Foreign and Commonwealth Office Annual Report 2008-09 - Foreign Affairs Committee Contents


2  Finance-related issues

Q 1  Impact of the fall of Sterling

Sterling's decline and the FCO budget, 2008-10

21.  The finances available to the FCO in 2008-09, like those of other departments, were determined in the 2007 Comprehensive Spending Review (CSR 07), which set broad departmental spending limits for the three years 2008-11. On the basis of a budget of £1.58 billion in 2007-08, the FCO's settlement was for additions to this baseline of £99 million in 2008-09, £125 million in 2009-10 and £123 million in 2010-11.[30] We considered the FCO's CSR 07 settlement in detail in our Report on the Department's 2006-07 Annual Report, which we published in November 2007 shortly after the settlement had been reached. We calculated then that the CSR settlement represented budget growth in real terms of 3.4%, -1.2% and -2.8% in each of the three years concerned, which averaged at an annual real reduction of 0.2% over the three-year period. We concluded that the FCO's CSR 07 settlement, "one of the tightest in Whitehall, risks jeopardising the FCO's important work".[31]

22.  There have been minor changes to the FCO's budget since the outlines set out in the CSR 07. The Department's outturn was for spending of £2.03 billion in 2007-08, followed by £2.26 billion in 2008-09. The plan for 2009-10 is £2.12 billion.[32]

23.  Compared to those of other departments, the FCO's budget is distinctive in three respects:

i.  It is small: £2.3 billion represented 0.6% of government departments' combined spending in 2008-09. By comparison, the Department for International Development (DFID) took £5.7 billion (1.6% of the total) and the Ministry of Defence (MOD) £45.4 billion (12.7%).[33]

ii.  A large proportion of the FCO's spending is relatively inflexible, because it goes on staff salaries and buildings, rather than programmes. The FCO considers around 80% of overseas Posts' costs to be inflexible in the short term.[34] The FCO is also primarily responsible for paying the UK's subscriptions and other dues to international organisations such as the United Nations (UN), which are typically determined according to a set formula which the UK is unlikely to be able to alter in the short term (see paragraph 36). Out of its total budget, the FCO considers its available "discretionary" spending—excluding international subscriptions, peacekeeping and conflict-related spending, and the ring-fenced funding for the British Council and BBC World Service—to be only around £830 million, which represents 39% of its total 2009-10 budget.[35]

iii.  Over half the FCO's budget is spent in currencies other than Sterling.[36] This is the highest proportion in Whitehall.[37] DFID makes its overseas aid disbursements largely in Sterling:[38] that Department's Permanent Secretary told the International Development Committee in November 2009 that its Euro-denominated contribution to the European Development Fund was its only major spending commitment to have been hit by Sterling's recent fall.[39] The FCO's foreign currency spend includes many of the costs which are also relatively inflexible, such as subscriptions and other assessed contributions to international organisations (which are typically paid in US Dollars or Euros), and the local costs of maintaining the FCO's overseas estate and paying locally-engaged staff.[40] By contrast, the foreign currency spend of the MOD, for example, is accounted for to a much greater extent by major capital projects. The MOD's foreign currency spending is also largely in US Dollars,[41] whereas it has proved a particular constraint on the FCO that it spends in 120 different foreign currencies (see paragraph 119).[42]

Given the small size of the FCO's overall budget, the impact of exchange-rate losses and/or rises in inflexible costs is larger, proportionately, than for departments with larger overall spends.

24.  The Treasury determines departmental budgets in Sterling terms. Until the CSR 07, the Treasury and the FCO operated the Overseas Price Mechanism (OPM), in order to even out the effects of exchange-rate fluctuations, and thus maintain the purchasing power of the FCO's budget in local currencies when Sterling weakened compared to the exchange rate assumed by the Treasury when setting the budget. The two Departments had been operating the arrangement at least since the 1980s.[43] Reflecting the uniqueness of its budget in terms of exposure to currency risk, the FCO was the only Department with which the Treasury operated such a mechanism.[44] Under the OPM, every six months the FCO calculated the net effect of exchange-rate fluctuations and differential inflation rates on its overall purchasing power overseas. When the FCO's purchasing power was greater than intended, because Sterling had strengthened, it returned money to the Treasury. When the FCO lost out because Sterling had weakened, the Treasury made up the shortfall (from the Treasury Reserve). According to the National Audit Office (NAO), in the three years before 2007-08, the operation of the OPM meant that the FCO transferred funds to the Treasury, to the tune of £5-14 million each year. In 2007-08, the year in which the CSR 07 took place, the weakening of Sterling obliged the Treasury to transfer £1.4 million to the FCO.[45]

25.  As part of the CSR 07, the Treasury withdrew its support from the OPM, and left the FCO largely exposed to the effects of exchange-rate fluctuations. According to the NAO:

[The] Treasury's purpose in withdrawing [the] OPM was to introduce what it saw as more modern methods of risk management. It has long been the Government's policy to ask departments to bear the risk of predictable variations in expenditure in their Departmental Expenditure Limits (DEL). At the time of the CSR 07 settlement, the Treasury considered it appropriate to extend this to include currency movements, particularly as there were risk management instruments commonly available in the financial markets.[46]

The NAO told us that, by contrast, the FCO considers that its foreign currency spending should be counted outside its DEL, and instead as Annually Managed Expenditure (AME), which is expenditure which is "subject to variation that is unpredictable and results in cost variations of a scale that cannot be managed within Departments' DELs".[47] The NAO added that, at the time of the CSR 07, "what neither the FCO nor the Treasury foresaw was the extreme volatility in foreign currency markets in the early part of the CSR period following the global financial crisis".[48]

26.  The NAO also told us that "the Treasury looks to [the] FCO to factor in exchange-rate changes as a part of resource allocation decisions".[49] The then Chief Secretary to the Treasury, Yvette Cooper MP, told the House in March 2009 that the OPM "did not provide the [FCO] with the incentive to factor in medium-term changes in currency costs when it allocated its resources".[50] The NAO noted that the FCO:

contends that in several areas of foreign policy priorities, such as the need to negotiate a climate change agreement or to respond to the terrorism threat, the risks and opportunities to the United Kingdom of doing business abroad, or choosing not to, do not change alongside rises or falls in foreign exchange rates.[51]

Sir Peter Ricketts confirmed that he did "not think you can allow foreign exchange to drive foreign policy".[52] To make the point, if since November 2007 the FCO had sought to favour spending in the major currencies against which Sterling had weakened least, it would have prioritised spending in Indian Rupees, Russian Roubles, Turkish Liras and South Korean Won.[53] If the Department had sought to favour spending in the major currencies against which Sterling had been most stable, it would have allocated extra resources to spending in Turkish Liras and Swedish Kronor.[54] Sir Peter Ricketts told us that, if the Treasury wished the FCO to allocate resources partly on the basis of reducing exchange-rate risk, he would "find that quite hard to turn into operational effect".[55]

27.  In our Report on the FCO's 2007-08 Annual Report, published in February 2009, we warned that "given its spending commitments in foreign currencies, the FCO is likely to be more adversely affected than most other government departments by a depreciation of Sterling". We expressed concern in case the FCO's performance against its targets was affected by Sterling weakness.[56] In its response, in April 2009, the FCO said that it was "too early to say" what effect Sterling's fall might have on its performance.[57]

28.  As financial years 2008-09 and especially 2009-10 have unfolded, the impact of the OPM's withdrawal on the FCO's finances, under current economic circumstances, has become ever-clearer and more serious. The CSR 07 took place when Sterling was at historic highs against the US Dollar and Euro. In the CSR, the Treasury assumed exchange rates of £1=$2.0143 and £1=€1.4578.[58] Since then, Sterling has been below these levels—permanently against the Euro, and for all except the very beginning of the period against the Dollar. Sterling fell especially sharply below the CSR rates after the full onset of the global financial crisis in autumn 2008 and the subsequent drastic deterioration in the UK's public finances.[59] As we prepared this part of our Report in late January 2010, Sterling was down by nearly 22% against the Euro and nearly 20% against the Dollar compared to the rates assumed in the CSR. Sir Peter Ricketts told us that Sterling was down by 25% against "many of the major currencies".[60]

29.  We conclude that the withdrawal of the Overseas Price Mechanism (OPM) made the 2007 Comprehensive Spending Review (CSR 07) settlement a uniquely risky one for the FCO, compared to other departments. We take no pleasure in pointing out that we warned of the possible effects of the OPM's withdrawal a year ago. Especially in the light of exchange-rate developments since the CSR 07, we cannot see that it remains credible to regard the costs of currency fluctuations as predictable ones which the FCO might reasonably be expected to absorb. Apart from the substantive spending effects involved, requiring the FCO to absorb such serious exchange-rate risk undermines accountability and strong budgetary planning. We further conclude that any suggestion that the FCO should allocate its resources partly on the basis of exchange-rate considerations is ludicrous. We agree with the FCO's Permanent Under-Secretary Sir Peter Ricketts, that exchange rates should not drive UK foreign policy.

30.  To compensate for the impact of the fall of Sterling on its purchasing power since autumn 2008, the FCO:

  • in its 2008-09 Winter Supplementary Estimate drew down all the funds remaining in its 2008-09 contingency reserve (the Departmental Unallocated Provision [DUP]), totalling £17 million, leaving the Department with no contingency for the rest of the financial year;[61]
  • in its 2008-09 Spring Supplementary Estimate used £6.5 million in End-Year Flexibility,[62] as well as claiming £24 million for international subscriptions and £27.6 million for conflict prevention from its Treasury reserve (see paragraphs 42 and 99);
  • in its 2009-10 Winter Supplementary Estimate again drew down all of its DUP, totalling £17 million;[63] and
  • in its 2009-10 Spring Supplementary Estimate transferred £16 million from capital to administration spending, including £3 million transferred from capital End-Year Flexibility, and increased current non-cash Annually Managed Expenditure (AME) by £30 million.[64] On 9 March 2010, the FCO announced that it required £90 million of the total £134.6 million in additional funds it was seeking in the 2009-10 Spring Supplementary Estimate as a repayable cash advance from the Contingencies Fund, in order to cover ongoing operational costs such as the payment of suppliers until Parliament approved the Spring Supplementary Estimate towards the end of March 2010.[65]

31.  In March 2009, the Foreign Secretary estimated the potential budgetary pressure on the FCO in 2008-09 arising from Sterling's fall at £90 million (including around £60 million affecting the spending of overseas Posts).[66] By November 2009, the NAO put the figure for 2008-09 at around £100 million, or around 5% of the Department's total budget.[67] Despite this, in 2008-09 the FCO remained within its budget.[68]

32.  As regards 2009-10, we noted in our previous Report that the FCO anticipated a "tougher challenge" and a "very tight" budgetary position, and that it had raised the likelihood that it would have to "curtail activities".[69] In correspondence in January 2009, the FCO told us that "if Sterling continues to fall, it may not be possible to continue the FCO's operationally essential work in a global network of Posts, without additional funding". The FCO estimated that "unless Sterling strengthens from its present low levels, the FCO will need to find significant amounts of additional savings, possibly up to £95 million, in each of 2009-10 and 2010-11 to meet [its] projected commitments".[70] In its 2009 Autumn Performance Report, the FCO stated that "continuing pressure on international and UK resources could affect delivery" of the Government's "Global Conflict" Public Service Agreement (PSA 30), which the Treasury had agreed for the CSR 2007 period with the FCO as the lead Department (see paragraph 288).[71]

33.  In a letter to us of October 2009, the FCO summarised the situation as it saw it:

from within one of the smallest Departmental Expenditure Limits in Government, we have to manage a risk that is neither foreseeable nor regular in its impact across the network. Over half the Department's budget is spent in foreign currencies. Exchange-rate movements can consequently impact on our ability to deliver in our priority foreign policy areas. […] [The] fall in the purchasing power of Sterling—by a third against the Dollar and a quarter against the Euro—has had a major impact on our resources which will continue through 2009/10 and 2010/11.[72]

34.  In March 2009, the Foreign Secretary suggested that exchange-rate pressures on the FCO in 2009-10 might again amount to at least £90 million.[73] In November 2009, the NAO confirmed that the FCO estimated exchange-rate pressures in 2009-10 as amounting to around £100 million, or around 12% of the £830 million which the Department reckons as being available for its "discretionary" spending.[74] On 20 January 2010, the FCO Minister Baroness Kinnock said that the shortfall in the FCO's budget for 2009-10 now stood at £110 million.[75] Sir Peter Ricketts told us in December that the Department was "struggling" to meet its budget in 2009-10.[76] Overall, the NAO assessed the withdrawal of the OPM and the subsequent fall of Sterling as having had "a major impact on the FCO's business worldwide".[77]

35.  We conclude that, on the basis of the figures given by Baroness Kinnock in January 2010, the FCO has lost around 13% of the purchasing power of its core 2009-10 budget as a consequence of the fall of Sterling. We concur with the National Audit Office, that the withdrawal of the Overseas Price Mechanism and the subsequent fall of Sterling have had "a major impact on the FCO's business worldwide". We note that the budgetary transfers which the FCO has made to try to help cope with the hit have absorbed all of the Department's contingency reserve at the Treasury in both 2008-09 and 2009-10, and we conclude that this represents an unacceptable risk to the FCO's ability to perform its functions.

DUES TO INTERNATIONAL ORGANISATIONS

36.  A particular issue in relation to the FCO's budget and the fall of Sterling is that of the UK's subscriptions and other obligatory ("assessed") contributions to international organisations, such as assessed peacekeeping costs. The UK's subscriptions are paid almost entirely out of the budget of the FCO (see paragraph 42); assessed conflict-related costs are shared with the MOD and DFID. Contributions to international organisations are typically paid in US Dollars or Euros, depending on the organisation.[78] A state takes on a legal obligation to pay the relevant subscriptions and other assessed contributions when it accedes to an international organisation. Member States' dues are normally calculated as a share of the relevant budget, the share being based on a formula which is often subject to only difficult and infrequent renegotiation, and which typically reflects most heavily the sizes of Member States' economies—although, certainly at the UN, the UK pays a disproportionately large share compared to some states with larger and/or rapidly growing economies.[79]

37.  Year-on-year, Member States can control the size of their dues to international organisations most directly by influencing the size of the organisations' budgets. For example, in its 2008-09 Annual Report the FCO noted that it had "successfully maintained a zero real growth budget […] for the Council of Europe".[80] The Foreign Secretary told the House in March 2009 that the Department was seeking to do likewise across the range of international organisations as they set their budgets for 2009-10.[81] During our 2008-09 inquiry into "Global Security: Non-Proliferation", we noted with some disquiet the Government's unwillingness to countenance an increase in the core budget of the International Atomic Energy Agency (IAEA), despite its support for an expansion in the Agency's activities[82]—although we also identified scope for rationalisation of the large number of organisations and initiatives in the non-proliferation field.[83] However, at least as regards the UN, Sir Peter Ricketts admitted that there was "little [the FCO] can do" about the "inexorable" rise in the UK's subscription, because of the UN's consensus-based decision-making.[84]

38.  The UK's dues to many international organisations are rising independently of Sterling weakness, and are set to continue to do so in forthcoming years. This is partly because the UN and the EU are undertaking more peacekeeping activities (the UK is the fourth-largest funder of UN peacekeeping);[85] and partly the result of a number of one-off capital projects, such as the construction of NATO's new headquarters (for which the UK is liable for 13% of the cost).[86] Sir Peter Ricketts told our inquiry two years ago that the FCO's budget had "not kept pace" with rising international subscriptions.[87] Former Ambassador Sir Ivor Roberts was more forceful, telling us in evidence at that time that it was "disgraceful that the Foreign Office should somehow be penalised for the fact that international subscriptions, over which it has no control at all, are going up, partly reflecting the success of the British economy".[88]

39.  Given that they are due in foreign currencies, the fall of Sterling has directly increased the Sterling costs of the UK's international subscriptions and other dues, and therefore the FCO's spending obligations. For example, the FCO told us that the Sterling cost of the UK's share of the NATO HQ project had risen from £98 million in 2007 to £129 million as of October 2009.[89] At our request, the FCO provided us with a table comparing the changes in the UK's dues in foreign currency terms with the same changes converted into Sterling. The figures show that, for example, while in Dollar terms the UK's payment to the UN Regular Budget is expected to rise by 18.8% from 2008-09 to 2009-10, in Sterling terms this converts into an expected increase of 30.9%. Whereas the UK secured an expected reduction in its Euro-denominated subscription to the Organisation for Security and Co-operation in Europe (OSCE) of 10.3% between 2008-09 and 2009-10, in Sterling terms this converted into an expected 6.8% rise.[90]

40.  In Sterling terms, the UK's total payments for international subscriptions rose from £136.2 million in 2007-08 to £147.5 million in 2008-09 and an expected £172.7 million in 2009-10.[91] For 2010-11, in March 2009 the FCO was estimating likely international subscription costs of £163 million.[92] However, its estimate of likely subscription costs for 2009-10 has shifted from around £146 million in February 2009 to £193 million in March 2009 to £173 million in its February 2010 letter to us.[93] This highlights the serious difficulties involved in predicting the required payments in Sterling terms.

