speeds and currents do not vary that much over the UK and in particular over a local area and there is every reason to encourage windfarms to be moved to previously developed land or land where the impacts are not so severe.

 

The sequential test should therefore apply exactly as it does to other development all other considerations being equal - ie approximate wind speeds, separation distances from homes etc.

 

The sequential test should not simply be dropped but should be offset by the special siting considerations that apply to windfarms.

 

If the sequential test is dropped then this will make a charter for windfarm operators to be simply lazy. They will choose that land which is easiest and cheapest to develop ( ie greenfield) hiding behind the pretence that this is the only place where the windspeed is just right .

 

Biodiversity and Geological Conservation

 

2.7.36 and 2.7.38 to 2.7.41

 

It is not just that birds and bats might be struck by rotating blades. The introduction of massed turbines into previously open winter grazing spaces for birds like lapwing and golden plover can render those spaces useless as there is not enough clear space to get the flock down. These species graze at about 7 metre centres so a very large uninterrupted area is required to land a flock of 1000 birds.

 

IPC Decision making

 

2.7.43

 

It is strange how this section picks out birds, bats and peat as if these are the only considerations of particular importance to windfarms under the heading of Biodiversity and Geological Conservation. Another very important consideration is the effect of the large concrete foundations on aquifiers (groundwater used for drinking) and ground drainage.

 

Mitigation

 

2.7.44 and 2.7.44

 

This sub section is naïve and has absolutely nothing to say. Has it been written by a child?

 

Future Surveys and Monitoring

 

2.7.46

 

Such monitoring requirements are a good idea but it is naïve to think that the IPC by simply placing a monitoring requirement on the wind farm operator will achieve objective results. Any monitoring must be independent and not instructed by the windfarm operator who clearly is biased.

 

Historic Environment

 

Applicant's assessment

 

2.7.48

 

Yes, 'visualisations' usually will be required! But please do not think that these are in any way objective or scientific - they have a tendency to do the job that the applicant wants them to do. Local authorities often have to appoint their own specialist consultants to evaluate independently the work of the applicant in the EIA - this raises the question of whether the IPC will be required to do that and whether the results will be publicly available.

 

IPC Decision Making

 

2.7.49

 

It is absurd to state that 'onshore wind turbines are not permanent features in the landscape'. With a life stated as typically 25 years and the chance that they will be continuously renovated or replaced, wind turbines are as permanent as houses. As stated before the Town and Country Planning system recognizes temporary uses as those with a life of up to only three years. This statement is ridiculous. 25 years is a generation. It is outrageous to suggest that somehow any indirect effects on historic environment features such as effects on setting will not be permanent and therefore should not count as much in weighing up the decision. Does this mean that if one wants to experience the beauty of a Cistercian Abbey in its setting one might have to come back in 30 years time ( if still alive)? Does this mean that the IPC should allow windfarms all around Stonehenge? What about the thousands of other less well known historic settings that this country is known for?

 

There should be a requirement for the land on which windfarms stand to be reinstated when they become disused for a given period of time ( say a year) and not just when the consent period runs out (it is pointless having a long consent period as we show next) . This is to prevent the possibility of wind turbines, towers and infrastructure standing disused for 25 years when their operation might cease for a host of unknown reasons.

 

 

2.7.50

 

See our remarks under 2.7.49. This just repeats the Philistine attitude of the author. The' length of time consent is sought for' is a total red herring - in any other planning application there is no requirement to say how long the development is for because all development is regarded as permanent ( unless it is a temporary consent for up to three years) . Indeed if after a long period of time a building needs replacing the planning system usually allows it to be replaced once planning consent has been given in the first place. There is no reason to suppose that windfarms will be any different - indeed EN3 , earlier, encourages replacement. Where on earth has this idea of windfarms having their impacts lowered in importance because they are not permanent come from? The reason why we protect and conserve our historic landscapes is so that people can enjoy them - to take them out of the equation for 25 years or longer is simply not an option.

