Public Expenditure on Health and Personal Social Services 2009 - Health Committee Contents


2.  CAPITAL EXPENDITURE

2.1.4  Could the Department list all publicly funded capital projects with a total cost above £10 million which are under construction? Could this include original and current estimated completion dates and costs and percentage time/cost overruns and savings? (Q9)

Answer

  1.  The information requested is given in table 9.

Table 9

PUBLICLY FUNDED CAPITAL PROJECTS WITH A TOTAL COST OF OVER £10 MILLION WHICH ARE UNDER CONSTRUCTION DURING 2009-10 (PROCURE21 PROJECTS)




Code
Trust/project
Description of project
Original estimated
completion date
Current estimated
completion date
% Time overrun
(+) / saving (-)
Original estimated
cost £million
(1)
Current estimated
cost £million(2)
% Cost overrun
(+) / saving (-)

5C2Barking and Dagenham PCT Maternity, Urgent Treatment Centre, Sexual Health, General Practice & Outpatients
12-Apr-10
12-Apr-10
0.0%
10.1
10.1
0.0%
RMCBolton Hospitals NHS Trust Making it Better (Making it Better) Maternity & Paediatrics
31-Jul-11
31-Jul-11
0.0%
19.6
21.0
7.1%
RXTBirmingham and Solihull Mental Health NHS Foundation Trust Moseley Hall Hospital (Mental Hall Development)
18-Nov-10
18-Nov-10
0.0%
13.8
13.8
0.0%
RXLBlackpool, Fylde and Wyre Hospitals NHS Foundation Trust Phase 6 Development—New Surgical Unit
30-Jun-11
30-Jun-11
0.0%
34.0
34.0
0.0%
RBVChristie Hospital NHS Foundation Trust Oak Road Development—New Patient Treatment Centre
25-Oct-10
25-Oct-10
0.0%
35.0
35.0
0.0%
RXPCounty Durham and Darlington NHS Foundation Trust Mechanical and Electrical Infrastructure Replacement Works
30-Mar-12
30-Mar-12
0.0%
26.0
26.0
0.0%
RWHEast and North Hertfordshire NHS Trust Womans And Children's Reconfiguration
23-Oct-09
23-Oct-09
0.0%
16.0
16.0
0.0%
RXREast Lancashire Hospitals NHS Trust Women's and Newborn's Unit BGH
04-Jun-10
04-Jun-10
0.0%
26.5
26.5
0.0%
5QAEastern and Coastal Kent PCT King's Avenue Development—New Health Centre
30-Jun-11
30-Jun-11
0.0%
14.1
14.1
0.0%
RTEGloucestershire Hospitals NHS Foundation Trust Womens Services Re-development
22-Nov-10
22-Nov-10
0.0%
26.0
26.0
0.0%
RCDHarrogate and District NHS Foundation Trust "A" Wards Redevelopment & Associated Works
01-Jan-11
01-Jan-11
0.0%
12.5
12.5
0.0%
5LAKensington and Chelsea PCT Refurburbishment of Health Centre  
11-Feb-10
11-Feb-10
0.0%
12.0
12.0
0.0%
RNQKettering General Hospital NHS Trust New Women & Children"`s Unit
07-Mar-11
07-Mar-11
0.0%
16.0
16.0
0.0%
RR8Leeds Teaching Hospitals NHS Trust Clinical Services Reconfiguration project
12-Nov-10
12-Nov-10
0.0%
25.0
25.0
0.0%
RR8Leeds Teaching Hospitals NHS Trust Electrical Infrastructure Upgrade
30-Mar-10
30-Mar-10
0.0%
17.0
17.0
0.0%
RT5Leicestershire Partnership NHS Trust Mental Health Refurbishment 2012 Vision
01-Nov-12
01-Nov-12
0.0%
25.0
25.0
0.0%
RNHNewham University Hospital NHS Trust Maternity & Newborn Development
30-Sep-11
30-Sep-11
0.0%
18.2
18.2
0.0%
RVJNorth Bristol NHS Trust Academic & Pathology