41.  These figures for international subscriptions exclude assessed peacekeeping costs, which came to £309.6 million in 2008-09.[94] For 2009-10, the FCO said in March 2009 that it was budgeting for £456 million in combined payments from itself, DFID and the MOD for assessed peacekeeping, a rise of around 50% on 2008-09 (see paragraph 101).[95]

42.  As part of the CSR 07, the Treasury agreed that when the Sterling costs of the UK's international subscriptions exceeded £102 million a year, it would fund 60% of the excess. Previously, from 2003-04, the Treasury had funded 50% above the same baseline.[96] The Treasury regarded the increase as compensation for the withdrawal of the OPM. The increase in the Treasury's obligation under the cost-sharing agreement partly accounts for the successive rises in the amount for international subscriptions claimed by the FCO from the Treasury Reserve in the Spring Supplementary Estimate, from £12.8 million in 2006-07 to £18.5 million the following year, £24 million in 2008-09 and £44.5 million in 2009-10.[97] In total, the FCO said that it received just under £30 million from the Treasury in 2008-09 under the international subscriptions cost-sharing agreement.[98] This should have reduced the costs paid by the FCO to around £120.2 million (5.3% of the Department's overall budget), compared to the UK's total subscription costs of £147.5 million. For 2009-10, on the basis of the FCO's forecast of £172.7 million in overall subscription costs, the cost-sharing agreement should make the FCO's share around £130.3 million, or around 6.1% of the Department's total budget. While the cost-sharing agreement has not saved the FCO from encountering serious difficulties as a result of the UK's rising subscriptions, the Department welcomed the fact that it at least means that "the risks of rising subscriptions and exchange-rate losses are shared between the FCO and the Treasury".[99]

43.  We conclude that the rising Sterling costs of the UK's subscriptions and other obligatory contributions to international organisations are placing very severe strains on the FCO's budget and materially affecting its ability to continue with other spending. The FCO expects to spend around 6.1% of its total budget on international subscriptions in 2009-10. We further conclude that the strain on the FCO's budget is arising despite the fact that the increase in costs is to a significant extent beyond the Department's control, as it arises partly from Sterling's fall and partly from complex multilateral factors at the organisations concerned.

44.  In our Report on the FCO's 2007-08 Annual Report, we said that we were "deeply concerned that as a result of the Treasury's decision to withdraw its support for the Overseas Price Mechanism, the FCO may not be able to meet higher international subscriptions over the next two financial years unless it cuts its activities".[100] We also said that the UK's subscriptions to international organisations benefit other departments, as well as the FCO. Under these circumstances, we said that it was "deplorable that the FCO should have to shoulder" all of the financial burden arising. We recommended that "additional non-discretionary costs [of the UK's international subscriptions] should properly be met by the Treasury".[101] In its response, the FCO told us that our recommendation would have to be considered in the next Comprehensive Spending Review.[102]

45.  In April 2009, after the Foreign Secretary announced reductions in UK secondments to international civilian post-conflict missions as a result of Sterling's fall (see paragraphs 101-104), the Chairman of the Committee wrote to the Prime Minister (copied to the Chancellor and Foreign Secretary) to express our growing disquiet. The Chairman said that it was:

a matter for great concern that work in critically important fields such as conflict prevention is being undermined as a consequence of currency fluctuations which are outwith the control of the FCO. My colleagues and I are strongly of the opinion that cuts in conflict prevention could prove very short-sighted and may lead to heavier burdens on public spending in the future. We wish to repeat our recommendation that the Government should pay non-discretionary costs such as subscriptions to international institutions directly from Treasury funds, and should put in place a mechanism to ensure that at this time of financial difficulties the work of the FCO, critical to long-term international stability and the interests of the UK, can be maintained at its previous level. We consider it appropriate for such allocations to be made wholly from the Treasury reserve.[103]

The Chairman received no reply.[104]

46.  The Foreign Secretary told us in December 2009 that "in [his] experience, one must always be careful about suggesting to the Treasury that it should take responsibility for international subscriptions. What happens is that it allows you to bear the rise in costs, and then if ever the costs go down, it will snaffle the gain. There are swings and roundabouts that have to be handled quite carefully".[105]

47.  We suggested to Sir Peter Ricketts that international civilian missions which support the police and judicial sectors in vulnerable states bring benefits to the UK which may be felt by the Home Office, and perhaps the Ministry of Justice, as much as the FCO or DFID. We wondered whether there might be a case for asking these Departments also to contribute to the costs of such missions. Sir Peter said that it was a "fair point" and that he would "take away [the] idea".[106]

48.  We conclude that the UK's membership of international organisations such as the United Nations benefits many government departments. We therefore reiterate our previous recommendation that the costs of the UK's international subscriptions should be shared more equitably across Government, rather than falling almost entirely on the budget of the FCO. We recommend that the Government should agree a stable long-term mechanism to distribute more widely the costs of the UK's membership of international organisations as part of the Comprehensive Spending Review which is expected after the 2010 General Election. We further recommend that consideration should be given to involving relevant home departments in supporting international missions in the police and judicial sectors.

49.  The increased international peacekeeping activities which are increasing the strain on the FCO's budget can be seen as evidence that the Department is making progress towards the policy objectives which the Treasury agreed for it. One of the performance indicators for the Government's Public Service Agreement 30 (PSA 30) on "Global Conflict", for which the FCO is the lead Department, is the existence of "more effective international institutions, better able to prevent, manage and resolve conflict and build peace".[107] Similarly, for its Departmental Strategic Objective on conflict (DSO 6), the FCO aims to encourage a "better-integrated national and international approach to peace support operations", "better […] early action to prevent conflict" and "increased national and international capabilities to tackle conflict".[108] Under its Departmental Strategic Objective to develop effective international institutions (DSO 8), the FCO aims to foster "greater international institutional capacity to deal with emerging global crises such as […] conflict".[109] In one example, the FCO cited to us the EU's new anti-piracy maritime operation "Atalanta" off the Horn of Africa as evidence of the Union's increased willingness to tackle security threats, in accordance with DSO 6.[110] Sir Peter Ricketts noted that "the growth of UN peacekeeping is not in itself a bad thing […] but [the] financial burden on our available money is becoming very serious".[111]

50.  Inasmuch as the FCO can influence the size of the international budgets to which it must contribute, we conclude that its current policy and budgetary framework provides it with contradictory incentives—both to promote reform and an expansion in activities at international organisations, which might help the FCO to achieve its policy objectives; and to favour the status quo in order to keep its own budget down. We recommend that, while maintaining its strong commitment to international organisations, the FCO should continue to bear down on their costs—where this is compatible with the achievement of UK policy objectives—and pursue the more equitable sharing of costs among Member States as part of its agenda for international institutional reform.

SPENDING CUTS

51.  In March 2009, the Foreign Secretary said that the FCO was "minimising" the impact of Sterling's fall on its budget through "delayed activity, by making additional efficiency savings, and implementing a strategy of forward purchasing of foreign exchange" (see paragraphs 110-123).[112] In July 2009, after examining the FCO's first results for the 2009-10 financial year, the FCO Board agreed that the Department would have to reallocate funds within its budget, including perhaps to some of the Posts worst affected by Sterling's fall.[113] By September 2009, the FCO Board felt obliged to agree to "a package of measures to address the pressures on the FCO budget, many of which were as a direct or indirect consequence of the collapse of Sterling".[114] Sir Peter Ricketts described the measures to the Public Accounts Committee in October as "pretty drastic", and said that they had been triggered when it became clear that the FCO was heading for an overspend on its 2009-10 budget.[115]

52.  The NAO told us in November 2009 that the measures taken by the FCO had "led to wide-ranging cuts to programmes supporting international priorities, including counter-terrorism". The NAO said that cuts had been made to security abroad, health and safety (including essential works in Africa), and "current and future capability".[116]

53.  In his evidence to us in December, Sir Peter Ricketts confirmed that the FCO was having to "stop a lot of activity […] in order to come within our parliamentary control totals". He said that the Department had:

stopped whatever programme activity was not committed, stopped most of our training and cut into our travel and our hospitality for posts overseas. […] local staff have not had overtime payments or, in some cases pay rises, and some are on involuntary unpaid leave or four-day weeks. We have a real problem within the budget at the current levels of Sterling.[117]

The NAO told us in November that the FCO regarded the cuts as "severely impacting on its ability to deliver frontline diplomacy".[118] Sir Peter Ricketts told us that the cuts had "not stopped [the FCO's] diplomats around the world doing the key jobs that they should be doing" and had not "as yet […] had an impact on our effectiveness as an organisation. If they continue, […] they will".[119]

54.  The scale of the cutbacks being implemented by the FCO gained widespread attention in January 2010, when FCO Minister Baroness Kinnock told the House of Lords that FCO budget constraints had led to "staff redundancies, cuts to travel and training, and reduced programme funding including our work on counterterrorism and climate change". Baroness Kinnock went on:

We have had staff redundancies in Argentina, Japan and across the United States. Counter-narcotics programmes in Afghanistan, capacity building to help conflict prevention in Africa, and counterterrorism and counter-radicalisation in Pakistan have all been cut; the list goes on.[120]

55.  Baroness Kinnock's remarks triggered intense political debate about the level of UK funding for counter-terrorism work in Pakistan. FCO Ministers told both Houses in answer to urgent questions that the FCO's overseas counter-terrorism budget was rising, from £35 million in 2008-09 to £36.9 million in 2009-10 and around £38 million in 2010-11; and that Pakistan was receiving the largest share, with counter-terrorism spending there rising from £6.2 million in 2008-09 to £8.3 million in 2009-10 and a projected £9.0-9.5 million in 2010-11.[121] However, Parliamentary Under-Secretary Chris Bryant MP admitted that the FCO would be "spending less in 2010-11 than [it] had an ambition to spend".[122]

56.  In its 2009 Autumn Performance Report, the FCO classed as a "risk" to its counter-terrorism work the fact that "the volume of counter-terrorism-related litigation is putting increasing pressure on [the FCO's] resources in London".[123] In subsequent correspondence, the FCO clarified that the costs of counter-terrorism litigation were not being met from programme funds but from the Counter-Terrorism Department's administration budget and from central funds.[124]

57.  In November 2009, the FCO Board "agreed that the cuts imposed at the end of the first quarter were serving to bring down the projected shortfall, though the impact of foreign exchange movements over the remainder of the year could not be predicted". The Board "emphasised the importance of maintaining downward pressure on spending, but decided that the organisation could not absorb further cuts to compensate for foreign exchange pressures".[125]

58.  In the course of our current inquiry and other work in 2009-10, we have been made aware of the impact of the financial pressures facing the FCO in two areas in particular, namely spending at its overseas Posts, and secondments to international civilian peacekeeping missions, particularly in the Western Balkans. We consider each of these in more detail below.

Overseas Posts

59.  The FCO operates a network of over 260 Posts in over 170 countries. Its Posts comprise sovereign ones, namely Embassies, High Commissions (to Commonwealth countries) and Missions, Delegations and Permanent Representations to international organisations; and subordinate ones, comprising consulates and trade and other representative offices. There is also the network of Posts in 12 of the 14 Overseas Territories (OTs).[126] To date, the FCO has set each Post's devolved budget each year in Sterling.

60.  We discussed the state of the FCO's network of overseas Posts in our Report on the FCO's 2007-08 Annual Report, in February 2009. We warned then that "bearing in mind the FCO's tight financial situation, its desire to operate in particularly difficult places and the prospect of future staff reductions, […] there is a serious risk of over-stretch in some areas".[127]

61.  In March 2009, the FCO put the pressures on spending by its overseas Posts arising from Sterling's fall as amounting to around £60 million in 2008-09.[128] In evidence which suggested the much greater difficulties being faced by the FCO, DFID's Permanent Secretary told the International Development Committee in November 2009 that that Department had had to purchase only around £3 million in extra foreign currency for 2008-09 to cover the additional administration costs at its overseas offices arising from Sterling's fall; and that for 2009-10 the extra purchase amounted to around £2.1 million.[129] For 2009-10, for the FCO, the Foreign Secretary said in December 2009 that he expected pressures on the overseas network to come to around £80 million.[130] Sir Peter Ricketts said in December 2009 that for 2010-11 the expected figure was around £120 million.[131] The Foreign Secretary told the House in December that 190 Posts in the FCO network—that is, over 70%—had faced exchange-rate and inflationary pressures against which the OPM would previously have offered protection.[132]

62.  We referred to cuts being made at overseas Posts in paragraphs 52-54 above. In its November 2009 submission to our inquiry, the NAO confirmed that, in order to remain within their budgets, Posts were introducing short-time working, requiring unpaid leave and making redundancies among locally-engaged staff.[133] The Foreign Secretary has confirmed that programme activity has been stopped in Berne, Madrid, Reykjavik, Stockholm and Valletta.[134] Looking ahead, Sir Peter Ricketts told us that "the budgetary pressures […] put a question mark over whether we can maintain the number of people we have abroad […] there will have to be further reductions in the size of Posts".[135]

63.  We have been made aware of the effects of the financial situation at overseas Posts during visits which we have made in connection with other inquiries, in October 2009 to the United States (New York and Washington) and the Western Balkans (Belgrade, Pristina and Sarajevo), and in January 2010 to Madrid, Lisbon, Nicosia and Valletta. Our impression is that the cuts are impacting on both large and small Posts, in different ways—unsettling remaining staff, demanding significant management resources, curtailing planned programme and diplomatic work, and significantly limiting Posts' capacity to respond to unexpected developments if necessary. At large Posts, such as Washington, even a small weakening of Sterling can result in large absolute losses to local budgets; while at small Posts, such as in the Western Balkans, exchange-rate losses can render nearly unworkable budgets for small-scale programme projects. In his letter accompanying the Annual Report of the FCO's Strategic Programme Fund for 2008-09, the Foreign Secretary noted that the Report "illustrates how relatively small funds can help us to make a real impact on policy delivery".[136]

64.  We were particularly shocked during our visit to the US by the scale of the cutbacks being required to the operation of UK Posts in that country. As it must do its local spending in Dollars, the US network of Posts is seeing its budget being particularly badly affected by Sterling's decline against the US currency. We found that Posts in the US had made locally-engaged staff redundant, asked staff to take unpaid leave, frozen recruitment, cut overtime and suspended some employer pension payments; halted programme spending for the rest of the financial year; cancelled non-core training; cut travel and entertainment budgets; and halted all but urgent and essential maintenance work on the estate. Our impression was that the measures were making the work of the UK's Posts in the US considerably more difficult. We have pursued the question of the possible impact of the cuts on the FCO's work with the US as part of our current inquiry into "Global Security: UK-US Relations", and will report our detailed findings in that Report. Sir David Manning, former British Ambassador to Washington, told that inquiry that "if we keep taking people away and if, by some chance, we find ourselves apparently deciding on the numbers of people we have [at Posts in the US] according to the fluctuations of the exchange rate, we will certainly be in trouble".[137]

65.  We assume that other countries' diplomatic networks will be aware of the cutbacks at overseas Posts that the FCO is having to make—indeed, we have anecdotal evidence that this is the case—and that they will read messages into them, both about the importance which the UK attributes to the relevant bilateral relationship, and about the UK's capacity to continue to support its global diplomatic network. We take the view that diplomatic work to a significant extent involves personal interactions and contacts, including at what may appear, mistakenly, to be purely social functions. We also note that the impact of the cuts on locally-engaged staff will mean that local societies in the countries concerned are likely to be aware of the reduction in UK operations.

66.  One element in the efficiency savings programme which the FCO is required to implement under the CSR 07 (see paragraph 144) is a programme to "reduce the overhead costs of overseas representation". According to the Department's 2009 Autumn Performance Report, far from yielding savings, this project is costing money, as it cannot deliver savings large enough to outweigh the impact of the fall of Sterling on the costs of overseas Posts. The "overseas representation" efficiency programme delivered "negative" savings of £5.12 million in 2008-09, a figure which had fallen to a cumulative "loss" of £2.28 million by the end of the second quarter of 2009-10, and was expected to deliver "negative" savings of £0.58 million by the end of the three-year period.[138]

67.  We conclude that the FCO's overseas Posts are facing very severe financial pressures as a result of the fall of Sterling that in some cases are a significant strain on their work and in others are unacceptably disrupting and curtailing it. We further conclude that the cuts that the FCO is making at its overseas Posts represent a serious reputational risk to the Department and the UK, and thus a threat to the FCO's effectiveness.

68.  Sir Peter Ricketts told us, in July 2009, that he was commissioning a review of all allowances for staff serving overseas, to ensure that they:

provide value for money to the Department and the taxpayer, support our business needs, fit the family circumstances of FCO staff in the 21st century, provide the right incentives to staff to serve in the places where we need them most and offer a fair and flexible package to enable staff and families to maintain a UK-level quality of life (or compensation for it) wherever they serve.[139]

Sir Peter said that the FCO was consulting on this issue with the MOD and DFID, which were engaged in a similar process.

69.  After completion of the review, Sir Peter told us in December 2009 that the FCO was recommending "reduced access to business class air fares; less extra leave overseas; changes to education allowances; and the abolition, simplification or consolidation of a number of financial allowances". Sir Peter told us that the Department was negotiating with the trade unions on the proposals, and hoped to implement many of them by April 2010.[140] Sir Peter said that the review "should result in a set of allowances which are fit for purpose, firmly based on the actual extra costs or hardships of living and working overseas, and simple to understand and administer".[141] The Government's Public Value Programme aims to generate £13 million in savings by 2012-13 from "ensuring payments made to public servants posted overseas reflect modern lifestyles and family circumstances".[142] We consider the possible impact on staff morale of changes to allowances, plus the other cuts affecting staff serving overseas, in the next chapter.