 

Mitigation

 

2.7.51

 

This is a non-sequitor. The NPS has not mentioned below ground archaeology so far. In any case the injury to below ground archaeology can be indirect and does not have to be below the actual works . This paragraph achieves nothing - indeed it perhaps encourages applicants not to research such things completely in advance of starting work.

 

2.7.52

 

The naïve approach returns. This basically says it does not really matter if we do not research the archaeology properly because we can always move things later!

 

2.7.53

 

The naivety gets worse. This just re-emphasises the approach that things can always be moved ( precisely sited) later (so it doesn't really matter if we get them wrong first time) . If this principle was applied to the whole 50 year old Town and Country Planning system in Britain it would fall down. Applicants would only show roughly what they intended to do and then they could do almost anything by way of correction. Once consent is given control goes.

 

Landscape and Visual

 

2.7.57

 

Having just said , correctly, in para 2.7.56 that wind turbines are large structures and will always be visible in the landscape it is suggested here that by 'careful design' and 'arrangement' of the turbines on the site the adverse effects on landscape can be minimized. If the effects are adverse the only real solution is to choose another site - the author is clutching at straws if he thinks that moving around 130metre high turbines within a site is going to make any significant difference to their landscape and visual impact.

 

2.7.58

 

Keeping turbines at a safe distance from homes is a key requirement. This concerns noise impacts even more than visual amenity. EN3 should set a minimum distance between turbines and any residential accommodation. This would then save a great deal of work and argument by the IPC, the power companies and by communities who otherwise might be in opposition and make the whole business of approving windfarms easier which seems to be the Government's objective. This distance should be 2km. This is the distance recommended by La Societee de Medicins in France and it is the distance for the search criteria for windfarm sites issued by the Scottish Government. If there are one or two isolated homes within the 2 kilometre radius of a turbine then there should be a compulsory purchase power in order to move and compensate that home (at present there is no such power and some home owners who have been much closer than 2km have been forced to leave their homes - such as the Gray family in Deeping, Lincolnshire).

 

2.7.59

 

Having just said in 2.7.57 that windfarms might be rearranged to minimize landscape impacts ( a contention which we have argued is likely to make little difference considering their height) the proposition is then taken away in this paragraph. Why is reducing the electricity generating capacity of the windfarm apparently made off the agenda by this paragraph? Surely if compromise can be achieved between adverse impacts and electricity production it should be. It is ridiculous to suggest that the design of a windfarm might be changed to accommodate adverse landscape impacts (in 2.7.57) and then contradict this to say so long as the power production is not affected. Is the maximum power production such a holy cow that it cannot be changed? As we have said earlier many applicants may well play the game of submitting 'maximum' schemes only to build smaller and cheaper schemes when they come to tender the turbine provision. So presumably the author is thinking that the windfarm might be made smaller in terms of power production if the developer is happy but not if he is unhappy. This is not equitable. He cannot be forced to construct in any case.

 

 

Noise

 

Applicant's Assessment

 

2.7.63 to 2.7.68

 

The reliance on ETSU-R-97 in this and following paragraphs for the testing of noise effects from windfarms is unreliable because it dates from 1996 when there were very few and much smaller wind turbines in the UK. Much more is now known internationally about the noise effects from windfarms and their repercussions for human health including vibro acoustic disease. This 14 year old standard must be urgently reviewed in the light of empirical evidence including that of families who have been forced to leave their homes (such as the Davis family at Market Deeping in Lincolnshire) or whose lives have been made a misery ( such as the Rashleigh family near to the Bicker windfarm in Lincolnshire - see precognition by Steve Rashleigh , attached at Appendix 1)

 

2.7.65

 

It is stated that 'The IPC should use ETSU-R-97 to satisfy itself that the noise from the operation of the wind turbines is within acceptable levels' but will the IPC really carry out its own independent tests? Experience has shown that it is very easy for applicants to contrive the results of noise tests. This is particularly the case because the practice has developed of using laboratory/workshop readings for noise from particular turbines and this does not simulate the actual field conditions neither does it simulate the cumulative effect of several turbines combined with wind noise. The actual arrangement of the turbines on site can significantly affect noise generation. It is vital that the noise tests are taken from the same operational turbines that the applicant proposes to construct. If a new machine is envisaged then it should not be accepted until field tested in real operational conditions.