19-Oct-09
19-Oct-09
0.0%
40.2
40.2
0.0%
RATNorth East London NHS Foundation Trust Site Rationalisation
25-Feb-11
25-Feb-11
0.0%
17.0
17.0
0.0%
RHANottinghamshire Healthcare NHS Trust High Secure Learning Disability Unit for Men
11-Jun-10
11-Jun-10
0.0%
34.9
34.9
0.0%
RTHOxford Radcliffe Hospitals NHS Trust Cardiac Development
19-Dec-08
30-Apr-09
16.3%
26.0
30.0
15.5%
RTHOxford Radcliffe Hospitals NHS Trust Renal Transplant & Medicine
27-Feb-11
27-Feb-11
0.0%
22.0
22.0
0.0%
RW6Pennine Acute Hospitals NHS Trust Women's & Children's development
14-May-10
04-Jun-10
2.6%
32.0
29.0
-9.4%
RW6Pennine Acute Hospitals NHS Trust Ambulatory Radiotherapy Centre
31-May-10
31-May-10
0.0%
16.7
16.2
-3.0%
RT2Penning Care NHS Foundation Trust Low Secure Unit
31-Jan-11
31-Jan-11
0.0%
11.0
11.0
0.0%
5FEPortsmouth City Teaching PCT Portsmouth City Teaching, St.Mary's Campus
11-Nov-11
11-Nov-11
0.0%
18.8
18.8
0.0%
RXERotherham, Doncaster and South Humber Mental Health NHS Foundation Trust Modernisation of Rotherham Mental Health Services
30-Dec-11
30-Dec-11
0.0%
17.0
17.0
0.0%
RHWRoyal Berkshire NHS Foundation Trust Bracknell Spoke
30-May-10
30-May-10
0.0%
11.5
11.5
0.0%
5QLSomerset PCTRefurbishment and new build of Community Hospital—South Petherton
30-Mar-11
30-Mar-11
0.0%
13.3
13.3
0.0%
5FWSomerset PCTRe-provision of Minehead Community Hospital
19-Dec-10
19-Dec-10
0.0%
15.5
15.5
0.0%
RTRSouth Tees Hospitals NHS Trust Oncology Project
01-Apr-11
01-Apr-11
0.0%
23.2
23.2
0.0%
5F7Stockport PCTSt. Thomas Community Hospital
30-Apr-11
30-Apr-11
0.0%
30.0
30.0
0.0%
RT6Suffolk Mental Health Partnership NHS Trust Modernisation of Suffolk Mental Health Services
29-Nov-10
29-Nov-10
0.0%
22.0
22.0
0.0%
RTDThe Newcastle Upon Tyne Hospitals NHS Foundation Trust Institute of Transplant
15-Apr-11
15-Apr-11
0.0%
24.0
24.0
0.0%
RM2University Hospital of South Manchester NHS Foundation Trust Wythenshawe Maternity Unit
01-Nov-11
01-Nov-11
0.0%
12.3
12.3
0.0%
RJEUniversity Hospital of North Staffordshire NHS Trust Refurbishment and alterations to retained estate  
30-Dec-12
30-Dec-12
0.0%
42.0
42.0
0.0%
RWQWorcestershire PCT Malvern Community Hospital
29-Oct-10
29-Oct-10
0.0%
13.5
13.5
0.0%
5A3South Gloucestershire PCT Yate Community Healthcare Centre and integrated children's centre
28-Aug-09
28-Jul-09
-6.0%
11.2
11.2
0.0%

Source:
Estates and Facilities, DH
 
Footnotes:
1.  The "Original Estimated Cost" represents the cost of the project once final design has been agreed and before construction starts on site. This is known as the Guaranteed Maximum Price (GMP) under the ProCure21 procurement programme. For projects which have not yet reached final design the cost shown will be the estimated GMP.
2.  The "Current Estimated Cost" is the current cost of the project. This cost may be higher than the original estimated cost in cases where the trust have taken the opportunity to request additional works, which may extend the construction period and increase cost.




 