70.  As of January 2010, the FCO did not appear to have closed any Posts as a direct result of the financial pressures arising from Sterling's fall, although we assume that the budgetary environment always figures in any decision about the shape of the network. Since 2007, the FCO has closed three High Commission offices (in St Vincent and the Grenadines, Antigua and Grenada, countries to which the High Commissioner in Barbados is accredited), plus the consulate in Nagoya (Japan) and trade offices in Aleppo (Syria) and southern Taiwan. In the same period, the FCO has opened Embassy offices in Goma (Democratic Republic of Congo) and Juba (Sudan), and a British Interests Section in Madagascar.[143]

71.  The FCO last closed a sovereign Post, the Embassy in Dili (East Timor), in October 2006. This was the final step in implementing the last major round of Post closures, announced by the FCO in 2004 and 2005 after the publication of the Department's first formal strategy document in December 2003[144] and the 2004 Spending Review. The closures implemented at that time left the UK with no Embassy/High Commission in Paraguay, the Bahamas, Lesotho, Swaziland or Madagascar.[145] At the time, we expressed regret at the closures of British sovereign Posts in Madagascar and the Commonwealth countries of Lesotho and Swaziland in particular.[146] We note that a British Interests Section in Madagascar, where the FCO closed the Embassy in August 2005, is one of the posts that the FCO has decided recently to open. As regards new sovereign Posts, after the UK recognised their independence in 2006 and 2008, respectively, the FCO converted non-sovereign Posts into Embassies in Montenegro and Kosovo.

72.  As part of the "Strategy Refresh" initiated by the Foreign Secretary after he took office in June 2007, the FCO undertook a review of the "role and shape" of its overseas network.[147] As a result, the FCO's new Strategic Framework, which was agreed with the Treasury as the FCO's set of Departmental Strategic Objectives (DSOs) for 2008-11, included maintenance of a "flexible global network" as a DSO (DSO 1). Maintenance of a network of Posts around the world was not mentioned among the FCO's previous strategic priorities. Moreover, the post-2007 Strategic Framework refers to the network "serving the whole of the British Government".[148] Under the post-2007 framework, therefore, overseas Posts are conceptualised as resources for the whole of the Government, and as platforms from which departments other than the FCO may operate overseas, including by basing their staff there.

73.  The FCO's assertion of its overseas network as a key asset came at a time when observers were sometimes questioning the added value of Embassies abroad, as the advent of instant global communications allowed all parts of Government to access their own information about developments overseas and conduct business directly with counterparts there, without having to go through Embassies and other Posts. We return to this debate in paragraphs 328-330 at the end of our Report.

74.  The financial pressures facing the FCO have given rise to renewed press and political speculation about the possibility of further Post closures.[149] This is particularly the case because around half the FCO's Posts have fewer than four members of staff, meaning that there might appear to be few money-saving options short of closure.[150] The FCO's 2009 Autumn Performance Report already warned that "if the current budget pressure [as] a result of the sharp fall in Sterling continues, we may not be able to sustain our current global presence".[151] An internal FCO memo from Sir Peter Ricketts from the turn of 2009-10, of which the FCO gave us sight, said that the resources which were in prospect for the FCO at that time for 2010-11 would require the Department to close Posts.[152]

75.  We asked Sir Peter Ricketts about the possibility of Post closures. He said that he thought that:

the [FCO] Board and Ministers would be absolutely clear that our primary asset is our global network of Embassies and Consulates—our capacity to reach every country in the world, either for foreign policy or to help British citizens in terms of consular assistance. That is what we will seek to preserve. That is […] our particular asset.[153]

However, Sir Peter also said that, since "the tightness of the budget […] means we have to look at every option", he would not rule out the possibility of Post closures, and it would be one of the money-saving measures which the Department would be looking at in early 2010. As of December, Sir Peter said that the Department had not conducted an exercise to identify where any Post closures would fall, and that there was "no secret list" of such Posts.[154] In January, Chris Bryant repeated to the House Sir Peter's denial that plans existed for Post closures.[155]

76.  Given the dispersal around the world of potential threats and areas of concern to the UK, and the large numbers of British citizens who travel widely overseas, closures of FCO overseas Posts risk leaving potentially damaging gaps in UK information-gathering, provision of assistance and exercise of influence. Post closures are also costly to reverse if judged subsequently to have been mistaken. We therefore conclude that the FCO is correct to identify as its top priority the maintenance of global UK representation through a network of overseas Posts. However, we further conclude that, without a marked easing in the financial pressures which they are facing, the FCO risks maintaining some Posts which are insufficiently resourced to carry out much effective work. We recommend that funding for the FCO should be increased to redress this.

77.  The most significant development in the FCO's overseas network under the post-2007 Strategic Framework so far has been a major shift of personnel out of continental Europe, where the FCO considered that work could be carried out by fewer staff, and into Posts seen as more important for the FCO's global objectives, primarily in Asia, the Middle East and parts of Africa, Russia and Latin America. The shift encompasses UK-based as well as locally-engaged staff.[156] The FCO has said that 77 policy jobs have been eliminated in continental Europe, with others being eliminated in London and the Americas, and 172 created elsewhere.[157] Sir Peter Ricketts told us that he thought the FCO would have to continue to shape the network on the basis of these kinds of considerations.[158]

78.  As noted in paragraph 72, under its post-2007 Strategic Framework the FCO has been encouraging other departments to base their staff working overseas at its Posts. Sir Peter Ricketts confirmed that the FCO believes "that the Embassy is the best place normally to have all the different parts of HMG's operations overseas".[159]

79.  When departments other than the FCO base staff in overseas Posts, the FCO seeks to recover the full economic costs involved by signing the relevant departments and agencies up to Service Level Agreements, which set out what the FCO will provide and the costs it will recover. The FCO expects to recover £37 million from other departments through such arrangements in 2009-10, plus a further £161 million from the UK Border Agency (UKBA).[160]

80.  Both the process of reaching Service Level Agreements with the FCO, and what is seen as the high level of its charges, continue to be a difficulty for other departments. According to the FCO's 2009 Survey of Whitehall Partners, unclear and high costings were the main sources of dissatisfaction with the Service Level Agreements among other departments and agencies. The Cabinet Office's 2009 Capability Review of the FCO noted that "the charging system used in overseas Posts is a particular frustration for many other government departments".[161] In its recent report on the FCO's management of its estate, in February 2010, the NAO found that the charging regime "lack[ed] transparency and [was] confusing and costly".[162] Sir Peter Ricketts told us in May 2009 that the FCO had "implemented a number of initiatives to simplify and streamline" the charging process,[163] and in July he said again that the FCO was "working to improve the arrangements for charging full economic costs to other government departments".[164] However, he also acknowledged that "other departments find [the FCO] expensive as a place to operate from".[165] This is particularly because FCO buildings overseas have more burdensome security requirements than those that other departments might face if operating independently. This is especially the case since the fatal attack on the British Consulate in Istanbul in 2003, which continues to shape the FCO's security requirements for its overseas buildings.

81.  The difficulties involved in the FCO's cost-recovery process with other departments are being compounded by Sterling's fall and the financial pressures facing all of Government. The FCO pointed out that "costs directly incurred by the FCO at overseas Posts on behalf of other departments are passed onto those departments at the daily exchange rate and the other departments therefore bear the exchange-rate risk for these costs".[166] According to Keith Luck, FCO Director General Finance, other relevant departments are in turn "under the same sort of financial pressures [as the FCO] and are finding it difficult to find additional resources to cover the exchange-rate losses".[167]

82.  In February 2010, Sir Peter Ricketts told us that the FCO had decided to retain the existing charging framework for other departments using FCO Posts for the rest of the CSR 07 period, but that "work [had] begun on identifying how funding for the overseas platform can be improved for the next Spending Review with a view to moving away from the current charging framework".[168]

83.  We concur with the FCO that as a general rule all British government departments and agencies should base their operations in any given overseas city in a single location. While we appreciate that other departments' use of FCO buildings may carry unavoidable extra security costs for them, we conclude that co-location in FCO premises is likely to enhance cross-departmental co-ordination and the projection of the UK presence.

84.  Where other departments make use of the FCO's overseas Posts, we conclude that the current department-by-department system by which the FCO recovers the associated costs is cumbersome and inefficient. We note that the numbers of personnel and departments using FCO overseas Posts may rise, and we therefore welcome indications that the system may be re-examined as part of the next Comprehensive Spending Review (CSR) which is expected after the 2010 General Election. We recommend that the CSR should review the costs of the overseas network across relevant parts of Government and consider sharing costs on a more regularised, equitable and ongoing basis.

85.  There has been a particular drive for the FCO and DFID to share overseas offices, in order to reduce the number of countries in which the two Departments are maintaining separate representations, and facilitate the joint provision of corporate services, thereby reducing overall costs. Sir Peter Ricketts told our inquiry last year that co-location also had policy benefits.[169] In October 2009, the FCO told us that since the start of the CSR 07 period FCO-DFID co-locations had taken place in Brasilia, Georgetown, Harare, Kampala and Lilongwe. Work was underway for co-location in Dhaka, New Delhi and Jerusalem. However, the FCO noted at the same time that opportunities for co-location had fallen, because DFID had closed its offices in some countries as a result of restructuring.[170] The FCO said that co-location in Abuja, Beijing, Bridgetown and Pretoria would now be considered in the next CSR period.

86.  The FCO and DFID are seeking to harmonise the pay and conditions of their local staff at Posts where the two Departments are co-located. In September 2009, the FCO told us that two of three pilot Posts had nearly completed their reviews of local staff pay, and that a further ten Posts had started the process.[171] In January 2010, the Foreign Secretary said that six co-located Posts had now completed the process.[172] The aim is for all co-located Posts to complete their joint pay reviews by mid-2010.[173] The two Departments are also "exploring collaborative procurement opportunities".[174]

87.  We recommend that in its response to this Report the FCO should list the number of locations where there is currently co-location with DFID and set out the number of co-locations with DFID which it expects will be completed in the CSR 07 period, confirming whether the number will be lower than originally planned.

88.  In its 2008-09 Annual Report, the FCO noted the creation of the Nordic-Baltic network, as an innovation aimed at facilitating the maintenance of even small Posts, by reducing the costs associated with each one. The FCO described the network as a "pilot scheme in which one larger Embassy (Stockholm) provides policy and administrative support to five much smaller embassies in the region".[175] The 2009 Cabinet Office Capability Review said that the network was "pioneering new regional working arrangements that promise better use of scarce skills and knowledge, more resilience and greater efficiency".[176] We had the opportunity to see for ourselves how the Nordic-Baltic network was operating when we visited Stockholm and Tallinn in October 2009, during the Swedish Presidency of the EU Council. We heard that work on particular issues was distributed around the network (which now involved eight Posts), so that specialist staff in one Embassy might cover an issue for the whole of the network. We also heard that the arrangement would allow the Ambassadors to the Nordic countries in the network, other than Sweden, to be appointed at a lower grade than previously.

89.  The Cabinet Office Capability Review said that other regions were "keen to learn from the experience" of the Nordic-Baltic network.[177] The FCO Annual Report noted that the High Commission in Pretoria conducts work for several neighbouring states.[178] In subsequent correspondence, the FCO told us that the High Commission in Bridgetown acts as a hub for the Eastern Caribbean; the three posts in the Indian Ocean were already operating as a single network; posts in the South Pacific were moving towards this; the ten Posts in the Arabian Peninsula were starting to work more closely together, "with a view to creating an Arabian Peninsula Network" in 2010; Posts in the Levant and North Africa were looking at integrating their work more closely; and other sets of Posts operated as networks for specific issues. In particular, the FCO noted that its Iberian Peninsula Posts operate as a network for consular issues, something which we were able to see for ourselves during our visit to Madrid and Lisbon in January 2010 (see paragraph 308).[179]

90.  Given the severe budgetary constraints facing the FCO, we conclude that the development of regional networks of Posts such as the Nordic-Baltic network, sharing work and resources while retaining representation in each country, represents a sensible—and potentially beneficial—way of maintaining the global network while reducing costs, as long as it does not come to act as "cover" for the downgrading or closure of British Embassies. We recommend that our successor Committee should keep this issue under review, and that the FCO should provide updated information on the development of regional networks of Posts in its response to this Report.

91.  As a further means of reducing the costs of maintaining a global presence, the FCO has been making increased use of information technology—such as videoconferencing, to reduce the need to travel for meetings; and "laptop diplomacy", to enable staff to work without having to have access to a permanent office.[180] As part of the rollout of the FCO's new IT system, Third Generation Firecrest (F3G), the Department has been deploying laptops compatible with the new system and able to handle material with a "Restricted" classification, better enabling staff to work outside the office.[181] In our previous Report, we largely welcomed the FCO's willingness to be innovative in this respect, although we expressed some concern in case "laptop diplomacy" becomes a way of saving money in the short term while failing to implement worthwhile longer-term projects.[182]

92.  A new factor in the environment for the FCO's operation of its global network of Posts has arrived with the establishment of EU Delegations in third countries under the Lisbon Treaty, which came into force on 1 December 2009. The EU Delegations will form part of the European External Action Service (EEAS), which was formally created by the Lisbon Treaty and which is expected to become operational under the terms of a planned EU Council Decision which was under very active discussion in Brussels when we visited there at the beginning of March 2010. Under the Lisbon Treaty, over 130 EU Delegations in third countries have been established, by converting the previous European Commission Delegations. Whereas the previous European Commission Delegations were active only in limited areas, the new EU Delegations are to have a role across the full range of EU external activities, including the intergovernmental Common Foreign and Security Policy (CFSP).[183] In batches, depending on a number of technical and political factors, the new Delegations are being given upgraded powers compared to their Commission-only predecessors, including to chair the meetings of EU Member State Ambassadors and High Commissioners in the relevant capital on a permanent basis rather than rotating with the country having the EU Presidency, and to have Heads of Delegation who are authorised to speak publicly in the name of the EU, on the basis of statements pre-approved by all 27 Member States.[184] It is expected that, as the EEAS develops, EU Delegations may be established in new locations, and some existing Delegations—for example, to the UN in New York—may be significantly expanded in size to handle their larger post-Lisbon responsibilities. A key issue for the future will be how far individual EU Member States will, under budgetary pressures, decide to discontinue their bilateral Embassies and High Commissions in particular countries in the knowledge of a presence there of an EU Delegation.

93.  In our Report on Foreign Policy Aspects of the Lisbon Treaty in January 2008, we concluded that "the emergence in third countries of EU Delegations which may be active in Common Foreign and Security Policy areas will at the least require careful management by UK Embassies on the ground".[185] We have also previously raised concerns in case the new EU Delegations were to begin to encroach on the consular role of British Posts overseas.[186] In third countries where their state is not represented, EU Member State nationals are already entitled to receive consular assistance from a Member State other than their own. Member States often currently implement this right through informal agreements amongst themselves concerning the assistance to be provided to particular Member States' nationals in specific third countries.[187] Under the Lisbon Treaty, the new EU Delegations "shall contribute" to the implementation of citizens' right to consular assistance in states where they are not otherwise represented.[188] In the context of the discussion about consular assistance, we note with concern a parliamentary answer in March 2010 in which the FCO said that it was no longer collecting data on the numbers of non-UK nationals being assisted by its Posts overseas, an issue on which we have previously commented.[189]

94.  The FCO has stated consistently that, in the words of the Foreign Secretary, it sees the new EU Delegations as "complementary, not substitutive" as regards British Posts overseas.[190] As regards the Delegations' impact on the FCO's management of its global network of Posts and its overseas estate, Sir Peter Ricketts said that he felt the FCO's budgetary constraints were a far bigger pressure on the Department's global presence than the incipient EEAS.[191] In evidence on 1 March 2010 to the Public Accounts Committee, Sir Peter suggested that, if anything, the arrival of EU Delegations around the world might open up new opportunities for the FCO. Just as states' national diplomatic representations sometimes share premises in a given location, Sir Peter suggested that EU Delegations might become potential fee-paying occupiers (or purchasers) of some of the spare capacity which exists in some FCO buildings overseas; and that the FCO could co-locate small UK Posts into EU Delegation premises if this would enable a British presence where there would otherwise be no UK national diplomatic representation in the country in question.[192] Sir Peter said that such co-location "would only be to increase our coverage in countries where [the UK] is currently not represented".[193]

95.  In October 2009, the European Council invited the EU's new High Representative for Foreign Affairs and Security Policy, Baroness Ashton, to bring forward her proposed Council Decision on the operation of the EEAS "with a view to its adoption by the Council at the latest by the end of April 2010".[194] The Council must adopt the Decision by unanimity, after consulting the European Parliament and obtaining the consent of the European Commission.[195] Chris Bryant, Minister for Europe, has given an assurance to the European Scrutiny Committee that Baroness Ashton's proposal will be deposited in Parliament at least two months before any Council decision, in line with the new procedures for national parliamentary scrutiny of EU proposals.[196] However, our discussions in Brussels at the beginning of March suggested that, of the two-month and the end-April timetables, at least one might slip. Discussions are also underway about the involvement of national Parliaments in the oversight of the EEAS, given the Service's role regarding the EU's intergovernmental Common Foreign and Security Policy.[197] The Chairman of the Committee and of the European Scrutiny Committee wrote jointly to the High Representative on this issue in December 2009.[198] Scrutiny of the EEAS and the CFSP by national Parliaments assumes even more importance given the right of the High Representative under the Lisbon Treaty to bring forward Common Foreign and Security Policy proposals.[199]

96.  We recommend that in its response to this Report the FCO should provide updated information on the number, size and development of the network of EU Delegations in third countries and at international organisations and on their relationship with UK overseas Posts, with particular respect to the future arrangement of the FCO global network, given current UK budgetary pressures. We also recommend that in its response to this Report the FCO states whether it is examining the closure of its Embassy or High Commission in certain countries in the knowledge of the likely presence there of an EU Delegation and, if so, in which countries. We further recommend that the FCO should set out the steps that it is taking to ensure that the High Representative for Foreign Affairs and Security Policy and the European External Action Service function within the parameters of the Lisbon Treaty and do not take over the decision-making and other functions of national foreign ministries, including with respect to consular tasks. We further recommend that the FCO should confirm whether it has ceased collecting data on the numbers of non-UK nationals being assisted by its overseas Posts, and if so, explain the reasons for this change of practice, and that it should recommence the collection of this important data.