 

2.7.68

 

A correction is required. The words ground transmitted must be inserted before low frequency in the last line ( as earlier in the paragraph) because all noise from turbines is low frequency.

 

Mitigation

 

2.7.69

 

This mitigation in order to reduce ambient noise can be achieved by so-called 'good design' but it should be spelt out that the variables of this design which will change noise effects are (a) the precise type of turbine (b) the height of the turbine and (c) the distance from any human habitation. It is therefore extremely important that these variables are pinned down in the application and consent and not subject to the flexibility advocated earlier in EN3.

 

A great deal of time and effort in studying, debating and testing noise effects could be saved ( and possibly ETSU-97-R not reviewed) if a set minimum distance between any turbine and any place of human habitation was made.

 

Keeping turbines at a safe distance from homes is a key requirement. EN3 should set a minimum distance between turbines and any residential accommodation. This would then save a great deal of work and argument by the IPC, the power companies and by communities who otherwise might be in opposition and make the whole business of approving windfarms easier which seems to be the Government's objective. This distance should be 2km. This is the distance recommended by La Societee de Medicins in France and it has been the distance for the search criteria for windfarm sites issued in planning advice by the Scottish Government. If there are one or two isolated homes within the 2 kilometre radius of a turbine then there should be a compulsory purchase power in order to move and compensate that home (at present there is no such power and some home owners who have been much closer than 2km have been forced to leave their homes - such as the Davis family in Deeping, Lincolnshire.

 

2.7.70 and 2.7.71

 

This is weak. Yes the IPC should condition consents in respect of the maximum noise levels of machines. But control is much more effective and easier before a consent is given. How is the IPC going to monitor noise levels after developments have been constructed? Is it really going to close down turbines that are too noisy? This amounts to shutting the stable door after the horse has bolted. This provision would be much more effective if the application and consent was required to be for specific machines and turbine locations - it is the concept of flexibility earlier in EN3 that contradicts the recognized need to control noise levels. All these details should be fixed at the time of application ( they can always be changed with a new application or amendment just like normal planning applications)

 

Shadow Flicker

 

This section needs to have its logic broken down. Shadow flicker is a real problem , as the section acknowledges ( see evidence of Steve Rashleigh at Appendix 1 in relation to the Bicker windfarm) .

 

If it is right that shadow flicker only occurs within 8 rotor diameters of a turbine then we agree that a zone of 10 rotor daimeters should be drawn (2.7.75). But because shadow flicker can occur in this area under certain conditions then no amount of testing will remove this possibility. The whole problem is therefore solved and unnecessary work for the applicant and the IPC avoided by simply stating that because of the risk of shadow flicker no turbine shall be constructed within 10 rotor blade diameters of a human habitation.

 

Of course if our proposal to limit all turbines to a minimum distance of 2km from any human habitation this has the advantage of removing any concerns about shadow flicker as well as noise.

 

Mitigation

 

2.7.80

 

This is naïve. No condition can remove the possibility of shadow flicker except through requiring relocation of the turbine to the distance where the risk cannot occur ( 10 rotor diameters as stated above).

 

Traffic and Transport

 

We believe that the author has got the guidance right in this section in respect of the possible adverse effects on communities of heavy traffic during the construction period. This largely applies to where traffic is using the existing main highways through villages and close to homes and one aspect of this possible impact ( in addition to disturbance, noise and road safety effects) is the effect on the stability of older buildings, many of which, built before the 19th Century, do not have proper foundations. This impact should be acknowledged.

 

 

However there is one very important adverse impact which the section does not identify. This is the threat of the increased urbanization of the countryside brought about by the new construction or so-called improvement of minor roads and tracks right up to the windfarms. In para 2.7.91 the statement correctly identifies that after construction the use of these final sections of access roads is very light. If these roads are required by the highway authority to be widened, given black-top concrete surfaces and (worst of all) given concrete kerbs and radii and hard drainage then there will be an immediate and sinister erosion of the rural nature of these areas ( someone may even start arguing that these roads are used for other forms of development).

