2.  CAPITAL EXPENDITURE

2.1.5  Could the Department provide a commentary on publicly funded capital projects where there are significant discrepancies between original estimates of completion dates and/or expenditures and current estimates? (Q10)

Answer

Oxford Radcliffe Hospitals NHS Trust—Cardiac Development

  1.  The scheme was extended from December 2008 to 30 April 2009 due to complexities around equipment procurement and instructions, from the NHS trust, for additional work to be included on the project. The additional works comprised accommodation and laboratory fit out works increasing the original estimated cost from £26 million to £30 million.


 