97.  We recommend that, if it has not already done so by the time this Report is published, the FCO should copy to us at the earliest opportunity the High Representative's proposed Council Decision on the European External Action Service, since we would wish to consider it and to have the option of commenting on it prior to the dissolution of this Parliament. We recommend that our successor Committee in the next Parliament should continue to take a close interest in the operation of the External Action Service, through its scrutiny of the FCO and its Ministers at the national level, and through mechanisms for the involvement of national Parliaments at the EU level.

Civilian conflict-related work: secondments to international missions

98.  Funding for UK support for international missions for peacekeeping and other conflict-related activities takes place under Public Service Agreement 30 (PSA 30), "Global conflict", for which the FCO is the lead Department. Some UK funding for such missions is due as obligatory assessed contributions to the organisations concerned (as discussed in paragraphs 36-41). Other UK funding is discretionary. For 2009-10, programme funding for PSA 30 originally comprised £556 million: £109 million through the Conflict Prevention Pool (CPP), £73 million through the Stabilisation Aid Fund (SAF) (for non-military activities in Iraq and Afghanistan), and a call on the Treasury Reserve of up to £374 million for peacekeeping (both assessed and discretionary). The CPP and SAF are owned jointly by the FCO, DFID and MOD. As part of the CSR 07, it was agreed that if peacekeeping costs rose above £374 million, the CPP would be the first port of call for the excess.[200]

99.  There were signs through the winter of 2008-09 that the FCO was finding it increasingly difficult to fund its share of peacekeeping activities: it requested an additional £131 million from its DEL reserve at the Treasury for this purpose in its 2008-09 Winter Supplementary Estimate, and a further £27.6 million in its 2008-09 Spring Supplementary Estimate.[201]

100.  On 2 March 2009, the Financial Times reported that the UK would be withdrawing police personnel from international missions as a result of funding cuts. The paper said that the move represented "the first signs of the economic crisis eroding the UK's foreign policy clout".[202] The Chairman of the Committee wrote to the Foreign Secretary to seek clarification.[203] This came in the form of a Written Ministerial Statement on 25 March (delivered also on behalf of the Secretaries of State for Defence and International Development) with a covering letter,[204] followed by a further letter of reply from the Foreign Secretary in April.[205]

101.  In his 25 March statement, the Foreign Secretary confirmed that assessed peacekeeping costs in 2009-10 were set to rise substantially, owing to increased peacekeeping activities by the EU and UN and the decline of Sterling (as discussed in paragraphs 38-41). As a result, £456 million of the total £556 million PSA 30 funding for the year was having to be allocated for assessed peacekeeping costs—i.e. all of the relevant Treasury Reserve, plus £82 million of the £109 million in the CPP, leaving only £100 million in total for all discretionary activity under PSA 30 (including discretionary peacekeeping). The FCO, DFID and MOD between them found an additional £71 million to add to the £100 million. However, the Foreign Secretary said that £171 million was insufficient to fund all planned activities, and that cuts were therefore being made to "prioritise UK discretionary conflict expenditure more tightly on countries where the risk and impact of conflict is greatest".[206]

102.  The Foreign Secretary announced that the Stabilisation Aid Fund was to be merged into the Conflict Prevention Pool, and that the CPP was henceforth to have five programmes. This represented a further consolidation of the Government's conflict-related funding streams, after the CPP had itself incorporated the previously separate Africa Conflict Prevention Pool. Under the new arrangements, levels of CPP activity would be sustained in Afghanistan, as part of a South Asia programme of £61.3 million (36% of the total). Activity would be reduced in Africa (£43 million, 25%), Europe (£33 million, 19%) and the Middle East (£18 million, 11%), and ended in Latin America. As the fifth strand, there would be a £6.5 million thematic programme supporting the work of international organisations on conflict-related issues. The three Departments also felt obliged to keep back a reserve of £9.2 million in case of further Sterling weakening and/or increases in assessed contributions.[207] Sir Peter Ricketts summarised the changes as meaning that UK conflict-related funding was "focused on the UN peacekeeping contributions and our contributions to Afghanistan".[208]

103.  We have been made especially aware of the impact of the FCO's spending cuts on EU civilian missions in the Western Balkans. In his April 2009 letter, the Foreign Secretary provided a table showing expected numbers of UK civilian secondees to international missions in 2009-10 compared with 2008-09. This showed the number of police seconded to the EU's new rule-of-law mission in Kosovo, EULEX, falling from 45 to 17, and the number of other civilian secondees to the mission down from 18 to 15; and the number of police seconded to the EU police mission in Bosnia-Herzegovina down from 9 to 3. The number of civilians seconded to missions of the Organisation for Security and Co-operation in Europe (OSCE) was also expected to be down from 15 to 6. The Foreign Secretary highlighted that the numbers of UK civilian secondees to the EU police mission in Afghanistan and the EU monitoring mission in Georgia were being maintained.[209]

104.  Our impression is that both the suddenness and the scale of the reduction in the UK presence in EULEX, in particular, caused considerable embarrassment and personal inconvenience for the staff involved. During our visit to the region in October 2009, we heard concerns that the UK's reduced participation in the mission might weaken its influence in Kosovo, in the key early stage of the country's existence as an independent state. We heard similar concerns about the UK's reduced presence in Bosnia-Herzegovina. Leaving aside the scale of its presence in international missions, the UK has otherwise been a committed supporter of Kosovo independence and taken a prominent role in seeking to rescue Bosnia-Herzegovina's troubled reform and European integration processes.[210]

105.  In its March report, the Financial Times suggested that the reductions in UK participation would be "a humbling setback for Gordon Brown, […] who has made expanding civilian reconstruction efforts a top policy priority".[211] For example, according to its 2008 National Security Strategy, the Government "advocate[s] the development of a stronger international capacity, including through the EU and UN, to deploy civilian stabilisation experts, including judges, lawyers and police, at short notice and in larger numbers and to make them available for multilateral deployment".[212] As regards the EU in particular, in his Warsaw speech in June 2009 the Foreign Secretary said with respect to the Union's response to crises that its "ability to draw upon civilian expertise [...] [was] critical for dealing with fragile and failing states".[213] In a letter to us in December 2009 in connection with the Western Balkans, Mr Miliband reiterated that "the UK remains fully committed to civilian missions under the European Security and Defence Policy as a key tool to manage international crises and to prevent and resolve conflict".[214]

106.  The Foreign Secretary also told us in December that it was "highly unlikely" that funding would be found in 2009-10 for additional UK secondments to civilian missions. He said that he was not yet able to give numbers for UK secondments in 2010-11.[215]

107.  In December 2009, DFID announced the launch by the joint FCO-DFID-MOD Stabilisation Unit of a Civilian Stabilisation Group comprising 1,000 civilian personnel potentially deployable to post-conflict missions overseas.[216] The personnel consist of 200 civil servants and 800 external experts. The Group is managed by three Stabilisation Unit staff.[217] As a result of the creation of the Group, the Government expects the number of civilians that the Stabilisation Unit could deploy at any one time to rise to 200 if required.[218] The FCO confirmed that no additional funding was accompanying the creation of the Group, which would continue to be funded from discretionary monies in the Conflict Prevention Pool.[219]

108.  We conclude that, as a result of the need for spending cuts, the FCO has made reductions to the numbers of UK secondees to international civilian missions in the Western Balkans which are deeply regrettable. As regards support for secondees, we recognise that the UK must prioritise among a large number of international civilian missions, and that the UK continues to have a large presence in some cases. However, the UK has a significant interest in the success of the international post-conflict effort in the Western Balkans. We conclude that the message sent by the reduction in UK participation in these high-profile missions sits uncomfortably with the Government's stated commitment to the region and to the development of effective international civilian post-conflict capabilities.

109.  We conclude that the creation of the Civilian Stabilisation Group under the joint FCO-DFID-MOD Stabilisation Unit is to be welcomed, as potentially increasing the UK's ability quickly to deploy a wide range of civilian experts to post-conflict missions overseas. However, we further conclude that a major constraint on UK civilian deployments has been funding, and that the creation of the Civilian Stabilisation Group does not in itself address this. We recommend that the FCO should inform us, in its response to this Report or earlier if the information is available, of the funding that will be available for peacekeeping and other post-conflict and conflict prevention activities in 2010-11, and of the numbers of UK secondees to international civilian missions that it expects to be able to support in that year. We further recommend that our successor Committee may wish to consider inquiring into the UK's capacity to deploy civilians to post-conflict missions overseas.

MANAGEMENT OF EXCHANGE-RATE RISK

110.  We outlined in our Report last year the FCO's initial efforts to mitigate the effects of exchange-rate risk, following the withdrawal of the OPM, through the forward-purchasing of foreign currencies.[220] The NAO explained these efforts more fully in its submission to our current inquiry.[221] The NAO told us that the FCO began considering how to manage its exposure to exchange-rate risk immediately after receiving confirmation that the CSR 07 settlement would involve the withdrawal of the OPM. The FCO decided to start to forward-purchase at least some of its foreign currency needs, and received Treasury approval for this strategy. The FCO further decided to forward-purchase a substantial share, rather than all of its requirements, in major currencies, in order to allow for error.

111.  In April 2008, the FCO contracted a specialist foreign exchange trading company, HiFX Intelligent, to provide it with advice. HiFX made recommendations for derivative-based hedging strategies, which the FCO initially approved. However, the Treasury has a stated policy of refusing any proposals to speculate, and it therefore rejected the FCO's proposed strategies. The FCO then submitted revised proposals for straightforward forward-purchasing, which the Treasury approved. The FCO went ahead in May 2008 with the forward-purchase of 80% of its US Dollar and Euro requirements for 2008-09. The FCO has subsequently started also to forward-purchase some of its requirement for Japanese Yen. The Treasury agreed in August 2008 that the FCO could proceed with forward-purchases for its 2009-10 requirements, and it has subsequently given approval for forward-purchases into the post-2011 period. In December 2008, rather than simply buying a given month's exposure one year in advance as it had been doing, the FCO began to buy each month one-twelfth of each of the following 12 months' exposure, as a means of gaining greater budget certainty and spreading the risk of sudden exchange-rate fluctuations.

112.  The FCO pays HiFX a fee of £41,400 a year.[222] Explaining the FCO's decision to take professional advice from the company, Sir Peter Ricketts told us that the Department wanted to be "very, very careful" about engaging in forward-purchasing, especially in order to avoid any suspicion that it was speculating.[223] Keith Luck, the FCO's Director General Finance, also told us that the Department had originally lacked the specialist skills required. However, the NAO told us that on-the-job training had since been provided and that there had been no need to recruit additional staff.[224] Mr Luck said that HiFX's contract was now "tiny" and consisted of "making sure that our Treasury Management policy documents are up to date, that we are complying and that our people have somebody they can go to—the two or three individuals who work on this area—if they need particular advice".[225] The NAO confirmed that the FCO regards the ongoing in-house staff costs of operating its forward-purchasing regime as "relatively small".[226]

113.  Apart from the overall costs occasioned by the fall of Sterling since 2007, the FCO confirmed that it lost money specifically as a result of the fact that it only placed its first forward contract for its 2008-09 foreign currency needs in May 2008 (rather than sooner after the conclusion of the CSR 07 in October 2007), and Sterling had by then already fallen compared to the rates assumed in the CSR 07. The FCO suggested that the delay arose partly because the withdrawal of the OPM was only confirmed late in the CSR process, and partly owing to its own need to develop a response and the capacity to implement it. The FCO told us that:

The timing of the decision meant that we had only a short time to build up the technical skills to implement an operation to forward purchase our foreign currency requirements and we are still improving the skills required. We also incurred additional costs from the need to build and buy in exchange rate management capacity at short notice. By the time we had developed sufficient skills and agreed how to operate, Sterling had started to decline from the levels it had occupied in 2007.[227]

114.  The NAO noted that, while the day-to-day costs of operating the forward-purchasing regime are small, the FCO "considers [that] the indirect costs of managing the broader consequences of the withdrawal of the OPM have been far greater, with a considerable amount of senior management time, including that of the FCO Board, Heads of Mission and Management Officers, taken up in managing the impact of currency fluctuations".[228] The Foreign Secretary told us in December 2009 that he would "prefer to spend all [his] time on policy questions, but […] can't when there are financial and management issues" of the kind raised by the impact of the OPM's withdrawal.[229]

115.  In June 2009, the NAO published a report on Financial Management in the FCO, in which it noted that "foreign exchange is new territory for the Department" but said that, as of that time, the FCO had "taken appropriate action to seek to manage this risk".[230] The NAO also told us that the FCO's Director of Finance had commissioned external consultants to review the Department's foreign currency management arrangements. In their report, completed in September 2009, they concluded that progress had been made in a number of areas but that there was a need for a formal guidance document. They noted that a formal Treasury policy was being drafted, and recommended that the Treasury should supplement this with a procedures manual.[231]

116.  We conclude that, because Sterling weakened between the conclusion of the 2007 Comprehensive Spending Review (CSR 07) in October 2007 and the time at which the FCO placed its first forward contracts for foreign currency purchases in May 2008, the FCO incurred direct extra costs as an immediate consequence of the withdrawal of the Overseas Price Mechanism (OPM) under the CSR 07, and as a result of the timing of the decision. We further conclude that the failure to put mitigating arrangements in place by the time the withdrawal of the OPM was put into effect, at the start of the 2008-09 financial year, suggests a lack of effective joint working between the FCO and the Treasury, and that this amounts to poor management of the withdrawal.

117.  We conclude that as a result of the OPM's withdrawal, managers throughout the FCO network, including those at the most senior level, have spent considerable amounts of time since late 2007 seeking to manage and mitigate the effects of currency fluctuations. We do not consider that senior FCO staff are the most appropriate personnel to be carrying out this work, nor that this is the best use of their time and skills.

118.  The FCO's forward-purchasing activity was one of the factors which helped it to remain within budget in 2008-09. The FCO did not, in the end, need to draw the full £15 million in 2008-09 End-Year Flexibility which the Treasury had authorised to compensate for exchange-rate losses, as the Department made gains under its early forward-purchase contracts.[232] In the 2008-09 Spring Supplementary Estimate, the FCO was able to transfer £29 million which it had gained through forward contracts towards peacekeeping in Africa.[233] According to the NAO, the FCO's forward-purchasing operations gained it some £40 million overall in 2008-09, compared to the situation which would have prevailed had the Department continued only to make spot purchases.[234]

119.  As long as Sterling remains below the levels assumed in the CSR 07, forward-purchasing cannot provide complete protection from the effects of Sterling decline.[235] The NAO pointed out that, as Sterling was largely weaker in 2009-10 than in 2008-09, the gap between the CSR assumptions and the rates available in forward-purchase contracts would be wider, resulting in a greater loss of purchasing power.[236] At the same time, the FCO said that it had entered into some forward contracts in December 2008-January 2009 when Sterling was at its weakest, and that inasmuch as Sterling subsequently strengthened, these contracts would result in an exchange-rate loss for the Department.[237] In addition, the FCO has not considered it cost-effective to forward-purchase any currencies other than US Dollars, Euros and Yen. It has exposure of over £4 million in only another three currencies, and its exposure in 14 currencies is below £2 million a year.[238] Forward-purchasing is in any case not available for the majority of the 120 currencies in which the FCO operates, as they cannot be purchased in the UK.

120.  Rather than protection against losses, under current circumstances forward-purchasing mainly provides certainty. In a letter to us of October 2009, the FCO summarised the situation thus:

although the forward purchasing strategy we developed for US Dollar/Euro/Japanese Yen helped us plan our activity in these currencies around our known costs, […] it has done nothing to help us manage the long term impact of, and the additional costs generated by, Sterling's collapse in the autumn of 2008 against nearly all currencies. […] Forward purchasing cannot solve this.[239]

121.  We commend the FCO for developing, after an uncertain start, a forward-purchasing operation which reduced the scale of the losses that would otherwise have arisen from Sterling's fall and helped the Department to remain within budget in 2008-09. However, we conclude that forward-purchasing in a limited number of foreign currencies, as the FCO has done, whilst providing greater foreign exchange certainty, cannot protect the Department's non-Sterling purchasing power from the basic fact of Sterling depreciation. We deplore the fact that the policy of the Treasury and the ending of the Overseas Price Mechanism in 2007 have made forward-purchasing by the FCO necessary.

122.  The FCO suggested in January 2009 that forward-purchasing could help it to achieve the savings it requires in 2009-10, perhaps to the tune of £90 million in total over the two years 2009-10 and 2010-11, although the Department warned that "the reality of course could be very different".[240] By October 2009, the FCO said that the forecast net gain over the two years had fallen to £19.3 million, because Sterling had strengthened compared to the rates fixed in its forward contracts. The expected net gain arose from a forecast gain of £36.4 million in 2009-10 and a forecast loss of £17.1 million in 2010-11.[241]

123.  We recommend that in its response to this Report the FCO should set out how it is weighing the increased certainty which is achieved through forward-purchasing, on the one hand, against the risk, on the other, that forward contracts could be less favourable than spot purchases if Sterling strengthens. We further recommend that in its response to this Report, or earlier if possible, the Department should provide an update on its foreign currency management plans for the 2010-11 financial year.