 

All works to widen and 'improve' minor rural roads and tracks for the purposes of construction traffic should be conditioned to be removed once the windfarm is operational. Our concern is that over zealous highway authorities will get their standards books out and require everything to be upgraded to an urban standard. Much heavy machinery - combine harvesters, drainage equipment etc uses these routes already and the routes simply recover. This should be the same for windfarms. No permanent improvements should be required.

 

We believe that the industrialization and urbanization of our fast disappearing English countryside is just as affected, in an insidious way, by the access works to windfarms as by the turbines themselves. Indeed if the windfarms truly are temporary as the author would have us believe then these impacts threaten to last longer than they do.

 

2.7.95

 

This paragraph importantly acknowledges the need for 'non-permanent highway improvements' which reflects the point we are making about therefore not requiring (urban) highway standards that would be required for permanent routes (concrete kerbs etc) . However it is worrying that the IPC is being guided in the direction of keeping these routes just in case a future windfarm comes along in the vicinity. This will tend to lead to the routes becoming permanent and therefore subject to the creeping highways urbanization that we so fear.

 

Other Impacts

 

EN3 should mention other possible adverse impacts including:

 

1. The adverse effect of turbines upon radar at airports and airfields (safety consideration) - see Appendix 2 where South Kesteven District Council in association with the MOD has used this as a recommendation for refusal of a windfarm

2. The adverse effect of turbines in areas with frequent light aviation use (safety consideration) - see Appendix 2

3. The effect of the large concrete foundations upon the water table - both aquifers for drinking water and upon ground drainage

4. The effect of large concrete foundations upon carbon generation

5. The effect on TV and mobile phone reception

 

January 2010

 

Appendix 1

 

PRECOGNITION BY STEVE RASHLEIGH

 

MONTREATHMONT PUBLIC INQUIRY

 

 

1. My name is Steve Rashleigh, my wife and I live at White House Barn, North Drove, Bicker Fen PE20 3BQ. Our home is on the Fens and has two and a half acres of land. Our family run a double glazing business.

 

2. During the summer Wind Prospect erected thirteen REpower 2mw wind turbines at Bicker Fen. From the beginning they were noisy. We complained and were told it was early days and it was only a temporary problem. When the remaining turbines were erected and it was operating properly there would not be a problem.

 

3. We waited but when the development was completed the noise problem was worse.

 

4. Our home is approximately 800m from the closest turbine. It is a barn conversation and has buildings on three sides. The noise seems to enter the courtyard and bounce round the buildings. The noise we experience sounds just like an old steam train.

 

5. The noise is almost constant as the noise we receive comes with the prevailing wind.

6. We were told that we would not notice the noise so much when it was windy. This is not the case, when it is windy the noise is very much worse. It is a thumping noise like an old steam train coming in.

 

7. During the day when we are moving around and the television is on, it is bearable. At night it is not. The thumping noise just goes on all night. Sometimes it is impossible for us to get to sleep.

 

8. We have done everything we can to try to kill the noise. We already had double glazing but, at our own expense, we installed 6mm secondary double glazing. We now have four layers of glass at our windows. This has reduced the noise a little but it is still unbearable at night. Unfortunately our bedroom windows face the turbines.

 

9. We have also spent £1000 and planted trees between us and the turbines but of course it will be some time before we know whether they will have an effect on the level of the noise.

 

10. We wrote to Wind Prospect and asked them whether they would pay for these trees but they did not reply.

 

11. We have spent a considerable sum to try and reduce the noise from the windfarm and have received no help whatsoever from the developers/operator.

 

12. In contrast, when E.On built a substation near to other properties to take the power from the turbines to the grid they provided eight neighbouring properties with double glazing free of charge - We know this is correct because our company installed the double glazing.

 

13. Although the noise is the main problem we have with these turbines we also suffer from shadow flicker.

 

14. We can suffer shadow flicker for over an hour. It is very difficult to cope with this. We close the curtains but you can still see the shadows flickering. We are particularly concerned about the shadow flicker as our son is epileptic. He is not living at home at the moment but we have to be very careful when he visits.