124.  In an evidence session with the Public Accounts Committee (PAC) in October 2009, Sir Peter Ricketts discussed possible co-operation between departments in the management of exchange-rate risk.[242] Our understanding is that the MOD has used relatively long-term forward-purchasing for many years, to secure the foreign currency needed to make fixed-date payments on major capital projects.[243] As of early 2010, DFID has not felt a need to make forward-purchases of foreign currency, and its witnesses indicated to the International Development Committee in November 2009 that the Department could probably continue to manage without doing so, with the exception of its Euro-denominated contribution to the European Development Fund, for which it might forward-buy its currency requirement.[244] Sir Peter told the PAC that he "would see lots of value in other departments clubbing together" with the FCO to forward-purchase foreign currencies.[245] The PAC recommended that "with input from the Treasury, [the FCO] should work alongside other Departments, such as the Ministry of Defence and Department for International Development, to identify the most effective way to manage exchange-rate risk for the Government as a whole".[246]

125.  We recommend that in its response to this Report the FCO should update us on any discussions which it is having with other government departments about the possible joint management of exchange-rate risk, and on the development by the Treasury of cross-government guidance on foreign currency management.

PROSPECTS FOR 2010-11 AND BEYOND

126.  The figure currently given for the FCO's expected 2010-11 DEL budget is £1.69 billion.[247] However, this includes no spending on conflict prevention and thus appears to represent an artificially large drop (21%) compared to the FCO's budget for 2009-10. The FCO told us in February 2010 that conflict prevention allocations for 2010-11 had not yet been confirmed.[248]

127.  In February 2009, the FCO Board minutes already described the Department's budgetary prospects for 2010-11 as "sombre".[249] In her January 2010 parliamentary answer, Baroness Kinnock said that the FCO expected its projected budget shortfall of £110 million in 2009-10 to "increase slightly" in 2010-11,[250] although in his subsequent Written Ministerial Statement of 10 February the Foreign Secretary put the expected figure for 2010-11 back at £110 million.[251] Once the effects of Sterling's fall are factored in, the minutes show that as of December 2009 the FCO Board was expecting the Department's budget for 2010-11 to be "8-9% lower than the one for 2009-10, due mostly to the continued fall of Sterling". The Board said that coping with this would require "difficult decisions".[252] The FCO confirmed in February 2010 that the 8-9% figure was "indicative of the likely reductions in planned spending needed to stay within our parliamentary control totals and CSR settlement in the light of our exchange-rate pressures".[253]

128.  As we prepared this Report in late January and February 2010, departments' discussions with the Treasury over the details of their 2010-11 budget settlements remained underway.[254] In 2008-09, late internal allocation of budgets within the FCO caused problems at the start of the financial year, but the FCO issued its 2009-10 budgets in March 2009, and for 2010-11 it planned to do so in February.[255] Sir Peter Ricketts also told us that he wanted to "get to a position as soon as [he could] where Posts have certainty about their budgets in local currency for the year ahead, so that they are in a sense protected from movements of sterling during that year".[256] This was confirmed in an internal FCO memo from Sir Peter of which the FCO gave us sight, in which Sir Peter also referred to plans to "create a central fund to manage in-year currency fluctuations".[257] If the FCO plans to convert Posts' budgets into local currencies before the start of the financial year, and put new internal arrangements in place to protect the Department against subsequent Sterling weakening, this suggests another reason to try to reach a 2010-11 budget settlement with the Treasury relatively early.

129.  Given the way in which the FCO has recently improved the timeliness of its budgetary processes, and especially if it seeks to allocate Posts' budgets in local currencies rather than Sterling for the first time, we recommend that the Department should do all it can to ensure that it reaches a 2010-11 budgetary settlement with the Treasury in good time to allow it to allocate internal budgets before the start of the 2010-11 financial year.

130.  The FCO told us that in a letter to the Foreign Secretary of 22 November 2007, after the announcement of the CSR 07 settlement, the then Chief Secretary to the Treasury had said that "if there were a sudden and extreme pressure on the FCO relating from exchange-rate fluctuations [sic], the [Chief Secretary] would consider a Reserve claim if the alternative would be that the FCO would breach its DEL and Estimates".[258]

131.  The FCO has been frank in its responses to our questions about its finances, but in general the Department seems to have preferred to take a relatively discreet and low-key approach to its negotiations with the Treasury, rather than "go public" about the scale of the threat to its budget and the reasons for its difficulties. The Foreign Secretary told us in December 2009 that he had "not found that waving bleeding stumps in public is the way to impress one's colleagues".[259] We find the Foreign Secretary's choice of metaphor telling as an indication of the potential severity of the cuts facing the FCO.

132.  On 10 February 2010, the Foreign Secretary announced that, as a result of an agreement with the Treasury aimed at helping to manage exchange-rate pressures, in 2010-11:

  • an additional £25 million from asset sales would be recycled into the FCO's budget;
  • a further £35 million would be made available to the FCO from the Reserve, of which £20 million would form a "foreign exchange adjustment account", to be drawn on in agreement with the Treasury; and
  • a further £15 million would be made available in End-Year Flexibility, "focussed on restructuring and modernisation costs subject to a business case being made".[260]

In subsequent written answers, the FCO explained that the "foreign exchange adjustment account" would be a Departmental Unallocated Provision (DUP), and said expressly that it did not represent a return to the OPM.[261] As regards the asset sales, Sir Peter Ricketts clarified in evidence to the Public Accounts Committee on 1 March that the additional £25 million represented an increase in the maximum annual amount of funds which the Treasury allows the FCO to retain for itself from its own asset sales.[262] In his 10 February statement, the Foreign Secretary also said that he had agreed with FCO Services Trading Fund (for which, see paragraph 147) that it would make an additional contribution towards helping the main FCO budget in 2010-11, a contribution which has been identified subsequently as a dividend payment of £3 million.[263] The Foreign Secretary also said that the FCO itself would implement "a broad programme of streamlining and cost-savings" to further reduce its budgetary shortfall.[264]

133.  In his 10 February statement, the Foreign Secretary also said that he had agreed with the British Council and the BBC World Service that they would make additional contributions towards helping the main FCO budget in 2010-11. Both organisations provided further details in subsequent submissions to us. The BBC World Service told us that its projected underspend of £4 million in 2009-10 would be offset against the FCO's projected overspend, in line with normal practice. For 2010-11, as an "exceptional measure", £3.7 million of World Service funding was being made available to the FCO "with the express understanding that this will not be a permanent reduction in the BBC World Service baseline". The World Service said that, for the period beyond 2010-11, the FCO would "make every effort in the forthcoming Spending Review to support [it] in negotiating satisfactory funding".[265] For its part, the British Council is to provide £5 million to the FCO budget in 2010-11. Under plans approved by the Board of Trustees on 23 February 2010, the British Council is to raise £1.1 million from operating budget cuts, and £1.5 million by "refocusing" programme activity under its Reconnect initiative, which provides leadership training to young people in Muslim states, while seeking to "maintain impact in Pakistan and Afghanistan". A cut of £1.5 million represents half of the planned budget for the "Reconnect" initiative in 2010-11. The British Council will also pass on the net surplus raised from the sale of its Mumbai office, estimated at £2.4 million.[266]

134.  The Foreign Secretary said in his 10 February statement that the package of measures agreed with the Treasury would "substantially offset the foreign exchange pressures on the FCO budget" in 2010-11.[267] The measures costed as of mid-February 2010 totalled £90.7 million, which remained less than the FCO's expected shortfall for 2010-11 of around £110 million, but represented over 10% of the FCO's core budget of around £830 million. The remainder of the shortfall was presumably to be found from the FCO's own programme of cost savings, which remained to be finalised.

135.  We conclude that recent public statements by the Foreign Secretary and Baroness Kinnock are evidence that the FCO is "going public" about the scale of its financial difficulties. We welcome the agreement with the Treasury for additional financial resources for 2010-11 which appears to have resulted. We welcome in particular the Treasury's implicit acknowledgement that the management of the exchange-rate pressures which face the FCO requires support from the Treasury Reserve. We conclude that the measures announced in February 2010 should substantially reduce the pressures on the FCO budget in 2010-11 arising from the withdrawal of the Overseas Price Mechanism and the fall of Sterling, although we note that the currently costed plans do not make up all the expected shortfall. We regard it as unacceptable that as a result of Treasury policy the FCO's operations came to be under such strain before agreement on some financial relief was reached. We recommend that in its response to this Report the FCO should provide further details of the expected operation of the measures announced in February 2010, as well as its estimate of the cash increase to the FCO's 2010-11 budgeted income which is likely to be realised as a result.

136.  We are concerned that the agreement announced in February 2010 between the FCO and the Treasury on the FCO's finances for 2010-11 breaches the ring-fencing of funding for the British Council and BBC World Service. We recommend that in its response to this Report the FCO should provide an assurance that this will not be repeated.

137.  For the period beyond 2010-11, Departments' budgets are expected to be determined in a new Comprehensive Spending Review following the 2010 General Election. The Foreign Secretary appeared to imply that, in principle, he favoured adhering to a three-year settlement rather than seeking major changes during a spending round period.[268] The minutes of the January 2010 meeting show that the FCO Board is already planning on having to reduce the FCO's headcount by 10% over the next five years;[269] and Sir Peter Ricketts indicated that, if necessary, the FCO would continue to raise the difficulties it was facing with the Treasury into the new spending round.[270]

138.  We note that the agreement with the Treasury which was announced by the FCO in February 2010 comprises a set of one-off measures which apply only to the 2010-11 financial year and which do not address the impact of the withdrawal of the Overseas Price Mechanism (OPM) on a longer-term basis. We recommend that the OPM should be re-established, or an alternative mechanism put in place to protect the FCO, with its unique degree of exposure to currency fluctuations, from suffering severe financial consequences as a result of such fluctuations.

139.  The expected 2010 CSR will follow two spending rounds which were relatively tough for the FCO. We have noted previously that what Sir Peter Ricketts described to us as the FCO's "flat or less than flat"[271] real-terms budget under the 2004 and 2007 spending rounds contrasted with the increases enjoyed by some other departments and agencies. For example, the average real-term reduction in the FCO's budget under the CSR 07 which we identified in our Report two years ago, of 0.2% a year, contrasted with an average real increase for other departments of 2.1%.[272]

140.  Figures 1 and 2 show the real-term change in the Total Departmental Spending of the FCO, DFID, MOD and the Security and Intelligence Agencies (SIA) for the CSR 07 and 2004 Spending Review periods, using 2007-08 and 2004-05, respectively, as the reference years. The FCO's spending is shown both including and excluding conflict prevention spending, to enable comparison of plans for 2010-11 (for which conflict prevention funding is not yet allocated) with spending in previous years. The figures show that, whether for the post-2004 or post-2007 spending period, the FCO's expected spending for 2009-10 and 2010-11 is in real terms only slightly, if at all, above its level at the start, whereas the spend for DFID and the intelligence agencies is between 20% and 70% higher, depending on the basis used.

Figure 1: Real-term change in Total Departmental Spending of FCO, MOD, DFID and SIA,
2007-08 - 2010-11


Figure 2: Real-term change in Total Departmental Spending of FCO, MOD, DFID and SIA,
2004-05 - 2010-11


SIA - Security and Intelligence Agencies. The two Figures show the real-term percentage change in the respective bodies' Total Departmental Spending for the post-2007 Comprehensive Spending Review and post-2004 Spending Review periods, using 2007-08 and 2004-05 prices, respectively. Prices have been calculated in real terms using the HM Treasury Gross Domestic Product deflators; see http://www.hm-treasury.gov.uk/data_gdp_index.htm.

Sources for Total Department Spending figures: FCO, Departmental Report and Resource Accounts, 1 April 2008-31 March 2009, Vol. 2, HC 460-II, pp 14-15; DFID, Annual Report and Resource Accounts 2008-09, Vol. 1, HC 867-I, p 61; MOD, Annual Report and Accounts 2008-09, Vol. 1, HC 467-I, pp 20-21; Cabinet Office, Annual Report and Accounts 2008-09, HC 442, pp 125-126

141.  The Foreign Secretary suggested that departments' relative influence should not be judged by "the respective size of [their] cheque books", because the FCO exercised influence not by programme spending but by its "diplomatic and political links".[273]

142.  We conclude that the FCO has been losing out relative to other departments and agencies in the allocation of government spending, in a consistent trend over the last two spending rounds. In real terms, the FCO's Total Departmental Spending excluding conflict prevention (in Sterling terms) is expected to be around 3% above the 2004-05 baseline in 2009-10 and 0% above the same baseline in 2010-11, whereas the figures for DFID, for example, are around 50% and 70% higher, respectively. We agree with the Foreign Secretary that there is no absolute correlation between budgets and influence. Nevertheless, we recommend that the trend whereby the FCO has been losing out relative to other departments in the allocation of government spending should be reversed.

143.  We appreciate that all government departments face a major squeeze on public spending, and that protecting the work done by the FCO may not be at the top of the British public's list of priorities. Nevertheless, we conclude that the FCO has a strong case to make about the value of its work in the national interest, about the extent to which it has already made cuts, and about the severity of the budgetary situation in which it finds itself, largely for reasons beyond its control.

Efficiency savings

144.  Under the CSR 07, the FCO was set a target of 3% annual efficiency savings, like other government departments. For the FCO, this is equivalent to £144 million in net cash-releasing savings over the three-year period. In the Government's 2009 budget, it was announced that the FCO and its associated public bodies would be required to find additional savings of £20 million by 2010-11. The FCO has established a range of efficiency or value-for-money (VFM) programmes aimed at delivering its overall savings targets. We have commented in detail on several of these in previous Reports.[274]

145.  At the time of our Report on the Department's 2007-08 Annual Report, the FCO was forecasting that its efficiency programmes should yield £155 million in savings over the CSR 07 period. The Department thus deliberately built in a buffer to increase its prospects of achieving the £144 million target, even if projects failed to deliver fully or on time.[275] In its 2008-09 Annual Report, the FCO said that it was now running efficiency programmes which should yield £167.4 million in savings by 2010-11.[276] By the time of the 2009 Autumn Performance Report, the FCO was reporting that its efficiency savings programmes should save a cumulative total of £172.6 million over the CSR 07 period.[277]

146.  In 2008-09, the FCO's efficiency programmes delivered £85.8 million in savings (including £12.1 million by the BBC World Service and British Council), against £75.5 million forecast in the 2008 Autumn Performance Report.[278] As of the end of the second quarter of 2009-10, the FCO's cumulative savings since the start of the CSR 07 period amounted to £120.6 million. The FCO said that if it maintained its performance, it would be "on track" to achieve the CSR 07 target.[279] The FCO reaffirmed this expectation in letters to us in February 2010, when it said that the forecast was supported by initial indications from the 2009-10 third-quarter figures.[280]

147.  In our Report last year, we considered in particular detail the organisation FCO Services, which provides a range of services including logistics, IT, language services, biometrics, vetting and physical security, and which became a Trading Fund on 1 April 2008, with the aim of generating increasing revenues from non-FCO customers.[281] We concluded last year that "FCO Services [had] made a promising start following its transformation to a Trading Fund" but that "there must be concerns about its ability to expand into wider markets under current economic conditions".[282] In the event, FCO Services posted 15.3% growth in wider market revenue in 2008-09, above its 10% target. Sir Peter Ricketts told us that FCO Services' performance had "enabled it to play an important role in enabling [the FCO] to meet [its] overall efficiency saving obligations under the CSR".[283]

148.  The FCO told us in October 2009 that some of its efficiency projects were having to find more savings than planned, in order to compensate for exchange-rate fluctuations.[284] Similarly, the Department's 2009 Autumn Performance Report noted that "if exchange rates remain at their current level or fall further, the FCO is likely to have to exceed its efficiency targets in order to maintain delivery of its DSO and PSA targets".[285]

149.  The FCO commissioned an internal audit of its value-for-money programme, to assess compliance with Treasury guidance, which was completed in January 2009. The audit rated risk management of the programme as being "satisfactory". The FCO told us that the audit had made only five recommendations, all of which had been implemented by the end of the 2008-09 financial year.[286] The audit report also noted that "the FCO has received praise from […] HMT for being proactive in its approach to the CSR 07 VFM process and is seen to be ahead of other HMG Departments".[287]

150.  The FCO's CSR 07 programme of efficiency savings follows a similar programme established under the 2004 Spending Review, under which the FCO exceeded its savings target, achieving £132 million in savings against a target of £120 million.[288] Given the efficiencies that the FCO has implemented in recent years, Sir Peter Ricketts described as "limited" its scope to make further such savings in order to recoup its current budget shortfall.[289] Sir Peter said that the FCO had "been living on pretty thin rations for at least a couple of spending rounds" and had therefore already "got rid of the fat".[290]

151.  We conclude that in the last two spending round periods the FCO has consistently taken seriously the Government's efficiency savings requirements, and has met or exceeded savings targets. We recommend that the FCO should continue to make a sustained effort to reduce costs where it reasonably can, in line with the requirements of the Comprehensive Spending Review 2007—but that it should resist the temptation to seek savings over-aggressively in order to make up the Department's budgetary shortfall, at the risk of cutting into its substantive operations and capabilities.