 

 

15. We have complained to Trevor Gait of Fenland Wind Farms/Wind Prospect but he has done nothing.

 

16. We have complained repeatedly to Boston Borough Council. They have been reluctant to act but at last we understand that they are now obliging Fenland Wind Farms to commission a noise investigation. This is due to commence on 6th December 2008. We cannot understand why they are allowing the turbine developer to undertake this survey. We believe this should have been commissioned by the Council and undertaken by independent noise consultants.

 

17. At the moment life is unbearable and we are worried that in the event we ever wished to sell our home it would not be possible to find a buyer.

 

18. We are very disappointed with the lack of concern shown by Wind Prospect/Fenland Wind Farms and hope that between them and Boston Borough Council something will be done to reduce the noise and shadow flicker and improve the quality of our lives.

 

19. In view of the problems we have experienced, we wish to warn people of what can happen and at the same time object to the Montreathmont development. We were assured that noise would not be a problem and this has not been the case. This Company is obviously unable to ensure that noise is not a problem with their turbines and we do not believe that they should be allowed to erect further turbines until they have resolved the problems at their existing operating developments.

 

Appendix 2

 

Proposed Neslam Windfarm, South Kesteven Lincolnshire. Report to the Development Control Committee. September 2009

The reasons for recommended refusal are:

1. The Defence Estates have advised that the proposed development would have a detrimental impact on the Air Traffic Control radar at RAF Cottesmore, and RAF Cranwell. The proposed development would also adversely affect the Precision Approach Radar at RAF Cottesmore, to such an extent that the RAF would be unable to provide a full air traffic service in the area of the proposed wind farm. There are also two locally operated aerodromes in the area and it is considered that any degradation of the radar systems in this area would be detrimental to air traffic safety. Acceptance of the proposed development would therefore be contrary to the advice contained within Planning Policy Statement 22 (PPS22).

2. It is considered that the erection of six 125m high wind turbines at Neslam Farm, would have significant and detrimental impact on the setting and visual amenity of a number of heritage assets in the area including St Andrews Church Sempringham, St Andrews Church Billingborough, and Sempringham Priory. The proposed development is therefore considered to be contrary to the guidance contained within PPG15, PPG16 and PPS22, and policies 26, 27 and 40 of the East Midlands Regional Plan 2009, and policies EN1, C1 and C2 of the saved policies of the South Kesteven Local Plan. Consideration has been given to the wider environmental and economic benefits of the proposal but it is considered that they do not outweigh the harm which would be caused to the setting of the heritage assets in this area.

3. The proposed development would be located within 580m of Dove Cottage a residential property on Neslam Road. The noise assessment contained within the submitted Environmental Statement (ES) is based on a candidate turbine (Vestas V90 2MW turbine operating in mode 2). Based on the guidance contained within ETSU-R-97 it is considered that an appropriate upper daytime limit would be 38dB(A) given that the site is located within a tranquil rural location. The noise assessment contained in the ES indicates that the candidate turbine could only just achieve this level operating in a quite running mode. Given that the assessment is based on a candidate turbine and this may not be the final turbine used the Council is concerned that the proposed development would be unable to comply with any conditions restricting the noise output to 38dB(A). Given the lack of certainty in the ability of the development to comply with the necessary noise conditions it is considered that the proposed development would result in an adverse impact on the residential amenity of the occupiers of Dove Cottage due to increase noise disturbance. It is therefore considered that the proposed development would be contrary to the guidance contained within PPS22, policy 40 of the East Midlands Regional Plan 2009, and policy EN1 of the saved policies of the South Kesteven Local Plan.

4. The proposed 125m high turbines would because of their height, and movement of the blades appear intrusive and oppressive in the outlook from Dove Cottage, Herron Lodge, Neslam Fen Farm, Gosdale Farm House, Gosdale Farm and Church Farm. It is considered that the proposed development would have a significantly detrimental impact on the residential amenities of the occupiers of these properties. The proposed development is therefore considered to be contrary to the Guidance contained within Planning Policy Statement 22 (PPS22)