152.  In his quarterly management letter for January-March 2009, Sir Peter Ricketts told us that the FCO was looking especially to the Corporate Services Programme (CSP) to "save significant money from the next financial year onwards".[291] The FCO approved the CSP in September 2008 as a replacement for the Shared Services Programme, which had received a "red" rating from the Office of Government Commerce and which the FCO effectively admitted was flawed, although it also said that it had made some useful contributions. The CSP is intended to improve the Department's corporate services such as financial processing, facilities management, procurement and human resources, with a view in particular to providing more of such services from single centres to several overseas Posts at once, so that individual Posts can stop having to carry out all such functions.[292] A new FCO UK Corporate Services Centre opened in Milton Keynes in September 2009. The CSP is also running a project called "10,000 days", which is aimed at eliminating unnecessary bureaucracy; the FCO told us in May 2009 that the project had by that stage saved over 9,000 days of management time, and in February 2010 that it had now "removed over 50,000 days of processes from [the Department's] systems".[293]

153.  We recommend that in its response to this Report the FCO should set out the basis for its claims regarding the amount of management time being saved by the "10,000 days" project, with examples of the kinds of bureaucracy that have been eliminated. We further recommend that the FCO should provide details of the work which is planned under the Corporate Services Programme for 2010-11, including information on the savings which the programme is expected to generate over the year. We further recommend that the FCO should provide us with an assessment of the initial operation of the new Corporate Services Centre in Milton Keynes.

Financial management

154.  As we noted in paragraph 115, the NAO carried out an inquiry into "Financial Management in the FCO" which reported in June 2009.[294] We also have taken a close interest in the FCO's efforts to improve its financial management, which we said two years ago "continue[d] to need improvement".[295] Following the 2005 Collinson Grant review and the first Cabinet Office Capability Review of the Department in 2006-07,[296] the FCO's efforts to improve its finance function have been a prominent feature of its recent management activities, especially since the launch in July 2007 of a major reform programme known as "5 Star Finance". Under the programme, "5 Star" status is achieved when an organisation meets top NAO standards for the accuracy and timeliness of its financial information. Performance may be assessed both by the organisation concerned and by external bodies.

155.  We detailed some of the steps which the FCO was taking under the "5 Star Finance" programme in our Report last year, in which we welcomed the reforms.[297] Among further steps taken since publication of our Report, the FCO recruited a further seven accountancy trainees to join the Department in September 2009, following the eight who joined in 2008-09. The trainees pursue a dedicated career track aimed at equipping them to occupy senior management positions. The FCO has also continued to provide specialist financial training for existing finance staff.[298] The Department refers to these schemes as "growing its own" accountants (the FCO's Director General Finance, Keith Luck, was recruited externally in February 2007). The proportion of FCO finance staff with professional qualifications rose from 8% at the time of the NAO Report to 12% by September 2009;[299] this remained below the Whitehall average of 14%, but the FCO expected the figure to rise to 17% by the end of the financial year.[300] The FCO has also continued to provide financial training for general staff, including at senior management and Board levels.[301]

156.  We recommend that in its response to this Report the FCO should state whether it achieved its forecast of having 17% of its financial staff with professional qualifications by the end of the 2009-10 financial year.

157.  In its 2009 report, the NAO noted the use of a large number of consultants and contractors in the FCO Finance Directorate, and recommended that the Department should set targets for a reduction.[302] The FCO has subsequently set a target for a reduction of 45-50% in these temporary staff,[303] and it is recruiting onto its permanent staff a number of specialists, to allow it to achieve the cut.[304] The FCO also told us that it was implementing an Office of Governance Commerce Consultancy Value Programme to ensure that it was "bearing down" on consultancy costs, and that it expected to achieve £2 million in savings through this means.[305] The FCO's 2008-09 Annual Report said that consultancy spend in the year was an estimated £60 million, up from £30 million in 2007-08, but the Department said subsequently that the two figures were not comparable, as the 2008-09 figure included "managed service provision" which had not been included in 2007-08, and that the Department's actual spend on consultancy 'proper' in 2008-09 was £29.9 million.[306]

158.  We recommend that the FCO should continue to bear down heavily on its consultancy costs. We further recommend that the FCO should provide an estimate of its spending on consultancy in 2009-10 in its response to this Report.

159.  The 2009 Cabinet Office Capability Review of the FCO reported that "a number of stakeholders noted that [the] FCO underperforms when required to run programmes and projects", and that there was "a need to ensure that staff understand the importance of good programme and project management skills and apply them to deliver work on the ground".[307] The FCO told us that it had commissioned an action plan from the Office of Government Commerce for improving the Department's programme and project management capability, and was enhancing its training and information provision in this area.[308]

160.  We recommend that in its response to this Report the FCO should update us on the implementation of its action plan for improving programme and project management capability, including information on its plans for assessing the impact of the project.

161.  The Office of Government Commerce carried out a Procurement Capability Review of the FCO in September-November 2008 which was largely critical, noting a number of weaknesses in the FCO's procurement capabilities and practices.[309] In response to the review, the FCO has established an improvement plan, which is to be completed by February 2011. The Department told us in October 2009 that the plan had 39 elements, of which 11 were slipping from their original timescales.[310] The FCO said that four of these were related to work which needed to be carried out by the new Commercial Director, who arrived in post in August 2009. Through improved procurement, the FCO's aim is to make £11 million in savings during the CSR 07 period; it forecasts that it will in fact achieve £13.2 million.[311]

162.  We conclude that there appears to be significant scope for the FCO to improve its procurement practices. We recommend that in its response to this Report the FCO should update us on its progress in implementing its procurement improvement plan, and in particular set out whether all elements are now back on track for completion on time by February 2011. We further recommend that the FCO should provide its estimates for the savings achieved so far and likely to be achieved by the end of the project.

163.  A key indicator of weak financial management in the FCO in the past has been a consistent tendency to underspend.[312] In 2007-08, the FCO underspent by around 6%. In 2008-09, the Department's total underspend was 3.1%,[313] and Sir Peter Ricketts told us that the underspend on the main administration and programme budget was just 0.14%. This was below the 1% target set by the FCO Board at the start of the financial year. Sir Peter said that the reduced underspend was partly the result of the financial pressures facing the FCO, which had helped to "cure" the problem,[314] but that it was also "concrete evidence that the 5 Star Finance programme [was] delivering sustained improvement throughout the year in [the FCO's] financial management".[315] The FCO explained that, under the programme, budget holders are now required to report monthly on their expected spend for the year, and to identify activities which can be "switched on" or "switched off" at short notice, in order to increase the Department's prospects of avoiding both underspend and overspend.[316] In its June 2009 Report, the NAO said that more frequent and detailed internal scrutiny of budget forecasts appeared to be proving effective.[317]

164.  The FCO has been among the first of the major Departments to lay its Resource Accounts for two years in succession, 2008 and 2009. The NAO took this as evidence for its conclusion that the FCO had "improved the accuracy, reliability and timeliness of financial information reported both externally and internally".[318]

165.  We conclude that the way in which the FCO picked up on its likely overspend early in the 2009-10 financial year reflects the effectiveness of its efforts to improve its in-year budgetary monitoring.

166.  When it launched the "5 Star Finance" programme in mid-2007, the FCO assessed itself as being at "2½ stars". It aimed originally to achieve "5 Star" status by April 2009. It has not met this target. In our Report last year we noted that in late 2008 the FCO had encountered difficulties in achieving "4 Star" standards, and that the Department had modified its target date for the achievement of "5 Star" status to the 2009-10 financial year.[319] In its response to our Report, the FCO said that it was aiming for "5 Star" status by May 2010, but this subsequently slipped further to July 2010.[320] The FCO assessed itself as having achieved "4 Star" status in December 2009.[321] In November 2009, the FCO Board agreed to "consolidate" at that level, "before pushing on to 4½ in the summer of 2010".[322]

167.  We reported last year that the delay in achieving "5 Star" status had arisen partly because the FCO had toughened the detailed criteria involved, as standards of financial management had risen across Whitehall. We commended the FCO for resisting the temptation to "gild the lily" in its self-assessment.[323] In its June 2009 Report, the NAO judged that the FCO's then "3½ Star" self-assessment was "reasonable and soundly based".[324]

168.  Overall, in its June 2009 Report the NAO concluded that "the FCO has made significant progress in developing its financial management capability",[325] a conclusion which was endorsed by the Public Accounts Committee.[326] The NAO subsequently told that Committee that the FCO had "responded positively" to the recommendations for further improvements which it had made in its Report.[327] The 2009 Cabinet Office Capability Review concluded similarly that the "5 Star Finance" programme had had "a significant impact on the quality of financial information and on budgetary control".[328]

169.  The FCO told us that, as "5 Star" status and thus the end of the "5 Star Finance" programme approached:

a transition plan will be drawn up to move the transformation in financial management performance from being a step change programme activity to being an on-going business development activity within the FCO's normal scope of business. Consideration will be given at that point as to whether there is a need for further intensive activity through a new transformation programme to build on the progress made through the 5 Star Programme.[329]

170.  We conclude that the FCO's failure to complete its "5 Star Finance" programme during the 2009-10 financial year is disappointing. However, we further conclude that there is no evidence that the delay reflects any deterioration in FCO financial management. Rather, we concur with the National Audit Office and the Public Accounts Committee that the FCO's financial management has improved significantly in recent years. We conclude that the FCO's elimination of its underspending habit in 2008-09 is especially to be welcomed. We further conclude that the delay in achieving "5 Star" status largely reflects the high standards which the FCO is setting for itself; and that the fact that the Department too recognises that there remains scope for important improvement is to be welcomed. We recommend that in its response to this Report the FCO should provide its current estimated completion date for the "5 Star Finance" programme.

Estate management

171.  On the basis of the figures in the Department's 2008-09 Annual Report, the FCO's total estate was worth £2.2 billion at the end of March 2009 (including assets owned, leased and forming part of PFI arrangements).[330] According to the NAO, the FCO's overseas estate—defined as FCO-owned properties only—was worth £1.6 billion at open-market value.[331] The overseas estate comprises just over 4,000 properties.[332]

172.  Under the CSR 07, the Treasury required the FCO to deliver a minimum of £54 million from asset sales over the three-year period.[333] After the FCO delivered this amount early in the first year of the settlement, following some successful sales, the target was raised in-year to £60 million. In our Report last year, we expressed some concern in case the increased target placed extra pressure on the FCO to make sales which were not well-founded, especially at a time of international economic downturn and therefore depressed property prices.[334] We have consistently taken the view that sales of FCO properties around the world should take place solely on the merits of each case, rather than as a revenue-raising measure.[335]

173.  Sir Peter Ricketts includes details of the FCO's asset sales and purchases in each of his quarterly management letters to us.[336] The FCO generated £61.5 million from asset sales in 2008-09, of which almost £40 million accrued from the sale of the Embassy site in Madrid.[337] In the financial year, the FCO also sold properties in Abidjan, Amsterdam, Buenos Aires, Cape Town, Durban, Lilongwe, Manila, Montserrat, Ottawa, Stockholm and Wellington, and land in Tallinn. The final sale of Marlay Grange in Dublin, the intended but never-occupied new Residence, also fell in the 2008-09 year; we have commented extensively on the dispiriting Marlay Grange saga in previous Reports.[338] The property in Durban was the only other Residence of a Head of Mission to be sold in 2008-09. As regards purchases, in 2008-09 the FCO bought land in Dushanbe, and properties in Antalya, Montserrat, Washington and Panama, the last being a new Residence.[339]

174.  For 2009-10, the FCO's asset sales target is £8 million. As of December 2009, it had delivered £5.6 million, with a further £3 million under offer.[340]

175.  The financial pressures facing the FCO have prompted renewed speculation about the possibility of asset sales to raise cash. The Government's December 2009 Operational Efficiency Programme: Asset Portfolio publication identified a cross-government target of £16 billion to be delivered from asset and property sales by 2013-14.[341] In October 2009, Sir Peter Ricketts answered "no" when asked by the Public Accounts Committee if the FCO was going to "sell off cheaply Residences that do so much for our image just to meet some Treasury demand".[342] We requested and received the same assurance from Sir Peter in December; he told us that any sale would "be justified and make sense on its merits".[343] However, Sir Peter noted that "there will always be opportunities to sell buildings that are underused, obsolete or extremely valuable when compared with the benefit they bring us", and he confirmed that the FCO would "look to sell more of those in line with the Government's policy on greater asset disposals".[344] Sir Peter also confirmed that the FCO could use the vast majority of the proceeds from asset sales to invest back into its own estate.[345] In October, he told the Public Accounts Committee that driving asset sales would be part of the remit of the FCO's new Director of Estates, Alan Croney, who took up his post in June 2009.[346]

176.  In December 2009, the Foreign Secretary confirmed to the House that the FCO intended to sell 106 properties between 2010-11 and 2013-14, with a book value of £71 million. The list includes six Residences.[347] In his evidence to us in December 2009, Sir Peter Ricketts promised to keep the Committee "closely informed" when the FCO was planning to sell assets,[348] although the FCO has stated publicly that it does not reveal details of planned asset sales in advance, for commercial reasons and in order to realise the maximum possible value from disposals.[349] As noted in paragraph 132, revenue from asset sales forms a key element in the agreement reached between the FCO and the Treasury in February 2010 aimed at plugging the gap in the FCO's finances in 2010-11.

177.  Despite the FCO's need to plug its budget shortfall, we reiterate our previous conclusion that sales of FCO properties should take place on their merits, rather than purely to raise revenue. We continue to recommend that the FCO should keep us and our successor Committee closely informed about the FCO's plans for asset sales.

178.  Sir Peter Ricketts told the Public Accounts Committee in October 2009 that there was an "instruction from the top" of the FCO to "sweat the asset" as regards the FCO estate—that is, to use the Department's buildings to generate income.[350] Sir Peter confirmed to us that "a lot" of Ambassadors were now hiring out their Residences and appropriate Embassy spaces for commercial functions.[351] However, he also noted that the revenues raised from such activities "will never be more than quite a small proportion of what it cost[s] to run these buildings".[352]

179.  We conclude that the FCO's new strategy of seeking to exploit its estate for greater financial return is to be welcomed, but subject to the proviso that such efforts do not generate conflicts of interest or compromise the Department's reputation or policies. We recommend that in its response to this Report the FCO should list a sample of non-FCO events for which the Department hired out its premises in 2009-10 and provide an estimate of the income generated from such activities.

180.  We have previously expressed concerns where the FCO has appeared to be mismanaging estate projects. This has applied in recent years both to asset sales, such as that of Marley Grange, and to estate development projects.[353] Following our criticisms last year of the FCO's management of a residential project in Pakistan, Sir Peter Ricketts copied to us the "action plan" arising from the review which was conducted of the project, which appeared to include a number of important potential improvements to FCO project management procedures.[354]

181.  In the context of our previous concerns, we note that the cost of the new Embassy building in Harare—opened in March 2009—came in at £27 million, against an initial estimate of £17.5 million. The FCO attributed the overshoot to "difficult local conditions", highlighting that the project had been implemented during a period of "political upheaval and economic collapse" in Zimbabwe. The FCO said that it was conducting a full review of the project, "to establish whether those on the FCO side […] took all possible steps to keep costs down".[355] Among other recent estate projects, new Embassy buildings in Algiers and Warsaw also came in over-budget, partly owing to unfavourable exchange-rate movements.[356]

182.  We recommend that the FCO should give us sight of its review of the Harare Embassy project, or otherwise report to us in its response to this Report on the findings of the review.

183.  In February 2010, Sir Peter Ricketts informed the Public Accounts Committee and ourselves that work had had to be suspended at an early stage on the FCO's new Embassy offices in Damascus, after evidence came to light that the security of the site may have been compromised. Sir Peter told the PAC that he thought the case represented a "failure" on the FCO's part.[357]

184.  We were particularly dismayed during our inquiry this year to hear that the project for the renovation of the Residence in Moscow had not been completed on schedule by December 2007/spring 2008, and was only finished in time for the Ambassador to be expected to move in during March 2010; and that the cost of the project was expected to come in at £13.8 million, compared to an original forecast of £10.6 million.[358] We pursued further details of the project from the FCO. The Department told us that the delays had arisen partly because of a failure to keep to schedule by the main contractor and partly because the Russian authorities had made unexpected demands regarding standards for—and their own involvement in—the work, on what is a historic building. The delays in turn pushed up costs. In September 2009, the main contractor applied for protection from its creditors. The FCO told us that it was "assessing the implications" of this.[359]

185.  With regard to the Moscow Residence renovation project, we conclude that the Russian authorities may well have made unexpected demands, but that it appears that elements of the project may also have suffered from poor planning and management on the FCO side. We recommend that in its response to this Report, the FCO should state whether the new estate project management procedures which were introduced as a result of the recent troubled residential project in Pakistan would have prevented at least some of the difficulties which have been encountered with the Moscow Residence project; and if not, whether the Moscow experience will lead to any further strengthening of FCO practices.

186.  One of the FCO's recent high-profile estate developments was the opening of new Embassy offices in Madrid. We had the opportunity to see the new offices for ourselves during a visit there in January 2010, at the start of the Spanish Presidency of the EU Council. Sir Peter Ricketts had told us that the new premises comprised open-plan offices in a "fantastic, modern office tower in a wonderful position", and that the move had generated a "tangible" lift in staff morale and effectiveness.[360] During our visit, we were indeed impressed with the new premises, although we noted that they were well outside the centre of the city. However, following our visit, there was a serious flood in the premises, apparently caused by a faulty water sprinkler system. The incident may present the FCO with as-yet unknown financial liabilities.[361]

187.  In addition to the Algiers, Harare, Madrid and Warsaw projects, since 2008 the FCO has opened new Embassy and High Commission buildings in Basra, Boston, Mumbai and Podgorica, and a new housing complex in Bangkok.[362] The bilateral Embassy to Belgium has also moved into the same premises as the UK's Permanent Representation to the EU, an arrangement which we were able to see for ourselves during our visit to Brussels in March 2010.[363] To set alongside the over-budget projects which we have noted, several others—such as in Brussels—came in on (or under-) budget.[364]

188.  In connection with the opening in October 2009 of the new Embassy building in Warsaw, designed by Tony Fretton Architects, the specialist publication Building Design said that the FCO had been an "enlightened client" which believed that "buildings matter and good design is the only worthwhile option". However, the publication said that the Warsaw Embassy was now viewed within the FCO as "lavish" and that it "could be the last of its kind, thanks to a new cost-cutting drive" which was being established under the FCO's new estates strategy, which was itself being developed by Alan Croney, the FCO's new Director of Estates, Security and Facilities Management.[365]

189.  The Civil Service Capability Review in March 2009 had already indicated that the FCO was due to bring forward an estates management strategy for "making better use of the Department's assets", something which the Review saw as "an opportunity to improve efficiency".[366] The minutes show that the FCO Board "discussed a paper on the outlines of a new estates strategy" at its September 2009 meeting;[367] and Sir Peter Ricketts told the Public Accounts Committee on 1 March 2010 that the Board discussed the full draft strategy at its February 2010 meeting and expected to finalise it "very rapidly".[368] In a letter, Sir Peter shared with the PAC and ourselves the principles which will be applied to all future FCO estate projects, and he told PAC that he would send that Committee a copy of the new estates strategy when it was finalised.[369]

190.  We recommend that the FCO should send us or our successor Committee, as well as the Public Accounts Committee, a copy of its new estates strategy as soon as it is finalised.

191.  Mr Croney was recruited externally through an open competition; he followed Keith Luck, Director General Finance, in joining the FCO from the Metropolitan Police. Mr Croney heads a newly unified team covering estates, security and facilities management.[370] His appointment is part of the major effort which the FCO is now making to strengthen its estates management. Sir Peter Ricketts told us in May 2009 that the FCO was "looking at how to improve the governance and budgeting of future estate projects to ensure spend is tightly controlled and the taxpayer gets the best value for money".[371]

192.  The NAO published a major report on the FCO's estate, Adapting the FCO's global estate to the modern world, in mid-February 2010. The NAO found that the FCO's current estate strategy had only "scant" underpinning detail and did not constitute a "clear framework to assess estate performance and drive change". The NAO also found that the FCO's data on the cost and use of the estate was poor, and that this was one of the factors behind the existence of significant unused space and a failure to take up some potential opportunities for co-location with other government departments and agencies. As regards the management of estate projects, the NAO found that:

the FCO does not have an effective system for bringing together the information necessary to manage its programme of capital projects around its estate. Poor information hinders the FCO's ability to monitor effectively project costs against budget, or to identify the systemic causes of delays and cost overruns.[372]

The NAO also found that FCO management and incentive structures regarding the estate hampered its more effective use, and that there was no drive from above the Department for better cross-government use of FCO properties. Overall, the NAO concluded that "to date the [FCO] has not secured value for money in the way it manages its global estate as a whole".[373]

193.  We conclude that the Department's new drive to strengthen its estates management is to be welcomed. This is especially the case given our previous criticisms of some FCO estate projects and the shortcomings identified by the National Audit Office in its recent Report on the FCO's management of its estate. We recommend that the FCO's new estates management strategy should give due weight to the non-financial, 'prestige' value of some FCO properties, which we conclude can bring material benefits in terms of projecting the UK presence.


30   Departmental Expenditure Limit (DEL) budget i.e. Resource plus Capital DEL, net of depreciation; Foreign Affairs Committee, First Report of Session 2007-08, Foreign and Commonwealth Office Annual Report 2006-07, HC 50, para 20 Back

31   Foreign Affairs Committee, First Report of Session 2007-08, Foreign and Commonwealth Office Annual Report 2006-07, HC 50, para 21 Back

32   DEL budget; calculated from FCO, Departmental Report and Resource Accounts 1 April 2008-31 March 2009, Volume 2, HC 460-II, pp 14-15, Table 4. The DEL figures are lower than those for Total Departmental Spending (also known as Total Public Spending), which also include Annually Managed Expenditure (AME). Back

33   Calculated from HM Treasury, Pre-Budget Report, Cm 7747, December 2009, p 194, Table B17. These DEL figures understate total MOD spending, in particular, of which an especially large share is AME.  Back

34   Ev 134 [NAO] Back

35   Q 9; Foreign Affairs Committee, Developments in the European Union, Oral and written evidence, 9 December 2009, HC (2009-10) 144, Q 4 [David Miliband]; HL Deb, 20 January 2010, col 993; HC Deb, 21 January 2010, col 439; the budget referred to is the DEL budget. Back

36   Q 9; HC Deb, 8 December 2009, col 240-1W; HC Deb, 21 January 2010, col 439 Back

37   Q 45 Back

38   Q 45 Back

39   International Development Committee, Fourth Report of Session 2009-10, DFID's Performance in 2008-09 and the 2009 White Paper, HC 48-II, Q 51 Back

40   Ev 134 [NAO] Back

41   Q 45 Back

42   Ev 131 [NAO]; Public Accounts Committee, Third Report of Session 2009-10, Financial Management in the FCO, HC 164, Q 7 [Sir Peter Ricketts] Back

43   Ev 130 [NAO] Back

44   Ev 130 [NAO] Back

45   Ev 130 [NAO]; HC Deb, 8 December 2009, col 240-1W Back

46   Ev 130 Back

47   Ev 130-31 Back

48   Ev 131 Back

49   Ev 131 Back

50   HC Deb, 11 March 2009, col 421W Back

51   Ev 131 Back

52   Q 44 Back

53   Comparison of spot rates, 1 November 2007 versus 22 January 2010; information provided by the House of Commons Library.  Back

54   The same applies whether volatility is measured as the ratio of the highest to lowest spot rate during the period, or as the coefficient of variation; information provided by the House of Commons Library.  Back

55   Q 43 Back

56   Foreign Affairs Committee, Second Report of Session 2008-09, Foreign and Commonwealth Office Annual Report 2007-08, HC 195, para 57 Back

57   FCO, Second Report from the Foreign Affairs Committee Session 2008-09: Foreign and Commonwealth Office Annual Report 2007-08: Response of the Secretary of State for Foreign and Commonwealth Affairs, Cm 7585, April 2009, para 10 Back

58   Ev 29-30 [FCO] Back

59   Ev 134 [NAO] Back

60   Q 9 Back

61   Ev 20 Back

62   Ev 29, 32 Back

63   Ev 88 Back

64   Ev 109-110 Back

65   HC Deb, 9 March 2010, col 10WS Back

66   HC Deb, 2 March 2009, col 1237-8W; HC Deb, 8 December 2009, col 240-1W Back

67   Ev 133 Back

68   Summary minutes of FCO Board meeting, 23 July 2009, via www.fco.gov.uk; FCO, Departmental Report and Resource Accounts 1 April 2008-31 March 2009, Volume 2, HC 460-II, p 86 Back

69   Foreign Affairs Committee, Second Report of Session 2008-09, Foreign and Commonwealth Office Annual Report 2007-08, HC 195, paras 211-213 Back

70   Ev 29 Back

71   FCO, Autumn Performance Report, December 2009, p 5 Back

72   Ev 79 Back

73   HC Deb, 2 March 2009, col 1239-40W Back

74   Ev 134; HC Deb, 8 December 2009, col 240-1W Back

75   HL Deb, 20 January 2010, col 992 Back

76   Q 49 Back

77   Ev 134 Back

78   See Ev 103. Back

79   Q 22 Back

80   FCO, Departmental Report and Resource Accounts 1 April 2008-31 March 2009, Volume 1, HC 460-I, p xxii Back

81   HC Deb, 2 March 2009, col 1238-9W Back

82   Foreign Affairs Committee, Fourth Report of Session 2008-09, Global Security: Non-Proliferation, HC 222, paras 73-82 Back

83   Foreign Affairs Committee, Global Security: Non-Proliferation, paras 40-44 Back

84   Q 51 Back

85   Q 21 Back

86   Ev 78 Back

87   Foreign Affairs Committee, First Report of Session 2007-08, Foreign and Commonwealth Office Annual Report 2006-07, HC 50, para 15  Back

88   Foreign Affairs Committee, Foreign and Commonwealth Office Annual Report 2006-07, para 15 Back

89   Ev 78 Back

90   Ev 103-104 Back

91   Ev 103; these figures differ slightly from those given by the Department at HC Deb, 27 February 2009, col 1199-200W and FCO, Departmental Report and Resource Accounts 1 April 2008-31 March 2009, Volume 2, HC 460-II, p 128 Back

92   HC Deb, 26 March 2009, col 600-1W, 604-5W Back

93   HC Deb, 2 February 2009, col 1238-9W; HC Deb, 26 March 2009, col 600-1W, 604-5W; Ev 103 Back

94   Calculated from FCO, Departmental Report and Resource Accounts 1 April 2008-31 March 2009, Volume 2, HC 460-II, pp 33-36, Table 13 Back

95   HC Deb, 26 March 2009, col 598W, 602W; HC Deb, 2 April 2009, col 1307W Back

96   Ev 78 Back

97   Ev 32, 78, 113 Back

98   Ev 78 Back

99   Ev 78 Back

100   Foreign Affairs Committee, Second Report of Session 2008-09, Foreign and Commonwealth Office Annual Report 2007-08, HC 195, para 214 Back

101   Foreign Affairs Committee, Second Report of Session 2008-09, Foreign and Commonwealth Office Annual Report 2007-08, HC 195, para 214 Back

102   FCO, Second Report from the Foreign Affairs Committee Session 2008-09: Foreign and Commonwealth Office Annual Report 2007-08: Response of the Secretary of State for Foreign and Commonwealth Affairs, Cm 7585, April 2009, para 41 Back

103   Ev 119 Back

104   Although we were separately in correspondence with the Foreign Secretary about UK secondments to international post-conflict missions; see para 100 and Ev 42-44. Back

105   Foreign Affairs Committee, Developments in the European Union, Oral and written evidence, 9 December 2009, HC (2009-10) 144, Q 2 Back

106   Q 21 Back

107   FCO, Departmental Report and Resource Accounts 1 April 2008-31 March 2009, Volume 2, HC 460-II, p 47 Back

108   FCO, Departmental Report and Resource Accounts 1 April 2008-31 March 2009, Volume 2, HC 460-II, pp 66-67 Back

109   FCO, Autumn Performance Report, December 2009, p 25 Back

110   Ev 74 Back

111   Q 22 Back

112   HC Deb, 2 March 2009, col 1239-40W Back

113   Summary minutes of FCO Board meeting, 23 July 2009, via www.fco.gov.uk Back

114   Summary minutes of FCO Board meeting, 25 September 2009, via www.fco.gov.uk Back

115   Public Accounts Committee, Third Report of Session 2009-10, Financial Management in the FCO, HC 164, Q 106 Back

116   Ev 134 Back

117   Q 10 Back

118   Ev 134 Back

119   Q 41 Back

120   HL Deb, 20 January 2010, col 992 Back

121   HC Deb, 21 January 2010, col 439; HL Deb, 21 January 2010, cols 1105-7; see also Ev 102. Back

122   HC Deb, 21 January 2010, col 442 Back

123   FCO, Autumn Performance Report, December 2009, p 16 Back

124   Ev 102 Back

125   Summary minutes of FCO Board meeting, 27 November 2009, via www.fco.gov.uk Back

126   See Foreign Affairs Committee, Seventh Report of Session 2007-08, Overseas Territories, HC 147-I, para 9. Back

127   Foreign Affairs Committee, Second Report of Session 2008-09, Foreign and Commonwealth Office Annual Report 2007-08, HC 195, para 75 Back

128   HC Deb, 2 March 2009, col 1239-40W; see also HC Deb, 8 December 2009, col 240-1W. Back

129   International Development Committee, Fourth Report of Session 2009-10, DFID's Performance in 2008-09 and the 2009 White Paper, HC 48-II, Q 52 Back

130   Foreign Affairs Committee, Developments in the European Union, Oral and written evidence, 9 December 2009, HC (2009-10) 144, Q 4; HC Deb, 8 December 2009, col 240-1W; Ev 80 Back

131   Q 9 Back

132   HC Deb, 8 December 2009, col 240-1 Back

133   Ev 134 Back

134   HC Deb, 26 January 2010, col 835W Back

135   Q 26 Back

136   Ev 84 Back

137   Foreign Affairs Committee, Developments in the European Union, Oral and written evidence, 2 December 2009, HC (2009-10) 114-i, Q 142 Back

138   FCO, Autumn Performance Report, December 2009, pp 27-28 Back

139   Ev 62 Back

140   Ev 93; see also Ev 103. Back

141   Ev 93 Back

142   HM Treasury, Pre-Budget Report, Cm 7747, December 2009, p 110 Back

143   HC Deb, 9 July 2009, col 948-9W Back

144   FCO, UK International Priorities: A Strategy for the FCO, Cm 6052, December 2003 Back

145   FCO, Foreign and Commonwealth Office Departmental Report 1 April 2004-31 March 2005, Cm 6533, June 2005, p 158; HC Deb, 15 December 2004, col 137-140WS; HC Deb, 11 October 2005, col 21-3WS; HC Deb, 2 February 2009, col 883-4W Back

146   Foreign Affairs Committee, Second Report of Session 2005-06, Foreign and Commonwealth Office Annual Report 2004-05, HC 522, paras 110-118 Back

147   Foreign Affairs Committee, Second Report of Session 2008-09, Foreign and Commonwealth Office Annual Report 2007-08, HC 195, para 68 Back

148   Foreign Affairs Committee, Foreign and Commonwealth Office Annual Report 2007-08, paras 51, 67 Back

149   HC Deb, 26 February 2010, col 780W; "War of words over cut in terror budget", Financial Times, 22 January 2010 Back

150   HC Deb, 26 January 2010, col 245 WH Back

151   FCO, Autumn Performance Report, December 2009, p 8 Back

152   Ev 114 Back

153   Q 13 Back

154   Qq 23-24 Back

155   HC Deb, 21 January 2010, col 439; HC Deb, 26 January 2010, col 244-245WH Back

156   Foreign Affairs Committee, Second Report of Session 2008-09, Foreign and Commonwealth Office Annual Report 2007-08, HC 195, paras 69-72 Back

157   FCO, Second Report from the Foreign Affairs Committee Session 2008-09: Foreign and Commonwealth Office Annual Report 2007-08: Response of the Secretary of State for Foreign and Commonwealth Affairs, Cm 7585, April 2009, para 13 and Annex A; HC Deb, 28 January 2009, col 598-600W; Ev 66 Back

158   Q 16 Back

159   Q 46; see also the uncorrected transcript of oral evidence taken before the Public Accounts Committee on 1 March 2010, HC (2009-10) 417-i, Q 30 [Sir Peter Ricketts]. Back

160   Q 46; Ev 98 Back

161   Cabinet Office, Foreign and Commonwealth Office: Progress and next steps, Civil Service Capability Review, March 2009, p 11 Back

162   NAO, Adapting the Foreign and Commonwealth Office's global estate to the modern world, HC (2009-10) 295, 11 February 2010, p 11 Back

163   Ev 55 Back

164   Ev 61 Back

165   Q 46; on the full cost recovery issue, see also the uncorrected transcript of oral evidence taken before the Public Accounts Committee on 1 March 2010, HC (2009-10) 417-i, Qq 60-64, 87-90 [Sir Peter Ricketts]. Back

166   Ev 98 Back

167   Q 46; see also Ev 98. Back

168   Ev 105 Back

169   Foreign Affairs Committee, Second Report of Session 2008-09, Foreign and Commonwealth Office Annual Report 2007-08, HC 195, para 86 Back

170   Ev 76 Back

171   Ev 68 Back

172   HC Deb, 26 January 2010, col 835W Back

173   Ev 68; see also Q 27. Back

174   Ev 76 Back

175   FCO, Departmental Report and Resource Accounts 1 April 2008-31 March 2009, Volume 1, HC 460-I, p 3 Back

176   Cabinet Office, Foreign and Commonwealth Office: Progress and next steps, Civil Service Capability Review, March 2009, pp 11-12 Back

177   Cabinet Office, Foreign and Commonwealth Office: Progress and next steps, p 12 Back

178   FCO, Departmental Report and Resource Accounts 1 April 2008-31 March 2009, Volume 1, HC 460-I, p 3 Back

179   Ev 95-96 Back

180   Foreign Affairs Committee, Second Report of Session 2008-09, Foreign and Commonwealth Office Annual Report 2007-08, HC 195, paras 76-77 Back

181   Ev 62 Back

182   Foreign Affairs Committee, Foreign and Commonwealth Office Annual Report 2007-08, para 78 Back

183   Foreign Affairs Committee, Third Report of Session 2007-08, Foreign Policy Aspects of the Lisbon Treaty, HC 120-I, paras 195-199 Back

184   "EU Commission 'embassies' granted new powers", euobserver.com, 21 January 2010 Back

185   Foreign Affairs Committee, Third Report of Session 2007-08, Foreign Policy Aspects of the Lisbon Treaty, HC 120-I, para 199 Back

186   Foreign Affairs Committee, Foreign Policy Aspects of the Lisbon Treaty, paras 200-203 Back

187   Foreign Affairs Committee, First Report of Session 2007-08, Foreign and Commonwealth Office Annual Report 2006-07, HC 50, paras 176-178; oral evidence taken before the European Scrutiny Committee on 28 October 2009, HC (2008-09) 1076, Qq 16-18 [Chris Bryant MP] Back

188   Treaty on European Union, Article 35 Back

189   HC Deb, 1 March 2010, col 839W; Foreign Affairs Committee, First Report of Session 2007-08, Foreign and Commonwealth Office Annual Report 2006-07, HC 50, paras 176-178 Back

190   Foreign Affairs Committee, Foreign Policy Aspects of the Lisbon Treaty, para 199; see also Q 26 [Sir Peter Ricketts]. Back

191   Q 26 Back

192   Uncorrected transcript of oral evidence taken before the Public Accounts Committee on 1 March 2010, HC (2009-10) 417-i, Qq 46, 65, 76-81; on the issue of spare capacity in the FCO's global estate, see NAO, Adapting the Foreign and Commonwealth Office's global estate to the modern world, HC (2009-10) 295, 11 February 2010, p 28, Figure 11. Back

193   Uncorrected transcript of oral evidence taken before the Public Accounts Committee on 1 March 2010, HC (2009-10) 417-i, Q 80 Back

194   Presidency Conclusions, European Council, 29-30 October 2009 Back

195   Treaty on European Union, Article 27 Back

196   Oral evidence taken before the European Scrutiny Committee on 28 October 2009, HC (2008-09) 1076, Qq 6, 8, 36-48 Back

197   In particular, in light of Article 10 of the Lisbon Treaty's Protocol on the role of national parliaments in the EU, which provides that "a conference of Parliamentary Committees for the Affairs of the Union may submit any contribution it deems appropriate for the attention of the European Parliament, the Council and the Commission [...] [and] may also organise interparliamentary conferences on specific topics, in particular to debate matters of common foreign and security policy, including common security and defence policy". Back

198   See letter in reply from the High Representative (EU 118, 22 February 2010), published by the Committee at http://www.publications.parliament.uk/pa/cm200910/cmselect/cmfaff/memo/eudevelop/contents.htm Back

199   Foreign Affairs Committee, Third Report of Session 2007-08, Foreign Policy Aspects of the Lisbon Treaty, HC 120-I, para 97 Back

200   HC Deb, 25 March 2009, col 17-9WS Back

201   Ev 21, 33 Back

202   "Civilian role in foreign missions faces cuts", Financial Times, 2 March 2009 Back

203   Ev 42 Back

204   Ev 43 Back

205   Ev 44 Back

206   HC Deb, 25 March 2009, col 17-9WS Back

207   HC Deb, 25 March 2009, col 17-9WS; see also HC Deb, 3 June 2009, col 511-2W; Ev 43, 45. Back

208   Q 21 Back

209   Ev 45 Back

210   The UK was among the first states to recognise Kosovo, on 18 February 2008, the day following its declaration of independence. On Bosnia-Herzegovina, in July 2008, for example, the Foreign Secretary wrote jointly with his Czech counterpart to all other EU Foreign Ministers, to "flag up Bosnia as a big issue"; Foreign Affairs Committee, Developments in the European Union, Oral and written evidence,10 December 2008, HC (2008-09) 70-i, Q 56 Back

211   "Civilian role in foreign missions faces cuts", Financial Times, 2 March 2009 Back

212   Cabinet Office, The National Security Strategy of the United Kingdom, Cm 7291, March 2008, para 4.47 Back

213   "European Renewal Amidst Global Adversity", Warsaw, 23 June 2009, text at http://www.davidmiliband.info/speeches/speeches_09_07.htm Back

214   Letter to the Chairman (EU 107, 6 December 2009), published by the Committee at http://www.publications.parliament.uk/pa/cm200910/cmselect/cmfaff/memo/eudevelop/contents.htm  Back

215   Ibid.  Back

216   HC Deb, 16 December 2009, col 139WS Back

217   HC Deb, 29 January 2010, col 1135W Back

218   HC Deb, 16 December 2009, col 139WS; Ev 101 Back

219   Ev 101 Back

220   Foreign Affairs Committee, Second Report of Session 2008-09, Foreign and Commonwealth Office Annual Report 2007-08, HC 195, para 212 Back

221   Ev 129 Back

222   HC Deb, 8 December 2009, col 240-1W Back

223   Q 48 Back

224   Ev 132 Back

225   Q 48 Back

226   Ev 133 Back

227   Ev 79 Back

228   Ev 133 Back

229   Foreign Affairs Committee, Developments in the European Union, Oral and written evidence, 9 December 2009, HC (2009-10) 144, Q 4 Back

230   NAO, Financial Management in the Foreign and Commonwealth Office, HC (2008-09) 289, 3 June 2009, para 2.70 Back

231   Ev 133 Back

232   Ev 79, 133 Back

233   Ev 33 Back

234   Ev 133 Back

235   Ev 29 [FCO], 133 [NAO] Back

236   Ev 134 Back

237   Ev 80 Back

238   Ev 131 [NAO] Back

239   Ev 79 Back

240   Ev 29 Back

241   Ev 80 Back

242   Public Accounts Committee, Third Report of Session 2009-10, Financial Management in the FCO, HC 164, Q 21 Back

243   Ev 134 [NAO] Back

244   International Development Committee, Fourth Report of Session 2009-10, DFID's Performance in 2008-09 and the 2009 White Paper, HC 48-II, Q 53 Back

245   Public Accounts Committee, Financial Management in the FCO, Q 21 Back

246   Public Accounts Committee, Financial Management in the FCO, Conclusions and recommendations, para 6 Back

247   DEL budget, calculated from FCO, Departmental Report and Resource Accounts 1 April 2008-31 March 2009, Volume 2, HC 460-II, pp 14-15, Table 4 Back

248   Ev 101 Back

249   Summary minutes of FCO Board meeting, 27 February 2009, via www.fco.gov.uk Back

250   HL Deb, 20 January 2010, col 992 Back

251   HC Deb, 10 February 2010, col 53WS Back

252   Summary minutes of FCO Board meeting, 18 December 2009, via www.fco.gov.uk Back

253   Ev 100 Back

254   HC Deb, 21 January 2010, col 439-444 Back

255   Public Accounts Committee, Financial Management in the FCO, para 8 Back

256   Q 61 Back

257   Ev 114 Back

258   Ev 80 Back

259   Foreign Affairs Committee, Developments in the European Union, Oral and written evidence, 9 December 2009, HC (2009-10) 144, Q 3 Back

260   HC Deb, 10 February 2010, col 53WS  Back

261   HC Deb, 22 February 2010, col 213W Back

262   Uncorrected transcript of oral evidence taken before the Public Accounts Committee on 1 March 2010, HC (2009-10) 417-i, Q 97; see also paragraph 175 below. Back

263   HC Deb, 22 February 2010, col 214W Back

264   HC Deb, 10 February 2010, col 53WS Back

265   Ev 141 Back

266   Ev 142 Back

267   HC Deb, 10 February 2010, col 53WS Back

268   Foreign Affairs Committee, Developments in the European Union, Oral and written evidence, 9 December 2009, HC (2009-10) 144, Q 5 Back

269   Summary minutes of FCO Board meeting, 29 January 2010, via www.fco.gov.uk Back

270   Q 20 Back

271   Q 4 Back

272   Foreign Affairs Committee, First Report of Session 2007-08, Foreign and Commonwealth Office Annual Report 2006-07, HC 50, paras 18-21 Back

273   Foreign Affairs Committee, Developments in the European Union, Oral and written evidence, 9 December 2009, HC (2009-10) 144, Q 8 Back

274   Foreign Affairs Committee, First Report of Session 2007-08, Foreign and Commonwealth Office Annual Report 2006-07, HC 50, paras 77-93; Foreign Affairs Committee, Second Report of Session 2008-09, Foreign and Commonwealth Office Annual Report 2007-08, HC 195, paras 204-208 Back

275   FCO, Autumn Performance Report, December 2008, p 26 Back

276   FCO, Departmental Report and Resource Accounts 1 April 2008-31 March 2009, Volume 2, HC 460-II, p 3 Back

277   FCO, Autumn Performance Report, December 2009, p 27 Back

278   FCO, Autumn Performance Report, December 2008, p 26; FCO, Autumn Performance Report, December 2009, p 26 Back

279   FCO, Autumn Performance Report, December 2009, p 26 Back

280   Ev 103, 105 Back

281   Foreign Affairs Committee, Second Report of Session 2008-09, Foreign and Commonwealth Office Annual Report 2007-08, HC 195, paras 125-149 Back

282   Foreign Affairs Committee, Foreign and Commonwealth Office Annual Report 2007-08, para 141 Back

283   Ev 62 Back

284   Ev 74 Back

285   FCO, Autumn Performance Report, December 2009, p 26 Back

286   Ev 51 Back

287   FCO, Autumn Performance Report, December 2009, p 30 Back

288   Foreign Affairs Committee, Second Report of Session 2008-09, Foreign and Commonwealth Office Annual Report 2007-08, HC 195, para 205; FCO, Autumn Performance Report, December 2009, p 26 Back

289   Q 12 Back

290   Qq 14-15 Back

291   Ev 53 Back

292   Foreign Affairs Committee, Foreign and Commonwealth Office Annual Report 2007-08, paras 215-218 Back

293   Ev 52, 104 Back

294   NAO, Financial Management in the Foreign and Commonwealth Office, HC (2008-09) 289, 3 June 2009 Back

295   Foreign Affairs Committee, First Report of Session 2007-08, Foreign and Commonwealth Office Annual Report 2006-07, HC 50, para 106 Back

296   See Foreign Affairs Committee, Foreign and Commonwealth Office Annual Report 2006-07, paras 97-105. Back

297   Foreign Affairs Committee, Second Report of Session 2008-09, Foreign and Commonwealth Office Annual Report 2007-08, HC 195, paras 196-202 Back

298   Ev 53 Back

299   NAO, Financial Management in the Foreign and Commonwealth Office, HC (2008-09) 289, 3 June 2009, p 5; Public Accounts Committee, Third Report of Session 2009-10, Financial Management in the FCO, HC 164, para 5 Back

300   NAO, Financial Management in the Foreign and Commonwealth Office, p 17; Public Accounts Committee, Financial Management in the FCO, Q 65 Back

301   Ev 53 Back

302   NAO, Financial Management in the Foreign and Commonwealth Office, Summary, para 16c Back

303   Public Accounts Committee, Third Report of Session 2009-10, Financial Management in the FCO, HC 164, Ev 13 Back

304   Ev 81 Back

305   Ev 78; FCO, Autumn Performance Report, December 2009, p 28 Back

306   FCO, Departmental Report and Resource Accounts 1 April 2008-31 March 2009, Volume 2, HC 460-II, p 39; HC Deb, 14 July 2009, col 320W; HC Deb, 29 January 2010, col 1115W Back

307   Cabinet Office, Foreign and Commonwealth Office: Progress and next steps, Civil Service Capability Review, March 2009, p 12 Back

308   Ev 82 Back

309   Office of Government Commerce, Procurement Capability Review Programme, FCO Review Report, September-November 2008, http://www.ogc.gov.uk/documents/FCO_PCR_Report.pdf Back

310   Ev 82 Back

311   FCO, Autumn Performance Report, December 2009, p 28 Back

312   NAO, Financial Management in the Foreign and Commonwealth Office, HC (2008-09) 289, 3 June 2009, paras 1.25-1.28 Back

313   Information provided by the House of Commons Department of Chamber and Committee Services Scrutiny Unit. On a different basis, the NAO put the figure at 2.5%; Public Accounts Committee, Third Report of Session 2009-10, Financial Management in the FCO, HC 164, Ev 13. See also FCO, Departmental Report and Resource Accounts 1 April 2008-31 March 2009, Volume 2, HC 460-II, p 86. Back

314   Q 49 Back

315   Ev 60 Back

316   Ev 81 Back

317   NAO, Financial Management in the Foreign and Commonwealth Office, HC (2008-09) 289, 3 June 2009, Summary, para 12 Back

318   NAO, Financial Management in the Foreign and Commonwealth Office, Summary, para 13; see also Ev 60 [FCO]. Back

319   Foreign Affairs Committee, Second Report of Session 2008-09, Foreign and Commonwealth Office Annual Report 2007-08, HC 195, paras 198-200 Back

320   FCO, Second Report from the Foreign Affairs Committee Session 2008-09: Foreign and Commonwealth Office Annual Report 2007-08: Response of the Secretary of State for Foreign and Commonwealth Affairs, Cm 7585, April 2009, para 40; Ev 80, 105 Back

321   Ev 105 Back

322   Summary minutes of FCO Board meeting, 27 November 2009, via www.fco.gov.uk; see also Ev 105. Back

323   Foreign Affairs Committee, Foreign and Commonwealth Office Annual Report 2007-08, paras 200-202 Back

324   NAO, Financial Management in the Foreign and Commonwealth Office, HC (2008-09) 289, 3 June 2009, Summary, para 4 Back

325   NAO, Financial Management in the Foreign and Commonwealth Office, Summary, para 4 Back

326   Public Accounts Committee, Third Report of Session 2009-10, Financial Management in the FCO, HC 164, Conclusions and recommendations, para 1  Back

327   Public Accounts Committee, Financial Management in the FCO, Ev 13 Back

328   Cabinet Office, Foreign and Commonwealth Office: Progress and next steps, Civil Service Capability Review, March 2009, p 11 Back

329   Ev 81 Back

330   Net book value; FCO, Departmental Report and Resource Accounts 1 April 2008-31 March 2009, Volume 2, HC 460-II, p 131, Table 12 Back

331   NAO, Adapting the Foreign and Commonwealth Office's global estate to the modern world, HC (2009-10) 295, 11 February 2010, p 13, Figure 2 Back

332   Ibid.  Back

333   Ev 77 Back

334   Foreign Affairs Committee, Second Report of Session 2008-09, Foreign and Commonwealth Office Annual Report 2007-08, HC 195, paras 92-93 Back

335   Foreign Affairs Committee, First Report of Session 2007-08, Foreign and Commonwealth Office Annual Report 2006-07, HC 50, para 161 Back

336   Ev 27, 55, 63-64, 107 Back

337   Ev 77 Back

338   Foreign Affairs Committee, First Report of Session 2007-08, Foreign and Commonwealth Office Annual Report 2006-07, HC 50, paras 162-166; Foreign Affairs Committee, Second Report of Session 2008-09, Foreign and Commonwealth Office Annual Report 2007-08, HC 195, paras 101-105 Back

339   Ev 64 Back

340   HC Deb, 8 December 2009, col 236W Back

341   HM Treasury, Pre-Budget Report, Cm 7747, December 2009, p 111 Back

342   Public Accounts Committee, Third Report of Session 2009-10, Financial Management in the FCO, HC 164, Q 9 Back

343   Q 53 Back

344   Q 53 Back

345   Qq 58-60 Back

346   Public Accounts Committee, Financial Management in the FCO, Q 8 Back

347   HC Deb, 8 December 2009, col 236W Back

348   Q 54 Back

349   HC Deb, 22 February 2010, col 213W; Ev 114 Back

350   Public Accounts Committee, Third Report of Session 2009-10, Financial Management in the FCO, HC 164, Q 53 Back

351   Q 54 Back

352   Q 54 Back

353   Foreign Affairs Committee, Second Report of Session 2008-09, Foreign and Commonwealth Office Annual Report 2007-08, HC 195, paras 94-105 Back

354   Not printed; see Ev 54. Back

355   Ev 54 Back

356   Uncorrected transcript of oral evidence taken before the Public Accounts Committee on 1 March 2010, HC (2009-10) 417-i, Qq 12-13 [Sir Peter Ricketts]  Back

357   Uncorrected transcript of oral evidence taken before the Public Accounts Committee on 1 March 2010, HC (2009-10) 417-i, Q 18 Back

358   Ev 61, 93 Back

359   Ev 96 Back

360   Q 53 Back

361   Uncorrected transcript of oral evidence taken before the Public Accounts Committee on 1 March 2010, HC (2009-10) 417-i, Qq 21-24 Back

362   Ev 26, 105-106 Back

363   Ev 106 Back

364   Ev 106 Back

365   "Foreign Office U-turn over embassy costs" and "End of an era for Embassies", Building Design, 16 October 2009 Back

366   Cabinet Office, Foreign and Commonwealth Office: Progress and next steps, Civil Service Capability Review, March 2009, p 12 Back

367   Summary minutes of FCO Board meeting, 25 September 2009, via www.fco.gov.uk Back

368   Uncorrected transcript of oral evidence taken before the Public Accounts Committee on 1 March 2010, HC (2009-10) 417-i, Q 2; see also summary minutes of FCO Board meeting, 26 February 2010, via www.fco.gov.uk. Back

369   Uncorrected transcript of oral evidence taken before the Public Accounts Committee on 1 March 2010, HC (2009-10) 417-i, Q 2 Back

370   Ev 61 Back

371   Ev 54 Back

372   NAO, Adapting the Foreign and Commonwealth Office's global estate to the modern world, HC (2009-10) 295, 11 February 2010, p 6 Back

373   NAO, Adapting the Foreign and Commonwealth Office's global estate to the modern world, p 9 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 21 March 2010